New Plutonium Facility Estimate Embraces $4.5 Billion

Buried in Volume 1 of the Department of Energy’s FY 2011 Congressional Budget Request are the Details of Project Cost Estimate for LANL’s proposed Chemistry and Metallurgy Research Building Replacement (CMRR) Project. (Pg.226 & 227)

The Details –

$164 million –       The cost of the Radiological Laboratory/Utility/Office Building (RLUOB) recently finished with construction

$199 million –       The estimated cost of equipment for the RLUOB scheduled to be installed by 2013.

$3.4 billion –          The current estimate of the Proposed Nuclear Facility due to be completed in 2018.

$782 million –       “Contingency”

$4.5 Billion –         Total

This does not D&D of the existing CMR (estimated at $500 million).

DOE Fails to Make Minimum Payment on Environmental Cleanup

Last I looked, the Cold War ended 18 years ago. We won. OK, I used to think we won, but there is still a big debt that needs to be paid off before any victory party.

The Department of Energy’s Agency Financial Report for Fiscal Year 2009 (Pg.52) gives some sobering figures. Even with extra Recovery funding ($5.1 billion) and all the usual appropriations (about $6 billion) the Department’s “total unfunded environmental cleanup and disposal liabilities” still increased by over $1 billion in 2009. The current estimate for the cleanup of environmental contamination resulting from past operations of the nuclear weapons complex is $262.7 billion. Given that this estimate will surely increase yearly, at this rate, DOE will pay off its existing Cold War environmental liability, well…never.

Yet the Department continues on a shopping spree and rings up new $4 billion facilities that will generate new wastes. DOE must stop creating new waste when the legacy waste is still posing a threat, and should greatly increase the annual cleanup funding at least until it starts to make a dent in the amount owed. Until then, somebody please, cut up the credit card.

More from the Agency Financial Report for Fiscal Year 2009 –

“At all sites where these activities took place, some environmental contamination occurred. This contamination was caused by the production, storage, and use of radioactive materials and hazardous chemicals, which resulted in contamination of soil, surface water, and groundwater. The environmental legacy of nuclear weapons production also includes thousands of contaminated buildings and large volumes of waste and special nuclear materials requiring treatment, stabilization, and disposal. Approximately one-half million cubic meters of radioactive high-level, mixed, and low-level wastes must be stabilized, safeguarded, and dispositioned, including a quantity of plutonium sufficient to fabricate thousands of nuclear weapons. “ (Pg.52)

Despite Non-Proliferation Pledge – $7B for Nuclear Arsenal

February 2, 2010 – Democracy Now!’s Amy Goodman interviews Jay Coghlan of Nuclear Watch

AMY GOODMAN: All forty Republican senators, as well as Joseph Lieberman, implied in a letter to Obama last month that they would block ratification of the new treaty with Russia unless he funds a, quote, “modern” warhead and new facilities at the Los Alamos National Lab, where you’re near right now in New Mexico, and the Y-12 plant in Oak Ridge, Tennessee. Jay?

JAY COGHLAN: You’re absolutely right. They’re playing muscle, and they’re rolling Obama and Biden. The Democrats are now surrendering. The executive administration is now surrendering to that demand.

…how is the US now going to walk in with a straight face, walk into the UN, and claim that it’s leading towards a world free of nuclear weapons, when in fact we are starting up a plutonium facility in Los Alamos, a uranium facility in Tennessee, but also a major new production plant in Kansas City for all of the non-nuclear components that go into a weapon?

So, basically, the US is revitalizing its nuclear weapons production base. And again, the laboratories, mark my words, and as the Republicans already wrote, they’re calling for or attempting to demand a, quote, “modern” warhead, that means new designs.

Update – Lab Shipment Scare at Sunport

Phil Parker at the Journal gives an update.

The package was labeled “explosives” on the inside, so the cargo handlers were rightfully concerned when their alarms went off. The cargo facility was closed for about four hours during the incident.

It was reported  that , “The containers are usually shipped via ground transportation but sometimes, he [LANL spokesperson] said, they’re sent by air.” I’m guessing that it costs more to send it by air, not to mention the extra cost of wasting time of the Albuquerque Police Department bomb squad, the cargo handlers, and Lab personnel.

The Journal reported, “Security at the airport didn’t know about the arrangement. “Apparently it was just a misunderstanding,” said airport spokesperson Daniel Jiron.” Once again, the Lab deflects any responsibility.

Lab Tries To Ship Explosives on Commercial Airline

KOB TV 4 broke the story and is still has the only account as best as I can tell. Read report and see video here.

Los Alamos National Laboratory sent an 8’ package labeled “explosives” to the Sunport to be flown to California on Southwest Airlines (where bags fly free). A sensor alarm alerted the cargo handlers to “a small amount of trace explosives” and the package never made it to the plane. It was reported that no flights were delayed and there was no danger. It was also reported that the Lab meant to ship the package by ground.

The danger here is that the Lab which is entrusted with the nation’s nuclear secrets cannot ship a package correctly. It was an 8’ package labeled “explosives.” It’s not like it got accidently mixed in with other packages and put on the wrong truck.

The public deserves all the facts. How did the “mix-up” occur? Has the Lab shipped similar packages before? What type of “explosive” label did the package have on it? Did it meet all shipping standards for explosives? Did the explosives pose a detonation hazard? Could the package really have been shipped by ground? How does an 8’ package labeled “explosives” even get unloaded into the air cargo building?

Lab’s Cyber Security Still Not Trustworthy

A GAO Report released Friday the 13th found that “significant information security control weaknesses remain on LANL’s classified computer network. LANL had vulnerabilities in several critical areas, including (1) identifying and authenticating the identity of users, (2) authorizing user access, (3) encrypting classified information, (4) monitoring and auditing compliance with security policies, and (5) maintaining software configuration assurance.”

The report explains that LANL spent approximately $433 million from fiscal years 2001 through 2008 to operate, maintain, protect, and procure equipment for its classified computer network. The largest expenditure for the classified computer network was for high-performance computing, which accounted for $322 million (or 74 percent) of total expenditures. LANL began to expand the classified computer network in 2005, accounting for $48 million (or 11 percent) of total expenditures during the fiscal year 2001 through fiscal year 2008 period. Expenditures for special initiatives, such as the Integrated Cyber Security Initiative and Multi-Platform Trusted Copy program, accounted for $19 million (or 4 percent) of total expenditures. The core classified cyber security program, which serves as the foundation of LANL’s protection strategy for the classified cyber security program, accounted for $45 million (or 10 percent) of total expenditures over the period.

Clearly, the Lab was more focused on high-performance computing rather than focusing on protecting the nation’s nuclear secrets, or maybe the Lab thought everything was OK.

This GAO report comes after the DOE Office of Enforcement devoted significant attention to monitoring compliance with a Secretarial Compliance Order that was issued in July 2007. Specifically, the DOE Secretary directed the contractor for the Los Alamos National Laboratory – Los Alamos National Security, LLC – to remediate deficiencies that contributed to a breach of classified information security controls and to correct longstanding deficiencies associated with classified information security, and classified and unclassified cyber security programs. Los Alamos National Laboratory reported that the actions were completed by December 2008, and the DOE Los Alamos Site Office formally validated completion of the required actions.

But problems were still not corrected. To satisfy the above July 2007 DOE Compliance Order, the laboratory reaccredited all classified computer systems. During 2008, as part of its reaccredidation process, LANL revised risk assessments for classified computer systems and included the results in the system security plans. However, of the five system security plans the GAO reviewed, one plan’s risk assessment did not adhere to the latest methodology and did not include evidence of a comprehensive threat analysis, as required by DOE. Furthermore, the remaining four plans noted that all known threats and vulnerabilities were not evaluated to determine risks. Without comprehensive risk assessments, risks to certain systems may be unknown and appropriate controls may not be in place to protect against unauthorized access to or disclosure of sensitive information, or disruption of critical systems and operations.

What’s the problem? A Special Report from the Government Computer News tells us –

According to data reported by the U.S. Computer Emergency Readiness Team (US-CERT), reported attacks on U.S. government computer networks climbed 40% last year, and more infiltrators are trying to plant malicious software they could use to control or steal sensitive data. Accounts of unauthorized access to government computers and installations of hostile programs rose from a combined 3,928 incidents in 2007 to 5,488 in 2008, The latest report, issued in February 2009, represented a small sampling – just 1% of federal agencies have fully developed tracking systems – and some of the uptick in reported attacks may be due to better reporting in the last year.

Government networks are targeted by foreign nations seeking intelligence, such as China and Russia, as well as criminal groups and individuals who may want to disrupt power, communication or financial systems. Some attackers are less interested in stealing data than in undermining a system’s ability to operate by planting software that could slow critical networks in emergencies. Security industry observers expressed alarm about phishing, in which seemingly legitimate e-mails solicit sensitive information, and ‘web redirects,’ which shunt a computer to a website where it downloads malicious software. According to reports, fewer attacks are being used to take down an organization’s entire IT system. Instead, attacks now penetrate IT systems without impairing them, primarily to siphon out sensitive information without detection.

Complete excavation of Area G now estimated at only $9.1 billion

Q: How much does it cost to cleanup a 65-acre, 50-year-old,  nuclear weapons laboratory unlined dump full of low-level radioactive waste (LLW), radioactively contaminated infectious waste, asbestos contaminated material, transuranic waste, polychlorinated biphenyls (PCBs), and much more?

A: About 8 years of the Lab’s nuclear weapons activities budget.

First, define cleanup. (Closure is the better term to use.)

The Lab recently submitted a revised (September 2009) corrective measures evaluation (CME) of Material Disposal Area (MDA) G, located within Area G of Technical Area 54, at Los Alamos National Laboratory to the NM Environment Department. The goal of the CME report was to recommend a corrective measures alternative for closure of the site and to address contamination releases in compliance with the March 1, 2005, Compliance Order on Consent (Consent Order).

This CME report screened 14 corrective measures alternatives based on their ability to meet the regulatory threshold and other qualitative screening criteria. Seven of the 14 alternatives evaluated met the screening criteria and capital costs were estimated:

1. Alternative 1B: maintenance of existing cover – $9.4 million;

2. Alternative 2B: evapotranspiration (ET) cover – $64.8 million;

3. Alternative 2C: ET cover with partial waste excavation – $46.5 million;

4. Alternative 2D: ET cover with partial waste excavation, targeted stabilization – $48 million;

5. Alternative 5B: complete waste excavation, waste treatment, off-site disposal – $9.1 billion (This is down from last year’s estimate of $20 billion.);

6. Alternative 5C: complete waste excavation, on-site waste treatment, disposal of wastes in a RCRA Subtitle C landfill – $6.1 billion; and

7. Alternative 5D: complete waste excavation, on-site waste treatment, disposal of wastes in a RCRA corrective action management unit – $6.1 billion.(All alternatives include monitoring and maintenance, and soil vapor extraction, but don’t include a 55% contingency.)

The Lab’s recommended corrective measures alternative is Alternative 2C.

The right thing to do would be Alternative 5B, complete waste excavation. The Lab could cover the $9.1 billion by redirecting the $1.2 billion it spends annually on nuclear weapons activities.

The hard-working folks over at NMED have to make the final decision, and there will be opportunities for public input.

Find the report MDA G CME R1 Sept 09 [Warning, it’s 14MB]

Operations at Plutonium Facility stood down due to fire suppression system

In the latest of a string of fire system deficiencies on Wednesday September 30th, LANL management declared the fire suppression system inoperable in PF-4 at TA-55. Facility activities were placed in stand-by mode, which were still stood down as of three weeks later on Oct. 23rd.

DNFSB explained that the stand down was based on recent hydraulic calculations that concluded the system does not achieve the water density coverage required. Basically, the sprinklers in 13 of approximately 100 fire suppression areas at PF-4 cannot meet the current required gallons per minute estimated to effectively extinguish a fire. (Read the Oct. 2nd-23rd DNFSB reports)

One has to wonder – What is the cost to the taxpayer of PF-4 being stood down for nearly a month?

These reports come on the heels of last week’s DNFSB recommendation that the Lab must immediately do something about its risk to the public of a seismically induced fire at PF-4, which was estimated to exceed the DOE guidelines by more than 100 times. In a worst-case situation, an earthquake-induced fire could set free enough breathable plutonium that a person on the perimeter of the facility would receive a lethal dose of radiation.

Speaking of seismically induced fires, I am reminded of a March 2007 LANL report, Seismic Fragility of the LANL Fire Water Distribution System (LA-14325), which explains how numerous valves in the fire water distribution system at the Lab would have to be manually closed to insure proper pressure to facilities on fire after a seismic event.

Granted, these may be low probability events, but they have high consequences. The Lab is playing with fire by not adequately funding upgrades to its existing fire systems now, before embarking construction of any new facilities.

Hikers, dogs found inside the fence

Summary Report of Occurrences Reviewed

From October 26 – 30, 2009
Near Miss –
NA – Los Alamos National Laboratory (Significance Category 3).
On October 22, a Water
Quality sampling crew discovered two hikers with three dogs at Technical Area 68 (TA-68)
during High Explosive (HE) Operations. The hikers were instructed to exit DOE property.
During interviews, the hikers stated they had hiked approximately one mile into TA-15.
During that time, TA-39-6 conducted two HE shots. A third shot scheduled for another shot
site was cancelled because of equipment issues. The hikers did not enter the TA-39-6 shot
Hazard Areas. Had the third shot been conducted, the hikers could have been within the
Hazard C Area with the potential for contamination or HE injury. A radiological control
technician surveyed the hikers and dogs for contamination. The contamination surveys
indicated no detectable activity and the hikers were released.

http://www.hss.energy.gov/csa/analysis/ll/occur/102609-103009.pdf

I’m glad everyone is OK, but I have some questions. The hikers clearly crossed a fence or a gate with one of those warning signs on it. There is no mention of security forces being called. The Lab has been busted for security issues many times in the past and can ill afford any more security problems. Is it possible that the Lab is trying to avoid having this incident count as a security violation? If they found me walking my dogs inside the fence, I’ll bet I would at get to explain my story to the guys in the black SUVs.


Los Alamos – Plutonium Center of Negligence

An October 27 press release from the Project on Government Oversight (POGO)
Defense Board Catches Los Alamos Trying to Dodge Plutonium Safety Vulnerability” revolves around a new Defense Nuclear Facilities Safety Board (DNFSB) revelation of public safety vulnerability and seismic issues at TA-55 (The Lab’s plutonium Technical Area).

The DNFSB has been very patient on the safety issues at TA-55. In a September 23, 2005 weekly report, they stated that LANL needed to try to justify a passive confinement strategy, continue plans to reduce radioactive materials, and to seismically upgrade the glove-box supports that have not already been upgraded. These issues are still unaddressed as of the latest DNFSB report.

Seismic issues run deep at Los Alamos. NNSA currently has plans to construct and operate the Chemistry and Metallurgy Research Replacement–Nuclear Facility (CMRR–NF) to support plutonium operations as a replacement for portions of the Chemistry and Metallurgy Research (CMR) facility, a 1950’s structure that faces significant safety and seismic challenges. In 1999, a fault was discovered under the old CMR building, which has been neglected, contaminated, and has several abandoned wings. This fault was the major reason given to build a new facility 1.2 miles away at TA-55.

The Lab has big plans for plutonium. In December 2008, NNSA released a Record of Decision for its Complex Transformation Environmental Impact Statement that keeps manufacturing and research and development involving plutonium at Los Alamos and blesses the building of the CMRR-NF. This decision was a combination of two alternatives – a Distributed Centers of Excellence and a Capability-Based alternative. But to compensate for the nearby fault lines, the CMRR-NF is now being designed with 10-foot thick concrete floors and there are plans being designed to pump grout into a layer of fragile volcanic ash under the proposed facility. Current construction estimates for this facility are $2 billion.

The Lab has been negligent in taking care of its plutonium flagship, TA-55. It has not been a good steward of plutonium missions. Los Alamos is the wrong location, seismically. Congress must seriously consider ending this unnecessary plutonium work.