Complete excavation of Area G now estimated at only $9.1 billion

Q: How much does it cost to cleanup a 65-acre, 50-year-old,  nuclear weapons laboratory unlined dump full of low-level radioactive waste (LLW), radioactively contaminated infectious waste, asbestos contaminated material, transuranic waste, polychlorinated biphenyls (PCBs), and much more?

A: About 8 years of the Lab’s nuclear weapons activities budget.

First, define cleanup. (Closure is the better term to use.)

The Lab recently submitted a revised (September 2009) corrective measures evaluation (CME) of Material Disposal Area (MDA) G, located within Area G of Technical Area 54, at Los Alamos National Laboratory to the NM Environment Department. The goal of the CME report was to recommend a corrective measures alternative for closure of the site and to address contamination releases in compliance with the March 1, 2005, Compliance Order on Consent (Consent Order).

This CME report screened 14 corrective measures alternatives based on their ability to meet the regulatory threshold and other qualitative screening criteria. Seven of the 14 alternatives evaluated met the screening criteria and capital costs were estimated:

1. Alternative 1B: maintenance of existing cover – $9.4 million;

2. Alternative 2B: evapotranspiration (ET) cover – $64.8 million;

3. Alternative 2C: ET cover with partial waste excavation – $46.5 million;

4. Alternative 2D: ET cover with partial waste excavation, targeted stabilization – $48 million;

5. Alternative 5B: complete waste excavation, waste treatment, off-site disposal – $9.1 billion (This is down from last year’s estimate of $20 billion.);

6. Alternative 5C: complete waste excavation, on-site waste treatment, disposal of wastes in a RCRA Subtitle C landfill – $6.1 billion; and

7. Alternative 5D: complete waste excavation, on-site waste treatment, disposal of wastes in a RCRA corrective action management unit – $6.1 billion.(All alternatives include monitoring and maintenance, and soil vapor extraction, but don’t include a 55% contingency.)

The Lab’s recommended corrective measures alternative is Alternative 2C.

The right thing to do would be Alternative 5B, complete waste excavation. The Lab could cover the $9.1 billion by redirecting the $1.2 billion it spends annually on nuclear weapons activities.

The hard-working folks over at NMED have to make the final decision, and there will be opportunities for public input.

Find the report MDA G CME R1 Sept 09 [Warning, it’s 14MB]

Operations at Plutonium Facility stood down due to fire suppression system

In the latest of a string of fire system deficiencies on Wednesday September 30th, LANL management declared the fire suppression system inoperable in PF-4 at TA-55. Facility activities were placed in stand-by mode, which were still stood down as of three weeks later on Oct. 23rd.

DNFSB explained that the stand down was based on recent hydraulic calculations that concluded the system does not achieve the water density coverage required. Basically, the sprinklers in 13 of approximately 100 fire suppression areas at PF-4 cannot meet the current required gallons per minute estimated to effectively extinguish a fire. (Read the Oct. 2nd-23rd DNFSB reports)

One has to wonder – What is the cost to the taxpayer of PF-4 being stood down for nearly a month?

These reports come on the heels of last week’s DNFSB recommendation that the Lab must immediately do something about its risk to the public of a seismically induced fire at PF-4, which was estimated to exceed the DOE guidelines by more than 100 times. In a worst-case situation, an earthquake-induced fire could set free enough breathable plutonium that a person on the perimeter of the facility would receive a lethal dose of radiation.

Speaking of seismically induced fires, I am reminded of a March 2007 LANL report, Seismic Fragility of the LANL Fire Water Distribution System (LA-14325), which explains how numerous valves in the fire water distribution system at the Lab would have to be manually closed to insure proper pressure to facilities on fire after a seismic event.

Granted, these may be low probability events, but they have high consequences. The Lab is playing with fire by not adequately funding upgrades to its existing fire systems now, before embarking construction of any new facilities.