New Nuclear Facility – An Attempt to Divide and Conquer

During our March 3, 2010 CMRR public meeting in Los Alamos, the CMRR DOE Project Manager told us the the final estimate for the CMRR Nuclear Facility was scheduled for 2014. Additionally we learned that the CMRR Project as a whole is planning to segment some of the work into smaller projects with their own separate schedules for estimates and construction.
This project and cost segmentation concerns us in that much of the preliminary (but huge) infrastructure construction will be completed before the final cost estimates of the CMRR-NF are available.
The Infrastructure Package Construction, including the concrete batch plant, utilities, excavation, etc., will be completed in 2013. The road relocation and the basemat, which includes 225,000 cubic yards of concrete, are also scheduled to be completed in 2013. Even the structural concrete for the building itself, another 130,000 yds3 of concrete, is due to start before estimated final project costs are available.
The current cost estimates for the entire CMRR Project are now pegged at $4.5 billion (from an original $660 million in 2004), but are also listed as “TBD” in the NNSA FY11 budget request, in other words still not known. To allow the infrastructure to be completed, or even started, before final cost estimates for the Nuclear Facility are complete would condone the NF being built at any price.
We request that Congress strongly pressure NNSA in the authorization and appropriations processes for final CMRR Project cost estimates, and bar NNSA from proceeding with major infrastructure investments for the Nuclear Facility until those final Project cost estimates are provided.
Scroll to top