Can it possibly cost $29 billion to clean up 51 acres? (That’s $568.6 million per acre!) The answer is yes if the estimate comes from Los Alamos National Laboratory.
NukeWatch has run cost comparisons between the estimate for Area G and two other excavation projects at the Lab. At six acres, excavation of Materials Disposal Area B is almost complete, so we have hard costs. (It is around $22.7 million per acre.) An evaluation of Materials Disposal Area Cwas released this September. The estimated costs for excavation of the 11.8-acre site came out to be $66.7 million per acre. View the cost comparison