New Plutonium Facility Estimate Embraces $4.5 Billion

Buried in Volume 1 of the Department of Energy’s FY 2011 Congressional Budget Request are the Details of Project Cost Estimate for LANL’s proposed Chemistry and Metallurgy Research Building Replacement (CMRR) Project. (Pg.226 & 227)

The Details –

$164 million –       The cost of the Radiological Laboratory/Utility/Office Building (RLUOB) recently finished with construction

$199 million –       The estimated cost of equipment for the RLUOB scheduled to be installed by 2013.

$3.4 billion –          The current estimate of the Proposed Nuclear Facility due to be completed in 2018.

$782 million –       “Contingency”

$4.5 Billion –         Total

This does not D&D of the existing CMR (estimated at $500 million).