NukeWatch Pushes Environment Department for More Public Input in Los Alamos Cleanup

NukeWatch Pushes Environment Department for More Public Input in Los Alamos Cleanup

An in-depth article, Consent order facing changes, by Mark Oswald in the Albuquerque Journal (October 9, 2015) lays out how legacy waste cleanup at Los Alamos National Laboratory (LANL) is being negotiated between DOE and the NM Environment Department (NMED) without the fully required public participation. The 2005 Consent Order (CO), which addresses the fence-to-fence cleanup of hundreds of thousands of cubic meters of Cold War legacy radioactive and hazardous waste in the ground at the Lab, was due to reach it’s final milestone this December. For many reasons, including the closure of WIPP due to improper radioactive waste drum packing practices at LANL, the December 2015 deadline will not be meet.

Please don’t think that, just because deadlines were not reached that it was a failure. Much progress on cleanup at LANL was made under the 2005 Consent Order. About 2,100 cleanup sites were originally identified, ranging from small spills to large landfills. Cleanup of about half of the sites has been completed. Initial investigation of about 90 percent of the remaining sites has been completed. Many cleanup alternatives were also investigated at the remaining sites and options have been presented. A groundwater monitoring well infrastructure was installed, with more monitoring wells on the way.

In Oswald’s article, NMED’s Kathryn Roberts stated that, “The 2005 deal was focused on investigative work and characterization of LANL’s legacy waste.” We at NukeWatch, feel that the goal of the 2005 Consent Order was always the cleanup of LANL and that the investigations and characterization of the many waste sites were just the first steps. There are milestones in the CO, with dates, for the actual cleanup of all the legacy waste sites at Los Alamos. The lab’s final “milestone” from the 2005 Consent Order was supposed to be a “remedy completion report,” due on Dec. 6, on how Area G, the Lab’s largest waste site, had been cleaned up.

NMED and DOE/LANL are negotiating the new CO now and have publically stated plans to rollout the draft for the new CO this November for a 60-day public comment period. Nuclear Watch NM believes that these negotiations must have public input.

This gets us to one of our main reasons why we feel the need for more public input. We are concerned that the new CO will not have enforceable milestones for all cleanup projects from the beginning. Deciding every 1 to 3 years which sites will be addressed for a cleanup ‘campaign’ and then what that schedule should be will insure that Los Alamos never addresses all the sites. This would revert cleanup back to the way it was done before the 2005 Consent Order with budget driving cleanup. But the purpose of the CO is to have cleanup drive the budget.  A schedule for all cleanups must be set from the beginning and the Lab must be held accountable every step along the way by getting the money and doing the work on time.

We will insist on a new final compliance date for the last milestone of the last legacy cleanup project. Cleanup at Los Alamos cannot be open-ended.

NukeWatch’s September 21 letter to NMED that explains our position that a “Class 3 Permit Modification” is required is here.

The 2005 Consent Order, as modified, is here.

 