Revised Estimates for Safer Gloveboxes Hurt Budget

On the heels of a GAO report made public Monday, which stated that accounting procedures used by various branches of the U.S. nuclear weapons complex are preventing NNSA from pinpointing the exact total cost of maintaining its nuclear deterrent, the Defense Nuclear Facilities Safety Board (DNFSB) has released a weekly report also showing LANL’s inability to accurately estimate even the tiniest of specific costs.

In the June 4th weekly report for Los Alamos Lab, the DNFSB stated that the Lab underestimated the cost of seismically upgrading gloveboxes at its plutonium pit production complex by an order of magnitude. The DNFSB stated, “…the expected cost of seismic upgrades to individual gloveboxes has risen from an original estimate of about $80,000 per glovebox to a current estimate of approximately $850,000.” In addition, the Lab also ended up doubling the number of gloveboxes that need the upgrades as a priority up to 157.

So, in effect, the Labs original estimate for this glovebox work was $6.4 million (80 gloveboxes at $80,000 each), but the revised estimate is now $133.4 million (157 gloveboxes at $850,000 each). It’s hard to understand how new bracing and bolts to upgrade the legs of these gloveboxes could cost $80,000 each, much less $850,000. It’s not rocket science. Maybe the private corporation running the Lab underestimated the profits that they wanted to make for this much-needed work.  Make no mistake, there will be performance- based incentive award fees  for the work, as well as for the design and even the estimates.

In safety documents, the Lab originally stated that these upgrades would be done by 2011 to mitigate the possible off-site dose of plutonium to the public in the event of a large earthquake and subsequent facility fire. Guess what? The Lab will be behind schedule as well as way over budget. But LANL is already using its commitment for future glovebox seismic upgrades to reduce the mitigated dose consequence for a seismically-induced event in its dose calculations. So the public will be safe, only on paper, until the Lab finds the time and the money to upgrade those glovebox legs.

The Lab should focus on upgrading existing facilities and equipment and prove its ability and desire to protect the public before embarking on unneeded new construction, such as the CMRR – Nuclear Facility.

Scroll to top