NNSA Considers Stuffing More Plutonium Into New Facility

Despite the fact that no one has come up with a good reason to increase plutonium pit production for the nation’s nuclear weapons stockpile, officials want to study the possibility of radically increasing the amount of plutonium allowed in a recently completed laboratory at the Los Alamos National Laboratory.

The Deputy Administrator for National Nuclear Security Administration (NNSA) Defense Programs, Don Cook, has requested an analysis to increase the radioactive materials inventory in the recently completed Radiological Laboratory Utility Office Building (RLUOB) to up to 400 grams of plutonium-239, the isotope used in nuclear weapons. The RLUOB, which originally was limited to 8.4 grams of Pu 239, was built as Phase 1 of the Chemistry and Metallurgy Research Replacement Project at LANL that would have expanded plutonium pit production to 50 – 80 pits per year (pits are the radioactive cores of nuclear weapons). LANL’s current capacity is 20 pits per year. Phase 2 of the CMRR project, the “Nuclear Facility,” was canceled because of lack of clear need and a bulging ten-fold increase in costs.

This RLUOB, along with some floor space in the existing Plutonium Facility (PF-4), will replace the old Chemistry and Metallurgy Research Building, which is slated for closure in 2019. The Laboratory was working on a plutonium strategy to move out of CMR and maintain the current plutonium capability.

But NNSA recently increased the maximum amount of radiological materials allowed in the RLOUB, and all “radiological” facilities, from 8.4 grams to 38.6 grams. Internal Lab documents floated plans that could have increased the limit again by two or three times by treating each little laboratory in the RLUOB as its own radiological facility. This could have increased the limit to 115.8 grams of Pu239.

But NNSA apparently wants to go big. The new analysis is to consider the RLUOB as a Hazard Category 3 nuclear facility, which is a huge step up from its current designation as a radiological facility.

Scott Kovac, Research and Operations Director for Nuclear Watch New Mexico, said, “This turkey of a plan is stuffed with bad ideas – The RLUOB is not seismically qualified for that amount of plutonium. A new supplemental environmental impact statement will be needed. There is no need for more plutonium pits, except for new nuclear weapons, because they last for around 100 years and nuclear weapons stockpiles are decreasing. And apparently LANL can’t safely handle plutonium anyway, as major operations with plutonium have been paused since June 2013 because of nuclear criticality safety issues. Finally, it was LANL’s improper handling of plutonium waste that contaminated 21 workers at the Waste Isolation Pilot Plant, causing it to close with at least a half billion dollars in costs to reopen. We say no to more plutonium at Los Alamos!”

# # #

Read the Defense Nuclear Facilities Safety Board report here.

 

NNSA Digs Deep To Find A Reason To Give Itself Award

The award for the largest nuclear facility project completed ahead of schedule and under budget by NNSA goes to a project came in only 1% under budget after spending $40 million in contingency.

In an April 2 2014 National Nuclear Security Administration press release titled, NNSA Receives Secretary’s Award for Project Management Excellence, the Chemistry and Metallurgy Research Building Replacement (CMRR) Radiological Laboratory/Utility/Office Building (RLUOB) Equipment Installation (REI) Project was touted for coming in $2 million under budget.

First, the CMRR is the now-deferred project at Los Alamos, whose third phase Nuclear Facility would have enabled increased plutonium pit production. The RLOUB was the first phase of the CMRR project. The second phase REI is only the “equipment” for the RLOUB.

The press release tells us –

“The REI installed glovebox and other enclosure systems, analytical and test instrumentation equipment, and telecommunications and safeguards/security systems within the RLUOB.”

Also included, but not mentioned in the press release, were a fuel oil storage tank, furniture, and the parking lot.

It looks like NNSA gave the award in part because it could have been worse. With one year left in the 3-year the contract, it was estimated that the project was $8 million over budget. So NNSA put a new team in charge and straightened out their mess-ups and turned it around to a $2 million savings.

The press release tells us –

“The CMRR/RLUOB REI Project is the largest nuclear facility capital asset project completed ahead of schedule and under budget by NNSA.”

The press release also neglects to give the total budget. Our documents show that REI had a total budget $199 million. That makes the $2 million that the REI came in under budget equal to 1% of the total budget.

But our documents also show that there was $41.6 million (26%) contingency included in the $199 total budget. After spending untold millions in design and then estimating the cost of the project, NNSA adds in a large contingency to every project so that it does not go over budget and have to go back to Congress for more money.

Is the REI, which spent $40 million in contingency, really $2 million under budget?

I think not. NNSA must give the public all the facts and figures when it gives glowing appraisals of itself.

 

Here’s what we have on the REI –

 

Still Time to Comment on LANL’s Burning Desire for Expanded Weapons Production

Ironically today (June 28) is the deadline for public comment under the National Environmental Policy Act (NEPA) for concerned citizens to comment on a proposed ~$5 billion facility at the Los Alamos Lab ponderously called the Chemistry and Metallurgy Research Replacement Project- Nuclear Facility. In short, it is a huge new plutonium facility that will provide materials characterization and analytical chemistry in direct support of production of the atomic cores or “triggers” of nuclear weapons, commonly called the plutonium pits. The Nuclear Facility will be the keystone to an expanded complex at LANL’s Technical Area-55 that will quadruple production capacity from 20 to 80 pits per year.

I say ironically because of the fire that is now threatening the Lab. We need to begin questioning whether expanded nuclear weapons production at Los Alamos is feasible in a possibly long-term drought and climate warming punctuated with catastrophic forest fires. More broadly, as we face increasing budget and resource constraints, we need to decide whether our money and water go into expanded nuclear weapons production, or do they go into repairing schools and infrastructure for the common good of society?

 