No Lethal High-Level Waste To New Mexico

Background

No Nuclear Waste
Photo Courtesy of No Nuclear Waste Aqui

"The most toxic and dangerous type of radioactive waste created by the nuclear industry"

This is waste generated by nuclear power plants called 'high-level radioactive waste' (HLW), also known as 'spent' or 'irradiated' fuel. This waste contains plutonium, uranium, strontium, and cesium; and will be radioactive for millions of years.

It is not like the waste currently stored at the Waste Isolation Pilot Project (WIPP) or any other waste site that exists today in the U.S.: it is far worse.

Two companies are proposing to build waste facilities near Carlsbad and Hobbs for the most toxic and dangerous type of radioactive waste created by the nuclear industry.

Holtec International is working with the Eddy-Lea Energy Alliance, LLC (ELEA) to apply for a license to build a Consolidated Interim Storage (CIS) facility approximately halfway between Carlsbad and Hobbs, and 16 miles north of WIPP.

The Nuclear Regulatory Commission (NRC) has declared the Holtec/ELEA application complete, NRC initiated a public comment period with 60 days for public comment. Note that transport of this waste poses risks to the environment and all life located near transportation routes.

Holtec proposal:

  • New CIS facility to store 100,000 metric tons of HLRW, with the potential to increase to 120,000 metric tons for 120 years
  • Shallow sub-surface burial system

New Mexicans and Texans are fighting the attempted licensing of these two proposed CIS facilities - Waste Control Specialists near Andrews, Texas and Eddy Lee/Holtec International east of Carlsbad, New Mexico.

These sites and any transport to these sites are not only dangerous but environmentally unjust. These sites present clear examples of environmental racism.

New Mexico's demographic is largely Latino. There are many communities of color, especially in the southern part of the state where the sites are being proposed. People of color would be disproportionately affected if the Eddy Lee/Holtec CIS site were licensed and constructed.

New Mexico and Texas do not consent to either proposed CIS facility and are fighting to avoid the environmental injustice and the unnecessary shipment of irradiated high-level nuclear waste through their communities.

NRC Environmental Report

Here's the Federal Register Notice

Consolidated Interim Storage Handout

A Better Option: Hardened On-Site Storage (HOSS)

Hardened On-Site Storage

Overview

Hardened On-Site Storage (HOSS) is a community-based concept that aims to protect the public from the threats posed by the current vulnerable storage of commercial irradiated fuel.


History

For decades, high level radioactive waste has accumulated at reactor sites and continues to do so as nuclear reactors generate more waste. Without a credible plan to permanently isolate it, storage pools, where irradiated nuclear waste is currently stored until it becomes less hot, have been tightly packed and re-racked to accommodate all the waste.

Unfortunately, the pools and dry casks have no robust containment. If the cooling pumps stopped operating or the water in the pools drained out, temperatures would quickly increase, as happened in Fukushima Japan, and could result in a similar disaster.

cask storage at reactor sites
Current dry cask storage at reactor sites (pictured above) is extremely vulnerable. There is often nothing more than a chain-link fence and a short distance that separates the highly radioactive waste containers and public access.

Establishing interim hardened on-site storage (HOSS) is a top priority. Hardened on-site storage allows waste generators to store high level waste as close to the site of generation as possible, thereby exposing fewer people to radiation, as safely as possible.

Rather than storing dozens of vulnerable dry-casks next to each other in the open air, the HOSS Principles established by concerned citizens mandate:

  • Irradiated fuel must be stored as safely as possible as close to the site of generation as possible;
  • HOSS facilities must not be regarded as a permanent waste solution, and thus should not be constructed underground and the waste must be retrievable;
  • The facility must have real-time radiation and heat monitoring for early detection of problems with containers;
  • The overall objective of HOSS should be that the amount of releases projected in even severe attacks should be low enough that the storage system would be unattractive as a terrorist target;
  • Placement of individual canisters that makes detection difficult from outside the site boundary.

Hardened On-Site Storage (HOSS) is supported by organizations in all 50 states. The Principles of Securing Nuclear Waste at Nuclear Reactor Sites are posted here. It would provide better security at reactor sites with robust dry storage and community oversight, including real-time monitoring of heat and radiation. HOSS is rooted in values of community protection and environmental justice and will provide increased protection from human or natural disasters, like terrorist attacks and earthquakes

HOSS facilities are not permanent waste solutions, and therefore should not be constructed deep underground as the waste must be retrievable. However, they are a workable solution that will allow us to explore scientifically sound, and socially and environmentally just long-term management systems.

Nuclear Power Has No Place in a Green Energy Future

Because of: Time Delay, Success of Renewables, Huge Costs, Dangers, Weapons Connection, and Wastes

from Yahoo News, 21 Oct 21, ”…….Practical concerns also temper enthusiasm for a nuclear future. The next generation of reactors, heralded as a game changer by supporters, still haven’t been proven in the real world. Even if those technologies are as revolutionary as advertised, skeptics say it could take decades before they make a real difference in the global energy grid — too long if the worst outcomes of climate change are to be avoided.

Renewable energy technologies can be enough on their own
“The drawbacks to nuclear are compounded by the burgeoning success of renewables — both solar and wind are getting cheaper and more efficient, year after year. There is also a growing realisation that a combination of renewables, smart storage, energy efficiency and more flexible grids can now be delivered at scale and at speed — anywhere in the world.” — Jonathon Porritt, Guardian

The world doesn’t have time to wait for next-gen nuclear
“When it comes to averting the imminent effects of climate change, even the cutting edge of nuclear technology will prove to be too little, too late. Put simply, given the economic trends in existing plants and those under construction, nuclear power cannot positively impact climate change in the next ten years or more.” — Allison Macfarlane, Foreign Affairs

A major ramp-up in nuclear technologies isn’t economically feasible
“While nuclear power may have once been cheaper than wind or solar, the economics have since changed dramatically. Nuclear power plants are very expensive to build and the economics of nuclear power are getting steadily worse. By contrast, renewables continue to come down in price.” — Ian Lowe, Conversation

There’s no way to guarantee that nuclear plants will be safe
“People around the world have witnessed the Three Mile Island, Chernobyl and Fukushima accidents. It is more than enough to believe that a safe nuclear power plant is nothing but a myth.” — Jang Daul, Korea Times

More nuclear power could lead to more nuclear weapons
“Some nations — India and Pakistan, and in all probability Israel — became nuclear powers after originally seeking nuclear technology for research or to develop nuclear power. … This is important: The technology used to turn on lights or charge mobile phones shouldn’t need to involve national or international defence apparatus.” — Editorial, Nature

Nuclear waste is still a major problem
“Nuclear waste lasts for hundreds of thousands of years before they are half-decayed. Our United States government — perhaps the longest continuous government in the world — is only 232 years old. Who will be around to manage uranium wastes?” — David Ross, Courier-Journal

Atomic Histories & Nuclear Testing

LANL’s Central Mission: Los Alamos Lab officials have recently claimed that LANL has moved away from primarily nuclear weapons to “national security”, but what truly remains as the Labs central mission? Here’s the answer from one of its own documents:

LANL’s “Central Mission”- Presented at: RPI Nuclear Data 2011 Symposium for Criticality Safety and Reactor Applications (PDF) 4/27/11

It seems we can’t find what you’re looking for. Perhaps searching can help.

NukeWatch Compilation of the DOE/NNSA FY 2020 Budget Request – VIEW

Nuclear Watch NM Files Lawsuit Over Lack of Cleanup at the Los Alamos Lab

May 17, 2016

Nuclear Watch NM Files Lawsuit

Over Lack of Cleanup at the Los Alamos Lab;

NM Environment Dept. Forgoes Nearly $300 Million in Penalties

Santa Fe, NM – Nuclear Watch New Mexico has filed a lawsuit in federal court against the Department of Energy and Los Alamos National Security LLC (LANS), the for-profit operator of the Los Alamos National Laboratory, over their failure to meet cleanup milestones under a 2005 “Consent Order” they agreed to with the New Mexico Environment Department. The New Mexico Environmental Law Center is representing NukeWatch in this legal action to enforce cleanup at LANL.

The suit was filed under the citizen suit provisions of the federal Resource Conservation and Recovery Act (RCRA), which the 2005 Consent Order explicitly incorporated. The law provides that any person who violates any requirement of RCRA is liable for a civil penalty up to $37,500 for each day of violation. Our suit claims twelve violations, which range in length of time of up to 675 days each. Our current cost estimate of the alleged violations approaches 300 million dollars and counting.

Jay Coghlan, NukeWatch Executive Director, commented, “The federal government plans to spend a trillion dollars over the next 30 years completely rebuilding U.S. nuclear forces. Meanwhile, cleanup at the Los Alamos Lab, the birthplace of nuclear weapons, continues to be delayed, delayed, delayed. We seek to make the for-profit nuclear weaponeers cleanup their radioactive and toxic mess first before making another one for a nuclear weapons stockpile that is already bloated far beyond what we need. Real cleanup would be a win-win for New Mexicans, permanently protecting our water and environment while creating hundreds of high paying jobs.”

In 2005 the New Mexico Environment Department compelled DOE and the University of California (LANL’s manager at the time) to enter into a detailed Consent Order that mapped the way toward comprehensive cleanup at LANL. However, beginning in 2011 with Governor Martinez’s administration, the New Mexico Environment Department allowed LANL’s new contractor, the for-profit Los Alamos National Security, LLC, to stop virtually all cleanup, instead engaging in a “campaign” to move above ground, monitored radioactive transuranic wastes to the Waste Isolation Pilot Plant (WIPP). That campaign ended in disaster when an improperly treated radioactive waste drum from LANL ruptured, contaminating 21 workers and indefinitely closing that multi-billion dollar facility.

The 2005 Consent Order required DOE and LANL to investigate, characterize, and clean up hazardous and mixed radioactive contaminants from 70 years of nuclear weapons research and production. It also stipulated a detailed compliance schedule that the Lab was required to meet. Ironically, the last milestone, due December 6, 2015, required a report from LANL on how it successfully cleaned up Area G, its largest waste dump. However, real cleanup remains decades away, if ever. The Lab plans to “cap and cover” Area G, thereby creating a permanent nuclear waste dump in unlined pits and shafts, with an estimated 200,000 cubic yards of toxic and radioactive wastes buried above the regional groundwater aquifer, four miles uphill from the Rio Grande.

Scott Kovac, NukeWatch Research Director, noted, “DOE and NMED agreed to all parts of the 2005 Consent Order, including the schedule. Then under the Martinez administration NMED granted more than 150 extensions requests, and DOE and LANS have still missed many of those deadlines. NukeWatch has taken this necessary step to enforce cleanup at LANL, to hold DOE accountable for protecting New Mexicans and make cleanup of legacy wastes the top priority. It’s ridiculous that we have to have this cleanup debate after 70 years of contamination from nuclear weapons research and production.”

The New Mexico Environment Department has issued a draft revised proposed Consent Order, for which the public comment period expires on May 31. The proposed new Consent Order specifically states that it “supersedes the 2005 Compliance Order on Consent (2005 Consent Order) and settles any outstanding alleged violations under the 2005 Consent Order.” (Sec. II.A.) This then would absolve DOE and LANS of nearly $300 million in potential penalties.

Moreover, the new draft Order puts DOE in the driver’s seat instead of New Mexico. It explicitly states that, “DOE’s project plans and tools will be used to identify proposed milestones and targets” (p. 27) and “DOE shall define the use of screening levels and cleanup levels” (p. 31) Moreover, DOE can opt out of any cleanup because of “impracticability” or cost of cleanup (p. 34) and that “DOE shall update the milestones…. [according to] changes in anticipated funding levels.” (p. 28). So the new Consent Order is made subordinate to DOE’s budget, which has been cutting cleanup while increasing funding for nuclear weapons programs that caused the mess to begin with. This is the opposite of the original Consent Order, whose intent was to make DOE and LANL get increased funding for cleanup.

The relief or remedy that Nuclear Watch New Mexico seeks through its lawsuit is simple, asking the Court to enter a judgment “Enjoining the Defendants [DOE and LANS] to take action to come into compliance with the March 1, 2005 Consent Order, as amended on October 29, 2012, according to a reasonable but aggressive schedule ordered by this Court…”

With that, Nuclear Watch New Mexico hopes to get real, comprehensive cleanup back on track at the Los Alamos National Laboratory.

# # #

 Nuclear Watch New Mexico’s lawsuit complaint is available at https://nukewatch.org/importantdocs/resources/NukeWatch-Complaint-Filed-20160512.pdf

Our complaint alleges twelve counts of milestone compliance violations where NMED did not grant extensions. From there we calculate 7,853 total days of noncompliance at $37,500.00 per day, equal to $294,487,500, with the clock still ticking.

Our May 5, 2016 second notice of intent to sue (which is a good summary of our complaint) is available at https://nukewatch.org/importantdocs/resources/NukeWatch-2nd-NOI-DOE-LANS-5-5-16.pdf

Our January 20, 2016 notice of intent to sue is available at https://nukewatch.org/importantdocs/resources/NukeWatch-NM-NOI-to-DOE-and-LANS-20160120.pdf

NMED’s revised Consent Order is available at http://energy.gov/em/nnmcab/downloads/nmed-revised-lanl-consent-order-draft-march-2016

 

 

LANL FY 2020 Budget Request – VIEW

Sandia FY 2020 Budget Request – VIEW

Livermore Lab FY 2020 Budget Chart – Courtesy TriValley CAREs – VIEW

Updates

It seems we can’t find what you’re looking for. Perhaps searching can help.

________________________________

Click the image to view and download this large printable map of DOE sites, commercial reactors, nuclear waste dumps, nuclear transportation routes, surface waters near sites and transport routes, and underlying aquifers. This map was prepared by Deborah Reade for the Alliance for Nuclear Accountability.

Nuclear Watch Interactive Map – U.S. Nuclear Weapons Complex

Waste Lands: America’s Forgotten Nuclear Legacy

The Wall St. Journal has compiled a searchable database of contaminated sites across the US. (view)
Related WSJ report: https://www.wsj.com

Atomic Histories & Nuclear Testing

NukeWatch Compilation of the DOE/NNSA FY 2020 Budget Request – VIEW

Nuclear Watch NM Files Lawsuit Over Lack of Cleanup at the Los Alamos Lab

May 17, 2016

Nuclear Watch NM Files Lawsuit

Over Lack of Cleanup at the Los Alamos Lab;

NM Environment Dept. Forgoes Nearly $300 Million in Penalties

Santa Fe, NM – Nuclear Watch New Mexico has filed a lawsuit in federal court against the Department of Energy and Los Alamos National Security LLC (LANS), the for-profit operator of the Los Alamos National Laboratory, over their failure to meet cleanup milestones under a 2005 “Consent Order” they agreed to with the New Mexico Environment Department. The New Mexico Environmental Law Center is representing NukeWatch in this legal action to enforce cleanup at LANL.

The suit was filed under the citizen suit provisions of the federal Resource Conservation and Recovery Act (RCRA), which the 2005 Consent Order explicitly incorporated. The law provides that any person who violates any requirement of RCRA is liable for a civil penalty up to $37,500 for each day of violation. Our suit claims twelve violations, which range in length of time of up to 675 days each. Our current cost estimate of the alleged violations approaches 300 million dollars and counting.

Jay Coghlan, NukeWatch Executive Director, commented, “The federal government plans to spend a trillion dollars over the next 30 years completely rebuilding U.S. nuclear forces. Meanwhile, cleanup at the Los Alamos Lab, the birthplace of nuclear weapons, continues to be delayed, delayed, delayed. We seek to make the for-profit nuclear weaponeers cleanup their radioactive and toxic mess first before making another one for a nuclear weapons stockpile that is already bloated far beyond what we need. Real cleanup would be a win-win for New Mexicans, permanently protecting our water and environment while creating hundreds of high paying jobs.”

In 2005 the New Mexico Environment Department compelled DOE and the University of California (LANL’s manager at the time) to enter into a detailed Consent Order that mapped the way toward comprehensive cleanup at LANL. However, beginning in 2011 with Governor Martinez’s administration, the New Mexico Environment Department allowed LANL’s new contractor, the for-profit Los Alamos National Security, LLC, to stop virtually all cleanup, instead engaging in a “campaign” to move above ground, monitored radioactive transuranic wastes to the Waste Isolation Pilot Plant (WIPP). That campaign ended in disaster when an improperly treated radioactive waste drum from LANL ruptured, contaminating 21 workers and indefinitely closing that multi-billion dollar facility.

The 2005 Consent Order required DOE and LANL to investigate, characterize, and clean up hazardous and mixed radioactive contaminants from 70 years of nuclear weapons research and production. It also stipulated a detailed compliance schedule that the Lab was required to meet. Ironically, the last milestone, due December 6, 2015, required a report from LANL on how it successfully cleaned up Area G, its largest waste dump. However, real cleanup remains decades away, if ever. The Lab plans to “cap and cover” Area G, thereby creating a permanent nuclear waste dump in unlined pits and shafts, with an estimated 200,000 cubic yards of toxic and radioactive wastes buried above the regional groundwater aquifer, four miles uphill from the Rio Grande.

Scott Kovac, NukeWatch Research Director, noted, “DOE and NMED agreed to all parts of the 2005 Consent Order, including the schedule. Then under the Martinez administration NMED granted more than 150 extensions requests, and DOE and LANS have still missed many of those deadlines. NukeWatch has taken this necessary step to enforce cleanup at LANL, to hold DOE accountable for protecting New Mexicans and make cleanup of legacy wastes the top priority. It’s ridiculous that we have to have this cleanup debate after 70 years of contamination from nuclear weapons research and production.”

The New Mexico Environment Department has issued a draft revised proposed Consent Order, for which the public comment period expires on May 31. The proposed new Consent Order specifically states that it “supersedes the 2005 Compliance Order on Consent (2005 Consent Order) and settles any outstanding alleged violations under the 2005 Consent Order.” (Sec. II.A.) This then would absolve DOE and LANS of nearly $300 million in potential penalties.

Moreover, the new draft Order puts DOE in the driver’s seat instead of New Mexico. It explicitly states that, “DOE’s project plans and tools will be used to identify proposed milestones and targets” (p. 27) and “DOE shall define the use of screening levels and cleanup levels” (p. 31) Moreover, DOE can opt out of any cleanup because of “impracticability” or cost of cleanup (p. 34) and that “DOE shall update the milestones…. [according to] changes in anticipated funding levels.” (p. 28). So the new Consent Order is made subordinate to DOE’s budget, which has been cutting cleanup while increasing funding for nuclear weapons programs that caused the mess to begin with. This is the opposite of the original Consent Order, whose intent was to make DOE and LANL get increased funding for cleanup.

The relief or remedy that Nuclear Watch New Mexico seeks through its lawsuit is simple, asking the Court to enter a judgment “Enjoining the Defendants [DOE and LANS] to take action to come into compliance with the March 1, 2005 Consent Order, as amended on October 29, 2012, according to a reasonable but aggressive schedule ordered by this Court…”

With that, Nuclear Watch New Mexico hopes to get real, comprehensive cleanup back on track at the Los Alamos National Laboratory.

# # #

 Nuclear Watch New Mexico’s lawsuit complaint is available at https://nukewatch.org/importantdocs/resources/NukeWatch-Complaint-Filed-20160512.pdf

Our complaint alleges twelve counts of milestone compliance violations where NMED did not grant extensions. From there we calculate 7,853 total days of noncompliance at $37,500.00 per day, equal to $294,487,500, with the clock still ticking.

Our May 5, 2016 second notice of intent to sue (which is a good summary of our complaint) is available at https://nukewatch.org/importantdocs/resources/NukeWatch-2nd-NOI-DOE-LANS-5-5-16.pdf

Our January 20, 2016 notice of intent to sue is available at https://nukewatch.org/importantdocs/resources/NukeWatch-NM-NOI-to-DOE-and-LANS-20160120.pdf

NMED’s revised Consent Order is available at http://energy.gov/em/nnmcab/downloads/nmed-revised-lanl-consent-order-draft-march-2016

 

 

LANL FY 2020 Budget Request – VIEW

Sandia FY 2020 Budget Request – VIEW

Livermore Lab FY 2020 Budget Chart – Courtesy TriValley CAREs – VIEW

NUCLEAR POWER

Important Documents & Articles Related to Nuclear Energy Production

Most Recent

It seems we can’t find what you’re looking for. Perhaps searching can help.

Nuclear Watch Interactive Map – U.S. Nuclear Weapons Complex

Waste Lands: America’s Forgotten Nuclear Legacy

The Wall St. Journal has compiled a searchable database of contaminated sites across the US. (view)
Related WSJ report: https://www.wsj.com

LANL’s Central Mission: Los Alamos Lab officials have recently claimed that LANL has moved away from primarily nuclear weapons to “national security”, but what truly remains as the Labs central mission? Here’s the answer from one of its own documents:

LANL’s “Central Mission”- Presented at: RPI Nuclear Data 2011 Symposium for Criticality Safety and Reactor Applications (PDF) 4/27/11