Plutonium Pit Production NEPA Talking Points

LANL Molten Plutonium for Pit
Molten plutonium in a crucible. 

The National Environmental Policy Act (NEPA) is the landmark environmental law which requires executive agencies to give the public the opportunity to formally review and comment on major federal proposals. These talking points outline the history of the Department of Energy’s NEPA compliance on its various proposals concerning the production of plutonium pits (the fissile cores of nuclear weapons). The conclusion is that DOE’s semi-autonomous National Nuclear Security Administration (NNSA) is legally required to prepare a supplemental programmatic environmental impact statement (PEIS) on its current plan to expand plutonium pit production.

There are at least three reasons why NNSA must complete a supplemental programmatic environmental impact statement for expanded plutonium pit production:
1)    Implementing regulations for the National Environmental Policy Act stipulate that “DOE shall prepare a supplemental EIS if there are substantial changes to the proposal or significant new circumstances or information relevant to environmental concerns…” 10. C.F.R. § 1021.314
2)    As precedence, since 1996 there have been five programmatic environmental impact statements related to pit production and its expansion. It is legally unlikely that NNSA could implement its current plan to expand plutonium pit production without a new supplemental PEIS.
3)    Now that NNSA is planning to produce more than 50 pits per year (or more than 80 pits under multiple shift operations), it is obliged by the 1998 court order to prepare a new PEIS.
Continue reading

What’s Not in NNSA’s Plutonium Pit Production Decision

 Today the National Nuclear Security Administration (NNSA) announced:

To achieve DoD’s [the Defense Department] 80 pits per year requirement by 2030, NNSA’s recommended alternative repurposes the Mixed Oxide Fuel Fabrication Facility at the Savannah River Site in South Carolina to produce plutonium pits while also maximizing pit production activities at Los Alamos National Laboratory in New Mexico.  This two-prong approach – with at least 50 pits per year produced at Savannah River and at least 30 pits per year at Los Alamos – is the best way to manage the cost, schedule, and risk of such a vital undertaking.

First, in Nuclear Watch’s view, this decision is in large part a political decision, designed to keep the congressional delegations of both New Mexico and South Carolina happy. New Mexico Senators Tom Udall and Martin Heinrich are adamantly against relocating plutonium pit production to South Carolina. On the other hand, South Carolina Senator Lindsay Graham was keeping the boondoggle Mixed Oxide (MOX) program on life support, and this pit production decision may help to mollify him. This could also perhaps help assuage the State of South Carolina, which is suing the Department of Energy for failing to remove plutonium from the Savannah River Site as promised.

But as important is what is NOT in NNSA’s plutonium pit production decision:

  There is no explanation why the Department of Defense requires at least 80 pits per year, and no justification to the American taxpayer why the enormous expense of expanded production is necessary.

•  NNSA avoided pointing out that expanded plutonium pit production is NOT needed to maintain the safety and reliability of the existing nuclear weapons stockpile. In fact, no production of plutonium pits for the existing stockpile has been scheduled since 2011, and none is scheduled for the future.

•  NNSA did not mention that in 2006 independent experts found that pits last a least a century. Plutonium pits in the existing stockpile now average around 40 years old. The independent expert study did not find any end date for reliable pit lifetimes, indicating that plutonium pits could last far beyond just a century.

• NNSA did not mention that up to 15,000 “excess” pits are already stored at the Pantex Plant near Amarillo, TX, with up to another 5,000 in “strategic reserve.” The agency did not explain why new production is needed given that immense inventory of already existing plutonium pits.

•  Related, NNSA did not explain how to dispose of all of that plutonium, given that the MOX program is an abysmal failure. Nor is it made clear where future plutonium wastes from expanded pit production will go since operations at the troubled Waste Isolation Pilot Plant are already constrained from a ruptured radioactive waste barrel, and its capacity is already overcommitted to existing radioactive wastes.

•  NNSA did not make clear that expanded plutonium pit production is for a series of speculative future “Interoperable Warheads.” The first IW is meant to replace nuclear warheads for both the Air Force’s land-based and the Navy’s sub-launched ballistic missiles. The Obama Administration delayed “IW-1” because the Navy does not support it. However, the Trump Administration is restarting it, with annual funding ballooning to $448 million by 2023, and “IW-2” starting in that same year. Altogether the three planned Interoperable Warheads will cost at least $40 billion, despite the fact that the Navy doesn’t support them.[1]

•  NNSA’s expanded plutonium pit production decision did not mention that exact replicas of existing pits will NOT be produced. The agency has selected the W87 pit for the Interoperable Warhead, but its FY 2019 budget request repeatedly states that the pits will actually be “W87-like.” This could have serious potential consequences because any major modifications to plutonium pits cannot be full-scale tested, or alternatively could prompt the U.S. to return to nuclear weapons testing, which would have severe international proliferation consequences.

•  The State of South Carolina is already suing the Department of Energy for its failure to begin removing the many tons of plutonium at the Savannah River Site (SRS). NNSA’s pit production decision will not solve that problem, even as it will likely bring more plutonium to SRS.

•  The independent Defense Nuclear Facilities Safety Board has expressed strong concerns about the safety of plutonium operations at both the Los Alamos National Laboratory (LANL) LANL and SRS, particularly regarding potential nuclear criticality incidents.[2] NNSA did not address those safety concerns in its plutonium pit production decision.

•  Politicians in both New Mexico and South Carolina trumpet how many jobs expanded plutonium pit production will create. Yet NNSA’s expanded plutonium pit production decision does not have any solid data on jobs produced. One indicator that job creation will be limited is that the environmental impact statement for a canceled $6 billion plutonium facility at LANL stated that it would not produce a single new Lab job because it would merely relocate existing jobs. Concerning SRS, it is doubtful that pit production could fully replace the jobs lost as the MOX program dies a slow death. In any event, there certainly won’t be any data on the greater job creation that cleanup and renewable energy programs would create. Funding for those programs is being cut or held flat, in part to help pay for nuclear weapons programs.

•  Finally, the National Environmental Policy Act (NEPA) requires that major federal proposals be subject to public review and comment before a formal decision is made. NNSA’s decision does not mention its NEPA obligations at all. In 1996 plutonium pit production was capped at 20 pits per year in a nation-wide Stockpile Stewardship and Management Programmatic Environmental Impact Statement (PEIS). NNSA failed to raise that production limit in any subsequent NEPA process, despite repeated attempts. Arguably a decision to produce 80 pits or more per year requires a new or supplemental nation-wide programmatic environmental impact statement to raise the production limit, which the new dual-site decision would strongly augment. This then should be followed by whatever site-specific NEPA documents might be necessary.

Jay Coghlan, Nuclear Watch Director, commented, “NNSA has already tried four times to expand plutonium pit production, only to be defeated by citizen opposition and its own cost overruns and incompetence. But we realize that this fifth attempt is the most serious. However, we remain confident it too will fall apart, because of its enormous financial and environmental costs and the fact that expanded plutonium pit production is simply not needed for the existing nuclear weapons stockpile. We think the American public will reject new-design nuclear weapons, which is what this expanded pit production decision is really all about.”

# # #

[1]     See 2012 Navy memo demonstrating its lack of support for the Interoperable Warhead at https://nukewatch.org/importantdocs/resources/Navy-Memo-W87W88.

[2]     For example, see Safety concerns plague key sites proposed for nuclear bomb production, Patrick Malone, Center for Public Integrity, May 2, 2108, https://www.usatoday.com/story/news/nation/2018/05/02/safety-concerns-nuclear-bomb-manufacture-sites/572697002/

 

Expanded Plutonium Pit Production at LANL Will Not Result in Significant Positive Effect On Job Creation and the Regional Economy

Abstract: Expanded production of plutonium pits, the fissile cores of modern thermonuclear weapons, is cynically being justified as a source of job creation. Precise data on employment in plutonium pit production at the Los Alamos National Laboratory (LANL) and the number of additional jobs if expanded is not publicly available to our knowledge. However, the National Nuclear Security Administration’s own documents quoted below explicitly state that expanded pit production would not have any significant positive effect on job creation and the regional economy of northern New Mexico. Further, Nuclear Watch argues that expanded plutonium pit production could actually have negative effect if expanded pit production blocks other economic alternatives such as comprehensive cleanup, which could be the real job producer. Moreover, given LANL’s poor safety and environmental record, expanded plutonium pit production could have a seriously negative economic effect on northern New Mexico in the event of any major accidents or additional contamination.

Final Supplemental Environmental Impact Statement for the Nuclear Facility Portion of the Chemistry and Metallurgy Research Building Replacement Project at Los Alamos National Laboratory, Los Alamos, New Mexico

https://energy.gov/nepa/eis-0350-s1-supplemental-environmental-impact-statement-nuclear-facility-portion-chemistry-and

Bolded emphasis added

Note: The CMRR-Nuclear Facility was the up to $6.5 billion dollar plutonium facility NNSA proposed to build at LANL in direct support of expanded plutonium pit production. The Obama Administration cancelled it in 2012 after costs rose so high. Nevertheless, the 2011 CMRR-Nuclear Facility supplemental environmental impact statement remains the most relevant source of publically available socioeconomic information concerning expanded plutonium pit production that we know of.

Volume 1, p. 2-43, Socioeconomics

Under the Modified CMRR-NF Alternative, an increase in construction-related jobs and businesses in the region surrounding LANL is also expected. Construction employment would be needed over the course of a 9-year construction period under either the Deep or Shallow Excavation Option. Construction employment under either option is projected to peak at about 790 workers, which is expected to generate about 450 indirect jobs in the region. Operation of the Modified CMRR-NF and RLUOB would involve about 550 workers at LANL, with additional workers using the facility on a part-time basis. The personnel working in the Modified CMRR-NF and RLUOB, when fully operational, would relocate from other buildings at LANL, including the existing CMR Building, so an increase in the overall number of workers at LANL is not expected.

Note: The first phase of the Chemistry and Metallurgy Research Replacement Project, the Radiological Laboratory Utility and Office Building (RLUOB), is already built. It is now being retrofitted to handle up to 400 grams of plutonium-239 equivalent instead of the original 8.4 grams. This will greatly increase its special nuclear materials analytical chemistry and materials characterization capabilities in direct support of expanded plutonium pit production.

Under the Continued Use of CMR Building Alternative, about 210 employees would continue to work in the CMR Building until safety concerns force additional reductions in facility operations. In addition, about 140 employees would be employed at RLUOB. A total of about 350 personnel would have their offices relocated to RLUOB. The personnel working in the CMR Building and RLUOB, when fully operational, would not result in an increase in the overall number of workers at LANL.

Pg. 4-12

4.2.9 Socioeconomics

Construction Impacts—Construction of new buildings at TA-55 to house CMR activities would require a peak construction employment level of 300 workers. This level of employment would generate about 852 indirect jobs in the region around LANL. The potential total employment increase of 1,152 direct and indirect jobs represents an approximate 1.3 percent increase in the workforce and would occur over the proposed construction period. This small increase would have little or no noticeable impact on the socioeconomic conditions of the region of influence (ROI).

 Operations Impacts—CMRR Facility operations would require a workforce of approximately 550 workers. As evaluated in the CMRR EIS, this would be an increase of about 340 workers over currently restricted CMR Building operational requirements. Nevertheless, the increase in the number of workers in support of expanded CMRR Facility operations would have little or no noticeable impact on socioeconomic conditions in the LANL ROI (region of influence). New LANL employees hired to support the CMRR Facility would compose a small fraction of the LANL workforce and an even smaller fraction of the regional workforce.

4.3.9 Socioeconomics

Construction Impacts – Deep Excavation Option—Construction of the Modified CMRR-NF under the Deep Excavation Option would require a peak construction employment level of about 790 workers (LANL 2011a:Data Call Tables, 002). This level of employment would generate about 450 indirect jobs in the region around LANL. The potential total peak employment of 1,240 direct and indirect jobs represents an increase in the ROI workforce of approximately 0.8 percent. Direct construction employment would average 420 workers annually over this time, approximately half of the estimated peak employment. The average direct construction employment would result in about 240 indirect jobs in the region around LANL. This total of 660 direct and indirect jobs represents an approximate 0.4 percent increase in the ROI workforce. These small increases would have little or no noticeable impact on the socioeconomic conditions of the ROI.

Pg. 4-54

Chapter 4 – Environmental Consequences

Construction Impacts – Shallow Excavation Option—The impacts under the Shallow Excavation Option from construction of the Modified CMRR-NF would be similar to the Deep Excavation Option. The peak employment number of about 790 construction workers would be the same as under the Deep Excavation Option, and the annual average would be 410 workers over the life of the project. The average direct construction employment would result in about 240 indirect jobs in the region around LANL. This total of 650 direct and indirect jobs represents an approximate 0.4 percent increase in the ROI workforce. Therefore, there would be little or no noticeable impact on the socioeconomic conditions of the ROI.

Operations Impacts—Operations at the Modified CMRR-NF and RLUOB would require a workforce of approximately 550 workers, including workers that would come from other locations at LANL to use the Modified CMRR-NF laboratory capabilities. The number of workers in support of Modified CMRR-NF operations would cause no change to socioeconomic conditions in the LANL four-county ROI (region of influence). Workers assigned to the Modified CMRR-NF and RLUOB would be drawn from existing LANL facilities, including the CMR Building. The number of LANL employees supporting the Modified CMRR-NF and RLUOB operations would represent only a small fraction of the LANL workforce (approximately 13,500 in 2010) and an even smaller fraction of the regional workforce (approximately 165,000 in 2010).

Volume 2, p. 2-13: As discussed in this CMRR-NF SEIS, operation of the new CMRR-NF, if built, is not expected to result in any increase in LANL employment. The people expected to work in the new facility would be transferred from other facilities at LANL where CMR-related activities are currently being accomplished (such as the CMR Building).

– End of NNSA quotes –

Note: The CMRR-Nuclear Facility was expected to cost up to $6.5 billion. It’s pathetic that the largest construction project ever in New Mexico (with the exception of the interstate highways) was going to create no new Lab jobs.

 Comprehensive cleanup at LANL would be a win-win for northern New Mexicans, permanently protecting the environment while providing hundreds of high paying jobs.

  • When DOE wants to do something, it lowballs the cost. When DOE doesn’t want to do something, it highballs the cost. LANL has estimated that comprehensive cleanup of Area G would cost $29 billion. Using actual costs of cleaning up smaller dumps, Nuclear Watch has extrapolated that cleanup of Area G would cost $7 to 8 billion. See https://nukewatch.org/facts/nwd/Area_G_Comparison_Costs-11-14-12.pdf
  • But of that $29 billion, DOE estimated that labor costs would be $13 billion. Applying that 45% proportion to Nuclear Watch’s estimate, that would be around $3.5 billion in jobs, jobs that northern New Mexico sorely needs.
  • Comprehensive cleanup could be the real job producer. It has the additional advantage of being more conducive to regional economic development in that more locally based contractors could possibly do the cleanup work, instead nuclear weapons work such as expanded plutonium pit production conducted by huge out-of-state defense contractors such as Bechtel and Lockheed Martin.

New nuclear ‘pit’ production at LANL is unnecessary

From the Albuquerque Journal
New nuclear ‘pit’ production at LANL is unnecessary
By Jay Coghlan
Friday, July 21st, 2017 at 12:02am

SANTA FE, N.M. — The Center for Public Integrity recently published a series of articles on nuclear safety lapses in plutonium pit production at the Los Alamos lab that captured a lot of national attention.

Plutonium pits are the fissile cores of nuclear weapons that initiate the thermonuclear detonation of modern weapons. The articles were largely based on the National Nuclear Security Administration’s annual contractor Performance Evaluation Reports. Those reports are publicly available only because Nuclear Watch New Mexico successfully sued for them in 2012.

The former plutonium pit production site, the Rocky Flats Plant near Denver, was shut down by a 1989 FBI raid investigating environmental crimes. A special grand jury indicted both Department of Energy (DOE) officials and the contractor, but a federal judge quashed the indictments at the urging of the local federal attorney general. It was only by sheer luck that a major plutonium fire on Mother’s Day 1969 didn’t contaminate Denver with highly carcinogenic plutonium.

I specifically recall senior DOE officials promising New Mexicans 20 years ago that serious lessons were learned from Rocky Flats and that re-established plutonium pit production at the Los Alamos National Laboratory (LANL) would always be safe. Since then, the lab has spent billions of taxpayers’ money on plutonium pit production but, as the recent articles document, LANL still can’t do it safely.

As the articles reported, a serious nuclear criticality accident was narrowly averted in July 2011, which resulted in the three-year shutdown of LANL’s main plutonium facility. Nevertheless, according to the fiscal year 2011 LANL Performance Evaluation Report, the lab contractor was paid $50 million in pure profit for that year.

In 2014, a radioactive waste barrel improperly prepared by LANL ruptured underground at the Waste Isolation Pilot Plant (WIPP), shutting down that multi-billion-dollar facility for nearly three years. Radioactive waste disposal at WIPP will remain constrained for years, raising the question of where future LANL bomb-making wastes will go.

Congress has required the Los Alamos lab to quadruple plutonium pit production, regardless of the technical needs of the stockpile. The requirement was drafted by professional staff on the House Armed Services Committee, one of whom was originally from the Sandia nuclear weapons lab.

That the existing stockpile doesn’t need pit production is demonstrated by the fact that none has been scheduled since 2011 when LANL finished up the production run that was stopped when Rocky Flats was shut down.

At NukeWatch’s request, former U.S. Sen. Jeff Bingaman (D-NM) required an independent study of the lifetimes of pits. The expert conclusion was that plutonium pits last at least a century, more than double government estimates (the oldest pits in the stockpile are now around 45 years old). Moreover, there are some 20,000 existing plutonium pits stored at the Pantex Plant near Amarillo, Texas.

Future plutonium pit production is for a new so-called “Interoperable Warhead” that is supposed to function both as a land-based ICBM and a sub-launched nuclear warhead. The nuclear weapons labs are pushing this $13 billion make-work project that the Navy doesn’t want.

Ironically, new-design pits for the Interoperable Warhead may hurt national security because they cannot be tested in a full-scale nuclear weapons test or, alternatively, testing them would have severe international proliferation consequences.

Given all this, why expand plutonium pit production when apparently it can’t be done safely and may decrease, not increase, our national security? One strong reason is the huge contractor profits to be had under the $1 trillion-plus “modernization” of the nuclear weapons stockpile and production complex started under Obama, which Trump promises to expand. Far from just “modernization,” existing nuclear weapons are being given new military capabilities, despite denials at the highest levels of government.

The directors of the Livermore, Sandia and Los Alamos nuclear weapons labs in truth wear two hats – the first as lab directors, the second as presidents of the for-profit limited liability corporations running the labs. This inherent conflict of interest skews U.S. nuclear weapons policy and should be brought to an end.

The New Mexico congressional delegation kowtows to the nuclear weapons industry in our state. I specifically call upon Senators Tom Udall and Martin Heinrich to certify within this calendar year that future plutonium pit production at the Los Alamos Lab will be safe, or otherwise end their support for it.

Jay Coghlan is the director of Nuclear Watch New Mexico.

The pit is in the primary
From pogo.org

NNSA Considers Stuffing More Plutonium Into New Facility

Despite the fact that no one has come up with a good reason to increase plutonium pit production for the nation’s nuclear weapons stockpile, officials want to study the possibility of radically increasing the amount of plutonium allowed in a recently completed laboratory at the Los Alamos National Laboratory.

The Deputy Administrator for National Nuclear Security Administration (NNSA) Defense Programs, Don Cook, has requested an analysis to increase the radioactive materials inventory in the recently completed Radiological Laboratory Utility Office Building (RLUOB) to up to 400 grams of plutonium-239, the isotope used in nuclear weapons. The RLUOB, which originally was limited to 8.4 grams of Pu 239, was built as Phase 1 of the Chemistry and Metallurgy Research Replacement Project at LANL that would have expanded plutonium pit production to 50 – 80 pits per year (pits are the radioactive cores of nuclear weapons). LANL’s current capacity is 20 pits per year. Phase 2 of the CMRR project, the “Nuclear Facility,” was canceled because of lack of clear need and a bulging ten-fold increase in costs.

This RLUOB, along with some floor space in the existing Plutonium Facility (PF-4), will replace the old Chemistry and Metallurgy Research Building, which is slated for closure in 2019. The Laboratory was working on a plutonium strategy to move out of CMR and maintain the current plutonium capability.

But NNSA recently increased the maximum amount of radiological materials allowed in the RLOUB, and all “radiological” facilities, from 8.4 grams to 38.6 grams. Internal Lab documents floated plans that could have increased the limit again by two or three times by treating each little laboratory in the RLUOB as its own radiological facility. This could have increased the limit to 115.8 grams of Pu239.

But NNSA apparently wants to go big. The new analysis is to consider the RLUOB as a Hazard Category 3 nuclear facility, which is a huge step up from its current designation as a radiological facility.

Scott Kovac, Research and Operations Director for Nuclear Watch New Mexico, said, “This turkey of a plan is stuffed with bad ideas – The RLUOB is not seismically qualified for that amount of plutonium. A new supplemental environmental impact statement will be needed. There is no need for more plutonium pits, except for new nuclear weapons, because they last for around 100 years and nuclear weapons stockpiles are decreasing. And apparently LANL can’t safely handle plutonium anyway, as major operations with plutonium have been paused since June 2013 because of nuclear criticality safety issues. Finally, it was LANL’s improper handling of plutonium waste that contaminated 21 workers at the Waste Isolation Pilot Plant, causing it to close with at least a half billion dollars in costs to reopen. We say no to more plutonium at Los Alamos!”

# # #

Read the Defense Nuclear Facilities Safety Board report here.

 

NNSA Digs Deep To Find A Reason To Give Itself Award

The award for the largest nuclear facility project completed ahead of schedule and under budget by NNSA goes to a project came in only 1% under budget after spending $40 million in contingency.

In an April 2 2014 National Nuclear Security Administration press release titled, NNSA Receives Secretary’s Award for Project Management Excellence, the Chemistry and Metallurgy Research Building Replacement (CMRR) Radiological Laboratory/Utility/Office Building (RLUOB) Equipment Installation (REI) Project was touted for coming in $2 million under budget.

First, the CMRR is the now-deferred project at Los Alamos, whose third phase Nuclear Facility would have enabled increased plutonium pit production. The RLOUB was the first phase of the CMRR project. The second phase REI is only the “equipment” for the RLOUB.

The press release tells us –

“The REI installed glovebox and other enclosure systems, analytical and test instrumentation equipment, and telecommunications and safeguards/security systems within the RLUOB.”

Also included, but not mentioned in the press release, were a fuel oil storage tank, furniture, and the parking lot.

It looks like NNSA gave the award in part because it could have been worse. With one year left in the 3-year the contract, it was estimated that the project was $8 million over budget. So NNSA put a new team in charge and straightened out their mess-ups and turned it around to a $2 million savings.

The press release tells us –

“The CMRR/RLUOB REI Project is the largest nuclear facility capital asset project completed ahead of schedule and under budget by NNSA.”

The press release also neglects to give the total budget. Our documents show that REI had a total budget $199 million. That makes the $2 million that the REI came in under budget equal to 1% of the total budget.

But our documents also show that there was $41.6 million (26%) contingency included in the $199 total budget. After spending untold millions in design and then estimating the cost of the project, NNSA adds in a large contingency to every project so that it does not go over budget and have to go back to Congress for more money.

Is the REI, which spent $40 million in contingency, really $2 million under budget?

I think not. NNSA must give the public all the facts and figures when it gives glowing appraisals of itself.

 

Here’s what we have on the REI –

 

QUESTIONS FOR DOE FY 2015 BUDGET

ALLIANCE FOR NUCLEAR ACCOUNTABILITY

A national network of organizations working to address issues of 

nuclear weapons production and waste cleanup

Ashish Sinha: (301) 910-9405 [email protected]

Bob Schaeffer: (239) 395-6773 [email protected]

 

for use with March 4, 2014 Obama Administration Budget Request

 QUESTIONS FOR THE U.S. DEPARTMENT OF ENERGY (DOE)

 FY 2015 NUCLEAR WEAPONS, REACTOR AND CLEANUP BUDGET

 

The U.S. nuclear budget is out of control. Huge cost overruns for unnecessary production facilities are common.  At the same time, cleanup of radioactive and toxic pollution from weapons research, testing, production and waste disposal is falling behind. The Department of Energy (DOE) budget for FY 2015 will reveal the Obama Administration’s nuclear priorities.

The Alliance for Nuclear Accountability (ANA), a 25-year-old network of groups from communities downwind and downstream of U.S. nuclear sites, will be looking at the following issues. For details, contact the ANA leaders listed at the end of this Media Advisory.

— Does the budget reflect the Administration’s commitment to curtail unnecessary spending on the $19 billion Uranium Processing Facility at Oak Ridge by downsizing it to the capacity needed to support stockpile surveillance, maintenance and limited life extension?

— Does the budget address the looming deficit in nuclear weapons dismantlement capacity so the United States can meet its international arms reduction commitments?

 

— Will the Obama Administration articulate its alternative plutonium strategy to the $6 billion “CMRR Nuclear Facility,” which was effectively cancelled in 2012? Is any expanded production needed when expert studies have found that existing plutonium pits are durable?

— Will NNSA reduce funding or impose meaningful milestones at the National Ignition Facility (NIF), which performed less than half of its planned Stockpile Stewardship experiments in FY2013 and still has not achieved ignition.

— Is the budget a de facto cancellation of plans to pursue “interoperable warhead designs” by imposing a delay of five years or more on the program? How much money will taxpayers save?

 

— Does the FY 2015 budget seek more than the $537 million requested for the B61 Life Extension Program last year? Will the “First Production Unit” from this $10 billion program continue to slip to 2020 or later delaying needed routine replacement of critical components?

— How much of the additional $26 billion in Defense Sec. Chuck Hagel’s “Opportunity, Growth and Security Initiative” will go to DOE nuclear weapons programs? 

— Will the Administration support increased funding for the Defense Nuclear Facilities Safety Board (DNFSB) to provide independent oversight of DOE projects given the many cost over-runs, schedule delays, safety issues and technical problems?

 

— What is the projected life-cycle cost of the plutonium fuel (MOX) program at Savannah River? Is DOE’s internal cost assessment consistent with ANA’s estimate of $27 billion? When will it be released? Have any nuclear reactor operators committed to using MOX fuel?

 

— Does the Request include continued funding for design and licensing of Small Modular Reactors (SMRs), which private investors have been unwilling to finance fully because of concerns about viability and risks? Does DOE have plans to finance SMR construction?

 

How much additional Environmental Management (EM) funding would be necessary in FY 2015 to meet all legally mandated cleanup milestones? States say cleanup agreements at a dozen major sites are underfunded by hundreds of million dollars.

— In which states does DOE face fines and lawsuits for missing milestones due to budget shortfalls? Which states are enforcing their binding clean-up agreements by imposing fines and taking further legal action?

— What is the high range for total life-cycle clean-up costs (LCC) for EM sites Because of funding shortfalls, are LCC costs continuing to increase? In the FY 2013 Budget Request High Range LCC was $308.5 billion, and in the FY 2014 Request LCC was $330.9 billion.
— Does the FY 2015 Request include funds to cleanup contamination from the recent radiation release at the Waste Isolation Pilot Plant (WIPP)?  How much will this incident delay shipments from the Idaho National Lab, Los Alamos, Savannah River, and Oak Ridge?

— How much money is included for construction of new double-shell tanks to replace those leaking radioactive waste at the Hanford site? Are funds included for emergency pumping of tanks found to be leaking?

— Is DOE allocating sufficient funds to monitor and address ignitable hydrogen gas buildup in Hanford’s nuclear waste tanks as recommended by the Defense Nuclear Facilities Safety Board to protect workers, the public and the environment from possible explosions?

— Is an independent review of the Hanford Waste Treatment Plant included in the budget request to address concerns about the reliability of many of the parts and materials?

– How much money is DOE allocating for building and development of the Hanford Waste Treatment Plant based on the current, flawed design and how much on redesign?

— For information about specific DOE nuclear weapons sites and programs, contact:

Meredith Crafton – Hanford: (206) 292-2850 x26 [email protected]

Tom Clements – Savannah River and MOX Plant: (803) 240-7268 [email protected]

Jay Coghlan – Los Alamos Lab and Life Extension: (505) 989-7342 [email protected]

Don Hancock – Environmental Management Program: (505) 262-1862 [email protected]

Ralph Hutchison – Oak Ridge Site and Dismantlement: (865) 776-5050 [email protected]

Marylia Kelley – Livermore Lab and Life Extension: (925)-443-7148 [email protected]

 

Report Reveals That Little is Known About Lab’s Future Plutonium Needs

Report Reveals That Little is Known About Lab’s Future Plutonium Needs
Except LANL Contractor Needs Money

A Government Accountability Office (GAO) report reveals how the future of expanded nuclear weapon component production at Los Alamos is unknown. The public has had enough of half-baked billion-dollar plans for nuclear facilities that do nothing but line contractors’ pockets. Congress must put away the check book and realize that the Lab’s plutonium future is unknown because it is unneeded.

Let’s get some details out of the way –

Los Alamos National Laboratory (LANL) houses most of the nation’s capabilities for plutonium research and development in support of the nuclear weapons mission. In addition, LANL’s scientists and technicians also perform research on plutonium to support other missions, such as conducting research on recycling plutonium for use as fuel in commercial nuclear reactors (MOX).

The National Nuclear Security Administration (NNSA), a separately organized agency within the Department of Energy (DOE), is responsible for the management of the nation’s nuclear weapons.

Plutonium pits are the fissile cores of modern nuclear weapons (fissile means capable of sustaining a nuclear reaction). When a nuclear weapon is detonated the pit is explosively compressed into a critical mass that rapidly begins atomic fission. In modern two-stage weapons the plutonium pit acts as the primary (or “trigger”) that initiates fusion in the thermonuclear secondary. Each pit is an atomic bomb in its own right, similar to the Trinity and Nagasaki bombs, both of which were plutonium bombs. In thermonuclear or hydrogen bombs the plutonium pit serves as the trigger that detonates the far more powerful fusion explosion characteristic of hydrogen bombs.

(The need for any more nuclear weapons production ever is actually zero.)

NNSA claims that the need is unknown –
Because of public participation, lack of need, and budget concerns, construction of the Lab’s $6 billion Chemistry and Metallurgy Research Replacement (CMRR) nuclear facility was deferred for at least five years starting in 2012. The CMRR would have enabled a production capacity of 50-80 pits per year. Theoretically, the Lab is currently capable of producing 10-20 pits per year, maybe. But it produced zero this year.

It is now unclear when or if the CMRR nuclear facility will be built, which the Lab claims may lead to insufficient capabilities to meet LANL’s plutonium research requirements. But no one really can say what these requirements are.

The report states the uncertainty–

The Nuclear Weapons Council is still evaluating specifications for nuclear weapons and their corresponding life extension program schedules, and it may take another year or two before final decisions are made, according to NNSA officials. Since the schedule has not been finalized, the number of pits that will be needed is uncertain as well. (Pg. 10)

Officials have announced that they are seeking alternatives to the CMRR that would provide the capabilities planned for the CMRR nuclear facility using existing facilities. This would be replacing deferred unneeded capabilities with unneeded capabilities. Instead of trying to replace the lacking capabilities of the CMRR, NNSA should first describe the actual pit needs, which are none.

Meanwhile, “NNSA has estimated that it needs to be able to ramp up its capabilities to manufacture about 30 pits each year by 2021” to meet expected life extension program requirements. (Life extension programs are intended to lengthen the lives of existing nuclear weapons by 20 to 30 years by repairing or replacing nuclear weapons components as needed.)

But the 30 number is just a guess “for planning purposes”.
For planning purposes, NNSA is studying the possibility of manufacturing about 30 pits per year… (Pg.10)
“Studying the possibility” is not a need.

NNSA now believes that LANL can support the manufacture of 30 pits per year just by upgrading its radiological laboratory and by repurposing available space in its existing plutonium facility. (Pg. 12)

Also,
Costs are unknown –
The cost estimates were characterized as “high-level and a rough order of magnitude and noted that the estimates should be viewed as preliminary and preconceptual that would not be useful for program definition or scoping.” (pg.15)

Staffing is unknown.

NNSA and LANL officials told us that recruiting additional staff for plutonium-related research necessarily takes years of advance planning, but that the uncertainty of where the new capabilities will be located or what the level of capacity is needed has complicated planning efforts. (Pg. 17)

What is know is the public is a problem –

Plans for transporting plutonium or other radioactive materials from LANL to facilities at other sites could also spur public opposition that may cause schedule delays or create other impediments…

Other impediments?
Like speaking up?

New Mexico Members of Congress Vote for Exorbitant Nuclear Bomb While State Is Ranked as the Worst for Children

Yesterday all three House members of the New Mexican congressional delegation voted against an amendment that would cut money added to a wasteful nuclear weapons program. In April the Obama Administration asked for $537 million in fiscal year 2014 for a “Life Extension Program” for the B61 Cold War nuclear bomb, 45% above the 2013 level. The House Appropriations Committee added $23.7 million to that bloated request, which the amendment would have cut. Overall, the B61 Life Extension Program has exploded in estimated costs to where each warhead will cost twice their weight in gold just to “refurbish” (which does not include original production and ongoing maintenance costs).

 The sponsor of the amendment, Rep. Mike Quigley, D-Ill., testified during floor debate:

At a time when we are slashing funds for disease research at the NIH [National Institute of Health], failing to fund our crumbling infrastructure, and underinvesting in our children¹s education, we are increasing funding to keep hundreds of nuclear bombs in operation that we will never use. The Cold War is over.

The Albuquerque Journal reported that Rep. Ben Ray Luján, D-N.M.,

…supported the full $551 million for the B61 Life Extension Program because it is a national security priority. “This funding is important for Los Alamos and Sandia labs’ effort to ensure the safety of the nuclear weapons stockpile, and cuts to that funding impact the ability to keep it secure,” Luján said.

Rather just ensuring safety and security the program will radically improve the bomb, giving it new military capabilities by turning it into a precisely targeted smart bomb and mating it to future bombers for supersonic stealthy delivery. Currently the main mission of B61 bombs is as tactical nuclear weapons in NATO countries, a relic of the Cold War. Improved B61’s fly in the face of Obama’s newly declared goal of reducing the presence of battlefield nuclear weapons in Europe, even as he proposes to negotiate with the Russians for further arms reductions. Moreover, if security is really the issue, the sure solution that saves taxpayers money and encourages nonproliferation is to withdraw the nuclear bombs from forward deployment in Europe, where a few years ago protesting peace activists were able to infiltrate within a few hundred yards of them.

Ironically, the B61 Life Extension Program may actually undermine our own national security by introducing major changes to existing bombs. Our stockpile has been extensively full-scale tested, and repeated studies have found our nuclear weapons to be even more reliable than previously believed. The Los Alamos and Sandia Labs propose to create a “frankenbomb” by mixing and matching four variants of the B61 bomb into a single new modification. Common sense dictates that the last thing we should do while seeking to maintain confidence in our reliable nuclear weapons stockpile is to introduce major changes that can’t be tested.

Our New Mexican congressional delegation represents a state that was just ranked as the worst of all fifty for the well-being of its children, where more than 25% live in poverty. In stark contrast, Los Alamos County, dominated by the lab, is the second richest county in the entire USA. Nuclear weapons programs are a poor producer of jobs, where for example according to the government’s own documents a new $6 billion plutonium facility was not going to produce a single new permanent job at Los Alamos Lab.

Contrary to the claimed economic benefits of the Los Alamos and Sandia Labs, New Mexico as a whole continues to fall from 37th in per capita personal income in 1959 to 44th in 2011. Nevertheless, the Labs have always had inordinate influence over New Mexican politicians. One extreme example is the recent starling revelation that in between unsuccessful Senate campaigns former Rep. Heather Wilson was paid more than $450,000 by the Los Alamos and Sandia Labs for “consulting” contracts that had no written work requirements.

The nuclear weapons labs have voracious appetites for federal funding, with their directors simultaneously acting as the presidents of the executive board of the for-profit limited liability corporations that run the labs (those private LLCs pay 2/3’s of the directors’ annual compensation of around one million dollars). Business will boom with never-ending Life Extension Programs, and Sandia and Los Alamos are not satisfied with just one Life Extension Program for the B61. They already plan yet another one 20 years from now that initial figures indicate would be even more expensive. In fact, the labs plan a never-ending cycle of Life Extension Programs that intentionally seek to implement major design changes for all existing types of nuclear weapons in our stockpile, costing at least $60 billion (while the doubling of costs has so far been the rule).

Jay Coghlan, director of Nuclear Watch New Mexico, commented, “Congressman Ben Ray Luján should ask himself the question what good does a Cold War nuclear bomb that the for-profit labs want to endlessly tinker with do for New Mexican children? Pork for the labs should not drive nuclear weapons policies, especially when it’s of little if any tangible benefit to average New Mexicans. Luján should, instead, dedicate himself to boosting funding for programs that would really help our children but are facing painful sequester cuts, such as education, medical care and food assistance. Those investments would really brighten their future, and help raise New Mexico from its shameful position as the worst state for kids.”

# # # 

See House rejects effort to trim $23.7M in funding for B61, Michael Coleman, Albuquerque Journal, July 11, 2013.

For New Mexico’s ranking as the worst state for kids see Kids Count Data Center http://datacenter.kidscount.org/updates/show/20-2013-data-book-rankings
For the scope and schedule of perpetual Life Extension Programs for existing nuclear weapons see NNSA’s FY 2014 Stockpile Stewardship and Management Plan
https://nukewatch.org/importantdocs/resources/SSMP-FY2014.pdf

Obama Calls For Further Nuclear Weapons Reductions While Increased Production and New Facilities at Los Alamos Are Still On the Table

Obama Calls For Further Nuclear Weapons Reductions
While Increased Production and New Facilities at Los Alamos Are Still On the Table

On June 19, in Berlin, President Barack Obama declared that, in concert with Russia, he plans to seek to cut the deployed strategic nuclear arsenal by up to one-third. He also said he will pursue significant bilateral cuts in tactical or battlefield nuclear weapons in Europe. In contrast, Obama’s National Nuclear Security Administration (NNSA) recently released plans for unneeded upgrades and dangerous improvements to existing nuclear weapons, which could force expanded nuclear component production and construction of new facilities at Los Alamos.

In the just released “FY 2014 Stockpile Stewardship and Management Plan” (SSMP), NNSA proposes perpetual Life Extension Programs for nuclear warheads that will result in three types of ballistic missile warheads and two types of nuclear air bombs. Although it’s still vague, the three so-called interoperable warheads would replace four types of existing warheads, which make little sense given the staggering estimated costs. These radical upgrades, if implemented, could not be full-scale tested, which would undermine confidence in their reliability. Our existing nuclear weapons designs have been extensively tested and subsequent studies have found them to be even more reliable and long-lived than originally thought.

The President’s speech is also incongruous with the SSMP in the area of plutonium pit production, and states “Preliminary plans call for pit production of potentially up to 80 pits per year starting as early as FY 2030.” (SSMP Pg. 62) With Obama’s further proposed arsenal reductions, any planned increase in weapons production is only a concession the nuclear weapons contractors profits. The alleged need for more plutonium pits cascades into a misplaced call for more production facilities. NNSA is “…evaluating the feasibility of constructing small laboratory modules connected to existing nuclear facilities…” (SSMP Pg. 8) to meet future claimed plutonium-manufacturing requirements. The SSMP states that Los Alamos can produce up to 30 pits per year without new facilities.

The need for increased pit production has never been explained adequately to the public, but the claim likely is centered on one of the interoperable warhead plans – the W78/88. In a May 7, 2013 testimony to the Senate Subcommittee on Strategic Forces, Dr. Penrose C. Albright, Director, Lawrence Livermore National Laboratory claimed that the W78/88 would require increased pit production at Los Alamos. He goes on to try to scare the Committee by saying that without construction funding for new pit facilities now, the W78/88 warhead upgrade could cost even more. He stated, “without going into the detail, the most likely option for the primary on the 78/88 does require the stand-up and operation of plutonium pit production capabilities at Los Alamos. And so any delay by the Government—any delay in funding to get that stood up—and that really has to start now—is going to add significant schedule risks to the program.” (Hearing Pg. 17)

The President should adopt the more fiscally prudent and technically sound alternative of replacing limited life components while he actually works to eliminate nukes altogether. This unending cycle of proposed Life Extension Program will waste huge sums of taxpayers money and is in direct conflict with the President’s own long-term goal of a future world free of nuclear weapons.

The full text of President’s Obama’s speech is available at http://www.whitehouse.gov/the-press-office/2013/06/19/remarks-president-obam

NNSA’s FY 2014 Stockpile Stewardship and Management Plan (SSMP) is available at https://nukewatch.org/importantdocs/resources/SSMP-FY2014.pdf

Hearing To Receive Testimony On National Nuclear Security Administration Management Of Its National Security Laboratories In Review Of The Defense Authorization Request For Fiscal Year 2014 And The Future Years Defense Program, Tuesday, May 7, 2013, U.S. Senate Subcommittee On Strategic Forces, Committee On Armed Services, Washington, DC.
http://www.armed-services.senate.gov/Transcripts/2013/05%20May/13-36%20-%205-7-13.pdf

The Lab’s New, $400 million, Plutonium Laboratory Springs Its First Leak

The Lab’s New, $400 million, Plutonium Laboratory Springs Its First Leak

On January 22, 2013 representatives of the Los Alamos National Laboratory discovered the presence of a diesel spill from an above ground storage tank system at the LANL Technical Area 55. The spill was from the new Radiological Laboratory Utilities Office Building’s (RLUOB’s) 12,000-gallon emergency generator diesel storage tank. The RLUOB is the recently completed first phase of the CMRR project. The main phase of the project, the CMRR Nuclear Facility (estimated at #6 billion), has been deferred for at least 5 years and will probably next be proposed next as a smaller project, if at all.

From the reports, it is unclear how long the sump pump union had been leaking before the spill was noticed. A leak detector alarm first went off in November. The Lab estimates that 350 gallons overflowed out a sump and spilled onto the ground, and workers have removed 5 cubic yards of contaminated soil. LANL and the State Environment Department Petroleum Storage TOppie greenank Bureau are working to figure out if more soil needs to be removed.

Read the report there.

Trinity Day — a good day to get money from the Fed?

Please check out Stephanie’s blog

Particle Beams
“Luminous Quanta of Divine Intelligence…” dispelling the nuclear delusion

Trinity Day — a good day to get money from the Fed?

Batter my heart, three-person’d God.   — John Donne, “Trinity”

Yesterday was the 67th anniversary of the very first atomic bomb test in the New Mexico desert, and alas for us, it was a success.

Across the globe, we still have 20,000 bombs ready to go, many of them on high alert.

Commemorating this event and its consequences were three different developments in New Mexico.

The first and most incongruous was news of a delegation embarking on that very day and heading to Washington, DC, to sell someone (not specified in the Los Alamos Post story) how much it means to the state of New Mexico to have the Labs here.

Nice way to celebrate the anniversary, que no? Drinks afterwards at the Capitol?

The delegation was composed of nearly 20 members of the business community accompanied by a representative from Governor Martinez’ office. We might have expected the head of the Chamber of Commerce, Simon Brackley, to be there, but it was a bit of a surprise to see Lilian Montoya Rael, a Board member from Christus St. Vincent’s Hospital.

But I suppose that the Labs, being so detrimental to health, are an indispensable asset to the Hospital.

Speaking of health, the second event, in marked contrast to the humble fundraising efforts of a few of our respected citizens, addressed the reality — the real impact of the bomb test on the lives of citizens, in this case the citizens of Tularosa, a small village that exists outside the presumed boundary of fallout that was expected from that event. These men, women and children have experienced a disproportionately higher-than-ever rate of cancers and other disabling conditions. July 16 was named Nuclear Disasters Day in Tularosa. They celebrated with luminarias at the town baseball field!

Last but not least, July 16 marks the first day of the Los Alamos Hunger Strike initiated by Alaric Balibreras. Thirty strikers have joined him in his plea to have a conversation with Those in Charge of the Lab’s affairs about coming up with a Plan to actually change the Lab’s Mission, currently the production of a-bombs (as posted on the Lab’s website), to production of Things that are Good for Us. (Remember “Better Living through Chemistry?” Such were the slogans that set off the hippie resistance of the 60s, and I’m told that the planets are aligned in a similar pattern today!!)

And which way will it go? Will the delegation of business people receive more money from Washington to produce more bombs, an activity so lucrative to the state that they can’t bear to let it go… or will this year be the year of The Rise of the Little People demanding an end to this profligacy and waste? Stay tuned. Alaric plans to fast until Nagasaki Day, August 9, anniversary of the day in 1945 when the US used the first plutonium bomb against the residents of that city, killing 130,000 on site and more later.

Enough, he says, and we say with him: Let’s have a Change of Heart, For a World of Beauty! Raise an empty glass with 30 hunger strikers and join them if you wish: you’ll find them on Facebook, at Los Alamos Hunger Strike.

We will be following the strike throughout the 21 days with updates and interviews. Here’s one newsflash from yesterday:

Los Alamos, July 16, 2012

STANDING AT THE GATES OF THE LAB some 20 protestors, most of them from Trinity Abolition, an Albuquerque group which protests at the Lab on a regular basis, as well as members of the hunger strike, joined hands outside the gates of the lab. “Lab people came down and took our pictures and got our names,” reports Ellie Voutselas of Pax Christi, one of the fasters.

Alaric then moved over to Ashley Pond, the original site of the Lab and now a public park, where he was joined by a young striker whose dog set up a howl for the duration. Guess that puppy has a few things to say about nuclear weapons, but the canine may provide an unneeded distraction if this keeps up.

Still Time to Comment on LANL’s Burning Desire for Expanded Weapons Production

Ironically today (June 28) is the deadline for public comment under the National Environmental Policy Act (NEPA) for concerned citizens to comment on a proposed ~$5 billion facility at the Los Alamos Lab ponderously called the Chemistry and Metallurgy Research Replacement Project- Nuclear Facility. In short, it is a huge new plutonium facility that will provide materials characterization and analytical chemistry in direct support of production of the atomic cores or “triggers” of nuclear weapons, commonly called the plutonium pits. The Nuclear Facility will be the keystone to an expanded complex at LANL’s Technical Area-55 that will quadruple production capacity from 20 to 80 pits per year.

I say ironically because of the fire that is now threatening the Lab. We need to begin questioning whether expanded nuclear weapons production at Los Alamos is feasible in a possibly long-term drought and climate warming punctuated with catastrophic forest fires. More broadly, as we face increasing budget and resource constraints, we need to decide whether our money and water go into expanded nuclear weapons production, or do they go into repairing schools and infrastructure for the common good of society?

 

Mother Earth Gives Nuclear Renaissance a Black Eye

Our hearts and prayers go out go out to the people of Japan.

As Japan is faced with the possibility of nuclear meltdowns in five earthquake-damaged nuclear reactors, the U.S. and other countries are re-considering nuclear plans. While it is unlikely that radiation that has leaked or will leak from the Japanese reactor accidents will reach the United States.  This could change if there is an explosion and/or fire affecting one or more of the reactor cores or spent fuel pools. The accident at Chernobyl (25th anniversary is April 26th) affected the entire Northern Hemisphere because of a massive explosion in the core, and an out-of-control fire that burned for days.  This same scenario is unlikely in Japan. But reactors have been damaged beyond repair and old questions are being raised again.

In the U.S., Sen. Joe Lieberman (I-Conn.) and Democratic Rep. Ed Markey of Massachusetts have made statements – “But I think we’ve got to kind of quietly put, quickly put, the brakes on until we can absorb what has happened in Japan as a result of the earthquake and the tsunami and then see what more, if anything, we can demand of the new power plants that are coming on line,” Lieberman stated. “Any plant that is being considered for a seismically vulnerable area in the United States should be reconsidered right now,” Markey said, adding that the Japanese earthquake registering 8.9 in magnitude was “a hundred times greater in intensity” than the level that U.S. plants are built to withstand.

Countries in Europe are pausing to re-consider, also. Japan’s nuclear emergency Monday prompted Germany and Switzerland to halt nuclear programmes as anxious Europe scrambled to review cross-border safety while safeguarding the powerful industry. More

Why were the Fukushima reactors at sea level? Japan’s nuclear accident exposes the dilemma of whether to build power plants on tsunami-prone coasts or inland sites where water supplies are unreliable, a problem likely to be aggravated by climate change, experts say. (More from Reuters)

What happened at the Fukushima plant? “Three of its six reactors were in operation when the earthquake hit. The reactors — which went into service between 1970 and 1979 — are designed to shut down automatically when a quake strikes, and emergency diesel generators began the task of pumping water around the reactors to cool them down. However, these stopped about an hour later. The failure of the back-up generators has been blamed on tsunami flooding by the International Atomic Energy Agency (IAEA).” More –

This event shows how Mother Earth can have her way with the best-made plans. The power company said that that 7.9 was the highest magnitude for which they tested the safety for their No. 1 and No. 2 nuclear power plants in Fukushima. The original magnitude was estimated to be 8.9, which would have been 10 ten times the magnitude 7.9 that the structures were tested for. The Japan Meteorological Agency up-rated Friday’s earthquake to 9.0 on the Richter scale, meaning that it was twice as powerful as initially thought. More

Here at home, we have no commercial reactors in New Mexico, but there are national nuclear weapons facilities, including Los Alamos National Laboratory, which currently has plans for a $5 billion addition to the Lab’s plutonium weapons production complex. This addition, called the Chemistry and Metallurgy Research Replacement project Nuclear Facility (CMRR-NF) is being designed to survive a 7.0 magnitude earthquake without releasing plutonium.  Much of the estimated cost is to seismically qualify the CMRR-NF to be built on the fault-ridden Pajarito Plateau. The plans call for a storage vault with the capacity of six metric tons of radioactive materials, such as plutonium.

Now would be a good time to re-consider any plans that make us feel invincible.

 

CMRR FY2012 Budget Request – Blank Check or Black Budget?

CMRR FY2012 Budget Request – Blank Check or Black Budget?

The FY2012 budget request shows $300 million for the Chemistry and Metallurgy Research Replacement (CMRR) Project, which is now estimated to cost a total of $6.22 billion. $29.9 million is requested for equipment in the recently completed first building, the Radiological Laboratory/Utility/Office Building (RLUOB). But exactly how will the remaining $270 million be spent? That’s literally “TBD” (To Be Determined). What a great deal – receive $270 million and then decide what to do with it. How lucky the Lab must feel to get a blank check in this era of fiscal restraint.

Is the Lab planning to use some of the $270 million to begin construction of the huge “Nuclear Facility”? Because there is a Supplemental Environmental Impact Statement (EIS) now underway for the NF, any construction funding now could prejudice any decision, or at least would smell like prejudice. A more likely scenario is that the Lab figures that it might be able to stash funds away in some black budget to use on construction later, in effect creating a slush fund that would insulate it from and possible future budget cuts.

Perhaps going back to last year will offer some clues. The FY2011 Congressional Budget Request projected that LANL would ask for a total of $322.1 million for FY2012.

The FY2011 breakout estimated for FY2012 was:

$29.9 million RLUOB Equipment Installation (REI) [This turned out to be exactly the amount requested for FY2012.]

$3 million for Other Project Costs (OPC) [This turned out to be “TBD” for FY 2012.]

$102.8 million for NF design [This turned out to be “TBD” for FY 2012. Not counting any FY2012 funding, $419 million has been spent to date on design of the NF.]

$186.4 million for NF construction [FY2012 was to be the first year that construction funds were to be requested for the NF. This turned out to be “TBD” for FY 2012. But it really should be “0” because there is a SEIS underway.]

If all of the $270 million requested for FY2012 is not for NF design, we deserve to know what it’s for.

CMRR is Key to Expanded Plutonium Pit Production

While being narrowly correct, LANL PR man Kevin Roark is misleading when he claims [in a June 25, Letter to the Editor of the Santa Fe New Mexican  newspaper] that plutonium pit production will not take place in the new Chemistry and Metallurgy Research Replacement Project (CMRR). What he fails to disclose is that the Lab is not building just one facility, but instead is creating an integrated manufacturing complex for expanded production for which the CMRR is absolutely key. This complex will consist of LANL’s existing production facility “PF-4” with ~$300 million in upgrades; CMRR’s already completed first phase, the $400 million “Rad Lab”; and the future $4 billion CMRR “Nuclear Facility,” now being debated.

The Nuclear Facility will be literally next door to PF-4 and linked to it via underground tunnel. While pits are physically manufactured in PF-4’s glovebox lines, the Nuclear Facility’s central missions of “materials characterization” and “analytical chemistry” are essential operations that ensure “weapons-grade” plutonium and pit production quality control. The National Nuclear Security Administration’s own documents show that the Nuclear Facility is being specifically sized to support expanded production of up to 80 pits per year, quadruple LANL’s currently approved rate. It is also planned to have a vault for up to six metric tons of “special nuclear materials,” capable of storing around 1,000 pits.

Roark must think that New Mexicans are naïve enough to accept the Lab’s claims that the CMRR is all about “science” even as LANL becomes more and more a production site. Sadly, this is only part and parcel of the substantial rebuilding of the U.S. nuclear weapons production complex, which will also include a new $3.5 billion Uranium Processing Facility in Tennessee and a new privately financed Kansas City Plant for production of the 1,000’s of nonnuclear components that go into a nuclear weapon.

Many New Mexicans hoped for serious mission diversification at Los Alamos, which some $5 billion sunk into its plutonium infrastructure will almost certainly shut the door on. Schools in Santa Fe and all across the country are being closed due to lack of funding. Nevertheless, our government is preparing to spend some $10 billion to build new production plants even as we are purportedly working toward the declared long-term national security goal of a nuclear weapons-free world. To get there, citizens need to push the politicians to meet the needs of everyday people, not those of the vested nuclear weaponeers.

Power of the Purse over DOE Projects

I was in Washington, DC last week and heard a number of congressional offices express support for the CMRR-Nuclear Facility, indicating what we already know, that it will be very difficult to defeat directly. However, the issue of costs is another matter, and I have some hope that the Nuclear Facility can die a death of 1,000 cuts.

For example, while in DC I met with a staff person knowledgeable about DOE project cost accounting requirements introduced by the Senate Armed Services Committee. I expressed my concern that LANL could implement its first segment of CMRR-Nuclear Facility construction without having come up with total costs, thus steamrolling the project.  [Reminder: we are now $4.5 billion for estimated total project costs and climbing.]  That staffer said that sort of thing will not be allowed to happen. Further, while being in favor of some advance site prep, that staffer said LANL would not be allowed to construct the concrete batch plant and replace 225,000 cubic yards of weak volcanic ash strata with “lean concrete” until total project costs are in.

The requirements were introduced as SEC. 4713. NOTIFICATION OF COST OVERRUNS FOR CERTAIN DEPARTMENT OF ENERGY PROJECTS.

I realize this is not a showstopper, but it is something. It should slow the CMRR-NF down some, which hopefully we can capitalize on. Further, it may provide us with ammo over the project’s tremendous and escalating costs.

Nick Roth of the Alliance for Nuclear Accountability was instrumental in suggesting this cost accounting requirement to Congress.

Three Huge New Facilities Rebuild U.S. Nuclear Weapons Production Capacity

Modern nuclear weapons are comprised of three general types of components: plutonium pit primaries, uranium/lithium secondaries that are triggered by the primaries, and the 1,000’s of non-nuclear components that create deliverable weapons of mass destruction (fuzes, radar, bomb cases, etc.). The U.S. is aggressively pursuing major new production facilities for all three types. At the Los Alamos National Laboratory (LANL) in New Mexico, the “Chemistry and Metallurgy Research Replacement (CMRR) Project” will be the keystone to a revived plutonium manufacturing complex. The proposed “Uranium Processing Facility” (UPF) at the Y-12 Site in Oak Ridge, Tennessee, will be the future production plant for warhead secondaries. A new “Kansas City Plant” (KCP) in Missouri for nonnuclear components production is slated for groundbreaking in August 2010. Each of these three major new production facilities is expected to operate for the next half-century, in sharp contradiction to the declared national and global security goal of a nuclear weapons-free world.

A Compromised START

Nuclear Watch New Mexico is a staunch supporter of arms control treaties, particularly since they can be confidence building steps toward the long term goal of creating the nuclear weapons-free world articulated by President Obama.

However, we fear that arms control treaties will be turned on their heads to become in effect armament treaties for the American nuclear weapons complex. We think our fears are now concretely realized by the Obama Administration’s “modernization plan” attached to yesterday’s submittal of New START to the Senate for ratification.

As you probably know, the Obama plan is to increase funding for the NNSA’s nuclear weapons programs from $6.4 billion in FY10 to $9 billion by FY 2018, which is a 76% increase above the Cold War annual average of $5.1 billion. We think that is obviously a serious step backwards on the road to a nuclear weapons-free world, especially when the labs seem intent on introducing new military capabilities to existing types of U.S. nuclear weapons.

There have been calls for unconditional public support of New START. Yet current political realities are that New START will be heavily conditioned by both the Obama Administration and the Senate to include the revitalization of the U.S. nuclear weapons complex.

In concrete terms, this means dramatically increased funding for huge new production plants for plutonium, uranium and nonnuclear components, respectively the Los Alamos CMRR-Nuclear Facility, the Y-12 Uranium Processing Facility and the new Kansas City Plant.

It also means future aggressive Life Extension Programs that will substantially modify the nuclear explosives package, a serious threshold that we have not yet crossed (and which could effectively recreate the Reliable Replacement Warheads that NNSA sought but Congress rejected, but by another name). We also need to remain aware of the failure to ratify the Comprehensive Test Ban Treaty in 1999, but which nevertheless profited the nuclear weapons labs and complex by some $100 billion to date under the Stockpile Stewardship Program to compensate for the loss of underground full-scale testing.

We don’t question that appeals for public support of New START should go forward. But as NGOs we are also entrusted with public responsibility to provide a fuller picture.

We argue that certain conditions for New START ratification, such as increased funding for new production facilities, LEPs and stockpile work, should be publicly explained, and lead to qualified instead of unconditional support of New START ratification.

Coghlan Report from NPT Rev Con

I’m in New York City for the first week of the Non-Proliferation Treaty Review Conference that opened today (Monday May 3). Yesterday global citizens marched from Times Square to the United Nations demanding nuclear weapons abolition. I was very moved to see ~10,000 people from ~25 countries pour into this little park across from the UN, where NukeWatch and some 40 other organizations had information waiting for them.

My main gig here is about the 3 proposed huge nuclear weapons production plants the U.S. is planning to spend some $10 billion on over the next decade. They are the “Nuclear Facility” that will keystone an expanded plutonium complex at Los Alamos; the Uranium Processing Facility (UPF) at the Y-12 Site near Oak Ridge, TN; and the new Kansas City Plant (KCP). These facilities will expand production capability up to 80 new warheads per year. For more, see New US Production Facilities.

When I talked to folks (half from other countries) here for the Conference about these new facilities, most invariably say, “But, but, buuuuuuuut… what about Obama?” Their eyes get big when I tell them Obama doubled FY 2011 funding for the Nuclear Facility and UPF (KCP is privately financed, hence outside the federal budget). I guess they heard the part loud and clear from Obama in Prague about a nuclear weapons-free world, but not so much when he said probably not in my lifetime.

If left just up to him, I suppose that would be the case, given that these production facilities are expected to operate until 2065. But at least there are ~10,000 global citizens here in NYC pushing for sooner than that. We’ll see what concrete results the NPT Review Conference brings.

LANL Installing Equipment for Manufacuring 80 Plutonium Pits Per Year

The question arose at the Alliance for Nuclear Accountability meeting this week over the potential level of future pit production at LANL and the role that the Chemistry and Metallurgy Research Replacement Project – Nuclear Facility will play in it.

See the below from the
FY10-14 Supplement to the Stockpile Stewardship Plan, p. 14, under “Recent Key Accomplishments”: (emphasis added)

“More than six new W88 plutonium pits
manufactured. New equipment installed as
scheduled for gradual capacity increases to
80 pits per year
potential by scheduled
operational date for Chemistry and Metallurgy
Research Replacement (CMRR) Nuclear Facility.”

This whole document is worthwhile reading (3.7MB).

Obama’s New Budget Increases Funding for Nuclear Weapons Production Facilities; Cuts Dismantlements

In the new budget request for 2011 the Obama Administration proposes to freeze discretionary domestic spending for programs such as education, nutrition, air traffic control and national parks for three years while dramatically increasing funding for new US nuclear weapons production facilities. Meanwhile the proposed budget for dismantling warheads retired from the stockpile is down by 40%. Funding for a new nuclear facility at Los Alamos National Laboratory to be used in direct support of plutonium pit production, the CMRR-NF, is increased to $225 million requested from $97M in FY10 (+132%). After FY11, funding is proposed to triple the FY10 amount to $300 million for each of the following four consecutive years.

Funding for a new “Uranium Processing Facility” (UPF) at the Y12 production plant near Oak Park Ridge, TN, is proposed to increase to $115M from $94M in FY10 (+22%). However, its big money is in the following four consecutive years, climbing to $320 million by 2015 (in all a 240% increase from FY10 funding). Totals costs for both the CMRR and UPF are still “TBD” [To Be Determined], meaning they don’t know, but each will probably cost $3 billion or more.

Outside of the federal budget, groundbreaking is expected this Spring on a new privately-financed ~$700 million Kansas City Plant for nonnuclear components production for US nuclear weapons, subsidized by Kansas City municipal bonds. This pretty well spans the spectrum of future US nuclear weapons production, with big increases for new facilities for plutonium, uranium and nonnuclear components. At the same time, the Obama budget proposes to cut dismantlement from $96.1 million in FY 2010 to $58 million.

Obama is preemptively surrendering to the nuclear weapons labs, the for-profit private corporations running those labs, and the 2/3rd’s Senate majority including Republicans needed for treaty ratifications. All of these special interests explicitly seek to extract more taxpayer funding for nuclear weapons programs in exchange for ratification of a renewed bilateral arms control treaty with Russia and a long-sought-for Test Ban Treaty.

We went through this a decade ago, when the nuclear weapons complex got billions of dollars and but ratification of the Comprehensive Test Ban Treaty failed. History is getting ready to repeat itself, this time with the nuclear weapons labs seeking the capability to produce future new-design weapons. Obama’s new budget begins to give them just that, welfare for warheads that can’t be used while American public needs are not adequately met.

Los Alamos – Plutonium Center of Negligence

An October 27 press release from the Project on Government Oversight (POGO)
Defense Board Catches Los Alamos Trying to Dodge Plutonium Safety Vulnerability” revolves around a new Defense Nuclear Facilities Safety Board (DNFSB) revelation of public safety vulnerability and seismic issues at TA-55 (The Lab’s plutonium Technical Area).

The DNFSB has been very patient on the safety issues at TA-55. In a September 23, 2005 weekly report, they stated that LANL needed to try to justify a passive confinement strategy, continue plans to reduce radioactive materials, and to seismically upgrade the glove-box supports that have not already been upgraded. These issues are still unaddressed as of the latest DNFSB report.

Seismic issues run deep at Los Alamos. NNSA currently has plans to construct and operate the Chemistry and Metallurgy Research Replacement–Nuclear Facility (CMRR–NF) to support plutonium operations as a replacement for portions of the Chemistry and Metallurgy Research (CMR) facility, a 1950’s structure that faces significant safety and seismic challenges. In 1999, a fault was discovered under the old CMR building, which has been neglected, contaminated, and has several abandoned wings. This fault was the major reason given to build a new facility 1.2 miles away at TA-55.

The Lab has big plans for plutonium. In December 2008, NNSA released a Record of Decision for its Complex Transformation Environmental Impact Statement that keeps manufacturing and research and development involving plutonium at Los Alamos and blesses the building of the CMRR-NF. This decision was a combination of two alternatives – a Distributed Centers of Excellence and a Capability-Based alternative. But to compensate for the nearby fault lines, the CMRR-NF is now being designed with 10-foot thick concrete floors and there are plans being designed to pump grout into a layer of fragile volcanic ash under the proposed facility. Current construction estimates for this facility are $2 billion.

The Lab has been negligent in taking care of its plutonium flagship, TA-55. It has not been a good steward of plutonium missions. Los Alamos is the wrong location, seismically. Congress must seriously consider ending this unnecessary plutonium work.