WIPP Sold With a 10,000 Year Guarantee

WIPP Sold With a 10,000 Year Guarantee

WIPP CRA Meeting June 17 2015, Albuquerque, NM

 

10,000 years ago:

  • Jericho has been inhabited for a thousand years
  • Many megafauna go extinct, including the giant ground sloths, woolly rhinoceros, cave bear, and sabre-toothed cats (Mammoths survive in small groups for another 6500 years)
  • Cattle are domesticated and the plow is invented
  • In what is now northern Iraq, cultivation of barley and wheat begins.
  • Beer is first brewed.

 

10,000 years from now:

  • Sea levels will rise 3 to 4 meters
  • Technological civilization could reach end of its lifespan
  • Humanity has a 95% probability of being extinct
  • Pioneer 10 will pass within 3.8 light years of Barnard’s Star
  • The Waste Isolation Pilot Plant, for nuclear weapons waste, is planned to be protected until this time, with a “Permanent Marker” system designed to warn off visitors through both multiple languages (the six UN languages and Navajo) and through pictograms

 

Department of Energy and Environmental Protection Agency officials are also guaranteeing that the Waste Isolation Pilot Plant (WIPP) in southeast New Mexico will not release larger amounts of radiation for 10,000 yrs from the time that WIPP closes. Before recent events, WIPP was to end operations in the 2030 to 2035 timeframe when the last underground waste panel was full of nuclear weapons generated transuranic waste. Then there will be a 5-10 year period where it will be filled in and closed.

This 10,000-year guarantee is reevaluated and recertified every 5 years during a Compliance Recertification Application (CRA) process. EPA, has a unique authority – included in the WIPP Land Withdrawal Act – regarding radiation. EPA could deny certification and close WIPP down.  EPA last recertified WIPP in November 2010. The recertification decision is not subject to judicial review.

The protection requirement focuses on the annual radiation dose to a person living on the surface just outside the WIPP Land Withdrawal Act (LWA) boundary. In particular, the LWA requires that the “WIPP be constructed in such a manner as to provide a reasonable expectation that, for 10,000 years after disposal, undisturbed performance of the disposal system will not cause the annual committed effective dose equivalent (hereafter called “dose”) to exceed 15 millirems (mrem) (150 microsieverts) to any member of the public in the accessible environment.” (Pg. 55-1)

The difference this go ‘round is that a waste drum, improperly packaged at Los Alamos National Laboratory, released radiation and contaminated 21 workers at WIPP in February 2014.  WIPP has been closed since then. Hundreds of similarly improperly packaged drums are still in the underground at WIPP.

But wait, due to the CRA cycle, input data for this CRA was cut off in December 2012. It is unclear how information from the 2014 accident will impact this CRA. What is WIPP but the sum of all its operations? But DOE claims that current operations will not cause any radiation releases for the 10,000 years after WIPP closes.

 

How can such a claim be made? DOE uses computer modeling to do a Performance Assessment (PA). DOE claims that the information can be boiled down to a simple chart. 

Figure PA- 83. CRA-2014 PA and CRA-2009 PABC Overall Mean CCDFs for Total Normalized Releases

I can’t explain it but I was assured that that the 2014 CRA showed that WIPP was safer for 10,000 years than the 2009 CRA showed. (The solid 2014 curve is farther away the notched “Release Limits” line than the dashed red 2009 curve.) Image that – WIPP allegedly got safer in the last 5 years.

 

I guess the good news is that DOE and EPA are thinking about 10,000 years. The bad news is that we have to. We cannot continue to generate this waste that is only safe into the future because some software deems it so. The existing radioactive waste should be monitored and stored as close to the generating site, as safely as possible, where it was generated.

The radioactive isotope of the transuranic waste in WIPP is mostly plutonium 239. Plutonium 239 has a half-life of 24,000 yrs – more than twice the time addressed in this assessment.

 

Thanks to all who came out to the WIPP/EPA meetings last Wednesday, June 17.  And thanks for your concern in this important issue.

 

Read Olivier Uyttebrouck’s Albuquerque Journal Report on the afternoon session.

There is a video of the evening session comments.

All the Compliance Recertification Application documents are here

 

There is an opportunity to comment.

Please consider commenting that:

EPA must consider including all aspects of the Feb 2014 accident in this CRA.

EPA must forward all public comments to DOE for an official response.

EPA must re-inspect LANL before it can ship to WIPP.

EPA should re-inspect and approve all waste generating sites related to waste characterization before allowing WIPP to reopen.

Do not recertify WIPP until an independent qualified organization (independent of DOE, DOE con) provides an analysis that WIPP operation meets the intents and the promises made to New Mexico, is compliant with all statutory and regulatory requirements.

 

Please contact me if you have any questions.

 

WATCHDOG GROUPS HEAD TO D.C.TO URGE CONGRESS TO CONFRONT “THE GROWING U.S. NUCLEAR THREAT”

Alliance for Nuclear Accountability

A national network of organizations working to address issues of nuclear weapons production and waste cleanup

Nuclear Watch New Mexico

 

May 14, 2015

 

WATCHDOG GROUPS HEAD TO D.C. TO URGE CONGRESS, OBAMA ADMIN.

TO CONFRONT “THE GROWING U.S. NUCLEAR THREAT;”

NEW REPORT SEEKS CUTS IN BOMB PLANTS, WARHEAD MODERNIZATION

DIVERTING SAVINGS TO CLEANUP AND WEAPONS DISMANTLEMENT

            Dozens of community leaders from around the country will travel to Washington, DC next week to oppose U.S. Department of Energy (DOE) nuclear weapons projects, which they say will waste billions in taxpayer funds, damage the environment and undermine the nation’s non-proliferation goals. The group will meet with leading members of Congress, committee staffers, and top administration officials with responsibility for U. S. nuclear policies to press for new funding priorities.

Activists from nearly a dozen states are participating in the 27th annual Alliance for Nuclear Accountability (ANA) “DC Days.” They will deliver copies of ANA’s just-published report, The Growing U.S. Nuclear Threat (http://bit.ly/growing_nuclear_threat). The new 20-page analysis dissects the Obama Administration’s latest plans to spend hundreds of billions more on nuclear weapons programs without, the authors conclude, enhancing U.S. security.

Joining the Alliance will be four members of Nuclear Watch New Mexico: Dr. James Doyle, a nonproliferation expert fired by the Los Alamos Lab after writing a study arguing for nuclear weapons abolition; Chuck Montano, former LANL auditor and author of his just-released book Los Alamos: A Whistleblower’s Diary (http://losalamosdiary.com/index.html); Jay Coghlan, Executive Director; and Scott Kovac, Operations Director. “We will use this opportunity to represent New Mexicans who oppose the open checkbook policy for nuclear weapons by Congress to the National Labs,” Kovac stated.

Both Doyle and Coghlan have recently returned from the NonProliferation Treaty (NPT) Review Conference at the United Nations in New York City where they witnessed U.S. officials claiming that one trillion dollar plans for nuclear weapons modernization “contribute to and do not detract from progress on our NPT nuclear disarmament obligations.” But as Ralph Hutchison of the Oak Ridge Environmental Peace Alliance, the report’s editor, noted, “Massive spending on nuclear weapons ‘modernization’ increases the nuclear danger for the U.S. Lack of accountability at DOE wastes billions and puts the public at even greater risk. ANA members from across the country will urge policy-makers to cut programs that fund dangerous boondoggles. The money saved should be redirected to cleaning up the legacy of nuclear weapons research, testing and production.” Participants in DC Days include activists from groups that monitor such U.S. nuclear weapons facilities as Hanford, Lawrence Livermore, Rocky Flats, Los Alamos, Kansas City Plant, Pantex, Sandia, Oak Ridge, Savannah River and the Waste Isolation Pilot Plant.

The Alliance for Nuclear Accountability is a network of local, regional and national organizations representing the concerns of communities downwind and downstream from U.S. nuclear weapons production and radioactive waste disposal sites. As part of its DC Days, ANA will sponsor an Awards Reception honoring leaders of the movement for responsible nuclear policies on Monday evening, May 18. Honorees include U.S. Senator Harry Reid, U.S. Representative John Garamendi, Los Alamos whistleblower Dr. James Doyle, former FBI investigator of Rocky Flats Jon Lipsky, and nuclear campaigner Michael Keegan: The event will take place in Room B-340 of the Rayburn House Office Building from 5:30pm to 7:30pm.

After learning of his award, Dr. James Doyle replied, “It is an honor to be recognized by citizen organizations across the country who have been opposing nuclear weapons at the grassroots for decades.  The Alliance for Nuclear Accountability is an important part of the fabric of our civil society and helps create an informed citizenry essential to our freedom and security.  My case shows that even in America you must be careful when you question nuclear weapons.  These groups have been trying to change that since before I knew what nuclear war would mean for humanity.  I am proud to be working with them to eliminate nuclear weapons.”

– – 3 0 – –

NM Environment Department Starts Clock on Four Legacy Waste Penalties at LANL

NM Environment Department Starts Clock on Four Legacy Waste Penalties at LANL

The New Mexico Environment Department (NMED) has sent notices to Los Alamos National Laboratory (LANL) that the State intends to assess penalties for four environmental reports that have missed required deadlines. Each report could be subject to penalties of $1000 per day for the first 30 days late and $3000 per day thereafter starting at the date of the notice. These four assessments for FY2015 reports under the Consent Order (CO) showed up on the Los Alamos Electronic Public Reading Room (EPRR) daily notifications.

These four are the first Stipulated Penalties since 2009 that have assessed by NMED under the 2005 Consent Order. In January 2012, the State and DOE/LANL agreed to a “Framework Agreement”, which focused on shipping transuranic (TRU) waste from LANL to WIPP, and put the CO on the back burner. We believe that there were no Stipulated Penalties Lists at all for FY13 and FY14. NMED granted approximately 100 extensions to CO deliverables during this time, which were not subject to penalties.

Before the beginning of each DOE fiscal year (October 1st) NMED and DOE/LANS work out which 15 deliverables to the CO will have potential penalties attached during the upcoming fiscal year. These deliverables are documents or reports that cover activities required under the 2005 Consent Order, which lays out the fence-to-fence cleanup of legacy waste on the Lab’s 36 square miles. For instance, after a mandatory monitoring well is drilled, a Well Completion Report would be required. Each year there may be 40 to 50 or so deliverables required by the State, of which only 15 are chosen to be subject to penalties for being late or deficient.

TRU waste shipments stopped in February 2014 when a TRU waste drum (improperly packaged at LANL) overheated and released radiation in the underground at WIPP. The radiation reached the surface of WIPP and contaminated 21 workers. This TRU waste at LANL is not actually covered under the Consent Order, but much of the aboveground TRU (originally scheduled to be shipped before 2012) is physically in the way of CO cleanup at the Lab.

In December 2014, NMED fined DOE/LANL $37 million and DOE/WIPP $17 million for the release at WIPP. NMED Secretary Ryan Flynn has hinted that there may be up to $104 million in possible additional fines to DOE/LANL that also have nothing to do with consent order. But the four recent notices are all about the Consent Order.

These CO Stipulated Penalties may seem small compared the potential $100 million fines, but the Consent Order itself is the primary driver for cleanup at the Lab. There are millions of cubic meters of hazardous and radioactive wastes and contaminated backfill buried at LANL. These wastes will pose a permanent threat to our aquifer unless removed.

“The Consent Order was designed to keep pressure on cleanup of legacy waste at Los Alamos. Penalties for missed deadlines are aimed at forcing DOE headquarters in DC to provide sufficient funding. We are pleased that NMED is focusing on the Consent Order again and not backing away from assessing penalties. We have a long way to go and we must all remain vigilant as the Lab addresses each of the many cleanup sites at Los Alamos.” ~ Scott Kovac, Operations and Research Director, Nuclear Watch New Mexico

Consent Order Stipulated Penalty Documents for Federal Fiscal Year 2015

LANL Consent Order Extensions as of Jan 6 2015

Intent To Assess Stipulated Penalties – Phase II Investigation Report For Upper Canada Del Buey Aggregate Area, March 13, 2015

Intent To Assess Stipulated Penalties – Investigation Report For Upper Water Canyon Aggregate Area, March 13, 2015

Intent To Assess Stipulated Penalties – Installation And Instrumentation Of Six Boreholes At Material Disposal Area T at Technical Area 21, March 18, 2015

Intent to assess stipulated penalties – Investigation report for Starmer/Upper Pajarito Canyon Aggregate Area

 

 

Los Alamos Cleanup Budget Request Slips to 8% for FY 2016

 

Los Alamos Cleanup Budget Request Slips to 8% for FY 2016

 

 

 

 

 

 

 

Even as Los Alamos National Laboratory (LANL) faces more fines from the State for missed environmental cleanup, the cleanup budget request slips to 8% of the Lab’s total budget of $2.2 billion. The request for cleanup for Fiscal Year 2016 is $185.2 million. See the full chart and Lab tables here.

Even this ridiculously small amount is under attack. The ABQ Journal reported that the Department of Energy could be planning to pay for existing LANL fines out of this cleanup budget. In December 2014 the New Mexico Environment Department (NMED) issued fines totalling $37 million for improper waste handling that closed the Waste Isolation Pilot Plant in SE NM.

But really, the breeched drum that closed WIPP (full operations will not resume until 2018 at the earliest) came from the nuclear weapons activities programs. It’s like the weapons program handed the environmental cleanup program a ticking time bomb and said, “You deal with it.” Then when it blows up, it gets blamed on the environment folks. Reckless historic environmental practices by the nuclear weapons programs at the Lab have left a legacy of radioactive and hazardous wastes in the ground above our aquifer.

The official estimate for the total cleanup at Los Alamos has yet to be released. But it could easily $15 – 20 billion to remove the contamination threatening our future. Doing the math, a $15 billion cleanup estimate at $200 million per year would take 75 years. That is too long.

Ask your Congressional Representatives to fully fund cleanup at Los Alamos National Laboratory and to NOT use cleanup funds to pay any fines!

NM Senator Tom Udall

NM Senator Martin Heinrich

NM Congressional Representative Ben Ray Lujan

Questions for the DOE FY 2016 Nuclear Weapons and Cleanup Budget Request

The Administration releases its  Congressional Budget Request this Monday, February 2, 2015.

Questions for the U.S. Department of Energy FY 2016 Nuclear Weapons and Cleanup Budget Request

From

Alliance for Nuclear Accountability

A national network of organizations working to address issues of nuclear weapons production and waste cleanup

The US nuclear weapons budget continues to spiral out of control. Look for double-digit increases in Department of Energy (DOE) weapons activities. Core nonproliferation programs will be cut because of funding for mixed-oxide fuel. Cleanup of radioactive and toxic pollution from weapons research, testing, production and waste disposal will fall further behind. The DOE budget for FY 2016 will illuminate the Obama Administration’s misplaced nuclear priorities.

The Alliance for Nuclear Accountability (ANA), a 28-year-old network of groups from communities downwind and downstream of U.S. nuclear sites, will be looking at the following issues. For details, contact the ANA leaders listed at the end of this Advisory.

— Does the budget request boost funding for “modernization” programs that indefinitely maintain nuclear warheads? Such funding is contrary to the Obama Administration’s previously declared goal of a future world free of nuclear weapons.

— Does the budget reflect the Administration’s commitment to reduce funding (currently $335 million) on the multi-billion dollar Uranium Processing Facility at Oak Ridge by downsizing it to the capacity needed to support stockpile surveillance, maintenance and limited life extension?

— Does the budget increase funds for nuclear weapons dismantlement capacity? Will cooperative programs with Russia be maintained?

— Is there increased funding for expanded production of plutonium bomb cores? Why is expanded production needed when expert studies find that existing plutonium pits are durable?

— Is more than $300 million provided for the National Ignition Facility (NIF) at Livermore Lab that has repeatedly failed to achieve “ignition”? What is the funding level for uncontained plutonium shots although they will taint the NIF target chamber and optics with alpha radiation?

— Does the budget seek an increase for the B61 Life Extension Program (currently $643 million)?

— As DOE affirms that the $30-billion plutonium fuel (MOX) project at the Savannah River Site is financially unsustainable, is the MOX plant construction again proposed for “cold standby” (~$200 million) or a level to barely allow it to survive (~300+ million)? Does the budget include the current validated base-line cost of MOX plant, a validated construction and operation schedule and names of nuclear utilities willing to use experimental MOX fuel?

— Does the budget include $0 for Yucca Mountain? No funding is consistent with past requests that terminate this technically flawed site that is strongly opposed by Nevada state officials and the public.

— Does the budget provide additional Environmental Management (EM) funding (currently $5 billion) to meet all legally mandated cleanup milestones? States say cleanup agreements at a dozen major sites are underfunded by hundreds of million dollars.

– How will DOE and its contractors pay fines for missing milestones? In the past three months, the states of New Mexico, Idaho, and Washington have issued fines of tens of millions of dollars, and fines loom in South Carolina. In which other states does DOE face fines and lawsuits for missing milestones?

— What is the high range for total life-cycle cleanup costs (LCC) for EM sites? Because of funding shortfalls, High Range LCC costs have increased from $308.5 billion in the FY 2013 Budget Request, to $330.9 billion in the FY 2014 Request, and were $328.4 billion in the FY 2015 Request.

— How much does the budget include for the shut down of the Waste Isolation Pilot Plant (WIPP)? How much is for recovery and how much for waste emplacement (previously $220 million a year) even though no waste is being emplaced? How much additional funding is requested for the Idaho National Lab, Los Alamos, Savannah River, and Oak Ridge because of the shutdown?

— Does the budget for Hanford (more than $2 billion) protect workers from toxic chemical exposures, provide an Operational Readiness Review of the nuclear safety of the Waste Treatment Plant, and fund construction of new double-shell tanks to replace the leaking ones?

— Does the budget increase funding (currently $28.5 million) for the Defense Nuclear Facilities Safety Board (DNFSB) to provide independent oversight of DOE projects because of the many cost overruns, schedule delays, safety culture issues and technical problems?

— Is the funding for design and licensing of Small Modular Reactors (SMRs) enough to make them viable? As private financing is lacking, will DOE reaffirm that it will not finance SMR construction?

 

For further information, contact:

Jay Coghlan jay(at)nukewatch.org

 

Download the pdf and more contact info here.

 

Nuclear Weapons Sites Evaluations Released After NukeWatch requests

Performance Evaluation Reports For Nuclear Weapons Sites Continue to be Released After Nuclear Watch NM Freedom of Information Act requests

In response to a Freedom of Information Act (FOIA) lawsuit filed by Nuclear Watch New Mexico on March 28, 2012, the National Nuclear Security Administration (NNSA) released the FY2011 Performance Evaluation Reports for its eight nuclear weapons sites. These reports are the government’s scorecard for awarding tens of millions of dollars to nuclear weapons contractors, and were available to the public until 2009. But after that time NNSA withheld them in a general move toward less contractor accountability. We sought to begin to reverse that with our litigation.

In Spring 2013, NNSA released “Summary Reports” of the Weapons Sites’ FY2012 Performance Evaluation Reports (PERs). Nuclear Watch NM requested and received the full reports, which are posted on our site.

By Fall 2014, the FY2013 had still not been made publically available. In November 2104, Nuclear Watch NM filed a Freedom of information Act request for the FY2013 PERs. These PERs were posted online in December 2014.

Getting tired of waiting for the PERs every year made us file a Freedom of Information Act request for the FY2014 PERs sooner, which we did in mid December. The FY14 Performance Evaluation Reports were released this week, which is the earliest in the year that the PERs which been released in many years.

NNSA should be posting these important reports online without making us take up our valuable time filing for them. The Freedom of Information Act requires that “Frequently Requested” documents be posted in a reading room.

We don’t like it that we have to keep asking for the same reports year after year, especially reports that relate to such important programs and such large sums of taxpayers’ money. NNSA But we will keep doing it.

Check out our NNSA Performance Evaluation Page.

 

Watchdogs Urge Big Cut to Contractor Fees at the Sandia Labs

Watchdogs Urge Big Cut to Contractor Fees at the Sandia Labs

December 19, 2014 – The Project On Government Oversight and Nuclear Watch New Mexico sent the Department of Energy Secretary a letter urging that the FY 2014 contractor incentive award fee for the Sandia National Laboratories be completely denied. The two watchdog organizations wrote to the Secretary earlier this month to urge him to cut performance incentive award fees at least in half for the Los Alamos Lab contractor because of substandard performance that led to the contamination of 21 workers at the Waste Isolation Pilot Plant and the indefinite closure of that multi-billion facility. As deplorable as the Los Alamos situation is, the Sandia case is arguably worse because it involves direct violations of federal law that prohibit contractor use of taxpayers’ dollars to lobby the government for further work.

The Sandia Labs are run by the for-profit Sandia Corporation, wholly owned by the country’s largest contractor, the Lockheed Martin Corporation. According to its current contract with the federal government, the Sandia Corporation could earn up to $9.8 million in FY 2014 performance incentive award fees (it also stands to receive $18.3 million in fixed fees). In addition, Lockheed Martin could receive $2.8 million for “Home Office And Other Corporate Support,” which includes the subcategory “Provision of Corporate Ethics.” The Department of Energy should refuse to pay both because of improper lobbying of Congress and federal officials and Lockheed Martin’s ethical failure while doing so.

The Sandia Corporation’s unlawful lobbying has been well documented in two recent Department of Energy Inspector General reports. The first report concluded that Sandia had improperly paid ex-Congresswoman Heather Wilson (R.-NM) around $226,000 in consulting fees to lobby for additional work for the Sandia Labs. This began in January 2009, the day after she stepped down from office representing the congressional district in which Sandia is located. The DOE IG investigation forced the Sandia Corporation to reimburse the government the monies it had received to pay Wilson.

The second DOE IG report concluded: We believe that the use of federal funds for the development of a plan to influence members of Congress and federal officials to, in essence, prevent competition was inexplicable and unjustified… The evidence indicated that SNL and LMC [Lockheed Martin Corp.] officials had conversations with members of Congress and federal officials to convince the department, NNSA and Congress of the merits of contract extension without competition.

Peter Stockton, POGO’s senior investigator, commented, “This blatant attempt to pass along lobbying costs to taxpayers is revolting. Another example of catch me if you can. Reimbursement isn’t enough; DOE must punish Sandia for violating the law.”

Jay Coghlan, Nuclear Watch Director, commented, “The for-profit Sandia Corporation has made no public acknowledgment of responsibility or remorse. The Department of Energy must seriously cut Sandia’s award fees to make sure contractors get the message that business as usual corrupted by unlawful lobbying will no longer be tolerated. There should be no more contract extensions. Instead the management contract should be put out to bid as previously planned, until it was short-circuited by the Sandia Corporation’s illegal actions.”

# # #

The POGO/Nuclear Watch NM letter to DOE Secretary Ernest Moniz urging reduced award fees for the Sandia Labs contractor is here.

For the DOE IG reports, see:

Concerns with Consulting Contract Administration at Various Department Sites, Inspection Report: DOE/IG-0889, June 7, 2013, and

Alleged Attempts by Sandia National Laboratories to Influence Congress and Federal Officials on a Contract Extension, Special Inquiry: DOE/IG-0927, November 2014

 

GAO Seeks Broader Analysis For Proposed Liquid Waste Facility at LANL

GAO Seeks Broader Analysis For Proposed Liquid Waste Facility at LANL

The Government Accounting Office (GAO) was mandated to review the  “analysis of alternatives” (AOA) process applied by NNSA. The process entails identifying, analyzing, and selecting a preferred alternative to best meet the mission need by comparing the operational effectiveness, costs, and risks of potential alternatives. GAO developed a set of practices by reviewing AOA policies and guidance used by seven public and private-sector entities with experience in the AOA process. GAO’s review of DOE’s requirements for AOAs found that they conform to only 1 of the 24 best practices: the practice of defining functional requirements based on mission need.

DOE and NNSA officials acknowledge that unreliable AOAs are a risk factor for major cost increases and schedule delays for NNSA projects. As GAO has previously reported, NNSA has spent billions of dollars designing and partially constructing projects with an estimated cost of $750 million or more, only to later reassess alternatives. NNSA may continue on this path and continue to have limited assurance that it is selecting alternatives that best meet its mission needs and will not result in major cost increases and schedule delays in the future.

Overall, the National Nuclear Security Administration’s (NNSA) analysis of alternatives (AOA) conducted for the Radioactive Liquid Waste Treatment Facility (RLWTF) project only partially met best AOA practices. The mission need for this project—to replace the current, aging facility—was approved in October 2004. NNSA approved an initial AOA for this project in 2006, and after substantial cost increases, conducted a second AOA (analyzed here) in 2013. NNSA currently estimates the project will cost between $168 million and $220 million.

The GAO compared the AOA conducted at the Radioactive Liquid Waste Treatment Facility at LANL with AOA best practices in 24 areas.

For instance in best practices, the team or the decision maker defines selection criteria based on the mission need. What LANL actually did only partially met best practices because the Lab included in the project documentation brief summaries of the selection criteria used but did not describe how these were based on the mission need. LANL included only one of these selection criteria—the scope—in the mission need statement.

In another case, the team or the decision maker is supposed to weigh the selection criteria to reflect the relative importance of each criterion. Here best practices were not met because LANL did not include weighting selection criteria in project documentation.

The ailing facility is still operating.

During 2013, all treated water from the RLWTF was fed to the effluent evaporator. The evaporator was operated 3654 hours on 201 days during 2013, in both one-burner and two-burner mode. A total of 2.64 million liters of treated water were fed to the evaporator, and 2.55 million liters were discharged to the environment as steam from the evaporator stack.

Curies of radioactive materials fed to the effluent evaporator during 2013 were calculated by multiplying the evaporator feed volume (2,638,330 liters) times the flow-weighted average concentration of each radionuclide. Feed to the effluent evaporator in 2013 contained approximately 4.9E-04 curie alpha radioactivity, 3.35E-04 curie beta radioactivity, and 1.7E-02 curie of tritium.

This RLWTF is vital to nuclear weapons production operations at the Lab. But equipment failures could pose a risk to facility workers.

 

DOE AND NNSA PROJECT MANAGEMENT: Analysis of Alternatives Could Be Improved by Incorporating Best Practices

GAO-15-37: Published: Dec 11, 2014. Publicly Released: Dec 11, 2014.

 

Authors: Del Signore, John C. [Los Alamos National Laboratory]

2014-11-25, LA-UR-14-29097

Comments to DOE Re: Transition of Legacy Clean-up Work at Los Alamos National Laboratory

December 10, 2014

Jack R. Craig, Jr.

DOE EM

Re: Transition of Legacy Clean-up Work at Los Alamos National Laboratory

Mr. Craig,

Please consider these preliminary comments and requests concerning the transition of legacy clean-up work at Los Alamos National Laboratory.

Through comprehensive research, public education and effective citizen action, Nuclear Watch New Mexico seeks to promote safety and environmental protection at regional nuclear facilities; mission diversification away from nuclear weapons programs; greater accountability and cleanup in the nation-wide nuclear weapons complex; and consistent U.S. leadership toward a world free of nuclear weapons.

First, we request that alternatives to the current Department of Energy contract process be considered. The privatization of the nuclear weapons complex may be failing the U.S. taxpayer. Cost overruns plague the current system. Different variations of the same contractors still continue to line up for different variations of the same contracts. Yet, with a few exceptions, cleanup only crawls along. Many of the sites are still contaminated decades after the work was completed.  And now, WIPP is shut down.

We ask that alternatives such as looking to governmental agencies instead of private contractors be tasked with cleanup at Los Alamos. For instance, could the Army Corp. of Engineers do the job?

We also strongly request that alternatives to “No-Bid” and “Cost-Plus” contracts be considered first. Recently, Senate Armed Services Committee Chairman John McCain spoke to prohibit the Pentagon from awarding cost-plus contracts, arguing such deals encourage nefariousness. (DefenseNews.com, December 5, 2014)

Second, if a conventional contract is used, we request that the following specific items be included in the proposed new EM contract at LANL. We also ask that these items be included in the ‘bridge’ contract:

  • Must be tied to LANL Consent Order and LANL RCRA permit.
  • Any “campaigns” must be legally binding, and not used as justification to miss Consent Order milestones.
  • Should be more incentive based – less fixed.
  • Should be more transparent like ARRA, including public availability of Performance Evaluations.
  • Should have dramatically lower overhead costs, for example lower security and no LDRD costs. These overhead costs should be made public just as the old Functional Support Costs were available to the public.
  • Must include public update meetings semi-annually.
  • Should favor local/regional economic development.
  • Must have public update meetings at least semi-annually.

Third, for the new bridge contract and any final contract we ask:

  • Cleanup must continue at current pace during transition.
  • There must be a new lifecycle baseline – with the range with assumptions spelled out. Comprehensive cleanup must be considered, not just cap and cover.
  • Corrective Measures Evaluations must be completed on all areas as one of the priorities.

Finally, concerning the new bridge contract, the synopsis doesn’t address the issue of how much LANS will be paid under the to-be-finalized bridge contract in relation to how much it would have been paid under the existing contract. It also doesn’t state which of the tasks mentioned are different than under the existing contract. We request that costs and tasks be fully described in the to-be-finalized bridge contract.

Thank you for your consideration in these matters and please call if you have any questions.

Sincerely,

Jay Coghlan                                                            Scott Kovac

Executive Director                                                Research Director

Safety Analysis Flaws Plague Los Alamos TRU Waste Handing Facility

Safety Analysis Flaws Plague Los Alamos TRU Waste Handing Facility

The Defense Nuclear Facilities Safety Board (DNFSB) believes that the Radioassay and Nondestructive Testing (RANT) Shipping Facility at Los Alamos National Laboratory must resolve safety issues prior to resuming operations. The DNFSB staff review team identified “significant flaws” in hazard and accident analyses.

The RANT Shipping Facility is used to load transuranic (TRU) waste, typically either waste drums or standard waste boxes, into TRUPACT shipping containers. This facility supports the LANL TRU program and will be used long-term. The RANT Shipping Facility is currently in standby with no TRU waste present, pending the resumption of TRU waste shipments.

In November 2013, the contractor, LANS, submitted a new safety analysis, called a Documented Safety Analysis (DSA), to DOE oversight officials at the Los Alamos Field Office (LAFO) for approval. In February 2014, WIPP was shut down due to a radiation leak in the underground. It is believed that wheat-based kitty litter was mixed with nitrate salts in a transuranic waste drum as it was processed at Los Alamos that potentially caused the reaction that breached the container. In July 2014, LAFO completed its review of the RANT DSA and noted only four actions needed.

The DNFSB staff reviewed the DSA and identified significant weaknesses in the hazard analysis (HA), accident analysis, and safety controls. The review revealed inadequate identification and implementation of safety controls to protect the public and workers.

The DNFSB report found that LANS and LAFO underestimated consequences from potential crane failure accidents, seismic events, and fires. Underestimating possible consequences like these can lead to increased radiologic releases to the environment.

Defense Nuclear Facilities Safety Board Staff Issue Report September 29, 2014

Below is a Google Earth image of the RANT facility. Notice the 8 TRUPACT trailers with three round TRUPACT containers each on them.

NukeWatch Urges Increasing DOE Accountability in Wake of Fines

On December 6, the New Mexico Environment Department (NMED) declared multiple violations at both the Waste Isolation Pilot Plant (WIPP) and Los Alamos National Laboratory (LANL). NMED plans to fine WIPP $17.7 million and LANL $36.6 million due to major procedural problems related to the handling of radioactive transuranic (TRU) wastes that contributed to two significant incidents at WIPP earlier this year.

In addition to “failure to adequately characterize waste” and other violations, LANL was cited for the processing of nitrate-bearing wastes and adding neutralizing agents to that waste stream. LANL treated this procedure as if it was outside the state hazardous waste permit, but NMED determined that these operations were not exempt. LANL treated 100s of waste drums without a permit, and one of these was apparently the cause of the February 14, 2014 radioactive release at WIPP that contaminated 21 workers.

WIPP was cited for, among other violations, not notifying NMED in a timely fashion of the February 14 radioactive release.

The $36.6 million fine at LANL is based on up to $10,000 per day per non-compliance, but still represents less than 2% of the Lab’s $2.1 billion annual budget. The contractor that runs the Lab, Los Alamos National Security, LLC, is eligible to earn $57 million in bonus award fees for the fiscal year that ended last September 30th. The fines should be taken out of the bonuses.

NMED stipulated that the penalties couldn’t be paid for out of designated funding for environmental cleanup or operational needs at LANL and WIPP.

Nuclear Watch New Mexico applauds these efforts to hold the Department of Energy accountable in New Mexico and we urge NMED to not negotiate these relatively modest fines down, as is typically the case. These fines should be paid out of the contractor’s profits. The Lab had this waste for over 20 years and still could not get it right. We hope these NMED fines are a wake up call for safe, comprehensive cleanup of all the wastes left from the Cold War at the Los Alamos Lab.”

NMED information is available here.

Highlights of National Nuclear Security Administration Issues in the House FY 2015 National Defense Authorization Act

Highlights of National Nuclear Security Administration Issues

In the House FY 2015 National Defense Authorization Act

 

Sources: House FY 2015 NDAA, pages 1516 – 1555 and budget tables beginning page 1643.

http://docs.house.gov/billsthisweek/20141201/CPRT-113-HPRT-RU00-S1847.pdf

Compiled by Jay Coghlan, Nuclear Watch New Mexico. Any comments by me are italicized.

 

The House FY 2015 National Defense Authorization Act authorizes $8.2 billion for the National Nuclear Security Administration’s (NNSA’s) nuclear weapons programs, in contrast to the Obama Administration’s request of $8.3 billion.

It meets the Administration’s $643 million request for the B61 Life Extension Program, and raises the $9.4 million request for the Long-Range Stand-Off (AKA air-launched cruise missile) nuclear warhead to $17 million.

It raises the $30 million request for dismantlements to $40 million.

It meets the $335 million request for the Uranium Capabilities Replacement Project (AKA the Uranium Processing Facility).

It raises the $196 million request for construction of the MOX Fuel Fabrication Facility to $341 million.

It cuts the $410.8 million request for the NNSA Office of the Administrator to $386.9 million.

SEC. 3111. DESIGN AND USE OF PROTOTYPES OF NUCLEAR WEAPONS FOR INTELLIGENCE PURPOSES requires the lab directors to “develop a multiyear plan to design and build prototypes of nuclear weapons to further intelligence estimates with respect to foreign nuclear weapons activities and capabilities.” This effort “emphasizes the competencies of the national security laboratories with respect to designing and building prototypes of nuclear weapons.”

This could possibly be abused by U.S. designers to design new nuclear weapons under the rubric of gathering foreign intelligence.

SEC. 3112. PLUTONIUM PIT PRODUCTION CAPACITY declares that the “production of plutonium pits and other nuclear weapons components must be driven by the requirement to hedge against technical and geopolitical risk and not solely by the needs of life extension programs.” It goes on to require the actual production of not less than 10 plutonium war reserve pits during 2024, 20 during 2025, 30 during 2026, and demonstration of the capability to produce 80 pits per year by 2027.

How convenient to delink plutonium pit production from the actual needs of Life Extension Programs, since the only LEP that required new pit production has been indefinitely delayed. This was for the so-called Interoperable Warhead, which faced exorbitant costs and lack of support by the Navy. Nevertheless, the House Armed Services Committee now mandates expensive and provocative expanded plutonium pit production for which there is no clear need. Ironically, the Los Alamos National Laboratory has been unable to conduct plutonium operations at its pit production facility since June 2013 because of nuclear criticality safety issues.

SEC. 3118. COST CONTAINMENT FOR URANIUM CAPABILITIES REPLACEMENT PROJECT limits Phase 1 of construction of the Uranium Processing Facility to $4.2 billion. That cap could be adjusted if the DOE Secretary submits a detailed justification, including “a detailed description of the actions taken to hold appropriate contractors, employees of contractors, and employees of the Federal Government accountable for the repeated failures within the project.” It also requires that uranium operations in Building 9212 cease by 2025.

Notably, the House NDAA does NOT contain a definitional change that NNSA shopped to key congressional committees that would have narrowed the Uranium Processing Facility’s mission, thereby helping to contain its costs (which was previously capped at $6.5 billion). Thus the Uranium Processing Facility could soon be headed for another budget crisis.

SEC. 3119. PRODUCTION OF NUCLEAR WARHEAD FOR LONG-RANGE STANDOFF WEAPON requires that “The Secretary of Energy shall deliver a first production unit for a nuclear warhead for the long-range standoff weapon by not later than September 30, 2025.”

This is meant to block the Administration’s proposed two year delay. Rushing into the LRSO nuclear warhead makes no sense because it puts the cart before the horse when work on the new air-launched cruise missile has yet to start.

SEC. 3120. DISPOSITION OF WEAPONS-USABLE PLUTONIUM requires another report on possible alternatives to the MOX Program for plutonium disposition, including their life cycle costs.

Nevertheless, as previously stated, the Act increases funding for construction of the MOX Fuel Fabrication Facility to $341 million.

SEC. 3132. ANALYSIS OF EXISTING FACILITIES AND SENSE OF CONGRESS WITH RESPECT TO PLUTONIUM STRATEGY requires “analysis of using or modifying existing facilities of the nuclear security enterprise… to support [NNSA’s plutonium] strategy, as part of critical decision 1 in the acquisition process for the design and construction of modular structures associated with operations of the PF–4 facility at Los Alamos National Laboratory, Los Alamos, New Mexico.” This is to include “plans to construct two modular structures that will achieve full operating capability not later than 2027,” all for the purpose of “meet[ing] the requirements for implementation of a responsive infrastructure, including meeting plutonium pit production requirements.”

But there are no actual pit production requirements. Recall that the Act delinks plutonium pit production from the actual needs of the nuclear weapons stockpile to become a hedge against undefined and indefinite “technical and geopolitical risk.” The Act also requires major expansion of production at LANL, when significant budget, environmental and safety issues for existing plutonium pit production remain unresolved (witness the use of unauthorized waste treatment processes by the Lab that led to the contamination of 21 workers and the closure of the Waste Isolation Pilot Plant, with initial estimates of $.5 billion dollars to reopen). The House Armed Services Committee’s mandate of expanded plutonium pit production is an ideological statement of nuclear weapons forever, rather than being driven by the technical needs of the stockpile. This is an unnecessary and provocative waste of taxpayer’s money that if enacted is doomed for failure.

 

NNSA Considers Stuffing More Plutonium Into New Facility

Despite the fact that no one has come up with a good reason to increase plutonium pit production for the nation’s nuclear weapons stockpile, officials want to study the possibility of radically increasing the amount of plutonium allowed in a recently completed laboratory at the Los Alamos National Laboratory.

The Deputy Administrator for National Nuclear Security Administration (NNSA) Defense Programs, Don Cook, has requested an analysis to increase the radioactive materials inventory in the recently completed Radiological Laboratory Utility Office Building (RLUOB) to up to 400 grams of plutonium-239, the isotope used in nuclear weapons. The RLUOB, which originally was limited to 8.4 grams of Pu 239, was built as Phase 1 of the Chemistry and Metallurgy Research Replacement Project at LANL that would have expanded plutonium pit production to 50 – 80 pits per year (pits are the radioactive cores of nuclear weapons). LANL’s current capacity is 20 pits per year. Phase 2 of the CMRR project, the “Nuclear Facility,” was canceled because of lack of clear need and a bulging ten-fold increase in costs.

This RLUOB, along with some floor space in the existing Plutonium Facility (PF-4), will replace the old Chemistry and Metallurgy Research Building, which is slated for closure in 2019. The Laboratory was working on a plutonium strategy to move out of CMR and maintain the current plutonium capability.

But NNSA recently increased the maximum amount of radiological materials allowed in the RLOUB, and all “radiological” facilities, from 8.4 grams to 38.6 grams. Internal Lab documents floated plans that could have increased the limit again by two or three times by treating each little laboratory in the RLUOB as its own radiological facility. This could have increased the limit to 115.8 grams of Pu239.

But NNSA apparently wants to go big. The new analysis is to consider the RLUOB as a Hazard Category 3 nuclear facility, which is a huge step up from its current designation as a radiological facility.

Scott Kovac, Research and Operations Director for Nuclear Watch New Mexico, said, “This turkey of a plan is stuffed with bad ideas – The RLUOB is not seismically qualified for that amount of plutonium. A new supplemental environmental impact statement will be needed. There is no need for more plutonium pits, except for new nuclear weapons, because they last for around 100 years and nuclear weapons stockpiles are decreasing. And apparently LANL can’t safely handle plutonium anyway, as major operations with plutonium have been paused since June 2013 because of nuclear criticality safety issues. Finally, it was LANL’s improper handling of plutonium waste that contaminated 21 workers at the Waste Isolation Pilot Plant, causing it to close with at least a half billion dollars in costs to reopen. We say no to more plutonium at Los Alamos!”

# # #

Read the Defense Nuclear Facilities Safety Board report here.

 

DOE Sec. Moniz Calls To Speed Up WIPP Reopening While LANL Digs Up More Problems

US Department of Energy Secretary Ernest Moniz visited the Waste Isolation Pilot Plant (WIPP) recently and announced future recovery plans for WIPP and they include a target date to start some operations 18 months from now reported KRQE.

That date is extremely optimistic. Here’s a few reasons why –

  1. The exact cause of the February 14 release that shut WIPP down is still unknown. The cause must be determined before much else can happen.
  2. There are 360+ drums in Panel 6 that are suspected to have similar waste characteristics to the drum that leaked radiation. These have also now been re-characterized as “ignitable” by Los Alamos officials. Do these need to be removed and retreated? A decision is needed.
  3.  Panel 6 must be sealed off to protect mine workers from releases.
  4. There are 50+ suspect drums in Panel 7 where the original release happen.
  5. Parts of Panel 7 must be sealed off to protect workers.
  6. A new exhaust shaft is in the planning stages.
  7. The mine should be decontaminated.
  8. Funding for the recovery work will be needed.
  9. Fines will probably have to be paid.
  10. If the WIPP Hazardous Waste Permit with the State is changed substantially, public comments and possible hearings will be required.
  11. Hopefully, a truly independent review will be approved.

In addition to these, Los Alamos officials have retroactively re-characterized many waste drums as “ignitable”. See previous post. Today it was revealed that Los Alamos has re-characterized some waste drums as “corrosive”.  Ignitable (EPA waste code D001) and corrosive (EPA waste code D002) wastes are prohibited from WIPP.

The NM Environment Department, and its Secretary Ryan Flynn, has the final say about the final disposition of the now illegal waste drums and many of the other issues. We trust he will take the health of present workers and future generations into account in his decision-making. DOE’s imagined schedule should not be a consideration.

We appreciate that Los Alamos Laboratory officials have stepped up and re-characterized the drums. But we don’t think DOE officials should be making statements about the timing of WIPP’s reopening (or even that WIPP will reopen at all) until all the facts are in.

To make matters even worse, the Current Argus reported that “Moniz told the town hall meeting [that the Department of] Energy is considering the facility [WIPP] to store spent fuel from commercial nuclear power plants, but provided no time line.”

To even consider expanding WIPP when it is not even open shows the lack of focus on the current problems and shows the lessons have not been learned.

 

DOE Retroactively Classifies Suspect WIPP Drums As Ignitable

DOE Retroactively Classifies Suspect WIPP Drums As Ignitable

In two letters posted to the NMED website, Los Alamos contractor and DOE Field Office officials informed NMED that 86 drums currently stored at LANL and 368 drums underground in Panel 6 at WIPP are now considered to contain ignitable wastes. These drums are part of the same waste stream as the drum in Panel 7 that is suspected to have caused the Feb. 14 radiation release and the subsequent closure of the Waste Isolation Pilot Plant (WIPP).

The letters state that DOE applied EPA Hazardous Waste Number D001 for the characteristic of ignitability.

The WIPP Permit specifically prohibits D001 Wastes at WIPP –

2.3.3.7. Ignitable, Corrosive, and Reactive Wastes

Wastes exhibiting the characteristic of ignitability, corrosivity, or reactivity (EPA Hazardous Waste Numbers of D001, D002, or D003) are not acceptable at WIPP.

DOE stated that it had “reason to believe that the nitrate salt bearing waste in the containers described above is an oxidizer and therefore the D001 code should be applied to the respective containers”, but did not explain exactly what that reason was. What did LANL or the Accident Investigation Board (AIB) discover that lead them to apply the D001 classification? The AIB report investigating the Feb. 14 release is not due until September.

Now there are 368 illegal drums buried at WIPP. DOE can’t seal up Panel 6 until the exact cause of the Feb 14 release is known, even though there is a plan to expedite closure of Panel 6.  NMED Secretary Ryan Flynn has stated on several occasions that that we must know the exact cause before sealing up Panel 6. We agree. Otherwise we might be burying drums that should be retrieved and repackaged, as onerous of a task that that would be.

DOE stated, “Because the investigations are ongoing, the application of the D001 is considered provisional and may change to include and/or remove containers/waste streams in the future.”  But the WIPP permit has no provision for allowance for “provisional” classification wastes.

Either they are or they are not.

Missed WIPP Deadline May Put Real Cleanup at LANL Back On Track

Missed WIPP Deadline May Put Real Cleanup at LANL Back On Track

Santa Fe, NM – Today the New Mexico Environment Department (NMED) denied extension requests by Los Alamos National Laboratory (LANL) to delay cleanup milestones under a legally enforceable 2005 Consent Order. These denials by NMED counter a trend since January 2012 when NMED and LANL entered into a nonbinding “Framework Agreement” to ship 3706 cubic meters of above-ground transuranic waste from the Lab to the Waste Isolation Pilot Plant (WIPP) for permanent disposal. LANL radioactive wastes are now the main suspect in the February 14 contamination and subsequent shutdown of the multi-billion dollar WIPP.

NMED denied 14 extensions, now available in LANL’s Electronic Public Reading Room. These denials include construction of monitoring wells, and investigation reports for cleanup of contaminated areas. All of them included language that LANL requested an extension based on the Lab’s need to divert resources to remove transuranic waste in accordance with the Framework Agreement. The denials repeatedly state, “Based on the Permittees’ [LANL’s] statement that they will not be able to meet the deadlines that they committed to in the Framework Agreement [to ship TRU wastes to WIPP], the request is hereby denied.”

NMED had previously agreed to over 100 of these extension requests in favor of the so-called 3706 Campaign. The campaign was part of a non-binding agreement with the NM Environment Department so there are no penalties associated with lack of performance. The problem is that much other cleanup at the Lab was delayed while the 3706 Campaign was prioritized.

The Lab will miss the June 30 deadline of shipping 3,706 cubic meters of transuranic waste while the cleanup of over 1,000,000 cubic meters of all types of radioactive waste, hazardous waste, and contaminated backfill buried across the Lab were put on the back burner. These vast amounts of buried wastes, dating back to the Lab’s early days, are covered under the 2005 Consent Order for the “fence-to-fence” cleanup of legacy wastes. The Consent Order is enforceable with financial penalties for missed deliverables.

The Lab has claimed that there is not enough money to address all the Consent Order deliverables, but the original intent behind the Consent Order was that fines or the threat of fines would shake federal cleanup funding from DOE headquarters in Washington, DC. Cleanup without the big stick of possible fines just takes us back to the time when the small budget received annually just gets sprinkled around to where the cleanup “priorities” are perceived to be.

Jay Coghlan, Nuclear Watch New Mexico Executive Director, commented, “After granting more than one hundred extension requests to delay cleanup, we salute the New Mexico Environment Department for denying further requests. We encourage NMED to enforce what it already has, and make LANL comply with its legally mandated cleanup order. This in turn will drive increased federal funding for genuine cleanup at the Lab, creating hundreds of jobs while permanently protecting our precious water and environment.”

Scott Kovac, Nuclear Watch New Mexico Program Director, commented, “We look forward to continuing enforcement of the 2005 Consent Order and the necessary removal of Cold War legacy waste buried in unlined trenches above our aquifer.”

January 2012 Framework Agreement

LANL’s Electronic Public Reading Room

Sample of denial

 

 

DOE Headquarters Launches an Investigation Into the WIPP Release

DOE Headquarters Launches an Investigation Into the WIPP Release

On June 16, 2014, the U.S. Department of Energy (DOE) DC Office of Independent Enterprise Assessments notified Nuclear Waste Partnership, LLC, the operating contractor for DOE’s Waste Isolation Pilot Plant, of its intent to conduct an investigation.  The investigation will look into potential nuclear safety, worker safety, and health programmatic deficiencies associated with the two events in February.

WIPP has been shut down since February 5, 2014, when a salt-hauling truck caught fire, forcing evacuation of 86 workers from underground, 13 of whom were treated for smoke inhalation. Nine days later, an air monitor detected radiation underground where waste had recently been emplaced. The emergency filtration started, but radioactive particles were released to the environment. That resulted in contamination of all 13 people working above ground.

The DOE headquarters’ investigation may be a good start (hopefully), but Nuclear Watch NM, and many other groups, wants a truly independent, public investigation. This investigation should determine the cause of the WIPP radiation release, the extent of underground and surface contamination, the medical and compensation requirements for contaminated workers, and options for cleaning up underground and surface contamination.

In the meantime, TRU must be stored safely and securely at other DOE sites, regardless of how long WIPP is closed.  Unnecessary waste shipments should not occur while WIPP is closed. Additional newly-generated TRU waste from nuclear weapons production, which exacerbates existing problems, should not be produced.

After a Failed Campaign, the State Must Return to Enforceable Cleanup At LANL

After a Failed Campaign, the State Must Return to Enforceable Cleanup At LANL

The June 30 deadline of the “3706 Campaign” to remove 3706 cubic meters of transuranic waste stored on the surface on Los Alamos Lab will be missed due to the radiation release and shutdown of the Waste Isolation Pilot Plant. The campaign was part of a non-binding agreement with the NM Environment Department so there are no penalties associated with lack of performance. The problem is that much other cleanup at the Lab was delayed while the 3706 Campaign was prioritized.

The Lab missed the low bar of shipping 3,706 cubic meters of transuranic waste while the cleanup of over 1,000,000 cubic meters of all types of radioactive waste, hazardous waste, and contaminated backfill buried across the Lab were put on the back burner. These vast amounts of buried wastes, dating back to the Lab’s early days, are covered under a 2005 Consent Order for the “fence-to-fence” cleanup of legacy waste. The Consent Order is enforceable with stipulated penalties of up to $3000/day for missed deliverables. But NMED has been hesitant to impose fines, because of DOE claims that the fines come out of the cleanup budget. The deadline for the last cleanup under the Consent Order is currently December 2015, which everyone agrees is impossible. But that end date could be extended, and should be extended, especially if the Lab was actually working on the legacy cleanup

NMED, to date, has granted over 95 extensions for Consent Order deliverables in favor of the 3706 Campaign. These extensions allow the Lab to not drill monitoring wells and to not perform cleanup investigations and work plans for sites across the Lab. The Lab claims that there is not enough money to address all the Consent Order deliverables, but the idea behind the Consent Order was that fines and the threat of fines would shake cleanup funding from DOE headquarters in DC. Cleanup without the big stick of possible fines just takes us back to the time when the small budget received annually just gets sprinkled around to where the cleanup “priorities” are perceived to be. Urgency and comprehensiveness go out the window.

The Cold War has been over for twenty years now and we in Northern New Mexico have been patient in removing LANL’s legacy waste.

But now Northern New Mexico has neither a 3706 Campaign that is complete, nor a Consent Order that will be complete by its deadline. NMED officials have stated, upon the successful completion of the 3706 Campaign, that they would consider renegotiating the Consent Order. We are waiting to see how NMED deals with the 3706 failure and we urge NMED to make the Consent Order the priority again. The Campaign approach has now been proven not to work.

In the meantime, we also have contaminated WIPP workers.

We have 707 possibly explosive drums probably created by Los Alamos spread across New Mexico and West Texas.

We have a damaged WIPP, which is shut down for up to three years and missing its deadlines for disposing waste.

We have other impacted DOE sites across the country, which will be missing deadlines for radioactive waste disposal.

We the taxpayers are no doubt going to spend hundreds of millions on this fiasco while the contractors continue to put money in their pockets.

The New Mexico Environment Department is the regulator here. Relying on LANL’s promises and plans to make things better must end. Time to return to the 2005 Consent Order and actually use the enforceable provisions in it.

NNSA Digs Deep To Find A Reason To Give Itself Award

The award for the largest nuclear facility project completed ahead of schedule and under budget by NNSA goes to a project came in only 1% under budget after spending $40 million in contingency.

In an April 2 2014 National Nuclear Security Administration press release titled, NNSA Receives Secretary’s Award for Project Management Excellence, the Chemistry and Metallurgy Research Building Replacement (CMRR) Radiological Laboratory/Utility/Office Building (RLUOB) Equipment Installation (REI) Project was touted for coming in $2 million under budget.

First, the CMRR is the now-deferred project at Los Alamos, whose third phase Nuclear Facility would have enabled increased plutonium pit production. The RLOUB was the first phase of the CMRR project. The second phase REI is only the “equipment” for the RLOUB.

The press release tells us –

“The REI installed glovebox and other enclosure systems, analytical and test instrumentation equipment, and telecommunications and safeguards/security systems within the RLUOB.”

Also included, but not mentioned in the press release, were a fuel oil storage tank, furniture, and the parking lot.

It looks like NNSA gave the award in part because it could have been worse. With one year left in the 3-year the contract, it was estimated that the project was $8 million over budget. So NNSA put a new team in charge and straightened out their mess-ups and turned it around to a $2 million savings.

The press release tells us –

“The CMRR/RLUOB REI Project is the largest nuclear facility capital asset project completed ahead of schedule and under budget by NNSA.”

The press release also neglects to give the total budget. Our documents show that REI had a total budget $199 million. That makes the $2 million that the REI came in under budget equal to 1% of the total budget.

But our documents also show that there was $41.6 million (26%) contingency included in the $199 total budget. After spending untold millions in design and then estimating the cost of the project, NNSA adds in a large contingency to every project so that it does not go over budget and have to go back to Congress for more money.

Is the REI, which spent $40 million in contingency, really $2 million under budget?

I think not. NNSA must give the public all the facts and figures when it gives glowing appraisals of itself.

 

Here’s what we have on the REI –

 

WIPP Continues to Show Signs, Town Hall Webcast Tonight, LANL TRU to WCS, More Information

WIPP Continues to Show Signs, Town Hall Webcast tonight, LANL TRU to WCS, More Information

WIPP Underground Continues to Show Signs of Radiological Activity

The Waste Isolation Pilot Plant officials stated that there was another radiological release on March 11.  This was outside of the WIPP site exhaust shaft filter. An air sample from the outside of the ventilation exhaust recorded 61 disintegrations per minute of americium on a sample collected the evening of March 11. WIPP stated that, “This is expected given the amount of contamination captured by the WIPP ventilation system during the February 14 radiation release event. Engineers believe the contamination was from previous deposits on the inner surface of the exhaust ductwork.” The engineers did not state why they expected this and did not mention the LARGE amount of contamination captured by the WIPP ventilation system filters. The engineers also did not state why they believed this and not that more contamination was being produced in the underground.

Air sampling results before and after the High Efficiency Particulate Air (HEPA) filters at WIPP are available here. Station A samples air before the filters and Station B samples air after passing through the filters. These samples were analyzed following the detection of airborne radioactivity on February 14, 2014. They are not environmental samples, and are not representative of the public or worker breathing zone air samples.

The 3/11/14 4:19PM increase after the filters is shown here. There were other small releases on 03/02/2014 08:50 AM (38 dpm) and 03/05/2014 08:10 AM (60 dpm, although WIPP claims that the filter was “cross contaminated”)

There was a larger event, before the filters, that occurred 03/13/2014 08:30 AM (368 dpm) that has not been mentioned. All this shows that the underground could still be brewing radiological activity. Perhaps this will be explained better tonight at the Town hall.

 

Weekly Town Hall Meetings in Carlsbad?

Thursdays at 5:30 – Carlsbad City Council Chambers, City Hall, 101 N. Halagueno St.

Co-hosted by City of Carlsbad and U.S. Department of Energy (DOE) Carlsbad Field Office

Discuss recovery efforts following WIPP’s fire and radiological events in February.

Meetings available live online

 

The Show Goes On

The Department of Energy (DOE), is proposing to ship transuranic waste currently located at the Los Alamos National Laboratory (LANL) for temporary storage at Waste Control Specialists (WCS), located in western Andrews County, Texas. LANL has another ~546 cubic meters remaining out of the original 3706 cubic meters that was agreed to be moved to WIPP by June 2014.

Let’s be clear, there is no technical reason to store the waste temporarily at WSC.  DOE and LANL just want to show that they can meet a deadline. The extra cost of this operation has not been released. And don’t get me wrong, no one wants the waste – all the waste  – removed from LANL more than me.  Let’s hope that DOE and LANL show the same amount of interest and resources when it comes to removing the rest of the waste at Los Alamos, such as the hundreds of thousands of cubic meters of radioactive and hazardous wastes buried at Area G.

 

Official Websites

New Mexico Environment Department WIPP website

DOE/WIPP website

 

WIPP Informational Meeting in Santa Fe

A WIPP informational meeting will take place in Santa Fe on Monday, March 31st from 6 to 7:30 pm at the Santa Fe Main Library, located at 145 Washington, in downtown Santa Fe.  Please note the new location.  Don Hancock, of Southwest Research and Information Center, Scott Kovac, of Nuclear Watch New Mexico, and Sasha Pyle, longtime activist, will give presentations. Opportunities for public involvement will be discussed.

DOE releases predicted spread of WIPP contamination

We now have a look at DOE’s predicted contamination spread, available at the  Waste Isolation Pilot Plant (WIPP) update page.

This model is based on three air samplers, and no samplers to the Northeast. There are still many questions, including:

What caused this release in the first place?

How contaminated is the underground?

Are soil samples being collected? From where?

 

Modeling has been done to estimate onsite worker and offsite public dose that may have resulted from the February 14, 2014, event. The results of the modeling indicate that all potential doses were well below the applicable regulatory limits (see results below). The modeling results are consistent with actual worker bioassay results. For modeling data see: (http://www.wipp.energy.gov/Special/Modeling Results.pdf)

Estimated Dose Maximum estimated worker dose 10 mrem Maximum estimated public dose 0.1 < 1 mrem

Natural Background 310 mrem

Applicable Regulatory Limit

5000 mrem per year

DOE all?paths limit (adults) 100 mrem per year

DOE all?paths limit for children/pregnant women 25 mrem per year

EPA Air (NESHAPs) Standard for inhalation is 10 mrem per year

 

 

 

 

Mine Games – WIPP Update March 10, 2014

Mine Games

In a March 9th press release, the Nuclear Waste Partnership (NWP), the management and operations contractor at the Waste Isolation Pilot Plant (WIPP) for the U.S. Department of Energy (DOE), stated their plans to reenter the ailing salt mine/nuclear waste repository after a radiological release shut down operations over three weeks ago.

The press release tells us that, on March 7 and 8, radiological and air quality instruments were lowered down the Salt Handling and the Air Intake Shafts. The preliminary findings indicated that no “detectable radioactive contamination” in the air or on the equipment. The press release claims that these results were expected because the shafts that were sampled were not in the air flow path coming from the area where the radiation release originated.

But, there are 4 shafts to underground – the Salt Handling, the Air Intake, the Waste Handling, and the Exhaust Shafts. After the detection on a radiologic release, filters move into the Exhaust Shaft and air is drawn to the outside by fans blowing to the outside here. The other three shafts, mainly the Air Intake Shaft because it has no elevator in it, provide intake for the air flow path to the Exhaust Shaft. Strangely missing from the press release is any mention of the Waste Handling Shaft, which contains an elevator to take the waste down into the mine and should also have been out of the air flow path. DOE and NWP must explain why the Waste Handling Shaft was not sampled and, if it was, what are the results. The Waste Handling Shaft provides the normal entry to the underground, so why use the Salt Shaft? Also, the press release did not mention that any “soil” samples were taken from the walls of any of the shafts. Is the Waste Handling Shaft contaminated or presumed contaminated?

As far as the air flow path goes, it’s an elaborate game to get the air to flow where it is needed in the underground of WIPP. Getting the desired path requires blocking off numerous openings in the underground. Bob Martin from KRQE gave a hint of what is involved in his recent report. We have not been given the diagram for the air flow path at the time of the release or even if the path was in place. We don’t have the location of all the monitors in the underground and if they were working. What was the presumed path of the contaminated air to the Exhaust Shaft? Why are so many details left out out of the information released to the public?

Unfortunately, the press release also mentioned that four more WIPP workers had been contaminated. But it was not stated where or when these employees received the dose. Was it Friday night or Saturday? Why was this important information not in the press release?

We also have some new sample findings released. Some of the interesting information here is that the WIPP Laboratory Analyses are so much lower than the Screening Analyses. I will get back to you on that. But don’t forget that it is unlikely that the main release actually hit any of the air monitors dead-on. Also, notice the lack of samplers to the northeast.

We will have to wait for soil samples to come in before we can begin to estimate the main path of the release.

WIPP is not a secret facility. (They even let me down there last year.) Press releases that raise more questions than they answer must stop now.

WIPP Video Story and Congressional Delegation Statements from KRQE

KRQE TV 13 aired a news story last night that included statements from the five members of the NM Congressional Delegation:

On the recent radiation leak: “From my perspective on the (U.S. Senate Energy and Natural Resources) committee, the first priority is making sure that the personnel who actually work at WIPP are safe and that the community and environment around WIPP is safe.”

On whether high-level waste should be stored at WIPP: “WIPP was never designed as a high level facility, and I don’t think we should retrofit it to be a high level facility. There has been talk of moving other transuranic waste there that was generated in different ways than the transuranic waste that’s coming from Los Alamos, for example. That’s something we can have the conversation about, but it should never be a high level facility.”

On any future change in WIPP’s mission: “We have a very long standing and robust conversation in my office with the community in Carlsbad all the time. The input from the community is always critical.” “There is nothing more important than making sure that that community feels like we are doing everything possible to make sure that WIPP is a success, and that the people who work there in the surrounding community and their well-being is our first priority.”

~ U.S. Sen. Martin Heinrich, D-New Mexico

 

“It’s too early to say whether the leak factors into my thoughts about the future of WIPP because we don’t know what happened. I’m taking the leak very seriously, and our focus right now is on the immediate safety of the community and WIPP personnel and the recovery work. It would be premature to draw any conclusions. This is a very technical issue, and the science is extremely important. My position on expansion now is the same as it has always been. When it comes to proposals that would significantly change WIPP’s mission, I support the provision in the current law that bans high-level waste at WIPP. WIPP was not fully studied for high-level waste, and it does not meet permit requirements for high-level waste. Additionally, New Mexico’s people and state government are the ones who have the power to decide what waste our state will accept and under what terms. Any attempt to alter WIPP’s mission would take many years of study, permitting, and require the state of New Mexico’s full support.”

~ U.S. Sen. Tom Udall, D-New Mexico

 

On the radiation leak: “Congressman Pearce has introduced legislation to protect New Mexico jobs at WIPP, which has safely disposed of TRU waste for over a decade. Right now, Congressman Pearce is focused on monitoring the present situation closely, ensuring DOE and WIPP continue to make public safety the top priority. To date, all information shared with our office indicates there is no risk or danger to the community. At the appropriate time, the Congressman fully expects and will insist that the Department of Energy conduct a thorough investigation and answer all the public’s questions.”

On whether high-level waste should be stored at WIPP: “Now is not the time to speculate about proposals that are not even on the table. Taking high level waste at WIPP is not on the table. Congressman Pearce’s number one priority right now is public safety, and there are many questions that need to be answered before any changes in WIPP’s mission are discussed.”

~ Eric Layer, Spokesman for U.S. Rep. Steve Pearce, R-NM 2nd District

 

“Right now, the number one priority is the health and safety of the WIPP employees who were affected by the leak as well as the residents of the surrounding community. As the response effort continues, there must be nothing short of full transparency and accountability to ensure the public that they are safe. This incident further proves that any expansion of WIPP’s mission warrants close scrutiny that’s rooted in science and that includes extensive outreach to and input from all stakeholders and local communities.”

~ U.S. Rep. Michelle Lujan Grisham, D-NM 1st District

 

“I am very concerned about the recent detection of radiation near WIPP and the health and safety of those exposed to radiation. It will be important that answers are provided detailing the causes of the elevated levels and how this will be prevented in the future. The safety and security of the community must be the top priority.

As far as the larger discussion about changes at WIPP, one aspect that cannot be forgotten or overlooked – especially given the recent incident – is the reality of exposure and what will happen when workers or members of the community are exposed to harmful levels of radiation. Sadly in New Mexico, we are all too familiar with the story of those who worked in uranium mines and other government facilities and suffered exposure to radiation. They contributed to our national security, yet paid a steep cost as many individuals became sick and some paid with their life. I am still fighting in Congress to see that many of these workers are compensated for the health problems they developed as a result of their work. While we hope we never have to face a similar situation in the future, it is important we have these discussions now rather than when it’s too late, especially given the recent reports that 13 workers tested positive for radiation exposure.”

~ U.S. Rep. Ben Ray Lujan, D-NM 3rd District

QUESTIONS FOR DOE FY 2015 BUDGET

ALLIANCE FOR NUCLEAR ACCOUNTABILITY

A national network of organizations working to address issues of 

nuclear weapons production and waste cleanup

Ashish Sinha: (301) 910-9405 [email protected]

Bob Schaeffer: (239) 395-6773 [email protected]

 

for use with March 4, 2014 Obama Administration Budget Request

 QUESTIONS FOR THE U.S. DEPARTMENT OF ENERGY (DOE)

 FY 2015 NUCLEAR WEAPONS, REACTOR AND CLEANUP BUDGET

 

The U.S. nuclear budget is out of control. Huge cost overruns for unnecessary production facilities are common.  At the same time, cleanup of radioactive and toxic pollution from weapons research, testing, production and waste disposal is falling behind. The Department of Energy (DOE) budget for FY 2015 will reveal the Obama Administration’s nuclear priorities.

The Alliance for Nuclear Accountability (ANA), a 25-year-old network of groups from communities downwind and downstream of U.S. nuclear sites, will be looking at the following issues. For details, contact the ANA leaders listed at the end of this Media Advisory.

— Does the budget reflect the Administration’s commitment to curtail unnecessary spending on the $19 billion Uranium Processing Facility at Oak Ridge by downsizing it to the capacity needed to support stockpile surveillance, maintenance and limited life extension?

— Does the budget address the looming deficit in nuclear weapons dismantlement capacity so the United States can meet its international arms reduction commitments?

 

— Will the Obama Administration articulate its alternative plutonium strategy to the $6 billion “CMRR Nuclear Facility,” which was effectively cancelled in 2012? Is any expanded production needed when expert studies have found that existing plutonium pits are durable?

— Will NNSA reduce funding or impose meaningful milestones at the National Ignition Facility (NIF), which performed less than half of its planned Stockpile Stewardship experiments in FY2013 and still has not achieved ignition.

— Is the budget a de facto cancellation of plans to pursue “interoperable warhead designs” by imposing a delay of five years or more on the program? How much money will taxpayers save?

 

— Does the FY 2015 budget seek more than the $537 million requested for the B61 Life Extension Program last year? Will the “First Production Unit” from this $10 billion program continue to slip to 2020 or later delaying needed routine replacement of critical components?

— How much of the additional $26 billion in Defense Sec. Chuck Hagel’s “Opportunity, Growth and Security Initiative” will go to DOE nuclear weapons programs? 

— Will the Administration support increased funding for the Defense Nuclear Facilities Safety Board (DNFSB) to provide independent oversight of DOE projects given the many cost over-runs, schedule delays, safety issues and technical problems?

 

— What is the projected life-cycle cost of the plutonium fuel (MOX) program at Savannah River? Is DOE’s internal cost assessment consistent with ANA’s estimate of $27 billion? When will it be released? Have any nuclear reactor operators committed to using MOX fuel?

 

— Does the Request include continued funding for design and licensing of Small Modular Reactors (SMRs), which private investors have been unwilling to finance fully because of concerns about viability and risks? Does DOE have plans to finance SMR construction?

 

How much additional Environmental Management (EM) funding would be necessary in FY 2015 to meet all legally mandated cleanup milestones? States say cleanup agreements at a dozen major sites are underfunded by hundreds of million dollars.

— In which states does DOE face fines and lawsuits for missing milestones due to budget shortfalls? Which states are enforcing their binding clean-up agreements by imposing fines and taking further legal action?

— What is the high range for total life-cycle clean-up costs (LCC) for EM sites Because of funding shortfalls, are LCC costs continuing to increase? In the FY 2013 Budget Request High Range LCC was $308.5 billion, and in the FY 2014 Request LCC was $330.9 billion.
— Does the FY 2015 Request include funds to cleanup contamination from the recent radiation release at the Waste Isolation Pilot Plant (WIPP)?  How much will this incident delay shipments from the Idaho National Lab, Los Alamos, Savannah River, and Oak Ridge?

— How much money is included for construction of new double-shell tanks to replace those leaking radioactive waste at the Hanford site? Are funds included for emergency pumping of tanks found to be leaking?

— Is DOE allocating sufficient funds to monitor and address ignitable hydrogen gas buildup in Hanford’s nuclear waste tanks as recommended by the Defense Nuclear Facilities Safety Board to protect workers, the public and the environment from possible explosions?

— Is an independent review of the Hanford Waste Treatment Plant included in the budget request to address concerns about the reliability of many of the parts and materials?

– How much money is DOE allocating for building and development of the Hanford Waste Treatment Plant based on the current, flawed design and how much on redesign?

— For information about specific DOE nuclear weapons sites and programs, contact:

Meredith Crafton – Hanford: (206) 292-2850 x26 [email protected]

Tom Clements – Savannah River and MOX Plant: (803) 240-7268 [email protected]

Jay Coghlan – Los Alamos Lab and Life Extension: (505) 989-7342 [email protected]

Don Hancock – Environmental Management Program: (505) 262-1862 [email protected]

Ralph Hutchison – Oak Ridge Site and Dismantlement: (865) 776-5050 [email protected]

Marylia Kelley – Livermore Lab and Life Extension: (925)-443-7148 [email protected]

 

WIPP Update Feb 27 2014 – 13 Employees Contaminated

WIPP Update Feb 27 2014 – 13 Employees Contaminated

I’ll remind us all that the Waste Isolation Pilot Plant (WIPP) site is NOT a National Security site. It is a fancy landfill. There are really no secret programs there to protect. Maybe there are some secret parts buried there, but they have long-since been crushed. There is no reason to withhold news. The waste streams are well known and exactly where they are emplaced in WIPP is also well known. When the public gets news from WIPP officials, we deserve to have our questions answered clearly with all the important facts included.

Our best wishes go out to the employees.

Here’s the February 26, 2014 letter from the U.S. Department of Energy – Carlsbad Field Office, which provides oversight of the private contractor, Nuclear Waste Partnership, LLC, that currently manages and operates WIPP. Unfortunately, this letter raises many questions. Below are each of the paragraphs of the letter, followed by my questions and comments.

First Paragraph –

This morning (February 26), the 13 Waste Isolation Pilot Plant (WIPP) employees that were on site the evening of February 14 were notified that they have tested positive for radiological contamination. Employees were notified within about 12 hours of the receipt of preliminary sample results.

Ok, “the 13 Waste Isolation Pilot Plant (WIPP) employees that were on site the evening of February 14,” sounds like there were only 13 employees at WIPP on Feb 14. But the February 15, 2014, 9:17 PM WIPP press release states, “All non-essential employees were off-site by 5:30 PM MST.” The February 15, 2014, 9:17 PM WIPP press release also states, “No contamination has been found on any equipment, personnel, or facilities.” I guess we are to read this as, “No contamination has been found ON any personnel.”

Questions raised –

How many employees were onsite when?

Were the 13 contaminated employees essential or non-essential?

Were the non-essential employees (how many?) that left by 5:30 bioassayed?

How does an employee inhale rads and not have any on them?

 

Second Paragraph –

At the time of the event, these employees were performing above ground operations, and federal oversight duties at the WIPP facility. Nuclear Waste Partnership, LLC, the site contractor, requested that all workers on site the night of the event submit follow-up bioassay samples as they were considered more likely to have indications of potential exposure. Additional samples will be collected from these employees in the weeks ahead in order to perform complete analyses.

Questions raised –

When did Nuclear Waste Partnership, LLC request the bioassay samples from the night workers?

What made them “more-likely” to be exposed? What exactly were they doing?

Were the non-essential employees (how many?) that left by 5:30 bioassayed? When was this request made?

 

Third Paragraph –

It is premature to speculate on the health effects of these preliminary results, or any treatment that may be needed. However, on-site sampling and surveys and environmental monitoring, to date, continue to support National Atmospheric Release Advisory Center (NARAC) modeling, which indicates that airborne contamination was likely at very low levels.

Questions raised –

Where is the National Atmospheric Release Advisory Center (NARAC) modeling? The public must be allowed to read any and all reference documents. And by the way, NARAC is located at the Lawrence Livermore National Laboratory, which is a Department of Energy site. 

 

Fourth Paragraph –

The material for this release event is transuranic radionuclides. The release material was predominantly americium-241, material which is consistent with the waste disposed of at the WIPP. This is a radionuclide used in consumer smoke detectors and a contaminant in nuclear weapons manufacturing.

Questions raised –

Really? Smoke detectors? Here’s from the EPA

As long as the radiation source stays in the detector, exposures would be negligible (less than about 1/100 of a millirem per year), since alpha particles cannot travel very far or penetrate even a single sheet of paper, and the gamma rays emitted by americium are relatively weak. If the source were removed, it would be very easy for a small child to swallow, but even then exposures would be very low because the source would pass through the body fairly rapidly (by contrast, the same amount of americium in a loose powdered form would give a significant dose if swallowed or inhaled). Still, its not a good idea to separate the source from the detector apparatus.

All the americium at WIPP is the byproduct of Cold War nuclear weapons production. The Center for Disease Control (CDC) explains the health effects of americium.

The radiation from americium is the primary cause of adverse health effects from absorbed americium. Upon entering the body by any route of exposure, americium moves relatively rapidly through the body and is deposited on the surfaces of the bones where it remains for a long time. As americium undergoes radioactive decay in the bone, alpha particles collide with nearby cell matter and give all of their energy to this cell matter. The gamma rays released by decaying americium can travel much farther before hitting cellular material, and many of these gamma rays leave the body without hitting or damaging any cell matter. The dose from this alpha and gamma radiation can cause changes in the genetic material of these cells that could result in health effects such as bone cancers.

 

Fifth Paragraph – Here it states that inhalation did employees did occur.

Determining employee dose typically involves multiple sample analyses to determine employee’s radionuclide excretion rate over time. This allows the lab to estimate the employee’s accumulated internal dose. The time this process takes depends largely on the solubility of the inhaled particulate, with less water-soluble radioactive materials requiring more samples and time to accurately estimate the dose. Follow-up urine samples may require about three or more weeks to accurately predict dose.

 

Sixth Paragraph –

We are now focusing our sampling program on employees with work assignments that may have placed them at greater risk, including those on shift February 15. We are still reviewing staff assignments to determine if additional employees will need to be tested. However, employees who feel they were assigned positions or functions that placed them at risk will be included in follow-up bioassay monitoring at their request.

Questions raised –

How many employees were working on the 15th? Were they wearing safety protection?

What is the criterion “to determine if additional employees will need to be tested”?

 

Seventh Paragraph –

There is no risk to family or friends of these employees. As we learn more information, we will continue to share. If you have any questions or concerns, please contact 1-800-336-9477. Thank you.

Questions raised –

What is the current status at the site?

Are employees working there now?

Are they wearing protective gear?

 

There apparently is a Press Conference today (Feb27 2014) at 3pm MST.