NNSA Digs Deep To Find A Reason To Give Itself Award

The award for the largest nuclear facility project completed ahead of schedule and under budget by NNSA goes to a project came in only 1% under budget after spending $40 million in contingency.

In an April 2 2014 National Nuclear Security Administration press release titled, NNSA Receives Secretary’s Award for Project Management Excellence, the Chemistry and Metallurgy Research Building Replacement (CMRR) Radiological Laboratory/Utility/Office Building (RLUOB) Equipment Installation (REI) Project was touted for coming in $2 million under budget.

First, the CMRR is the now-deferred project at Los Alamos, whose third phase Nuclear Facility would have enabled increased plutonium pit production. The RLOUB was the first phase of the CMRR project. The second phase REI is only the “equipment” for the RLOUB.

The press release tells us –

“The REI installed glovebox and other enclosure systems, analytical and test instrumentation equipment, and telecommunications and safeguards/security systems within the RLUOB.”

Also included, but not mentioned in the press release, were a fuel oil storage tank, furniture, and the parking lot.

It looks like NNSA gave the award in part because it could have been worse. With one year left in the 3-year the contract, it was estimated that the project was $8 million over budget. So NNSA put a new team in charge and straightened out their mess-ups and turned it around to a $2 million savings.

The press release tells us –

“The CMRR/RLUOB REI Project is the largest nuclear facility capital asset project completed ahead of schedule and under budget by NNSA.”

The press release also neglects to give the total budget. Our documents show that REI had a total budget $199 million. That makes the $2 million that the REI came in under budget equal to 1% of the total budget.

But our documents also show that there was $41.6 million (26%) contingency included in the $199 total budget. After spending untold millions in design and then estimating the cost of the project, NNSA adds in a large contingency to every project so that it does not go over budget and have to go back to Congress for more money.

Is the REI, which spent $40 million in contingency, really $2 million under budget?

I think not. NNSA must give the public all the facts and figures when it gives glowing appraisals of itself.

 

Here’s what we have on the REI –

 

Excellence Unfulfilled at the LANL’s Plutonium Facility

A Los Alamos National Laboratory fact sheet touts the Lab as a plutonium “center of excellence”. However, the Laboratory Director paused operations in the Plutonium Facility on June 27, 2013. (The Plutonium Facility, called PF-4, is located at Technical Area 55 at Los Alamos National Laboratory (LANL). PF-4 is home for the Lab’s plutonium work, including nuclear weapons component production.) The pause was based on issues identified during safety reviews and findings from recent assessments. For one, the Defense Nuclear Facilities Safety Board (Board) performed a review of the Criticality Safety Program at Los Alamos National Laboratory (LANL) in May 2013. (The Board is an independent organization within the executive branch chartered with the responsibility of providing recommendations and advice to the President and the Secretary of Energy regarding public health and safety issues at Department of Energy (DOE) defense nuclear facilities.) This review identified significant non-compliances with DOE requirements and industry standards in the Lab’s Criticality Safety Program (CSP). In addition, this review identified criticality safety concerns around operations at the Plutonium Facility. The Board noted that some of these deficiencies are long standing and indicated flaws in federal oversight and contractor assurance. Much plutonium work, especially work with a high potential for criticality, will be stopped through the rest of 2013.

Nuclear criticality safety is defined as “protection against the consequences of an inadvertent nuclear chain reaction, preferably by prevention of the reaction.” The most potentially dangerous aspect of a criticality accident is the release of nuclear radiation if it maintains a self-sustaining nuclear chain reaction.

To date, the only thing self-sustaining is the Lab’s inability to address its criticality issues and yet still convince Congress to keep funding plutonium work there. To prevent bad things from happening, DOE’s regulations and directives require contractors to evaluate potential accident conditions and put in place appropriate controls and safety measures. History shows that the Los Alamos Laboratory just cannot do this, even though much of the work is performed on plutonium pits, the primaries of nuclear weapons. Even though actual need for this work has not been proven, the Lab has entrenched itself as the only place in the country where plutonium pits can be made, developed, and tested.

For fiscal year 2014, the budget request for nuclear ‘weapons activities’ at LANL was $1.4 billion. The exact amount that is spent on plutonium operations in PF-4 is unknown to us, but the budget request for 2014 for Directed Stockpile Work, which is where major parts of the plutonium operations are located, was $460 million. This is a 23% increase over last year’s budget. The funding pours into the Lab regardless of whether the Lab is actually doing any work, which is frequently stopped.

Here’s history of criticality problems and work stoppages at Los Alamos Laboratory:
In 2005, an assessment determined that LANL’s expert-based Criticality Safety Program (CSP) was not compliant with applicable DOE requirements and industry standards.

In 2006, LANS developed a Nuclear Criticality Safety Program Improvement Plan.

In 2007, in response to concerns raised by the Board’s staff, LANL determined that the authorized loading of vault storage rooms in PF-4 could lead to a critical configuration.

In 2008, the Government Accountability Office reported concerns about nuclear safety at LANL are long-standing. Problems included 19 occasions since 2003 where criticality safety requirements were violated, such as storing materials in quantities higher than safety limits allow, 17 of 19 of the site’s nuclear facilities operating without proper safety documentation, reported inadequacies in safety systems, radiological releases, and four enforcement actions for significant violations of nuclear safety rules.

Los Alamos Report for Week Ending April 3, 2009
LANL management placed the facility in stand-by mode until roughly 125 safety evaluations could be re-evaluated.

Los Alamos Report for Week Ending October 2, 2009
The Plutonium Facility was placed in standby mode because management declared the fire suppression system inoperable based on recent hydraulic calculations that concluded the system was not able to achieve the water coverage required. LANL had performed a system adequacy analysis in 2008. The hydraulic calculation completed for the system identified that 13 of approximately 100 hydraulic areas did not meet the requirement.

Los Alamos Report for Week Ending October 16, 2009
A general evacuation alarm was caused by a Criticality Alarm System signal because of a loss of all facility ventilation and failure of the Facility Control System at the Plutonium Facility. The facility was in standby mode during this event due to previously identified issues with the fire suppression system and, therefore, limited personnel were in the facility.

Los Alamos Report for Week Ending September 10, 2010
Operations in Plutonium Facility were suspended because potentially explosive ammonium nitrate was discovered in two filter ducts.

Los Alamos Report for Week Ending December 3, 2010
It was revealed that greater than 1000 items, or about 20%, of the total vault holdings are items packaged in potentially vulnerable containers with taped slip-top lids rather than in robust safety-significant containers that include a HEPA-filtered vent. The presence of these slip-top containers requires respirator use whenever operators access the vault. In FY10, LANL made meaningful progress in addressing these legacy materials.

In 2011, an event occurred at PF-4 in which fissile material handlers violated procedural requirements and criticality safety controls while moving and photographing plutonium rods.

Beginning in 2012, LANS experienced an 18-month exodus of criticality safety professionals from its criticality safety group. LANS currently employs 2 full-time and 2 part-time qualified criticality safety analysts, in addition to 3 part-time subcontractors—far fewer than the 17 criticality safety analysts it has determined to be necessary to support operations, meet mission goals, and maintain the CSP.

Los Alamos Report for Week Ending April 20, 2012
Plutonium Facility personnel use a software program called MAR Tracker to track plutonium that is used in the facility. A system engineer discovered an error in
MAR Tracker that caused only a small subset of applicable facility containers (roughly 1700 out of 13000 containers) to be checked during the required annual MAR surveillance. The Plutonium Facility was placed in Standby Mode.

Los Alamos Report for Week Ending June 15, 2012
LANL identified a number of fuel rods in TA-35 Building 27 that were not consistent with the criticality safety evaluation for the facility. Operations at this building had previously been suspended in late-May due to the discovery of three fuel rods that were not in the facility or institutional tracking systems.

Los Alamos Report for Week Ending December 14, 2012
LANL identified that the Criticality Safety Evaluations (CSEs) for two rooms did not adequately address the potential for interaction effects between storage locations. Plutonium Facility management suspended operations in these two vault rooms.

Los Alamos Report for Week Ending February 15, 2013
LANL began a focused training program (“boot camp”) to provide an intensive learning environment for new criticality safety staff. The program consisted of nine modules including: nuclear theory; criticality safety calculation methods; ANSI/ANS, DOE and LANL criticality safety standards and requirements; criticality safety evaluations; and criticality alarm and detection systems. This program along with on-the-job training and performance demonstrations was to provide a mechanism for achieving full qualification as a LANL criticality safety analyst. Conduct of the boot camp was part of the LANL corrective action plan for improving the nuclear criticality safety program.

Los Alamos Report for Week Ending May 3, 2013
The laboratory completed criticality safety assessments at LANL nuclear facilities. The review teams identified 3, 4, and 6 findings for TA-55, CMR, and Area G, respectively. In all cases, the assessments concluded adequate implementation of the Criticality Safety Program with the exception of identified findings. Notably, one of the findings at Area G identified that supervisors and operations center personnel did not have an adequate understanding of criticality safety requirements. Area G management paused operations based on this finding and conducted appropriate training to resolve this issue.

In May 2013, the staff of the Defense Nuclear Facilities Safety Board (Board) performed a review of the Criticality Safety Program at Los Alamos National Laboratory. This review identified significant non-compliances with applicable Department of Energy requirements and industry standards in the implementation of the Criticality Safety Program. The Board’s staff identified the following non-compliances during its review:
• Most criticality safety controls are not incorporated into operating procedures.
• Operators typically do not utilize written procedures when performing work.
• Fissile material labels do not list parameters relevant to criticality safety (e.g., mass).
• Some fissile material operations lack Criticality Safety Evaluations (CSEs).
• Some CSEs do not analyze all credible abnormal conditions.

Los Alamos Report for Week Ending June 28, 2013
The Laboratory Director paused programmatic activities at the Plutonium Facility. The pause was directed based on issues identified during procedural and criticality safety reviews and findings from recent assessments. Reviews at PF-4 have identified a number of procedural issues and the need for clarification and improvement of criticality safety controls.

Los Alamos Report for Week Ending July 26, 2013
Plutonium Facility personnel identified several criticality safety issues associated with recent construction activity. Even though plutonium work was paused, the Laboratory Director and the Facility Operations Director (FOD) approved construction activities that had the potential to affect nuclear materials.

For more information, please read the LAMonitor article By John Severance
Safety board visits LANL

New Mexico Members of Congress Vote for Exorbitant Nuclear Bomb While State Is Ranked as the Worst for Children

Yesterday all three House members of the New Mexican congressional delegation voted against an amendment that would cut money added to a wasteful nuclear weapons program. In April the Obama Administration asked for $537 million in fiscal year 2014 for a “Life Extension Program” for the B61 Cold War nuclear bomb, 45% above the 2013 level. The House Appropriations Committee added $23.7 million to that bloated request, which the amendment would have cut. Overall, the B61 Life Extension Program has exploded in estimated costs to where each warhead will cost twice their weight in gold just to “refurbish” (which does not include original production and ongoing maintenance costs).

 The sponsor of the amendment, Rep. Mike Quigley, D-Ill., testified during floor debate:

At a time when we are slashing funds for disease research at the NIH [National Institute of Health], failing to fund our crumbling infrastructure, and underinvesting in our children¹s education, we are increasing funding to keep hundreds of nuclear bombs in operation that we will never use. The Cold War is over.

The Albuquerque Journal reported that Rep. Ben Ray Luján, D-N.M.,

…supported the full $551 million for the B61 Life Extension Program because it is a national security priority. “This funding is important for Los Alamos and Sandia labs’ effort to ensure the safety of the nuclear weapons stockpile, and cuts to that funding impact the ability to keep it secure,” Luján said.

Rather just ensuring safety and security the program will radically improve the bomb, giving it new military capabilities by turning it into a precisely targeted smart bomb and mating it to future bombers for supersonic stealthy delivery. Currently the main mission of B61 bombs is as tactical nuclear weapons in NATO countries, a relic of the Cold War. Improved B61’s fly in the face of Obama’s newly declared goal of reducing the presence of battlefield nuclear weapons in Europe, even as he proposes to negotiate with the Russians for further arms reductions. Moreover, if security is really the issue, the sure solution that saves taxpayers money and encourages nonproliferation is to withdraw the nuclear bombs from forward deployment in Europe, where a few years ago protesting peace activists were able to infiltrate within a few hundred yards of them.

Ironically, the B61 Life Extension Program may actually undermine our own national security by introducing major changes to existing bombs. Our stockpile has been extensively full-scale tested, and repeated studies have found our nuclear weapons to be even more reliable than previously believed. The Los Alamos and Sandia Labs propose to create a “frankenbomb” by mixing and matching four variants of the B61 bomb into a single new modification. Common sense dictates that the last thing we should do while seeking to maintain confidence in our reliable nuclear weapons stockpile is to introduce major changes that can’t be tested.

Our New Mexican congressional delegation represents a state that was just ranked as the worst of all fifty for the well-being of its children, where more than 25% live in poverty. In stark contrast, Los Alamos County, dominated by the lab, is the second richest county in the entire USA. Nuclear weapons programs are a poor producer of jobs, where for example according to the government’s own documents a new $6 billion plutonium facility was not going to produce a single new permanent job at Los Alamos Lab.

Contrary to the claimed economic benefits of the Los Alamos and Sandia Labs, New Mexico as a whole continues to fall from 37th in per capita personal income in 1959 to 44th in 2011. Nevertheless, the Labs have always had inordinate influence over New Mexican politicians. One extreme example is the recent starling revelation that in between unsuccessful Senate campaigns former Rep. Heather Wilson was paid more than $450,000 by the Los Alamos and Sandia Labs for “consulting” contracts that had no written work requirements.

The nuclear weapons labs have voracious appetites for federal funding, with their directors simultaneously acting as the presidents of the executive board of the for-profit limited liability corporations that run the labs (those private LLCs pay 2/3’s of the directors’ annual compensation of around one million dollars). Business will boom with never-ending Life Extension Programs, and Sandia and Los Alamos are not satisfied with just one Life Extension Program for the B61. They already plan yet another one 20 years from now that initial figures indicate would be even more expensive. In fact, the labs plan a never-ending cycle of Life Extension Programs that intentionally seek to implement major design changes for all existing types of nuclear weapons in our stockpile, costing at least $60 billion (while the doubling of costs has so far been the rule).

Jay Coghlan, director of Nuclear Watch New Mexico, commented, “Congressman Ben Ray Luján should ask himself the question what good does a Cold War nuclear bomb that the for-profit labs want to endlessly tinker with do for New Mexican children? Pork for the labs should not drive nuclear weapons policies, especially when it’s of little if any tangible benefit to average New Mexicans. Luján should, instead, dedicate himself to boosting funding for programs that would really help our children but are facing painful sequester cuts, such as education, medical care and food assistance. Those investments would really brighten their future, and help raise New Mexico from its shameful position as the worst state for kids.”

# # # 

See House rejects effort to trim $23.7M in funding for B61, Michael Coleman, Albuquerque Journal, July 11, 2013.

For New Mexico’s ranking as the worst state for kids see Kids Count Data Center http://datacenter.kidscount.org/updates/show/20-2013-data-book-rankings
For the scope and schedule of perpetual Life Extension Programs for existing nuclear weapons see NNSA’s FY 2014 Stockpile Stewardship and Management Plan
https://nukewatch.org/importantdocs/resources/SSMP-FY2014.pdf

Obama Calls For Further Nuclear Weapons Reductions While Increased Production and New Facilities at Los Alamos Are Still On the Table

Obama Calls For Further Nuclear Weapons Reductions
While Increased Production and New Facilities at Los Alamos Are Still On the Table

On June 19, in Berlin, President Barack Obama declared that, in concert with Russia, he plans to seek to cut the deployed strategic nuclear arsenal by up to one-third. He also said he will pursue significant bilateral cuts in tactical or battlefield nuclear weapons in Europe. In contrast, Obama’s National Nuclear Security Administration (NNSA) recently released plans for unneeded upgrades and dangerous improvements to existing nuclear weapons, which could force expanded nuclear component production and construction of new facilities at Los Alamos.

In the just released “FY 2014 Stockpile Stewardship and Management Plan” (SSMP), NNSA proposes perpetual Life Extension Programs for nuclear warheads that will result in three types of ballistic missile warheads and two types of nuclear air bombs. Although it’s still vague, the three so-called interoperable warheads would replace four types of existing warheads, which make little sense given the staggering estimated costs. These radical upgrades, if implemented, could not be full-scale tested, which would undermine confidence in their reliability. Our existing nuclear weapons designs have been extensively tested and subsequent studies have found them to be even more reliable and long-lived than originally thought.

The President’s speech is also incongruous with the SSMP in the area of plutonium pit production, and states “Preliminary plans call for pit production of potentially up to 80 pits per year starting as early as FY 2030.” (SSMP Pg. 62) With Obama’s further proposed arsenal reductions, any planned increase in weapons production is only a concession the nuclear weapons contractors profits. The alleged need for more plutonium pits cascades into a misplaced call for more production facilities. NNSA is “…evaluating the feasibility of constructing small laboratory modules connected to existing nuclear facilities…” (SSMP Pg. 8) to meet future claimed plutonium-manufacturing requirements. The SSMP states that Los Alamos can produce up to 30 pits per year without new facilities.

The need for increased pit production has never been explained adequately to the public, but the claim likely is centered on one of the interoperable warhead plans – the W78/88. In a May 7, 2013 testimony to the Senate Subcommittee on Strategic Forces, Dr. Penrose C. Albright, Director, Lawrence Livermore National Laboratory claimed that the W78/88 would require increased pit production at Los Alamos. He goes on to try to scare the Committee by saying that without construction funding for new pit facilities now, the W78/88 warhead upgrade could cost even more. He stated, “without going into the detail, the most likely option for the primary on the 78/88 does require the stand-up and operation of plutonium pit production capabilities at Los Alamos. And so any delay by the Government—any delay in funding to get that stood up—and that really has to start now—is going to add significant schedule risks to the program.” (Hearing Pg. 17)

The President should adopt the more fiscally prudent and technically sound alternative of replacing limited life components while he actually works to eliminate nukes altogether. This unending cycle of proposed Life Extension Program will waste huge sums of taxpayers money and is in direct conflict with the President’s own long-term goal of a future world free of nuclear weapons.

The full text of President’s Obama’s speech is available at http://www.whitehouse.gov/the-press-office/2013/06/19/remarks-president-obam

NNSA’s FY 2014 Stockpile Stewardship and Management Plan (SSMP) is available at https://nukewatch.org/importantdocs/resources/SSMP-FY2014.pdf

Hearing To Receive Testimony On National Nuclear Security Administration Management Of Its National Security Laboratories In Review Of The Defense Authorization Request For Fiscal Year 2014 And The Future Years Defense Program, Tuesday, May 7, 2013, U.S. Senate Subcommittee On Strategic Forces, Committee On Armed Services, Washington, DC.
http://www.armed-services.senate.gov/Transcripts/2013/05%20May/13-36%20-%205-7-13.pdf

The Lab’s New, $400 million, Plutonium Laboratory Springs Its First Leak

The Lab’s New, $400 million, Plutonium Laboratory Springs Its First Leak

On January 22, 2013 representatives of the Los Alamos National Laboratory discovered the presence of a diesel spill from an above ground storage tank system at the LANL Technical Area 55. The spill was from the new Radiological Laboratory Utilities Office Building’s (RLUOB’s) 12,000-gallon emergency generator diesel storage tank. The RLUOB is the recently completed first phase of the CMRR project. The main phase of the project, the CMRR Nuclear Facility (estimated at #6 billion), has been deferred for at least 5 years and will probably next be proposed next as a smaller project, if at all.

From the reports, it is unclear how long the sump pump union had been leaking before the spill was noticed. A leak detector alarm first went off in November. The Lab estimates that 350 gallons overflowed out a sump and spilled onto the ground, and workers have removed 5 cubic yards of contaminated soil. LANL and the State Environment Department Petroleum Storage TOppie greenank Bureau are working to figure out if more soil needs to be removed.

Read the report there.

Lab lacks ability to estimate emergency response as it also underestimates risk

Lab lacks ability to estimate emergency response as it also underestimates risk

There has been much in the recent news about Los Alamos National Laboratory underestimating how much radiation could leak from the nuclear weapons production plutonium lab after a major earthquake and fire. Read the POGO article here.

The Defense Nuclear Facilities Safety Board Report is here.

Among other problems, LANL computer models credited sheetrock walls with surviving an earthquake.

In a recently released May report, the Department of Energy’s very own oversight Department finished a separate review titled, “Independent Oversight Review of Site Preparedness for Severe Natural Phenomena Events at the Los Alamos National Laboratory”, that also questions the Lab’s safety procedures.

The Health Safety and Security Office (HSS) of Safety and Emergency Management Evaluations performed this independent review to evaluate emergency response capabilities at the Lab and how the Lab maintained them in a state of readiness in case of a severe natural phenomena event. The review showed that LANL would have trouble responding quickly with the appropriate emergency response in the case of a serious natural event.

As one of the conclusions states – “LANL does not have an adequate means for determining quickly whether an event occurring at the CMR facility, a criticality event at TA-55 PF-4 facility, or a severe natural phenomena event at either facility involves a significant quantity of HAZMAT and requires implementation of corresponding onsite protective actions or issuance of appropriate offsite protective action recommendations.” (Pg. 38)

For example, the Emergency Action Levels currently in the Lab’s Emergency Plan Procedure:

•            Do not reflect the CMR Emergency Planning Hazards Assessment isolation and downwind protective action distances for the majority of the events

•            Do not provide Emergency Action Levels for two severe natural phenomena events (earthquake and wildland fire) in the CMR Emergency Planning Hazards Assessment

•            Use a criticality alarm system as an Emergency Action Level entry indicator for a criticality event at CMR, even though CMR is not equipped with a criticality alarm system

•            Do not use the PF-4 criticality alarm system as an Emergency Action Level entry indicator for the criticality event analyzed in the TA-55 Emergency Planning Hazards Assessment.

 

In addition, the Lab’s generic natural disaster Emergency Action Levels do not provide sufficient information to accurately categorize and/or classify a severe natural phenomena event.

And LANL’s planning for onsite protective actions and offsite protective action recommendations provided in the Emergency Action Levels did not fully consider facility or site conditions for the analyzed events.

The report continues. The Independent Oversight observed outdated and incorrect information in the current set of CMR and TA-55 PF-4 Emergency Action Levels. Further, the generic Emergency Action Levels for severe natural phenomena events were not based on the potential for or an actual uncontrolled release of HAZMAT and are not linked to protective actions or protective action recommendations.

Additionally, the pre-planned protective actions for a TA-55 PF-4 seismic event are limited to shelter-in-place when there could be high radiation levels, and no effective shelters are available.

So, we have two different government agencies questioning safety after the Lab received a record $83 million in award bonuses.

These reports are another example of why the Lab must shut down plutonium operations now.

Operations at Plutonium Facility stood down due to fire suppression system

In the latest of a string of fire system deficiencies on Wednesday September 30th, LANL management declared the fire suppression system inoperable in PF-4 at TA-55. Facility activities were placed in stand-by mode, which were still stood down as of three weeks later on Oct. 23rd.

DNFSB explained that the stand down was based on recent hydraulic calculations that concluded the system does not achieve the water density coverage required. Basically, the sprinklers in 13 of approximately 100 fire suppression areas at PF-4 cannot meet the current required gallons per minute estimated to effectively extinguish a fire. (Read the Oct. 2nd-23rd DNFSB reports)

One has to wonder – What is the cost to the taxpayer of PF-4 being stood down for nearly a month?

These reports come on the heels of last week’s DNFSB recommendation that the Lab must immediately do something about its risk to the public of a seismically induced fire at PF-4, which was estimated to exceed the DOE guidelines by more than 100 times. In a worst-case situation, an earthquake-induced fire could set free enough breathable plutonium that a person on the perimeter of the facility would receive a lethal dose of radiation.

Speaking of seismically induced fires, I am reminded of a March 2007 LANL report, Seismic Fragility of the LANL Fire Water Distribution System (LA-14325), which explains how numerous valves in the fire water distribution system at the Lab would have to be manually closed to insure proper pressure to facilities on fire after a seismic event.

Granted, these may be low probability events, but they have high consequences. The Lab is playing with fire by not adequately funding upgrades to its existing fire systems now, before embarking construction of any new facilities.

Los Alamos – Plutonium Center of Negligence

An October 27 press release from the Project on Government Oversight (POGO)
Defense Board Catches Los Alamos Trying to Dodge Plutonium Safety Vulnerability” revolves around a new Defense Nuclear Facilities Safety Board (DNFSB) revelation of public safety vulnerability and seismic issues at TA-55 (The Lab’s plutonium Technical Area).

The DNFSB has been very patient on the safety issues at TA-55. In a September 23, 2005 weekly report, they stated that LANL needed to try to justify a passive confinement strategy, continue plans to reduce radioactive materials, and to seismically upgrade the glove-box supports that have not already been upgraded. These issues are still unaddressed as of the latest DNFSB report.

Seismic issues run deep at Los Alamos. NNSA currently has plans to construct and operate the Chemistry and Metallurgy Research Replacement–Nuclear Facility (CMRR–NF) to support plutonium operations as a replacement for portions of the Chemistry and Metallurgy Research (CMR) facility, a 1950’s structure that faces significant safety and seismic challenges. In 1999, a fault was discovered under the old CMR building, which has been neglected, contaminated, and has several abandoned wings. This fault was the major reason given to build a new facility 1.2 miles away at TA-55.

The Lab has big plans for plutonium. In December 2008, NNSA released a Record of Decision for its Complex Transformation Environmental Impact Statement that keeps manufacturing and research and development involving plutonium at Los Alamos and blesses the building of the CMRR-NF. This decision was a combination of two alternatives – a Distributed Centers of Excellence and a Capability-Based alternative. But to compensate for the nearby fault lines, the CMRR-NF is now being designed with 10-foot thick concrete floors and there are plans being designed to pump grout into a layer of fragile volcanic ash under the proposed facility. Current construction estimates for this facility are $2 billion.

The Lab has been negligent in taking care of its plutonium flagship, TA-55. It has not been a good steward of plutonium missions. Los Alamos is the wrong location, seismically. Congress must seriously consider ending this unnecessary plutonium work.