National Nuclear Security Administration Gives Green Light For Expanded Plutonium Pit Production at Los Alamos

 For immediate release January 15, 2016

Contacts:       Jay Coghlan, NWNM, 505.989.7342, c. 505.470.3154, jay[at]nukewatch.org

National Nuclear Security Administration Gives Green Light

For Expanded Plutonium Pit Production at Los Alamos

Santa Fe, NM – Today the Defense Nuclear Facilities Safety Board, an independent agency commissioned by Congress, posted a weekly report that makes explicit a decision by the National Nuclear Security Administration (NNSA) to expand plutonium pit production at the Los Alamos National Laboratory (LANL). Plutonium pits are the fissile cores or “triggers” of modern two-stage thermonuclear weapons, but they are also atomic weapons in their own right (a plutonium bomb incinerated Nagasaki in August 1945). Plutonium pit production has always been the chokepoint preventing industrial-scale U.S. nuclear weapons production ever since a FBI raid investigating environmental crimes shut down the notorious Rocky Flats Plant near Denver in 1989.

Jay Coghlan, Nuclear Watch Director, commented, “Expanded plutonium pit production at the Los Alamos Lab is really all about future new-design nuclear weapons with new military capabilities produced through so-called Life Extension Programs for existing nuclear weapons.” The relevant case-in-point is that LANL is now tooling up to produce pits for one type of warhead (the W87) to use in an “Interoperable Warhead” that will combine two other warheads (the W78, a land-based ICBM warhead, and the W88, a sub-launched warhead), clearly a radically new design even if as claimed only existing nuclear weapons components are used.

Coghlan further commented, “The real irony is that this Interoperable Warhead has been delayed for at least five years, if not forever, because of its enormous estimated expense and Navy skepticism. Yet this doesn’t keep LANL and the NNSA from spending billions of taxpayer dollars to upgrade existing and build new production facilities for unnecessary and provocative expanded plutonium pit production.”

Specifically, NNSA and LANL seek to raise the administrative limit on plutonium in the existing Radiological Lab (“RLUOB” in the Safety Board report below) from an original 8.4 grams to 400 grams, and proceed with the “Plutonium Modular Approach project.” In 2012, in the face of exploding costs and rising citizen opposition, NNSA dropped its proposal to build a $6.5 billion Walmart-sized “Chemistry and Metallurgy Research Replacement Project-Nuclear Facility” for expanded plutonium pit production of up to 80 pits per year. There was no technical justification for this expanded production, other than unspecified “Department of Defense requirements.”

These new moves by NNSA and LANL, which will cost around $4 billion before the usual cost overruns, are just another way to achieve their goal of raising plutonium pit production to up to 80 plutonium pits per year. Raising the amount of plutonium in the Radiological Lab will enable LANL to conduct all needed analytical chemistry quality control samples of new pits, as the Safety Board memo says to “primarily support the increased capacity required for larger pit manufacturing rates.” The Plutonium Modular Approach project will be newly constructed underground facilities for hot operations such as a plutonium foundry, likely beginning with two modules at a billion dollars each. It should be noted that proposed major federal actions require the opportunity for public review and comment under the National Environmental Policy Act, which has not been done for what NNSA calls this alternative plutonium strategy. Nevertheless, increased funding for LANL’s plutonium infrastructure will be likely included in the pending federal budget for FY 2017, scheduled to be released Monday February 9.

There is no need for expanded plutonium pit production to maintain the safety and reliability of the existing nuclear weapons stockpile, but it is vital for future new-designs that the nuclear weaponeers want. In fact, the U.S. government is planning to spend a trillion dollars over the next 30 years to “modernize” and completely rebuild its nuclear forces, despite its pledge in the 1970 NonProliferation Treaty to enter into serious negotiations leading to nuclear disarmament.

Background

In 1996 the plutonium pit production mission was formally relocated to LANL, with an approved upper limit of 20 pits per year. NNSA has tried four times since then to expand plutonium pit production. This started with a proposed “Modern Pit Facility” capable of producing up to 450 pits per year, with no justification of why that Cold War-like level of production was needed. In all four cases, in response to successful citizen activism, Congress either rejected or NNSA dropped efforts to expand production, in large part because of a pit life study that New Mexico Senator Jeff Bingaman required at Nuclear Watch’s request. That 2006 study by independent experts found that plutonium pits last at least 100 years (with no proscribed end date), more than double NNSA’s previous estimates of 45 years.

Nevertheless, NNSA now seeks for the fifth time to expand plutonium pit production beyond the currently approved level of 20 pits per year at LANL. After having produced 30 pits for the W88 sub-launched warhead (which was in production when the Rocky Flats Plant was shut down), there are no current requirements for plutonium pit production to maintain stockpile safety and reliability.

In the meanwhile, funding for cleanup at the Los Alamos Lab is being cut, while nuclear weapons programs that caused the mess to begin with are thriving. As a final irony, these plans to expand plutonium pit production are now being implemented, despite the fact that 1) major operations at LANL’s main plutonium facility have been suspended since June 2013 because of nuclear criticality safety concerns; and 2) the Los Alamos Lab has no place to send its radioactive plutonium pit production wastes ever since it sent a drum that ruptured and closed down the multi-billion dollar Waste Isolation Pilot Plant.

Nuclear Watch New Mexico is confident that this latest attempt to expand plutonium pit production will fall apart as well, but only as a result of continuing strong citizen activism.

# # #

•           Relevant excerpt from Defense Nuclear Facilities Safety Board Weekly LANL Report:

http://www.dnfsb.gov/sites/default/files/Board%20Activities/Reports/Site%20Rep%20Weekly%20Reports/Los%20Alamos%20National%20Laboratory/2015/wr_20151218_65.pdf
Los Alamos Report for Week Ending December 18, 2015

MEMORANDUM FOR: S.A. Stokes, Technical Director FROM: R.K. Verhaagen and J.W. Plaue

DNFSB Staff Activity: R. L. Jackson was onsite to plan oversight activities associated with Plutonium Infrastructure Strategy. Accordingly, he met with key project staff and walked down the Plutonium Facility, the Chemistry and Metallurgy Research (CMR) building, and the Radiological Laboratory Utility Office Building (RLUOB).

Plutonium Infrastructure Strategy: Late last month, the Deputy Secretary of Energy approved a restructuring of the subprojects covered under the CMR Replacement project. There are now four subprojects: (1) RLUOB Equipment Installation, Phase 2; (2) Plutonium Facility Equipment Installation, Phase 1; (3) Plutonium Facility Equipment Installation, Phase 2; and (4) Re- categorizing the RLUOB to Hazard Category 3 with a material-at-risk limit of 400 g plutonium- 239 equivalent. The first two subprojects enable LANL to cease programmatic activities in the CMR by 2019, while the latter two subprojects primarily support the increased capacity required for larger pit manufacturing rates. The memo requests an updated project execution plan within 90 days and indicates approval authority will remain with the DOE Deputy Secretary for subprojects 2–4 and with the NNSA Administrator for subproject 1.

In a separate action, the DOE Deputy Secretary also approved the mission need Critical Decision (CD)-0 for the Plutonium Modular Approach project. This project addresses life extension needs for the existing Plutonium Facility in support of Department of Defense requirements and Congressional Direction. The CD-0 schedule range for project completion is December 2025 to December 2027.

 

•           For an extensive history of successful citizen activism against plutonium pit production see https://nukewatch.org/facts/nwd/Pit-Production-History.pdf

Why Do DOE And LANL Refuse To Do A Pit Production Study?

Why Do DOE And LANL Refuse To Do A Pit Production Study?

A recent Congressional Research Service (CRS) Report Manufacturing Nuclear Weapon “Pits”: A Decisionmaking Approach for Congress, August 15, 2014 attempts to present the amount of space needed at Los Alamos National Laboratory for the Lab to produce 80 plutonium pits per year. CRS has to do this estimating task because the Lab has never done this calculation.

It is unclear to us why the Lab has yet to do this calculation. The Lab claims to be the “Plutonium Center of Excellence for the Nation”  yet the CRS report explains that no one knows whether existing buildings, without modifications, could manufacture 80 plutonium pits per year (ppy); or if modest upgrades would suffice; or if major construction would be needed to augment the current capacity of about 10 ppy.

A plutonium pit is a nuclear weapon component that is a hollow plutonium shell that is imploded with conventional explosives to create a nuclear explosion that triggers the rest of the weapon. Some argue that the capacity to manufacture new pits may be needed to extend the service life of unneeded weapons, to replace broken pits (which never happens), and to hedge against possible unnamed geopolitical surprises where only more nukes will solve the problem. How many pits that the country actually needs to produce annually is beyond the scope of the CRS report. We believe it is zero.

Along with the unknown space requirements, the Lab also does not know how much Material At Risk (MAR a.k.a. plutonium) would be needed in the building to produce 80 ppy. “…these data have never been calculated rigorously.”

CRS created some charts for this report to show what they believe to be current usage of the Lab’s Plutonium Facility (PF-4). But what this looks like for 80 ppy is still a guess.

We at NukeWatch have been demanding that LANL produce this information — most recently in our 2011 comments on the Draft CMRR-NF Supplemental Environmental Impact Statement

We think two things a probably happening. There is still not a need for 80 pits per year (or any). And if the Lab were to finally do a pit production study, Congress would find out that LANL has enough space now.

The money should be used to clean up the Lab’s legacy Cold War waste.

Plutonium-238 needs should be met through accelerated nuclear weapons dismantlements

Wired Magazine’s alarmist article NASA’s Plutonium Problem Could End Deep-Space Exploration argues that virgin production of plutonium-238 in nuclear reactors is needed, or U.S. space exploration is dead. Instead the nation’s future Pu-238 needs should be met through accelerated nuclear weapons dismantlements and recycling/scrap recovery efforts.

Processing and encapsulation of Pu-238 currently takes place at the Los Alamos National Laboratory in northern New Mexico. [Having said that, all plutonium operations at the Lab have been shut down since the end of June because of nuclear criticality safety issues, which is a story in and of itself]. A Pu-238 scrap recovery line capable of recovering 2-8 kilograms per year was slated to start in 2005, but apparently has never become fully operational. In fact, LANL claimed in a 2008 site-wide environmental impact statement that it was capable of recycling/recovering up to 18 kilograms of Pu-238 per year, far more than needed to take care of the nation’s needs.

LANL has a large existing inventory of Pu-238 scrap material. Moreover, the Pantex Plant was supposed to ship radioisotope thermoelectric generators (RTGs) from dismantled nuclear weapons to the Lab to harvest Pu-238. That hasn’t happened either, we conjecture because the LANL’s scrap recovery line hasn’t been properly working (or perhaps never really started in the Lab’s troubled Plutonium Facility-4). Indeed, the government estimated that approximately 3,200 RTGs would become available for recycling between 2009 and 2022 through nuclear weapons dismantlements. Significantly, increased dismantlements could also supply sufficient recycled tritium for existing nuclear weapons instead of current military production in civilian reactors, a big nonproliferation no-no. But unfortunately dismantlements at the Pantex Plant are substantially blocked by exorbitant “Life Extension Programs” that extend the service lives of existing nuclear weapons by three decades or more while giving them new military capabilities.

Before the U.S. resumes virgin Pu-238 production, the government should make LANL straighten out its Pu-238 recovery operations. Safely that is, because Pu-238 is a very energetic gamma emitter and therefore very dangerous to handle. But the nation’s future Pu-238 needs should be met through accelerated nuclear weapons dismantlements (instead of Life Extension Programs) and recycling/scrap recovery efforts, not new virgin production in nuclear reactors.

 