Federal inspection of Pilgrim plant finds only ‘minor’ violations

A federal inspection of the decommissioned Pilgrim Nuclear Power Station in Plymouth that began in July and stretched through September found “no violations of more than minor significance,” the U.S. Nuclear Regulatory Commission said.

By Colin A. Young, State House News Service PATRIOT LEDGER NEWS patriotledger.com

alt="Dry casks holding spent fuel assemblies are shown outside the Pilgrim Nuclear Power Station before its May 2019 shutdown. Owner Holtec International has reached an agreement with the state to ensure safe decommissioning of the plant and cleanup of the site."
Dry casks holding spent fuel assemblies are shown outside the Pilgrim Nuclear Power Station before its May 2019 shutdown. Owner Holtec International has reached an agreement with the state to ensure safe decommissioning of the plant and cleanup of the site. Cape Cod Times File Photo

The inspection included “an evaluation of the safety screening, safety review, onsite management review, engineering change processes, the fire protection program, maintenance program, and the available results for site radiological and non-radiological characterization,” the Nuclear Regulatory Commission said. The agency also conducted “a review and observation of the independent spent fuel storage installation (ISFSI) dry cask activities.”

Inspectors visited Pilgrim at least five times during the announced quarterly inspection to observe Holtec Decommissioning International’s activities “as they relate to safety and compliance with the commission’s rules and regulations” and the conditions of the company’s license.

“Based on the results of this inspection, no violations of more than minor significance were identified,” the Nuclear Regulatory Commission wrote in the inspection report.

The Plymouth nuclear plant, which employed about 600 people and had been generating about 680 megawatts of electricity per year since coming online in 1972, permanently ceased operations May 31, 2019.

Holtec has estimated that it can complete decommissioning work by the end of 2027.

Scroll to top