No Lethal High-Level Waste To New Mexico

Background

No Nuclear Waste
Photo Courtesy of No Nuclear Waste Aqui

"The most toxic and dangerous type of radioactive waste created by the nuclear industry"

This is waste generated by nuclear power plants called 'high-level radioactive waste' (HLW), also known as 'spent' or 'irradiated' fuel. This waste contains plutonium, uranium, strontium, and cesium; and will be radioactive for millions of years.

It is not like the waste currently stored at the Waste Isolation Pilot Project (WIPP) or any other waste site that exists today in the U.S.: it is far worse.

Two companies are proposing to build waste facilities near Carlsbad and Hobbs for the most toxic and dangerous type of radioactive waste created by the nuclear industry.

Holtec International is working with the Eddy-Lea Energy Alliance, LLC (ELEA) to apply for a license to build a Consolidated Interim Storage (CIS) facility approximately halfway between Carlsbad and Hobbs, and 16 miles north of WIPP.

The Nuclear Regulatory Commission (NRC) has declared the Holtec/ELEA application complete, NRC initiated a public comment period with 60 days for public comment. Note that transport of this waste poses risks to the environment and all life located near transportation routes.

Holtec proposal:

  • New CIS facility to store 100,000 metric tons of HLRW, with the potential to increase to 120,000 metric tons for 120 years
  • Shallow sub-surface burial system

New Mexicans and Texans are fighting the attempted licensing of these two proposed CIS facilities - Waste Control Specialists near Andrews, Texas and Eddy Lee/Holtec International east of Carlsbad, New Mexico.

These sites and any transport to these sites are not only dangerous but environmentally unjust. These sites present clear examples of environmental racism.

New Mexico's demographic is largely Latino. There are many communities of color, especially in the southern part of the state where the sites are being proposed. People of color would be disproportionately affected if the Eddy Lee/Holtec CIS site were licensed and constructed.

New Mexico and Texas do not consent to either proposed CIS facility and are fighting to avoid the environmental injustice and the unnecessary shipment of irradiated high-level nuclear waste through their communities.

NRC Environmental Report

Here's the Federal Register Notice

Consolidated Interim Storage Handout

A Better Option: Hardened On-Site Storage (HOSS)

Hardened On-Site Storage

Overview

Hardened On-Site Storage (HOSS) is a community-based concept that aims to protect the public from the threats posed by the current vulnerable storage of commercial irradiated fuel.


History

For decades, high level radioactive waste has accumulated at reactor sites and continues to do so as nuclear reactors generate more waste. Without a credible plan to permanently isolate it, storage pools, where irradiated nuclear waste is currently stored until it becomes less hot, have been tightly packed and re-racked to accommodate all the waste.

Unfortunately, the pools and dry casks have no robust containment. If the cooling pumps stopped operating or the water in the pools drained out, temperatures would quickly increase, as happened in Fukushima Japan, and could result in a similar disaster.

cask storage at reactor sites
Current dry cask storage at reactor sites (pictured above) is extremely vulnerable. There is often nothing more than a chain-link fence and a short distance that separates the highly radioactive waste containers and public access.

Establishing interim hardened on-site storage (HOSS) is a top priority. Hardened on-site storage allows waste generators to store high level waste as close to the site of generation as possible, thereby exposing fewer people to radiation, as safely as possible.

Rather than storing dozens of vulnerable dry-casks next to each other in the open air, the HOSS Principles established by concerned citizens mandate:

  • Irradiated fuel must be stored as safely as possible as close to the site of generation as possible;
  • HOSS facilities must not be regarded as a permanent waste solution, and thus should not be constructed underground and the waste must be retrievable;
  • The facility must have real-time radiation and heat monitoring for early detection of problems with containers;
  • The overall objective of HOSS should be that the amount of releases projected in even severe attacks should be low enough that the storage system would be unattractive as a terrorist target;
  • Placement of individual canisters that makes detection difficult from outside the site boundary.

Hardened On-Site Storage (HOSS) is supported by organizations in all 50 states. The Principles of Securing Nuclear Waste at Nuclear Reactor Sites are posted here. It would provide better security at reactor sites with robust dry storage and community oversight, including real-time monitoring of heat and radiation. HOSS is rooted in values of community protection and environmental justice and will provide increased protection from human or natural disasters, like terrorist attacks and earthquakes

HOSS facilities are not permanent waste solutions, and therefore should not be constructed deep underground as the waste must be retrievable. However, they are a workable solution that will allow us to explore scientifically sound, and socially and environmentally just long-term management systems.

Nuclear Power Has No Place in a Green Energy Future

Because of: Time Delay, Success of Renewables, Huge Costs, Dangers, Weapons Connection, and Wastes

from Yahoo News, 21 Oct 21, ”…….Practical concerns also temper enthusiasm for a nuclear future. The next generation of reactors, heralded as a game changer by supporters, still haven’t been proven in the real world. Even if those technologies are as revolutionary as advertised, skeptics say it could take decades before they make a real difference in the global energy grid — too long if the worst outcomes of climate change are to be avoided.

Renewable energy technologies can be enough on their own
“The drawbacks to nuclear are compounded by the burgeoning success of renewables — both solar and wind are getting cheaper and more efficient, year after year. There is also a growing realisation that a combination of renewables, smart storage, energy efficiency and more flexible grids can now be delivered at scale and at speed — anywhere in the world.” — Jonathon Porritt, Guardian

The world doesn’t have time to wait for next-gen nuclear
“When it comes to averting the imminent effects of climate change, even the cutting edge of nuclear technology will prove to be too little, too late. Put simply, given the economic trends in existing plants and those under construction, nuclear power cannot positively impact climate change in the next ten years or more.” — Allison Macfarlane, Foreign Affairs

A major ramp-up in nuclear technologies isn’t economically feasible
“While nuclear power may have once been cheaper than wind or solar, the economics have since changed dramatically. Nuclear power plants are very expensive to build and the economics of nuclear power are getting steadily worse. By contrast, renewables continue to come down in price.” — Ian Lowe, Conversation

There’s no way to guarantee that nuclear plants will be safe
“People around the world have witnessed the Three Mile Island, Chernobyl and Fukushima accidents. It is more than enough to believe that a safe nuclear power plant is nothing but a myth.” — Jang Daul, Korea Times

More nuclear power could lead to more nuclear weapons
“Some nations — India and Pakistan, and in all probability Israel — became nuclear powers after originally seeking nuclear technology for research or to develop nuclear power. … This is important: The technology used to turn on lights or charge mobile phones shouldn’t need to involve national or international defence apparatus.” — Editorial, Nature

Nuclear waste is still a major problem
“Nuclear waste lasts for hundreds of thousands of years before they are half-decayed. Our United States government — perhaps the longest continuous government in the world — is only 232 years old. Who will be around to manage uranium wastes?” — David Ross, Courier-Journal

Atomic Histories & Nuclear Testing

LANL’s Central Mission: Los Alamos Lab officials have recently claimed that LANL has moved away from primarily nuclear weapons to “national security”, but what truly remains as the Labs central mission? Here’s the answer from one of its own documents:

LANL’s “Central Mission”- Presented at: RPI Nuclear Data 2011 Symposium for Criticality Safety and Reactor Applications (PDF) 4/27/11

It seems we can’t find what you’re looking for. Perhaps searching can help.

NukeWatch Compilation of the DOE/NNSA FY 2020 Budget Request – VIEW

LANL Heading Down Slippery Slope With Proposed Biosafety Lab

The DOE Inspector General released Audit Report on “Management of the National Nuclear Security Administration’s Biosafety Laboratories” that calls for a re-evaluation of the proposed needs for Biolabs at nuclear weapons facilities such as Los Alamos.

The report stated that Los Alamos National Laboratory was considering a $9.5 million expansion of bio-laboratory capabilities even though the Lab could not assess current usage or future needs. Apparently the Lab based facility-planning decisions on perceptions about future demand.

From the report –

[DOE] identified the development of a BSL-3 facility at LANL as its preferred alternative for meeting biosafety laboratory needs even though it had not fully considered the need for and cost effectiveness of additional capacity. Nor, had it developed a sound basis for measuring the utilization of existing facilities – a critical factor in determining the need for additional capacity.

Biological containment levels range from BSL-1, which handles only agents not known to cause illness in humans, to BSL-4, which houses agents for which there are no known cures, such as Ebola. A BSL-3 designation permits work with virulent pathogens used in both defensive and offensive biological warfare research.

Although the BSL-3 building has been constructed, the need is very questionable. From the report –

Specifically, we contacted two of the three Federal agencies that LANL told us were prospective [Work For Other] WFO customers and officials representing those potential customers stated that they did not have any specific plans to contract for BSL-3 research at LANL. Further, officials at both agencies indicated that other existing BSL-3 facilities could satisfactorily meet their needs. In fact, one official told us that generally other existing BSL-3 laboratories were less expensive than expected at the new LANL facility and that several had comparable security.

While the BSL-3 building has been constructed, there is no compliance with the National Environmental Policy Act (NEPA).  The draft Environmental Impact Statement (EIS) currently being prepared for BSL-3 facility operations pursuant to NEPA has not even been released, much less a final EIS or Record of Decision (ROD).  The current schedule calls for the EIS to be released in August 2014, but if past schedule changes are indications, it is not going to happen.

The draft EIS has been in process for nine years and counting. We at NukeWatch demand that DOE start over and re-scope both the alternatives and need for the BSL-3 at LANL. LANL is working on a Biological Research Capability Assessment to assess bioscience needs, which must be completed before the BSL-3 is re-scoped.

We hope the current Assessment is more empirical than the 2011 Review, which proposed that the BSL-3 facility was essential to LANL’s mission without considering data such as available capacity at other locations and estimates of projected use from outside customers.

The LANL BSL-3 EIS was the result of a lawsuit. During 2001 and 2002 NukeWatch contested the arbitrary and capricious public process DOE was using to justify its decision to build the proposed BSL-3 facilities at LANL and Lawrence Livermore National Laboratory (LLNL). DOE failed to adequately address the many concerns raised by the public and proceeded to release final Environmental Assessments (EAs) for both laboratories, along with so-called Findings of No Significant Impact, which gives the Department the green light to begin the first steps leading to operations. Because DOE left so many legitimate questions and concerns unanswered, NukeWatch felt that a legal challenge was necessary.

In August 2003 NukeWatch and Tri-Valley CAREs, a citizens group based in Livermore, CA, jointly filed a lawsuit in the federal district court of northern California claiming that DOE had failed to fully analyze the environmental and health risks associated with the proposed operation of its BSL-3 facilities at LANL and LLNL. In effect, DOE wrote itself a blank check for a wide range of infectious disease research at the two labs. NukeWatch and Tri-Valley CAREs argued that DOE failed to consider the grave risks of introducing pathogens whose behavior may not be known or understood, and for which a cure may not exist.

In January 2004, DOE announced that it had revoked approval for its newly constructed, advanced bio-warfare agent research facility at Los Alamos. DOE went back to square one, and reviewed whether the agency needed to undertake a full Environmental Impact Statement – a key demand in the lawsuit. The BSL-3 at LLNL was built and is operating.

DOE released a notice for the LANL EIS on November 29, 2005. The Notice of Intent to prepare an EIS for the BSL-3 stated that one reason requiring preparation of an EIS was that “it was necessary to conduct additional seismic analysis of the location of the building on fill material on the sloping side of a canyon.” This calls into question not just whether BSL-3 activities can be safely conducted before these issues are resolved through the EIS, but whether any operations can be safely conducted at all.

The drawing below shows the LANL BSL-3 built in a seismic zone, on fill, and on a steep slope.

Review of the Stability Analysis for the LANL BSL-3 Building Foundation, UCRL-TR-226737, November 2, 2006


The DOE-IG report stated that LANL would need to spend about $437,000 in upgrades to attempt to mitigate this seismic concern.  DOE also is spending about $478,000 to complete the now required Environmental Impact Statement

Another $595,000 is needed to open the facility, which includes $368,000 of operating costs for maintenance, utilities, etc.

Can the Laboratory be the best place for bioscience? If the Lab is looking for more funding streams, shouldn’t it be directing its attention to non-proliferation programs and cleanup?

 

LANL FY 2020 Budget Request – VIEW

Sandia FY 2020 Budget Request – VIEW

Livermore Lab FY 2020 Budget Chart – Courtesy TriValley CAREs – VIEW

Updates

It seems we can’t find what you’re looking for. Perhaps searching can help.

________________________________

Click the image to view and download this large printable map of DOE sites, commercial reactors, nuclear waste dumps, nuclear transportation routes, surface waters near sites and transport routes, and underlying aquifers. This map was prepared by Deborah Reade for the Alliance for Nuclear Accountability.

Nuclear Watch Interactive Map – U.S. Nuclear Weapons Complex

Waste Lands: America’s Forgotten Nuclear Legacy

The Wall St. Journal has compiled a searchable database of contaminated sites across the US. (view)
Related WSJ report: https://www.wsj.com

Atomic Histories & Nuclear Testing

NukeWatch Compilation of the DOE/NNSA FY 2020 Budget Request – VIEW

LANL Heading Down Slippery Slope With Proposed Biosafety Lab

The DOE Inspector General released Audit Report on “Management of the National Nuclear Security Administration’s Biosafety Laboratories” that calls for a re-evaluation of the proposed needs for Biolabs at nuclear weapons facilities such as Los Alamos.

The report stated that Los Alamos National Laboratory was considering a $9.5 million expansion of bio-laboratory capabilities even though the Lab could not assess current usage or future needs. Apparently the Lab based facility-planning decisions on perceptions about future demand.

From the report –

[DOE] identified the development of a BSL-3 facility at LANL as its preferred alternative for meeting biosafety laboratory needs even though it had not fully considered the need for and cost effectiveness of additional capacity. Nor, had it developed a sound basis for measuring the utilization of existing facilities – a critical factor in determining the need for additional capacity.

Biological containment levels range from BSL-1, which handles only agents not known to cause illness in humans, to BSL-4, which houses agents for which there are no known cures, such as Ebola. A BSL-3 designation permits work with virulent pathogens used in both defensive and offensive biological warfare research.

Although the BSL-3 building has been constructed, the need is very questionable. From the report –

Specifically, we contacted two of the three Federal agencies that LANL told us were prospective [Work For Other] WFO customers and officials representing those potential customers stated that they did not have any specific plans to contract for BSL-3 research at LANL. Further, officials at both agencies indicated that other existing BSL-3 facilities could satisfactorily meet their needs. In fact, one official told us that generally other existing BSL-3 laboratories were less expensive than expected at the new LANL facility and that several had comparable security.

While the BSL-3 building has been constructed, there is no compliance with the National Environmental Policy Act (NEPA).  The draft Environmental Impact Statement (EIS) currently being prepared for BSL-3 facility operations pursuant to NEPA has not even been released, much less a final EIS or Record of Decision (ROD).  The current schedule calls for the EIS to be released in August 2014, but if past schedule changes are indications, it is not going to happen.

The draft EIS has been in process for nine years and counting. We at NukeWatch demand that DOE start over and re-scope both the alternatives and need for the BSL-3 at LANL. LANL is working on a Biological Research Capability Assessment to assess bioscience needs, which must be completed before the BSL-3 is re-scoped.

We hope the current Assessment is more empirical than the 2011 Review, which proposed that the BSL-3 facility was essential to LANL’s mission without considering data such as available capacity at other locations and estimates of projected use from outside customers.

The LANL BSL-3 EIS was the result of a lawsuit. During 2001 and 2002 NukeWatch contested the arbitrary and capricious public process DOE was using to justify its decision to build the proposed BSL-3 facilities at LANL and Lawrence Livermore National Laboratory (LLNL). DOE failed to adequately address the many concerns raised by the public and proceeded to release final Environmental Assessments (EAs) for both laboratories, along with so-called Findings of No Significant Impact, which gives the Department the green light to begin the first steps leading to operations. Because DOE left so many legitimate questions and concerns unanswered, NukeWatch felt that a legal challenge was necessary.

In August 2003 NukeWatch and Tri-Valley CAREs, a citizens group based in Livermore, CA, jointly filed a lawsuit in the federal district court of northern California claiming that DOE had failed to fully analyze the environmental and health risks associated with the proposed operation of its BSL-3 facilities at LANL and LLNL. In effect, DOE wrote itself a blank check for a wide range of infectious disease research at the two labs. NukeWatch and Tri-Valley CAREs argued that DOE failed to consider the grave risks of introducing pathogens whose behavior may not be known or understood, and for which a cure may not exist.

In January 2004, DOE announced that it had revoked approval for its newly constructed, advanced bio-warfare agent research facility at Los Alamos. DOE went back to square one, and reviewed whether the agency needed to undertake a full Environmental Impact Statement – a key demand in the lawsuit. The BSL-3 at LLNL was built and is operating.

DOE released a notice for the LANL EIS on November 29, 2005. The Notice of Intent to prepare an EIS for the BSL-3 stated that one reason requiring preparation of an EIS was that “it was necessary to conduct additional seismic analysis of the location of the building on fill material on the sloping side of a canyon.” This calls into question not just whether BSL-3 activities can be safely conducted before these issues are resolved through the EIS, but whether any operations can be safely conducted at all.

The drawing below shows the LANL BSL-3 built in a seismic zone, on fill, and on a steep slope.

Review of the Stability Analysis for the LANL BSL-3 Building Foundation, UCRL-TR-226737, November 2, 2006


The DOE-IG report stated that LANL would need to spend about $437,000 in upgrades to attempt to mitigate this seismic concern.  DOE also is spending about $478,000 to complete the now required Environmental Impact Statement

Another $595,000 is needed to open the facility, which includes $368,000 of operating costs for maintenance, utilities, etc.

Can the Laboratory be the best place for bioscience? If the Lab is looking for more funding streams, shouldn’t it be directing its attention to non-proliferation programs and cleanup?

 

LANL FY 2020 Budget Request – VIEW

Sandia FY 2020 Budget Request – VIEW

Livermore Lab FY 2020 Budget Chart – Courtesy TriValley CAREs – VIEW

NUCLEAR POWER

Important Documents & Articles Related to Nuclear Energy Production

Most Recent

It seems we can’t find what you’re looking for. Perhaps searching can help.

Nuclear Watch Interactive Map – U.S. Nuclear Weapons Complex

Waste Lands: America’s Forgotten Nuclear Legacy

The Wall St. Journal has compiled a searchable database of contaminated sites across the US. (view)
Related WSJ report: https://www.wsj.com

LANL’s Central Mission: Los Alamos Lab officials have recently claimed that LANL has moved away from primarily nuclear weapons to “national security”, but what truly remains as the Labs central mission? Here’s the answer from one of its own documents:

LANL’s “Central Mission”- Presented at: RPI Nuclear Data 2011 Symposium for Criticality Safety and Reactor Applications (PDF) 4/27/11