LANL Heading Down Slippery Slope With Proposed Biosafety Lab

The DOE Inspector General released Audit Report on “Management of the National Nuclear Security Administration’s Biosafety Laboratories” that calls for a re-evaluation of the proposed needs for Biolabs at nuclear weapons facilities such as Los Alamos.

The report stated that Los Alamos National Laboratory was considering a $9.5 million expansion of bio-laboratory capabilities even though the Lab could not assess current usage or future needs. Apparently the Lab based facility-planning decisions on perceptions about future demand.

From the report –

[DOE] identified the development of a BSL-3 facility at LANL as its preferred alternative for meeting biosafety laboratory needs even though it had not fully considered the need for and cost effectiveness of additional capacity. Nor, had it developed a sound basis for measuring the utilization of existing facilities – a critical factor in determining the need for additional capacity.

Biological containment levels range from BSL-1, which handles only agents not known to cause illness in humans, to BSL-4, which houses agents for which there are no known cures, such as Ebola. A BSL-3 designation permits work with virulent pathogens used in both defensive and offensive biological warfare research.

Although the BSL-3 building has been constructed, the need is very questionable. From the report –

Specifically, we contacted two of the three Federal agencies that LANL told us were prospective [Work For Other] WFO customers and officials representing those potential customers stated that they did not have any specific plans to contract for BSL-3 research at LANL. Further, officials at both agencies indicated that other existing BSL-3 facilities could satisfactorily meet their needs. In fact, one official told us that generally other existing BSL-3 laboratories were less expensive than expected at the new LANL facility and that several had comparable security.

While the BSL-3 building has been constructed, there is no compliance with the National Environmental Policy Act (NEPA).  The draft Environmental Impact Statement (EIS) currently being prepared for BSL-3 facility operations pursuant to NEPA has not even been released, much less a final EIS or Record of Decision (ROD).  The current schedule calls for the EIS to be released in August 2014, but if past schedule changes are indications, it is not going to happen.

The draft EIS has been in process for nine years and counting. We at NukeWatch demand that DOE start over and re-scope both the alternatives and need for the BSL-3 at LANL. LANL is working on a Biological Research Capability Assessment to assess bioscience needs, which must be completed before the BSL-3 is re-scoped.

We hope the current Assessment is more empirical than the 2011 Review, which proposed that the BSL-3 facility was essential to LANL’s mission without considering data such as available capacity at other locations and estimates of projected use from outside customers.

The LANL BSL-3 EIS was the result of a lawsuit. During 2001 and 2002 NukeWatch contested the arbitrary and capricious public process DOE was using to justify its decision to build the proposed BSL-3 facilities at LANL and Lawrence Livermore National Laboratory (LLNL). DOE failed to adequately address the many concerns raised by the public and proceeded to release final Environmental Assessments (EAs) for both laboratories, along with so-called Findings of No Significant Impact, which gives the Department the green light to begin the first steps leading to operations. Because DOE left so many legitimate questions and concerns unanswered, NukeWatch felt that a legal challenge was necessary.

In August 2003 NukeWatch and Tri-Valley CAREs, a citizens group based in Livermore, CA, jointly filed a lawsuit in the federal district court of northern California claiming that DOE had failed to fully analyze the environmental and health risks associated with the proposed operation of its BSL-3 facilities at LANL and LLNL. In effect, DOE wrote itself a blank check for a wide range of infectious disease research at the two labs. NukeWatch and Tri-Valley CAREs argued that DOE failed to consider the grave risks of introducing pathogens whose behavior may not be known or understood, and for which a cure may not exist.

In January 2004, DOE announced that it had revoked approval for its newly constructed, advanced bio-warfare agent research facility at Los Alamos. DOE went back to square one, and reviewed whether the agency needed to undertake a full Environmental Impact Statement – a key demand in the lawsuit. The BSL-3 at LLNL was built and is operating.

DOE released a notice for the LANL EIS on November 29, 2005. The Notice of Intent to prepare an EIS for the BSL-3 stated that one reason requiring preparation of an EIS was that “it was necessary to conduct additional seismic analysis of the location of the building on fill material on the sloping side of a canyon.” This calls into question not just whether BSL-3 activities can be safely conducted before these issues are resolved through the EIS, but whether any operations can be safely conducted at all.

The drawing below shows the LANL BSL-3 built in a seismic zone, on fill, and on a steep slope.

Review of the Stability Analysis for the LANL BSL-3 Building Foundation, UCRL-TR-226737, November 2, 2006


The DOE-IG report stated that LANL would need to spend about $437,000 in upgrades to attempt to mitigate this seismic concern.  DOE also is spending about $478,000 to complete the now required Environmental Impact Statement

Another $595,000 is needed to open the facility, which includes $368,000 of operating costs for maintenance, utilities, etc.

Can the Laboratory be the best place for bioscience? If the Lab is looking for more funding streams, shouldn’t it be directing its attention to non-proliferation programs and cleanup?

 

DOE Retroactively Classifies Suspect WIPP Drums As Ignitable

DOE Retroactively Classifies Suspect WIPP Drums As Ignitable

In two letters posted to the NMED website, Los Alamos contractor and DOE Field Office officials informed NMED that 86 drums currently stored at LANL and 368 drums underground in Panel 6 at WIPP are now considered to contain ignitable wastes. These drums are part of the same waste stream as the drum in Panel 7 that is suspected to have caused the Feb. 14 radiation release and the subsequent closure of the Waste Isolation Pilot Plant (WIPP).

The letters state that DOE applied EPA Hazardous Waste Number D001 for the characteristic of ignitability.

The WIPP Permit specifically prohibits D001 Wastes at WIPP –

2.3.3.7. Ignitable, Corrosive, and Reactive Wastes

Wastes exhibiting the characteristic of ignitability, corrosivity, or reactivity (EPA Hazardous Waste Numbers of D001, D002, or D003) are not acceptable at WIPP.

DOE stated that it had “reason to believe that the nitrate salt bearing waste in the containers described above is an oxidizer and therefore the D001 code should be applied to the respective containers”, but did not explain exactly what that reason was. What did LANL or the Accident Investigation Board (AIB) discover that lead them to apply the D001 classification? The AIB report investigating the Feb. 14 release is not due until September.

Now there are 368 illegal drums buried at WIPP. DOE can’t seal up Panel 6 until the exact cause of the Feb 14 release is known, even though there is a plan to expedite closure of Panel 6.  NMED Secretary Ryan Flynn has stated on several occasions that that we must know the exact cause before sealing up Panel 6. We agree. Otherwise we might be burying drums that should be retrieved and repackaged, as onerous of a task that that would be.

DOE stated, “Because the investigations are ongoing, the application of the D001 is considered provisional and may change to include and/or remove containers/waste streams in the future.”  But the WIPP permit has no provision for allowance for “provisional” classification wastes.

Either they are or they are not.

Relevant to NNSA biolabs – – C.D.C. Closes Anthrax and Flu Labs After Accidents

Today’s New York Times has a very relevant article for those concerned about biolabs at National Nuclear Security Administration  sites (i.e., Los Alamos and Livermore Labs).

The money quote: “Dr. Frieden [Director of the CDC] himself suggested that the accidents had implications for labs beyond his agency, arguing that the world needs to reduce to absolute minimums the number of labs handling dangerous agents, the number of staff members involved and the number of [bio]agents circulating.”

As Marylia Kelley of Tri-Valley CAREs can attest to, Livermore is conducting aerosolized experiments with anthrax and other “select agents.” In its inadequate environmental assessment (a lesser cousin of an “environmental impact statement”) LLNL disingenuously declared a certain amount of pathogens to be at risk during a major event. We discovered only through litigation discovery that ~10 times the amount of pathogens would be permanently kept at the biolab in freezers, which NNSA did not disclose in the EA. This, of course, is near the  densely populated, highly seismic Bay Area, which  could have its electrical grid destroyed during a major earthquake.

See:

http://www.nytimes.com/2014/07/12/science/cdc-closes-anthrax-and-flu-labs-after-accidents.html?emc=edit_th_20140712&nl=todaysheadlines&nlid=60715476&_r=0

C.D.C. Closes Anthrax and Flu Labs After Accidents

By JULY 11, 2014

Los Alamos Rated Easiest County to Live in

Los Alamos Rated Easiest County to Live in

The team at The Upshot, a NYTimes news and data-analysis venture, compiled six basic metrics to give a picture of the quality and longevity of life in each county of the nation. They were attempting to answer the question, Where are the hardest places to live in the U.S.? To create an overall ranking, they averaged each county’s relative rank in these categories: educational attainment, household income, jobless rate, disability rate, life expectancy and obesity rate.

The #1 ranking, and hence easiest place to live, went to Los Alamos County, home of Los Alamos National Laboratory, which spends 65% of its annual budget on nuclear weapons production and design. “The Lab directly employs one out of every five county residents and has a budget of $2.1 billion, which an enormous economic engine for a county of just 18,000 people,” the article states. A look at surrounding counties shows that this engine does not power the surrounding counties equally.

Rio Arriba is ranked #1966 out of 3,135 counties

Taos County = #1234

Sandoval County = #420

Santa Fe County =  #148

 

Some specific comparisons:

63.2 percent residents have at least a bachelor’s degree in Los Alamos.

Rio Arriba County = 15.9%

Taos County = 28.8%

Sandoval County = 28.1%

Santa Fe County = 39.3%

 

The median household income in Los Alamos County is $106,426.

Rio Arriba County = $40,791

Taos County = $33,835

Sandoval County = $58,116

Santa Fe County =  $53,642

 

In Rio Arriba County, 8 percent of residents are unemployed, and 1.9 percent are on disability.

The corresponding figures in Los Alamos County are 3.5 percent and 0.3 percent.

Taos County = 9.1%, and 1.2%

Sandoval County = 8%, and 1%

Santa Fe County = 5.5% are unemployed, 1% are on disability

 

Los Alamos County residents live on average 82.4 years

Rio Arriba County = 75 years

Taos County = 79.3 years

Sandoval County = 79.4 years

Santa Fe County = 80.1 years

 

And Los Alamos County’s obesity rate is 22.8 percent,

Rio Arriba County = 34%

Taos County = 29%

Sandoval County = 32%

Santa Fe County = 22%

 

Making nukes and the livin’s easy.

Missed WIPP Deadline May Put Real Cleanup at LANL Back On Track

Missed WIPP Deadline May Put Real Cleanup at LANL Back On Track

Santa Fe, NM – Today the New Mexico Environment Department (NMED) denied extension requests by Los Alamos National Laboratory (LANL) to delay cleanup milestones under a legally enforceable 2005 Consent Order. These denials by NMED counter a trend since January 2012 when NMED and LANL entered into a nonbinding “Framework Agreement” to ship 3706 cubic meters of above-ground transuranic waste from the Lab to the Waste Isolation Pilot Plant (WIPP) for permanent disposal. LANL radioactive wastes are now the main suspect in the February 14 contamination and subsequent shutdown of the multi-billion dollar WIPP.

NMED denied 14 extensions, now available in LANL’s Electronic Public Reading Room. These denials include construction of monitoring wells, and investigation reports for cleanup of contaminated areas. All of them included language that LANL requested an extension based on the Lab’s need to divert resources to remove transuranic waste in accordance with the Framework Agreement. The denials repeatedly state, “Based on the Permittees’ [LANL’s] statement that they will not be able to meet the deadlines that they committed to in the Framework Agreement [to ship TRU wastes to WIPP], the request is hereby denied.”

NMED had previously agreed to over 100 of these extension requests in favor of the so-called 3706 Campaign. The campaign was part of a non-binding agreement with the NM Environment Department so there are no penalties associated with lack of performance. The problem is that much other cleanup at the Lab was delayed while the 3706 Campaign was prioritized.

The Lab will miss the June 30 deadline of shipping 3,706 cubic meters of transuranic waste while the cleanup of over 1,000,000 cubic meters of all types of radioactive waste, hazardous waste, and contaminated backfill buried across the Lab were put on the back burner. These vast amounts of buried wastes, dating back to the Lab’s early days, are covered under the 2005 Consent Order for the “fence-to-fence” cleanup of legacy wastes. The Consent Order is enforceable with financial penalties for missed deliverables.

The Lab has claimed that there is not enough money to address all the Consent Order deliverables, but the original intent behind the Consent Order was that fines or the threat of fines would shake federal cleanup funding from DOE headquarters in Washington, DC. Cleanup without the big stick of possible fines just takes us back to the time when the small budget received annually just gets sprinkled around to where the cleanup “priorities” are perceived to be.

Jay Coghlan, Nuclear Watch New Mexico Executive Director, commented, “After granting more than one hundred extension requests to delay cleanup, we salute the New Mexico Environment Department for denying further requests. We encourage NMED to enforce what it already has, and make LANL comply with its legally mandated cleanup order. This in turn will drive increased federal funding for genuine cleanup at the Lab, creating hundreds of jobs while permanently protecting our precious water and environment.”

Scott Kovac, Nuclear Watch New Mexico Program Director, commented, “We look forward to continuing enforcement of the 2005 Consent Order and the necessary removal of Cold War legacy waste buried in unlined trenches above our aquifer.”

January 2012 Framework Agreement

LANL’s Electronic Public Reading Room

Sample of denial

 

 

DOE Headquarters Launches an Investigation Into the WIPP Release

DOE Headquarters Launches an Investigation Into the WIPP Release

On June 16, 2014, the U.S. Department of Energy (DOE) DC Office of Independent Enterprise Assessments notified Nuclear Waste Partnership, LLC, the operating contractor for DOE’s Waste Isolation Pilot Plant, of its intent to conduct an investigation.  The investigation will look into potential nuclear safety, worker safety, and health programmatic deficiencies associated with the two events in February.

WIPP has been shut down since February 5, 2014, when a salt-hauling truck caught fire, forcing evacuation of 86 workers from underground, 13 of whom were treated for smoke inhalation. Nine days later, an air monitor detected radiation underground where waste had recently been emplaced. The emergency filtration started, but radioactive particles were released to the environment. That resulted in contamination of all 13 people working above ground.

The DOE headquarters’ investigation may be a good start (hopefully), but Nuclear Watch NM, and many other groups, wants a truly independent, public investigation. This investigation should determine the cause of the WIPP radiation release, the extent of underground and surface contamination, the medical and compensation requirements for contaminated workers, and options for cleaning up underground and surface contamination.

In the meantime, TRU must be stored safely and securely at other DOE sites, regardless of how long WIPP is closed.  Unnecessary waste shipments should not occur while WIPP is closed. Additional newly-generated TRU waste from nuclear weapons production, which exacerbates existing problems, should not be produced.

Los Alamos Budget is 65% Nuclear Weapons

Los Alamos Budget is 65% Nuclear Weapons

LANL Lab Table Chart FY 2015
Percentages of the Los Alamos annual budget for 2015

There are people who don’t realize that there still are nuclear weapons in the world. There are those who don’t realize that Los Alamos is still in the nuclear weapons business. I’ve created a chart that illustrates that nuclear weapons activities are 65% of the Lab’s annual $2.1 billion dollar budget. The actual Laboratory table from the Department of Energy’s (DOE’s) budget is included.

First, please remember to add three zeroes to all the numbers in the table because all “Dollars in Thousands”.  And remember that the Fiscal Year (FY) 2015 Request numbers are just the President’s request, which Congress then slices and dices to arrive at the final appropriation during the congressional budget process.

Notice the largest FY 2015 Request budget by far is “Total Weapons Activities” at $1,417,502,(000). That’s $1.4 billion. “Total Defense Environmental Cleanup”, which is the remediation of radioactive and hazardous waste, is $222,262,(000). That’s $222 million.

The full budget categories are described in Volume 1 of the DOE budget here.

This page also has the Laboratory Tables on it. In addition, there is a “FY 2015 State Table” that shows all of New Mexico receives a total of $4.6 billion from DOE annually including $3.4 billion for nuclear weapons. Sandia National Laboratory in Albuquerque has a $1.5 billion request for nuclear weapons for FY 2015.

What is not on the Laboratory Tables is “Work For Others”, which is work that Los Alamos performs for government agencies other than DOE. This number is estimated at $250 million for FY 2015.

Let me know if you have any questions.

GAO report on NNSA’s dismantlement program

There are lots of interesting nuggets in the Government Accountability Office’s  recent dismantlement report. “Nuclear Weapons: Actions Needed by NNSA to Clarify Dismantlement Performance Goal,” April 2014, GAO-14-449, www.gao.gov/assets/670/662840.pdf

Selected highlights below. Verbatim excerpts follow page numbers (add 5 for PDF page number). General points in italics are mine.

Republican presidents, not Dems, make significant stockpile cuts, and do so unilaterally.

1: …in September 1991, the President announced several unilateral initiatives to reduce the U.S. nonstrategic nuclear weapons arsenal. The following month, the Soviet President responded that the Soviet Union would reduce its nonstrategic nuclear weapons. In addition, as part of the annual presidential stockpile review process, in 2004, the President directed that the U.S. nuclear weapons stockpile be reduced by more than 40 percent by 2012 and, in 2007, he directed an additional reduction of the stockpile, making it roughly one-quarter the size of cold war-era levels.

Dismantlements resulting from New START are being held hostage to construction of the Uranium Processing Facility and the Chemistry and Metallurgy Research Replacement Nuclear Facility at LANL.

29: DOD officials told us that the retirement of additional weapons from the stockpile stemming from New START will be predicated on the successful restoration of the NNSA weapons production infrastructure, including the construction and operation of new NNSA facilities supporting nuclear weapons production—the Chemistry and Metallurgy Research Replacement Nuclear Facility at LANL, and the Uranium Production Facility at Y-12—which they did not believe could be achieved until the late 2020s or early 2030s.

Pantex dismantlement workforce could be lost.

29: …this gap in dismantlement workload in the mid-2020s could result in the loss of certified dismantlement personnel because dismantlement technicians at Pantex lose their certifications if they have not worked on a weapon type within the past year. As a result, Pantex may need to retrain and recertify sufficient numbers of new dismantlement personnel in the late 2020s to resume dismantlement efforts to address retired weapons stemming from New START.

NNSA dismantlement rates have plummeted.

21: According to our analysis of dismantlement data, since the early 1990s, NNSA’s dismantlement rates have generally decreased, with NNSA dismantling about 1,000 fewer weapons annually in recent years than it was dismantling in the mid-1990s. In addition, in some years, only one or two types of retired war reserve weapons were dismantled.

NNSA dismantlement reporting is misleading.

23: How NNSA measures progress toward its performance goal of dismantling all weapons retired prior to fiscal year 2009 by the end of fiscal year 2022 is unclear and may make its reported progress misleading, including its practice of not tracking the actual date of retirement of individual dismantled weapons and its plans to reinstate to the stockpile—rather than dismantle—certain weapons retired prior to fiscal year 2009.

 Nine percent of “retired” nuclear weapons may go back to the active stockpile.

25: …how NNSA measures progress toward its dismantlement performance goal is also unclear and may be misleading because some weapons retired prior to fiscal year 2009 are reinstated to the stockpile rather than dismantled. Specifically, in our analysis of NNSA’s dismantlement schedule as of March 2013 for weapons retired prior to fiscal year 2009, we found that approximately 9 percent of the weapons retired prior to fiscal year 2009 are scheduled to be reinstated during fiscal year 2013 through fiscal year 2022 or later.

Long retired weapons may come back to active stockpile.

27: The W84-0s and W80-1s currently in managed retirement may not be available to NNSA for dismantlement prior to fiscal year 2022 because both of these systems are being held in managed retirement as candidates for potential reuse as the warhead on a future long-range standoff missile to replace the Air Force’s current ALCM.

Contrary to NNSA claims Life Extension Programs will not decrease total stockpile size, especially when coupled with slower dismantlement rates.

28: As a hedge against technical problems in the life extension program process and in the refurbished warheads, however, the W76-0s are to remain in managed retirement and be unavailable for dismantlement until the life extension program processes and W76-1 unit reliability are “satisfactorily established,” …creating uncertainty as to whether the W76-0s in managed retirement will be released to NNSA in time for dismantlement by the end of fiscal year 2022.

Inconsistent W76-1 production.

28: These officials stated that it would be difficult to predict the completion of the W76-1 life extension program given inconsistent production, and that it was impossible to say whether the W76-0s in managed retirement could be released for dismantlement prior to fiscal year 2019 without additional confidence in NNSA’s production capability.

New START does not change total stockpile numbers, and as previously stated retired weapons can be pulled back to the active stockpile.

29: DOD officials said that the United States will meet the New START ceiling—1,550 operationally deployed nuclear weapons—to be in force by 2018 by transitioning currently deployed nuclear weapons to nondeployed “hedge” status without any significant change in the total stockpile size.

Interesting allusion to the Navy’s lack of support for the interoperable warhead, which could doom it for good.

32: …potential loss of military interest in a future planned common, or interoperable, warhead to replace the W78 and W88

GAO quotes NNSA estimated amounts for accelerated dismantlements, which might be handy for advocacy purposes. However, perhaps as a matter of its timing, the report fails to note the Obama Administration’s proposed 45% cut for dismantlement funding in FY 2015. Separately, the FY 2015 NNSA Stockpile Stewardship and Management Plan states that dismantlements are only 1% of funding for Direct Stockpile Work.

33: NNSA estimated at the time that approximately $212 million in additional funding on top of the projected baseline budgets… would be needed to achieve the fiscal year 2018 dismantlement scenario. Alternatively, NNSA estimated that $265 million in additional funding on top of the projected baseline budgets… would be needed to achieve the fiscal year 2020 scenario.

 Dismantlements save money!

35: According to Navy officials we interviewed, accelerating dismantlement of retired W76-0 warheads allowed the Navy to avoid constructing new weapon storage facilities, saving the Navy approximately $190 million in estimated construction costs.

41: NNSA is retaining two types of CSAs [Canned Subassemblies, AKA secondaries] as options for reuse in a potential future W78 warhead refurbishment… In addition, NNSA is also retaining four types of CSAs as options for reuse in a warhead on the Air Force’s planned long-range standoff missile… NNSA officials told us that CSAs associated with a certain warhead indicated as excess in the 2012 Production and Planning Directive are being retained in an indeterminate state pending a senior-level government evaluation of their use in planetary defense against earthbound asteroids… the national labs’ retention letter has also characterized the CSA associated with this warhead as an “irreplaceable national asset.”

42: Y-12 is projected to disassemble far fewer CSAs than in NNSA’s 2009 Production and Planning Directive.

45: As of May 2013, Pantex was storing 3 million mark quality nonnuclear components as a contingency inventory for potential reuse in maintaining active stockpile or refurbished weapons.

49: Pantex site contractors told us that some of these boxes may contain parts that are up to 60 years old and that may be radiologically contaminated, which makes them difficult to handle and identify.

After a Failed Campaign, the State Must Return to Enforceable Cleanup At LANL

After a Failed Campaign, the State Must Return to Enforceable Cleanup At LANL

The June 30 deadline of the “3706 Campaign” to remove 3706 cubic meters of transuranic waste stored on the surface on Los Alamos Lab will be missed due to the radiation release and shutdown of the Waste Isolation Pilot Plant. The campaign was part of a non-binding agreement with the NM Environment Department so there are no penalties associated with lack of performance. The problem is that much other cleanup at the Lab was delayed while the 3706 Campaign was prioritized.

The Lab missed the low bar of shipping 3,706 cubic meters of transuranic waste while the cleanup of over 1,000,000 cubic meters of all types of radioactive waste, hazardous waste, and contaminated backfill buried across the Lab were put on the back burner. These vast amounts of buried wastes, dating back to the Lab’s early days, are covered under a 2005 Consent Order for the “fence-to-fence” cleanup of legacy waste. The Consent Order is enforceable with stipulated penalties of up to $3000/day for missed deliverables. But NMED has been hesitant to impose fines, because of DOE claims that the fines come out of the cleanup budget. The deadline for the last cleanup under the Consent Order is currently December 2015, which everyone agrees is impossible. But that end date could be extended, and should be extended, especially if the Lab was actually working on the legacy cleanup

NMED, to date, has granted over 95 extensions for Consent Order deliverables in favor of the 3706 Campaign. These extensions allow the Lab to not drill monitoring wells and to not perform cleanup investigations and work plans for sites across the Lab. The Lab claims that there is not enough money to address all the Consent Order deliverables, but the idea behind the Consent Order was that fines and the threat of fines would shake cleanup funding from DOE headquarters in DC. Cleanup without the big stick of possible fines just takes us back to the time when the small budget received annually just gets sprinkled around to where the cleanup “priorities” are perceived to be. Urgency and comprehensiveness go out the window.

The Cold War has been over for twenty years now and we in Northern New Mexico have been patient in removing LANL’s legacy waste.

But now Northern New Mexico has neither a 3706 Campaign that is complete, nor a Consent Order that will be complete by its deadline. NMED officials have stated, upon the successful completion of the 3706 Campaign, that they would consider renegotiating the Consent Order. We are waiting to see how NMED deals with the 3706 failure and we urge NMED to make the Consent Order the priority again. The Campaign approach has now been proven not to work.

In the meantime, we also have contaminated WIPP workers.

We have 707 possibly explosive drums probably created by Los Alamos spread across New Mexico and West Texas.

We have a damaged WIPP, which is shut down for up to three years and missing its deadlines for disposing waste.

We have other impacted DOE sites across the country, which will be missing deadlines for radioactive waste disposal.

We the taxpayers are no doubt going to spend hundreds of millions on this fiasco while the contractors continue to put money in their pockets.

The New Mexico Environment Department is the regulator here. Relying on LANL’s promises and plans to make things better must end. Time to return to the 2005 Consent Order and actually use the enforceable provisions in it.

LANL Management Irregularities Continue

LANL Management Irregularities  Continue

Los Alamos National Security (LANS), the private consortium that runs Los Alamos National Laboratory under contract for the federal government will manage $2.1 billion of our taxpayer dollars this year. LANS should remember that they were hired to represent the nation’s interests, not the interests of the for-profit corporations running the Lab.

 Scott Sandlin, Albuquerque Journal Staff Writer, reported a $3.64 million judgment against Los Alamos National Laboratory for “breach of implied contract and breach of the duty of good faith and fair dealing.” The plaintiffs claimed that Los Alamos conducted the federally funded bidding process, procurement and subsequent protest “using secret policies and procedures inimical to a fair and open bidding procedure.” The Journal disclosed that, according to the lawsuit, the contract was worth roughly $395 million over the first five years  and almost $800 million over the decade.

Despite the judgment, LANS denied that it had departed from procedures and also denied deviating from its customary practices.

 

This follows the March resignation of Los Alamos National Laboratory Deputy Director Beth Sellers, the second-highest ranking administrator at the Lab, for failure to properly report a potential conflict of interest when her husband received a lab consulting contract in 2012. This was also from the ABQ Journal.

The Lab determined that the consultant agreement did not conform to prescribed LANL procedures and processes.” The consultant/husband charged two hours “for a discussion on environmental matters that never took place” and which was actually a visit to the Santa Fe Opera. Los Alamos National Security (LANS), the private consortium that runs the lab under contract with the federal government, reimbursed the government for over $23,000 for the improper contract.

 

This comes after the November 2013 revelation that Ex-Congresswoman Heather Wilson was paid by nuclear weapons labs the day after she left office. An Albuquerque Journal article built upon a Department of Energy (DOE) Inspector General investigation, which determined that the Sandia and Los Alamos Labs had made approximately $450,000 in improper payments to Wilson up until March 2011, when she began to campaign for the Senate.

A DOE IG report said that the facts indicate that federal funds were used for prohibited lobbying activities, which that office is still investigating. The Labs were forced to return that money to the government, but not Wilson.

The Albuquerque Journal received the new information concerning the dates of Wilson’s contract with Sandia from Nuclear Watch New Mexico. The watchdog organization obtained the documents by appealing an initially rejected federal Freedom of Information Act (FOIA) request.

 

Nuclear Watch New Mexico Is A Proud Participant In Give Grande

Give ¡Grande! New Mexico is Tomorrow!

On Tuesday, May 6th, you have the opportunity to support local nonprofits and generate significant funds for causes in New Mexico. Large and small gifts will combine for big impact that will support local efforts!

Just log onto www.givegrandenm.org and give to the nonprofits of your choice. Make a tax-deductible contribution online, and your gifts will be added to those of others as the whole state comes together to support the causes we all care about.

Also, come celebrate with us on Tuesday in Santa Fe! Join us to celebrate New Mexico’s first “Day of Giving” from 3:00-6:00 pm at San Isidro Plaza on the South Side! Print out and bring your Give ¡Grande! receipt to get 10 % off your meal at the Plaza Cafe Southside, the Capitol Bar & Grill, and Pizza Centro.

At 5 p.m. Plaza Cafe Southside will cut a giant cake shaped like the state of New Mexico. We also have invited TV stations to stop by about 5:00 pm to do broadcasts for their evening news.

98.1 Radio Free Santa Fe and 107.5 Outlaw Country will be broadcasting live throughout the celebration, and computers will be available for you to make donations on-site.

The Community Foundation Coalition of New Mexico (Coalition), comprised of the Albuquerque, Taos, Southern New Mexico, New Mexico and Santa Fe Community Foundations, is proud to host Give Grande NM, the biggest online philanthropic event in New Mexico history! Community members will come together to raise as much money as possible for local nonprofits in 24 hours. Every dollar will go directly to nonprofits! It’s a great way to recognize and support the positive work of these local organizations.

Donations will begin being accepted on May 06, 2014 12:00 AM MDT.

 

Enabled by your contribution Nuclear Watch will continue to work diligently to:

• Oppose so-called “modernization” of the nuclear weapons complex and directly related expanded capabilities for increased nuclear weapons production.

• Oppose modernization of the nuclear weapons stockpile itself, which we believe is substantially about creating new military capabilities through planned “Life Extension Programs.”

• Stop expansion of WIPP.

• Promote comprehensive cleanup at Los Alamos and all DOE sites.

• Promote mission change at LANL. We will continue to redirect the Lab from core nuclear weapons research, testing and production programs to today’s critical national security challenges, such as preventing the proliferation of nuclear weapons, promoting clean national energy independence, and studying global climate changes.

• Strive to be your worthy representative locally and in Washington, DC, on nuclear weapons issues that affect our communities, New Mexico, the nation, and the world.

Thank you!


U.S. Nuclear Weapons Agency Claims Phony Budget Savings

New Report: U.S. Nuclear Weapons Agency Claims Phony Budget Savings;
Misleads Congress and Taxpayers About Real Costs of New Warheads; Nonproliferation and Dismantlement Programs Cut

Santa Fe, NM – The House Armed Services Committee is currently pushing a defense bill that pushes back against the Obama Administration’s plans to delay production of a new air launched cruise missile warhead and new nuclear warheads that would be “interoperable” between land-based ICBMs and sub-launched missiles. Related, the bill also calls for speeding up expanded plutonium pit production at the Los Alamos National Laboratory.

The House Armed Services Committee is objecting to delays, but not the substance, of plans by the Department of Energy (DOE) to heavily modify existing nuclear weapons during “Life Extension Programs” to create the new nuclear warheads. DOE’s FY 2014 “Stockpile Stewardship and Management Plan” (SSMP), which first introduced these new warheads, caused considerable sticker shock in Congress. Now DOE has released a new FY 2015 SSMP that it claims is “generally affordable and more executable than the program proposed in the FY 2014 SSMP.” However, an analysis by Nuclear Watch New Mexico concludes that DOE’s new sales pitch is based on overly optimistic claims and outright omissions that should alarm Congressional budget hawks.

DOE’s nuclear weapons agency, the National Nuclear Security Administration (NNSA), is notorious for cost overruns. Its FY 2015 plan misrepresents reduced costs by:

•     Delaying projects and their costs – which almost always results in higher total costs.

•     Lowering budget estimates while claiming undocumented improved cost modeling – when NNSA has an abysmal record in cost estimates.

•     Claiming $7.5 to $9.5 billion in savings for NOT doing a Life Extension Program – which in fact was never planned.

•     Omitting costs of directly related programs – which may exceed the costs of the Life Extension Programs themselves.

•     Depicting costs as gradually tapering off – while failing to disclose that even more expensive follow-on programs are planned 20 years after the first round of Life Extension Programs.

•     Perhaps most significantly, assuming the armed services will help pay for heavily modified nuclear weapons – when in fact the U.S. Navy does not want them (see internal memo below).

Missing is justification of why an extensively tested, reliable stockpile needs to be heavily modified during Life Extension Programs. According to a recent DOE Inspector General audit report, NNSA failed to diligently keep original “as-built” designs, when that information “is the foundation upon which the NNSA surveillance program assesses the current stockpile. Without it, NNSA loses confidence in its nuclear weapons stockpile assessments.” Changes could possibly erode confidence in nuclear weapons reliability, especially if original design information is lacking as a baseline.

The non-partisan Congressional Budget Office (CBO) recently reported that NNSA and the Pentagon plan to spend $355 billion over the next decade on nuclear weapons and their delivery systems. Meanwhile, the Obama Administration’s FY 2015 budget request cuts funding for nonproliferation, dismantlement and nuclear safety programs, and keeps cleanup funding flat.

Jay Coghlan, Nuclear Watch Director, commented, “Congress should demand that NNSA rigorously justify any proposed changes to existing reliable nuclear weapons. The antidote to exorbitantly expensive, potentially harmful modifications to the reliable stockpile is genuine stewardship that would preserve original weapons designs. This is far less risky and provocative, and would free up money for critically needed nonproliferation, dismantlement, nuclear safety and cleanup programs.”

Strongly recommended: Nuclear Watch’s detailed analysis of NNSA’s FY 2015 Stockpile Stewardship and Management Plan, including sources and key NNSA excerpts https://nukewatch.org/importantdocs/resources/FY2015-SSMP-analysis.pdf

An Executive Summary is available at https://nukewatch.org/importantdocs/resources/FY2015-SSMP-analysis-summary.pdf

# # #

The NNSA FYs 2014 and 2015 Stockpile Stewardship and Management Plans are available at https://web.archive.org/web/20170714130201/https://nnsa.energy.gov/ourmission/managingthestockpile/ssmp

The Congressional Budget Office report Projected Costs of Nuclear Forces 2014 -2023 is available at http://www.cbo.gov/sites/default/files/cbofiles/attachments/12-19-2013-NuclearForces.pdf

For U.S. Navy lack of support for heavily modified nuclear warheads see “Navy Perspective of W78/88 LEP Phase 6.2,” September 27, 2012, https://nukewatch.org/importantdocs/resources/Navy-Memo-W87W88.pdf

 

NNSA Digs Deep To Find A Reason To Give Itself Award

The award for the largest nuclear facility project completed ahead of schedule and under budget by NNSA goes to a project came in only 1% under budget after spending $40 million in contingency.

In an April 2 2014 National Nuclear Security Administration press release titled, NNSA Receives Secretary’s Award for Project Management Excellence, the Chemistry and Metallurgy Research Building Replacement (CMRR) Radiological Laboratory/Utility/Office Building (RLUOB) Equipment Installation (REI) Project was touted for coming in $2 million under budget.

First, the CMRR is the now-deferred project at Los Alamos, whose third phase Nuclear Facility would have enabled increased plutonium pit production. The RLOUB was the first phase of the CMRR project. The second phase REI is only the “equipment” for the RLOUB.

The press release tells us –

“The REI installed glovebox and other enclosure systems, analytical and test instrumentation equipment, and telecommunications and safeguards/security systems within the RLUOB.”

Also included, but not mentioned in the press release, were a fuel oil storage tank, furniture, and the parking lot.

It looks like NNSA gave the award in part because it could have been worse. With one year left in the 3-year the contract, it was estimated that the project was $8 million over budget. So NNSA put a new team in charge and straightened out their mess-ups and turned it around to a $2 million savings.

The press release tells us –

“The CMRR/RLUOB REI Project is the largest nuclear facility capital asset project completed ahead of schedule and under budget by NNSA.”

The press release also neglects to give the total budget. Our documents show that REI had a total budget $199 million. That makes the $2 million that the REI came in under budget equal to 1% of the total budget.

But our documents also show that there was $41.6 million (26%) contingency included in the $199 total budget. After spending untold millions in design and then estimating the cost of the project, NNSA adds in a large contingency to every project so that it does not go over budget and have to go back to Congress for more money.

Is the REI, which spent $40 million in contingency, really $2 million under budget?

I think not. NNSA must give the public all the facts and figures when it gives glowing appraisals of itself.

 

Here’s what we have on the REI –

 

WIPP Continues to Show Signs, Town Hall Webcast Tonight, LANL TRU to WCS, More Information

WIPP Continues to Show Signs, Town Hall Webcast tonight, LANL TRU to WCS, More Information

WIPP Underground Continues to Show Signs of Radiological Activity

The Waste Isolation Pilot Plant officials stated that there was another radiological release on March 11.  This was outside of the WIPP site exhaust shaft filter. An air sample from the outside of the ventilation exhaust recorded 61 disintegrations per minute of americium on a sample collected the evening of March 11. WIPP stated that, “This is expected given the amount of contamination captured by the WIPP ventilation system during the February 14 radiation release event. Engineers believe the contamination was from previous deposits on the inner surface of the exhaust ductwork.” The engineers did not state why they expected this and did not mention the LARGE amount of contamination captured by the WIPP ventilation system filters. The engineers also did not state why they believed this and not that more contamination was being produced in the underground.

Air sampling results before and after the High Efficiency Particulate Air (HEPA) filters at WIPP are available here. Station A samples air before the filters and Station B samples air after passing through the filters. These samples were analyzed following the detection of airborne radioactivity on February 14, 2014. They are not environmental samples, and are not representative of the public or worker breathing zone air samples.

The 3/11/14 4:19PM increase after the filters is shown here. There were other small releases on 03/02/2014 08:50 AM (38 dpm) and 03/05/2014 08:10 AM (60 dpm, although WIPP claims that the filter was “cross contaminated”)

There was a larger event, before the filters, that occurred 03/13/2014 08:30 AM (368 dpm) that has not been mentioned. All this shows that the underground could still be brewing radiological activity. Perhaps this will be explained better tonight at the Town hall.

 

Weekly Town Hall Meetings in Carlsbad?

Thursdays at 5:30 – Carlsbad City Council Chambers, City Hall, 101 N. Halagueno St.

Co-hosted by City of Carlsbad and U.S. Department of Energy (DOE) Carlsbad Field Office

Discuss recovery efforts following WIPP’s fire and radiological events in February.

Meetings available live online

 

The Show Goes On

The Department of Energy (DOE), is proposing to ship transuranic waste currently located at the Los Alamos National Laboratory (LANL) for temporary storage at Waste Control Specialists (WCS), located in western Andrews County, Texas. LANL has another ~546 cubic meters remaining out of the original 3706 cubic meters that was agreed to be moved to WIPP by June 2014.

Let’s be clear, there is no technical reason to store the waste temporarily at WSC.  DOE and LANL just want to show that they can meet a deadline. The extra cost of this operation has not been released. And don’t get me wrong, no one wants the waste – all the waste  – removed from LANL more than me.  Let’s hope that DOE and LANL show the same amount of interest and resources when it comes to removing the rest of the waste at Los Alamos, such as the hundreds of thousands of cubic meters of radioactive and hazardous wastes buried at Area G.

 

Official Websites

New Mexico Environment Department WIPP website

DOE/WIPP website

 

WIPP Informational Meeting in Santa Fe

A WIPP informational meeting will take place in Santa Fe on Monday, March 31st from 6 to 7:30 pm at the Santa Fe Main Library, located at 145 Washington, in downtown Santa Fe.  Please note the new location.  Don Hancock, of Southwest Research and Information Center, Scott Kovac, of Nuclear Watch New Mexico, and Sasha Pyle, longtime activist, will give presentations. Opportunities for public involvement will be discussed.

DOE Nuclear Weapons Budget Surpasses Cold War Record

FOR IMMEDIATE RELEASE March 17, 2014

DOE Nuclear Weapons Budget Surpasses Cold War Record

Bomb with New Military Capabilities up 20%

Dismantlements Cut By Nearly Half

Nonproliferation Programs Down 21%

Cleanup Funding Flat

 

Santa Fe, NM – The Obama Administration has finally released its detailed budget for fiscal year 2015, which starts October 1. By law the president’s proposed budget is required to be released not later than the first Monday of February.

Contrary to President Obama’s rhetoric about a future world free of nuclear weapons, most famously expressed in his April 2009 speech in Prague, the President asks for a 7% increase for nuclear weapons research and production programs under the Department of Energy’s semi-autonomous National Nuclear Security Administration (NNSA). NNSA’s “Total Weapons Activities” are slated to rise to $8.3 billion in FY 2015, and to an astounding $9.7 billion by FY 2019, 24% above this current fiscal year 2014. Obama FY 2015 budget request sets a new record for DOE nuclear weapons spending, even exceeding the Cold War high point in 1985 under President Reagan’s military buildup.

Of particular interest is the hands-on nuclear weapons work in the budget category “Directed Stockpile Work,” increased by $305 million (or 12.5% above FY 2014), whose overwhelming focus is Life Extension Programs (LEPs). President Obama wants $634 million (+20%) for the B61 nuclear bomb LEP, which has already exploded in costs from an originally estimated $4 billion to more than $10 billion. Each bomb will end up costing more than twice its weight in gold.

In addition to extending the service life of the bomb by decades, this Life Extension Program will combine three tactical or “battlefield” variants and one strategic variant together into one all-purpose nuclear bomb. The LEP will also transform the B61 from a simple analogue bomb into a digital bomb that interfaces with future super-stealthy fighter aircraft, which themselves will cost an astronomical $1 trillion (although not all will be assigned to a nuclear mission). A separate $1.8 billion Defense Department program for a new tail fin guidance kit will transform the B61 into the world’s first nuclear smart bomb. Despite all this, the U.S. government denies that it would ever endow existing nuclear weapons with new military capabilities.

While rebuilding nuclear weapons at exorbitant expense, the Obama Administration proposes to slash dismantlements by nearly half (45%), from an already paltry $54.2 million to $30 million. Dismantlement work at the Pantex Plant will be cut by 40%. Ironically, much of the dismantlement work that remains is “to provide parts for the life extension programs (B61 and W80-1).” Dismantlements will continue at the same rate at the Y-12 Plant, but its primary aim is to produce “feedstock [highly enriched uranium] for internal and external customers (e.g. Naval Reactors).” Dismantlements are described as a “a workload leveler across all programs,” indicating that instead of being a prioritized step toward a future world free of nuclear weapons, it is merely filler work in between rebuilding nuclear weapons during Life Extension Programs. NNSA FY15 budget, PDF page 109. [All following page numbers are in the same format.]

The construction of the Uranium Processing Facility at the Y-12 plant is capped at $6.5 billion. A recent study by the Pentagon’s Office of Cost Assessment and Project Evaluation predicted that this exorbitant facility, originally estimated by NNSA at ~$600 million, would cost between $12 to 19 billion. To bring it in at $6.5 billion NNSA has cut out all dismantlement and HEU downblending operations, making it a production-only nuclear weapons plant (pp. 319-323).

NNSA’s budget “Defer[s] the W78/88-1 LEP to some date beyond FY 2019” (p.  84), effectively meaning its cancellation. The W78/88-1 LEP was to produce a proposed “interoperable warhead,” using the plutonium pit from a third warhead, the W87. Nevertheless, the Los Alamos National Laboratory plans to “Build W87-design developmental pits each year to sustaining [sic] fabrication capability” (p. 117). The controversial Chemistry and Metallurgy Research Replacement (CMRR) Project for expanded plutonium pit production remains abandoned, but NNSA plans to raise the amount of plutonium used in the already constructed Rad Lab and pursue “pre-conceptual design efforts for the modular acquisition concept” to substitute for the CMRR (p. 219). NNSA still plans to “Execute a plutonium strategy [at LANL] that achieves a 30 pit per year capacity by 2026,” (p. 70) for which it gives no clear requirement or reason.

Key nonproliferation programs designed to halt the spread of nuclear weapons have been slashed by $300 million (-21%), even though nuclear weapons are recognized as the greatest existential threat to the United States. “Defense Environmental Cleanup”, the nation-wide program to clean up the Cold War legacy of radioactive and toxic contamination, is being cut from $5.8 billion to $5.6 billion, despite the fact that estimated costs keep climbing.

All of this is evidence of a pattern where the U.S. will spend massive amounts on nuclear weapons “modernization,” while nonmilitary domestic services are cut or flat lined. In December 2013 the nonpartisan Congressional Budget Office (CBO) released its study Projected Costs of Nuclear Forces 2014 -2023. Its stunning conclusion was that estimated costs for maintenance and “modernization” of the nuclear weapons stockpile, delivery systems, and research and production complex would total $355 billion over the next decade. The CBO also reported that costs after 2023 would increase yet more rapidly since “modernization” is only now beginning. The report did not attempt to project costs for maintenance and modernization of nuclear forces over the planned period of the next thirty years, but given current trends it will easily exceed one trillion dollars.

In one piece of good news the NNSA is finally putting the Mixed Oxide (MOX) Fuel Fabrication Facility at the Savannah River Site in South Carolina in “cold standby.” The MOX program is a failed attempt in the laudable goal of disposing of 34 metric tons of weapons-grade plutonium. The MOX Program’s life cycle costs have exploded to an estimated $30 billion, and NNSA is now studying cheaper alternatives. This has major positive impacts on the Los Alamos National Laboratory (LANL), which was slated to process 2.5 metric tons of plutonium every year as feedstock for the MOX Fuel Fabrication Facility. It also further undermines the need to build massive new plutonium facilities at LANL.

Jay Coghlan, Nuclear Watch New Mexico Director, commented, “Increased budgets for nuclear weapons are being paid off the back of dismantlements, nonproliferation and cleanup programs, which is just plain wrong. It’s common knowledge that NNSA’s nuclear weapons programs have a staggering track record of cost overruns, schedule delays and security breaches. It’s less well known that these programs may undermine stockpile reliability by introducing unneeded, incredibly expensive changes to existing nuclear weapons that have been extensively tested and are known to be even more reliable than originally thought. Clearly, NNSA’s nuclear weapons programs should be cut to help pay for the expansion of nonproliferation programs that actually enhance national security, cleanup programs that protect the environment while creating jobs, and dismantlement programs that get of nuclear weapons forever.”

# # #

For budget release requirement not later than the first Monday of February see U.S. Code, Title 31, Subtitle II, Chapter 11, § 1105, “Budget contents and submission to Congress.”

The FY 2015 DOE nuclear weapons request is calculated as the highest ever using data from Atomic Audit, Brookings Institute, 1998, Stephen Schwartz editor, Table A-2. It gives 5.494 billion in 1996 dollars as the cost for DOE nuclear weapons research, production and testing programs in 1985. Adjusted for inflation that is $8.259 billion in 2014 dollars.

The NNSA’s FY 2015 budget is available at http://energy.gov/sites/prod/files/2014/03/f12/Volume_1_NNSA.pdf

The Congressional Budget Office report Projected Costs of Nuclear Forces 2014 -2023 is available at http://www.cbo.gov/sites/default/files/cbofiles/attachments/12-19-2013-NuclearForces.pdf

 

WIPP Update March 14 – Truck Fire Report Is Released

WIPP Underground Fire Investigation Summary Report of Accident on February 5, 2014
The salt haul truck that caught fire was approximately 29 years old.
The investigation of the truck fire did not reveal exactly what started the blaze but did find:
•Maintenance program was ineffective
•Fire protection program was less than adequate
•Emergency management/preparedness and response program were ineffective

Truck Fire Accident Report Summary

Underground Salt Haul Truck Fire at the Waste Isolation Pilot Plant February 5, 2014 Accident Investigation Report

3/13/14 Town Hall Meeting Webcast from Carsbad

 

 

 

 

 

 

 

 

 

WIPP Town Hall Webcast Tonight, Thursday March 13 2014

 

Weekly Town Hall Meeting Scheduled for Thursday March 13 2014

Carlsbad Mayor Dale Janway and DOE will co?host weekly town hall meetings to update the community on recovery activities at WIPP. The meetings will be held every Thursday at 5:30 p.m. at the Carlsbad City Council Chambers, 101 N. Halagueno Street. If you can’t attend, you can view the meeting on line at https://web.archive.org/web/20140417222404/http://new.livestream.com:80/rrv/wipptownhall.

Here is a video of the March 6 DOE WIPP Town Hall.

 

 

 

DOE releases predicted spread of WIPP contamination

We now have a look at DOE’s predicted contamination spread, available at the  Waste Isolation Pilot Plant (WIPP) update page.

This model is based on three air samplers, and no samplers to the Northeast. There are still many questions, including:

What caused this release in the first place?

How contaminated is the underground?

Are soil samples being collected? From where?

 

Modeling has been done to estimate onsite worker and offsite public dose that may have resulted from the February 14, 2014, event. The results of the modeling indicate that all potential doses were well below the applicable regulatory limits (see results below). The modeling results are consistent with actual worker bioassay results. For modeling data see: (http://www.wipp.energy.gov/Special/Modeling Results.pdf)

Estimated Dose Maximum estimated worker dose 10 mrem Maximum estimated public dose 0.1 < 1 mrem

Natural Background 310 mrem

Applicable Regulatory Limit

5000 mrem per year

DOE all?paths limit (adults) 100 mrem per year

DOE all?paths limit for children/pregnant women 25 mrem per year

EPA Air (NESHAPs) Standard for inhalation is 10 mrem per year

 

 

 

 

Mine Games – WIPP Update March 10, 2014

Mine Games

In a March 9th press release, the Nuclear Waste Partnership (NWP), the management and operations contractor at the Waste Isolation Pilot Plant (WIPP) for the U.S. Department of Energy (DOE), stated their plans to reenter the ailing salt mine/nuclear waste repository after a radiological release shut down operations over three weeks ago.

The press release tells us that, on March 7 and 8, radiological and air quality instruments were lowered down the Salt Handling and the Air Intake Shafts. The preliminary findings indicated that no “detectable radioactive contamination” in the air or on the equipment. The press release claims that these results were expected because the shafts that were sampled were not in the air flow path coming from the area where the radiation release originated.

But, there are 4 shafts to underground – the Salt Handling, the Air Intake, the Waste Handling, and the Exhaust Shafts. After the detection on a radiologic release, filters move into the Exhaust Shaft and air is drawn to the outside by fans blowing to the outside here. The other three shafts, mainly the Air Intake Shaft because it has no elevator in it, provide intake for the air flow path to the Exhaust Shaft. Strangely missing from the press release is any mention of the Waste Handling Shaft, which contains an elevator to take the waste down into the mine and should also have been out of the air flow path. DOE and NWP must explain why the Waste Handling Shaft was not sampled and, if it was, what are the results. The Waste Handling Shaft provides the normal entry to the underground, so why use the Salt Shaft? Also, the press release did not mention that any “soil” samples were taken from the walls of any of the shafts. Is the Waste Handling Shaft contaminated or presumed contaminated?

As far as the air flow path goes, it’s an elaborate game to get the air to flow where it is needed in the underground of WIPP. Getting the desired path requires blocking off numerous openings in the underground. Bob Martin from KRQE gave a hint of what is involved in his recent report. We have not been given the diagram for the air flow path at the time of the release or even if the path was in place. We don’t have the location of all the monitors in the underground and if they were working. What was the presumed path of the contaminated air to the Exhaust Shaft? Why are so many details left out out of the information released to the public?

Unfortunately, the press release also mentioned that four more WIPP workers had been contaminated. But it was not stated where or when these employees received the dose. Was it Friday night or Saturday? Why was this important information not in the press release?

We also have some new sample findings released. Some of the interesting information here is that the WIPP Laboratory Analyses are so much lower than the Screening Analyses. I will get back to you on that. But don’t forget that it is unlikely that the main release actually hit any of the air monitors dead-on. Also, notice the lack of samplers to the northeast.

We will have to wait for soil samples to come in before we can begin to estimate the main path of the release.

WIPP is not a secret facility. (They even let me down there last year.) Press releases that raise more questions than they answer must stop now.

Great Article form La Jicarita – What’s Wrong with WIPP

 

What’s Wrong with WIPP by lajicarita

By DON HANCOCK, Southwest Research and Information Center (SRIC)

The world’s first geologic repository for military nuclear waste is making international news because of the radiation leak that was detected late at night on Valentine’s Day. An unknown amount of radioactive and toxic chemical waste was released to the environment from the Waste Isolation Pilot Plant (WIPP). On February 26, the 13 workers at the site when the leak was detected were notified that they tested positive for internal radiation contamination.

Since the Department of Energy (DOE) and Nuclear Waste Partnership (NWP), the operating contractor, have repeatedly stated that WIPP would “start clean, stay clean” and not release any radioactivity for at least 10,000 years, the leak was never supposed to happen. The health danger that persists for thousands of generations is the reason to put the wastes underground so they are not released to the environment. Thus, an obvious question: What’s wrong with WIPP?

Also, what effect does the leak have on DOE plans to expand WIPP and what is the opposition to such proposals?

*Some of the unknowns about the February 2014 radiation leak*

As of March 4, there is much more that is unknown than known:

* What caused the leak?

* How much leaked into the underground salt mine?

* How much leaked into the environment?

* Where are those radioactive and toxic wastes now?

* To what amount of radiation were the workers exposed?

* What are the health effects for those workers?

* What decontamination is necessary in the underground mine?

* What decontamination is necessary on the WIPP site and surrounding area?

* If WIPP reopens, what changes in the operation, monitoring, and safety culture will be implemented?

[Much, much more]

 

WIPP Video Story and Congressional Delegation Statements from KRQE

KRQE TV 13 aired a news story last night that included statements from the five members of the NM Congressional Delegation:

On the recent radiation leak: “From my perspective on the (U.S. Senate Energy and Natural Resources) committee, the first priority is making sure that the personnel who actually work at WIPP are safe and that the community and environment around WIPP is safe.”

On whether high-level waste should be stored at WIPP: “WIPP was never designed as a high level facility, and I don’t think we should retrofit it to be a high level facility. There has been talk of moving other transuranic waste there that was generated in different ways than the transuranic waste that’s coming from Los Alamos, for example. That’s something we can have the conversation about, but it should never be a high level facility.”

On any future change in WIPP’s mission: “We have a very long standing and robust conversation in my office with the community in Carlsbad all the time. The input from the community is always critical.” “There is nothing more important than making sure that that community feels like we are doing everything possible to make sure that WIPP is a success, and that the people who work there in the surrounding community and their well-being is our first priority.”

~ U.S. Sen. Martin Heinrich, D-New Mexico

 

“It’s too early to say whether the leak factors into my thoughts about the future of WIPP because we don’t know what happened. I’m taking the leak very seriously, and our focus right now is on the immediate safety of the community and WIPP personnel and the recovery work. It would be premature to draw any conclusions. This is a very technical issue, and the science is extremely important. My position on expansion now is the same as it has always been. When it comes to proposals that would significantly change WIPP’s mission, I support the provision in the current law that bans high-level waste at WIPP. WIPP was not fully studied for high-level waste, and it does not meet permit requirements for high-level waste. Additionally, New Mexico’s people and state government are the ones who have the power to decide what waste our state will accept and under what terms. Any attempt to alter WIPP’s mission would take many years of study, permitting, and require the state of New Mexico’s full support.”

~ U.S. Sen. Tom Udall, D-New Mexico

 

On the radiation leak: “Congressman Pearce has introduced legislation to protect New Mexico jobs at WIPP, which has safely disposed of TRU waste for over a decade. Right now, Congressman Pearce is focused on monitoring the present situation closely, ensuring DOE and WIPP continue to make public safety the top priority. To date, all information shared with our office indicates there is no risk or danger to the community. At the appropriate time, the Congressman fully expects and will insist that the Department of Energy conduct a thorough investigation and answer all the public’s questions.”

On whether high-level waste should be stored at WIPP: “Now is not the time to speculate about proposals that are not even on the table. Taking high level waste at WIPP is not on the table. Congressman Pearce’s number one priority right now is public safety, and there are many questions that need to be answered before any changes in WIPP’s mission are discussed.”

~ Eric Layer, Spokesman for U.S. Rep. Steve Pearce, R-NM 2nd District

 

“Right now, the number one priority is the health and safety of the WIPP employees who were affected by the leak as well as the residents of the surrounding community. As the response effort continues, there must be nothing short of full transparency and accountability to ensure the public that they are safe. This incident further proves that any expansion of WIPP’s mission warrants close scrutiny that’s rooted in science and that includes extensive outreach to and input from all stakeholders and local communities.”

~ U.S. Rep. Michelle Lujan Grisham, D-NM 1st District

 

“I am very concerned about the recent detection of radiation near WIPP and the health and safety of those exposed to radiation. It will be important that answers are provided detailing the causes of the elevated levels and how this will be prevented in the future. The safety and security of the community must be the top priority.

As far as the larger discussion about changes at WIPP, one aspect that cannot be forgotten or overlooked – especially given the recent incident – is the reality of exposure and what will happen when workers or members of the community are exposed to harmful levels of radiation. Sadly in New Mexico, we are all too familiar with the story of those who worked in uranium mines and other government facilities and suffered exposure to radiation. They contributed to our national security, yet paid a steep cost as many individuals became sick and some paid with their life. I am still fighting in Congress to see that many of these workers are compensated for the health problems they developed as a result of their work. While we hope we never have to face a similar situation in the future, it is important we have these discussions now rather than when it’s too late, especially given the recent reports that 13 workers tested positive for radiation exposure.”

~ U.S. Rep. Ben Ray Lujan, D-NM 3rd District

Nuclear Weapons Budget Increased, Nonproliferation and Cleanup Budgets Cut

FOR IMMEDIATE RELEASE March 4, 2014

Contact: Jay Coghlan, Nuclear Watch NM, 505.989.7342, c. 505.692.5854, [email protected]

 

Nuclear Weapons Budget Increased

Nonproliferation and Cleanup Budgets Cut

Good News: Wasteful Plutonium Program Shuttered

 The Obama Administration has released topline numbers for its FY 2015 budget for the National Nuclear Security Administration (NNSA), which owns the nation’s nuclear weapons complex of design laboratories and production plants. The NNSA’s budget category “Total Weapons Activities” is slated to be increased to $8.3 billion, $534 million above FY 2014 (+ 6.9%). Of particular interest is “Directed Stockpile Work,” increased by $305 million (+12.5%), whose overwhelming focus is Life Extension Programs. These programs not only extend the operational lives of existing nuclear weapons by decades, but also arguably give them new military capabilities, despite denials at the highest levels of government. Details are not yet available, but the increase for Directed Stockpile Work will probably mostly be for the B61 Life Extension Program. Its refurbishment of each nuclear bomb will cost more than twice their weight in gold.

This is the beginning of a pattern where the U.S. will spend massive amounts on nuclear weapons “modernization,” while nonmilitary domestic services are cut or flat lined. In December 2013 the nonpartisan Congressional Budget Office (CBO) released its study Projected Costs of Nuclear Forces 2014 -2023. Its stunning conclusion was that estimated costs for maintenance and “modernization” of the nuclear weapons stockpile, delivery systems, and research and production complex would total $355 billion over the next decade. The CBO also reported that costs after 2023 would increase yet more rapidly since “modernization” is only now beginning. The report did not attempt to project costs for maintenance and modernization of nuclear forces over the planned period of the next thirty years, but given current trends it will easily exceed one trillion dollars.

In stark contrast, key nonproliferation programs designed to halt the spread of nuclear weapons have been slashed by $300 million (-21%), even though nuclear weapons are recognized as the greatest existential threat to the United States. “Defense Environmental Cleanup”, the nation-wide program to clean up the Cold War legacy of radioactive and toxic contamination, is being reduced from $5 billion to $4.87 billion, despite the fact that estimated costs keep climbing.

Jay Coghlan, Nuclear Watch New Mexico Director, noted how Obama’s proposed nuclear weapons budget is upside down. He commented, “It’s common knowledge that NNSA’s nuclear weapons programs have a staggering track record of cost overruns, schedule delays and security breaches. It’s less well known that these programs may undermine stockpile reliability by introducing unneeded, incredibly expensive changes to existing nuclear weapons that have been extensively tested and are known to be even more reliable than originally thought. Clearly, NNSA’s nuclear weapons programs should be cut to help pay for the expansion of nonproliferation programs that actually enhance national security and cleanup programs that actually create jobs.”

In one piece of good news the NNSA is finally putting the MOX Fuel Fabrication Facility at the Savannah River Site in South Carolina on “cold standby.” The MOX program is a failed attempt in the laudable goal of disposing of 34 metric tons of weapons-grade plutonium. The MOX Program’s life cycle costs have exploded to an estimated $30 billion, and NNSA is now studying cheaper alternatives. This has major positive impacts on the Los Alamos National Laboratory (LANL), which was slated to process 2.5 metric tons of plutonium every year as feedstock for the MOX Fuel Fabrication Facility. It also further undermines the need to build massive new plutonium facilities at LANL.

# # #

Department of Energy and National Nuclear Security Administration topline budget numbers are available at

http://www.whitehouse.gov/sites/default/files/omb/budget/fy2015/assets/doe.pdf

and

http://www.energy.gov/sites/prod/files/2014/03/f8/15Highlights.pdf

 


QUESTIONS FOR DOE FY 2015 BUDGET

ALLIANCE FOR NUCLEAR ACCOUNTABILITY

A national network of organizations working to address issues of 

nuclear weapons production and waste cleanup

Ashish Sinha: (301) 910-9405 [email protected]

Bob Schaeffer: (239) 395-6773 [email protected]

 

for use with March 4, 2014 Obama Administration Budget Request

 QUESTIONS FOR THE U.S. DEPARTMENT OF ENERGY (DOE)

 FY 2015 NUCLEAR WEAPONS, REACTOR AND CLEANUP BUDGET

 

The U.S. nuclear budget is out of control. Huge cost overruns for unnecessary production facilities are common.  At the same time, cleanup of radioactive and toxic pollution from weapons research, testing, production and waste disposal is falling behind. The Department of Energy (DOE) budget for FY 2015 will reveal the Obama Administration’s nuclear priorities.

The Alliance for Nuclear Accountability (ANA), a 25-year-old network of groups from communities downwind and downstream of U.S. nuclear sites, will be looking at the following issues. For details, contact the ANA leaders listed at the end of this Media Advisory.

— Does the budget reflect the Administration’s commitment to curtail unnecessary spending on the $19 billion Uranium Processing Facility at Oak Ridge by downsizing it to the capacity needed to support stockpile surveillance, maintenance and limited life extension?

— Does the budget address the looming deficit in nuclear weapons dismantlement capacity so the United States can meet its international arms reduction commitments?

 

— Will the Obama Administration articulate its alternative plutonium strategy to the $6 billion “CMRR Nuclear Facility,” which was effectively cancelled in 2012? Is any expanded production needed when expert studies have found that existing plutonium pits are durable?

— Will NNSA reduce funding or impose meaningful milestones at the National Ignition Facility (NIF), which performed less than half of its planned Stockpile Stewardship experiments in FY2013 and still has not achieved ignition.

— Is the budget a de facto cancellation of plans to pursue “interoperable warhead designs” by imposing a delay of five years or more on the program? How much money will taxpayers save?

 

— Does the FY 2015 budget seek more than the $537 million requested for the B61 Life Extension Program last year? Will the “First Production Unit” from this $10 billion program continue to slip to 2020 or later delaying needed routine replacement of critical components?

— How much of the additional $26 billion in Defense Sec. Chuck Hagel’s “Opportunity, Growth and Security Initiative” will go to DOE nuclear weapons programs? 

— Will the Administration support increased funding for the Defense Nuclear Facilities Safety Board (DNFSB) to provide independent oversight of DOE projects given the many cost over-runs, schedule delays, safety issues and technical problems?

 

— What is the projected life-cycle cost of the plutonium fuel (MOX) program at Savannah River? Is DOE’s internal cost assessment consistent with ANA’s estimate of $27 billion? When will it be released? Have any nuclear reactor operators committed to using MOX fuel?

 

— Does the Request include continued funding for design and licensing of Small Modular Reactors (SMRs), which private investors have been unwilling to finance fully because of concerns about viability and risks? Does DOE have plans to finance SMR construction?

 

How much additional Environmental Management (EM) funding would be necessary in FY 2015 to meet all legally mandated cleanup milestones? States say cleanup agreements at a dozen major sites are underfunded by hundreds of million dollars.

— In which states does DOE face fines and lawsuits for missing milestones due to budget shortfalls? Which states are enforcing their binding clean-up agreements by imposing fines and taking further legal action?

— What is the high range for total life-cycle clean-up costs (LCC) for EM sites Because of funding shortfalls, are LCC costs continuing to increase? In the FY 2013 Budget Request High Range LCC was $308.5 billion, and in the FY 2014 Request LCC was $330.9 billion.
— Does the FY 2015 Request include funds to cleanup contamination from the recent radiation release at the Waste Isolation Pilot Plant (WIPP)?  How much will this incident delay shipments from the Idaho National Lab, Los Alamos, Savannah River, and Oak Ridge?

— How much money is included for construction of new double-shell tanks to replace those leaking radioactive waste at the Hanford site? Are funds included for emergency pumping of tanks found to be leaking?

— Is DOE allocating sufficient funds to monitor and address ignitable hydrogen gas buildup in Hanford’s nuclear waste tanks as recommended by the Defense Nuclear Facilities Safety Board to protect workers, the public and the environment from possible explosions?

— Is an independent review of the Hanford Waste Treatment Plant included in the budget request to address concerns about the reliability of many of the parts and materials?

– How much money is DOE allocating for building and development of the Hanford Waste Treatment Plant based on the current, flawed design and how much on redesign?

— For information about specific DOE nuclear weapons sites and programs, contact:

Meredith Crafton – Hanford: (206) 292-2850 x26 [email protected]

Tom Clements – Savannah River and MOX Plant: (803) 240-7268 [email protected]

Jay Coghlan – Los Alamos Lab and Life Extension: (505) 989-7342 [email protected]

Don Hancock – Environmental Management Program: (505) 262-1862 [email protected]

Ralph Hutchison – Oak Ridge Site and Dismantlement: (865) 776-5050 [email protected]

Marylia Kelley – Livermore Lab and Life Extension: (925)-443-7148 [email protected]

 

WIPP Update Feb 27 2014 – 13 Employees Contaminated

WIPP Update Feb 27 2014 – 13 Employees Contaminated

I’ll remind us all that the Waste Isolation Pilot Plant (WIPP) site is NOT a National Security site. It is a fancy landfill. There are really no secret programs there to protect. Maybe there are some secret parts buried there, but they have long-since been crushed. There is no reason to withhold news. The waste streams are well known and exactly where they are emplaced in WIPP is also well known. When the public gets news from WIPP officials, we deserve to have our questions answered clearly with all the important facts included.

Our best wishes go out to the employees.

Here’s the February 26, 2014 letter from the U.S. Department of Energy – Carlsbad Field Office, which provides oversight of the private contractor, Nuclear Waste Partnership, LLC, that currently manages and operates WIPP. Unfortunately, this letter raises many questions. Below are each of the paragraphs of the letter, followed by my questions and comments.

First Paragraph –

This morning (February 26), the 13 Waste Isolation Pilot Plant (WIPP) employees that were on site the evening of February 14 were notified that they have tested positive for radiological contamination. Employees were notified within about 12 hours of the receipt of preliminary sample results.

Ok, “the 13 Waste Isolation Pilot Plant (WIPP) employees that were on site the evening of February 14,” sounds like there were only 13 employees at WIPP on Feb 14. But the February 15, 2014, 9:17 PM WIPP press release states, “All non-essential employees were off-site by 5:30 PM MST.” The February 15, 2014, 9:17 PM WIPP press release also states, “No contamination has been found on any equipment, personnel, or facilities.” I guess we are to read this as, “No contamination has been found ON any personnel.”

Questions raised –

How many employees were onsite when?

Were the 13 contaminated employees essential or non-essential?

Were the non-essential employees (how many?) that left by 5:30 bioassayed?

How does an employee inhale rads and not have any on them?

 

Second Paragraph –

At the time of the event, these employees were performing above ground operations, and federal oversight duties at the WIPP facility. Nuclear Waste Partnership, LLC, the site contractor, requested that all workers on site the night of the event submit follow-up bioassay samples as they were considered more likely to have indications of potential exposure. Additional samples will be collected from these employees in the weeks ahead in order to perform complete analyses.

Questions raised –

When did Nuclear Waste Partnership, LLC request the bioassay samples from the night workers?

What made them “more-likely” to be exposed? What exactly were they doing?

Were the non-essential employees (how many?) that left by 5:30 bioassayed? When was this request made?

 

Third Paragraph –

It is premature to speculate on the health effects of these preliminary results, or any treatment that may be needed. However, on-site sampling and surveys and environmental monitoring, to date, continue to support National Atmospheric Release Advisory Center (NARAC) modeling, which indicates that airborne contamination was likely at very low levels.

Questions raised –

Where is the National Atmospheric Release Advisory Center (NARAC) modeling? The public must be allowed to read any and all reference documents. And by the way, NARAC is located at the Lawrence Livermore National Laboratory, which is a Department of Energy site. 

 

Fourth Paragraph –

The material for this release event is transuranic radionuclides. The release material was predominantly americium-241, material which is consistent with the waste disposed of at the WIPP. This is a radionuclide used in consumer smoke detectors and a contaminant in nuclear weapons manufacturing.

Questions raised –

Really? Smoke detectors? Here’s from the EPA

As long as the radiation source stays in the detector, exposures would be negligible (less than about 1/100 of a millirem per year), since alpha particles cannot travel very far or penetrate even a single sheet of paper, and the gamma rays emitted by americium are relatively weak. If the source were removed, it would be very easy for a small child to swallow, but even then exposures would be very low because the source would pass through the body fairly rapidly (by contrast, the same amount of americium in a loose powdered form would give a significant dose if swallowed or inhaled). Still, its not a good idea to separate the source from the detector apparatus.

All the americium at WIPP is the byproduct of Cold War nuclear weapons production. The Center for Disease Control (CDC) explains the health effects of americium.

The radiation from americium is the primary cause of adverse health effects from absorbed americium. Upon entering the body by any route of exposure, americium moves relatively rapidly through the body and is deposited on the surfaces of the bones where it remains for a long time. As americium undergoes radioactive decay in the bone, alpha particles collide with nearby cell matter and give all of their energy to this cell matter. The gamma rays released by decaying americium can travel much farther before hitting cellular material, and many of these gamma rays leave the body without hitting or damaging any cell matter. The dose from this alpha and gamma radiation can cause changes in the genetic material of these cells that could result in health effects such as bone cancers.

 

Fifth Paragraph – Here it states that inhalation did employees did occur.

Determining employee dose typically involves multiple sample analyses to determine employee’s radionuclide excretion rate over time. This allows the lab to estimate the employee’s accumulated internal dose. The time this process takes depends largely on the solubility of the inhaled particulate, with less water-soluble radioactive materials requiring more samples and time to accurately estimate the dose. Follow-up urine samples may require about three or more weeks to accurately predict dose.

 

Sixth Paragraph –

We are now focusing our sampling program on employees with work assignments that may have placed them at greater risk, including those on shift February 15. We are still reviewing staff assignments to determine if additional employees will need to be tested. However, employees who feel they were assigned positions or functions that placed them at risk will be included in follow-up bioassay monitoring at their request.

Questions raised –

How many employees were working on the 15th? Were they wearing safety protection?

What is the criterion “to determine if additional employees will need to be tested”?

 

Seventh Paragraph –

There is no risk to family or friends of these employees. As we learn more information, we will continue to share. If you have any questions or concerns, please contact 1-800-336-9477. Thank you.

Questions raised –

What is the current status at the site?

Are employees working there now?

Are they wearing protective gear?

 

There apparently is a Press Conference today (Feb27 2014) at 3pm MST.

WIPP update Feb 26 2014

The New York Times ran a WIPP story today, NUCLEAR WASTE REPOSITORY SET TO REOPEN AFTER LEAK, New York Times — February 26, 2014, By Matthew L. Wald

This is a good example of what is known, what is being said, and what is not being said.

1. One shaft has a filter with a monitor and three don’t. The article, and many others, quotes a WIPP press release,

But late on Feb. 14, at an hour when no one was in the mine, an air monitor indicated the presence of radioactive contamination. An automated system cut off most of the ventilation and routed the exhaust through filters that are supposed to capture 99.97 percent of all contamination, turning off fans and changing the air flow, in less than one minute. 

At WIPP, there are 4 ways for air to get to the surface – the Exhaust Shaft, the Salt Shaft, the Air Intake Shaft, and the Waste Handling Shaft. When radioactive contamination is detected, airflow is directed to the Exhaust Shaft as its filter is put into place. This shaft has the only filter and monitors on any of the shafts. WIPP officials claim that it was a monitor in Panel 7 that detected radiation and set into action the sending of all the air to the Exhaust Shaft. The Panel 7 monitor is around 2000 feet from the shafts. This means that the WIPP officials were relying on any contamination to set off the monitor before any contamination went up a shaft. We need a layout of the monitors, and if they were working, in the underground.

 

2. “Safe levels” of radioactivity? The article quotes a WIPP monitor,

“For someone living in town, I would say the dose was probably zero,” Russell Hardy, director of the Carlsbad Environmental Monitoring and Research Center, an independent monitoring organization that is part of New Mexico State University, said in a telephone interview Tuesday. He said that the event would not add to background levels of radiation — including bomb fallout — any more than an eyedropper full of water would contribute to the rise in the level of the Pacific Ocean.

Seriously, an eyedropper in the Pacific? I had to look it up

There are over 70 cubic million miles in the Pacific Ocean. Meaning there are 188,000,000,000,000,000,000 gallons in the pacific ocean. That is 187 quintillion gallons.

No problem, unless you eat the fish that drank that drop. Anyway, I don’t believe anyone knows how much radiation was released. The preliminary results are based on a ridiculously small number of air samples. The official projections are based on the implication that the samples represent the maximum contamination, which is unlikely.

 

3. Then, it was explained how to get dosed –

Even in the desert, the danger to humans was small, the mine’s operators said. The highest reading from the monitors indicated that a person could have inhaled radioactive material that would emit a dose, over the person’s lifetime, of 3.4 millirem, an amount roughly equal to three days of natural background radiation. But to get the dose, the person would have had to stand for hours in the desert, on the downwind side of the plant.

Again, the official projections are based on the implication that the samples represent the maximum contamination, which is unlikely. We await the many soil samples that will shed light on the actual amounts.

 

 

Scroll to top