GAO: Lab faces four-year delay, cost growth for making nuclear bomb cores

“The agency spending more on pit production than originally envisioned isn’t technically a cost overrun because no funding baseline was ever established…This means there’s no benchmark anyone can point to and say the agency has spent too much, she said, which in turn leaves funding for pits open-ended.”

By Scott Wyland [email protected] THE SANTA FE NEW MEXICAN | August 19, 2023 santafenewmexican.com

View/Download: GAO report on NNSA projects

Federal officials estimate Los Alamos National Laboratory won’t produce 30 nuclear bomb cores until 2030 — four years after the legally required deadline.

A plutonium pellet, “illuminated by its own energy,” according to the Department of Energy. DOE

The additional time needed to produce 30 bowling-ball-sized warhead triggers, known as pits, will cost the lab significantly more than originally estimated, a government watchdog said in a newly released report.

The agency in charge of the country’s nuclear arsenal estimates in the Government Accountability Office report it will take until 2030 for the Los Alamos lab’s plutonium facility to be capable of making 30 pits.

Scroll to top