NNSA Releases Expanded 2012 Performance Evaluation Reports

In response to a request from Nuclear Watch New Mexico, the National Nuclear Security Administration has released to us expanded versions of the 2012 Performance Evaluation Reports (PERs) for seven nuclear weapons complex sites. (The report for the Savannah River Site was not given to us.) The reports are used by NNSA to decide how much Award Fee it will give its nuclear weapons site contractors each year.

Design issues for the proposed Uranium Processing Facility (UPF) cost taxpayers over a 1/2 billion dollars. A statement from the Oak Ridge Environmental Peace Alliance (OREPA) sheds light on the FY2012 Y-12 Performance Evaluation Report

NNSA admitted publicly in October, five months after it first learned about it, that it had run into a “space/fit issue” with the UPF design. The building, as it approached 80% design completion, would not hold all the equipment it needs to hold…
“The engineering plan delivered on October 19, reported a TPC cost impact of $539M and 13 month impact to the overall project schedule as a result of the Space/Fit issue, effectively using 45% of the NNSA contingency established during CD-1 Reaffirmation in April.” (Performance Evaluation Report for Babcock and Wilcox Y-12 Technical Services, LLC, Evaluation Period: October 1, 2011 through September 30, 2012, p.7)

…more soon…