Lack Of Safety And Health Priorities Continue To Plague Los Alamos Beryllium Program

A new assessment finds that Department of Energy (DOE) is not conducting effective oversight of the Los Alamos National Laboratory (LANL) beryllium program, or of safety and health programs in general. In addition, DOE is not maintaining sufficient technical capability and knowledge of site and contractor activities to make informed decisions about hazards and risks. DOE indicated the lack of sufficient safety and health resources has presented a challenge to achieving effective oversight in this area.

Continue reading

Forum on June 14 in Aiken, SC on Expanded Production of Plutonium “Pits” for Nuclear Weapons

Forum on June 14 in Aiken, SC on Expanded Production of Plutonium “Pits” – for Nuclear Weapons – to Give Voice to Concerns in Face of DOE’s Failure to Engage and Inform the Public about the Risky Proposal

Columbia, SC– The controversial proposal by the U.S. Department of Energy to expand production of plutonium “pits”- the core of all nuclear weapons – will be the subject of a public forum in Aiken, South Carolina on Friday, June 14, 2019.  The event is free and open to all members of the public.

In response to DOE’s lack of public engagement about the proposal and its potential environmental and health impacts, three public interest groups that work on DOE and nuclear weapons issues have taken the initiative on the matter. The questionable proposal by DOE’s National Nuclear Security Administration is to expand pit production at the Savannah River Site into the shuttered MOX plant – a totally new and unproven mission for SRS – and at the Los Alamos National Lab to 80 or more pits per year.  Such pit production for new and “refurbished” nuclear weapons may help stimulate a new nuclear arms race. The vague proposal is far from finalized and is unauthorized and unfunded by Congress.

Continue reading

Plutonium Pit Production NEPA Talking Points

LANL Molten Plutonium for Pit
Molten plutonium in a crucible. 

The National Environmental Policy Act (NEPA) is the landmark environmental law which requires executive agencies to give the public the opportunity to formally review and comment on major federal proposals. These talking points outline the history of the Department of Energy’s NEPA compliance on its various proposals concerning the production of plutonium pits (the fissile cores of nuclear weapons). The conclusion is that DOE’s semi-autonomous National Nuclear Security Administration (NNSA) is legally required to prepare a supplemental programmatic environmental impact statement (PEIS) on its current plan to expand plutonium pit production.

There are at least three reasons why NNSA must complete a supplemental programmatic environmental impact statement for expanded plutonium pit production:
1)    Implementing regulations for the National Environmental Policy Act stipulate that “DOE shall prepare a supplemental EIS if there are substantial changes to the proposal or significant new circumstances or information relevant to environmental concerns…” 10. C.F.R. § 1021.314
2)    As precedence, since 1996 there have been five programmatic environmental impact statements related to pit production and its expansion. It is legally unlikely that NNSA could implement its current plan to expand plutonium pit production without a new supplemental PEIS.
3)    Now that NNSA is planning to produce more than 50 pits per year (or more than 80 pits under multiple shift operations), it is obliged by the 1998 court order to prepare a new PEIS.
Continue reading

New Contractors Selected For Expanded Nuclear Weapons Production at Los Alamos

Santa Fe, NM – Today the Department of Energy’s National Nuclear Security Administration (NNSA) announced its choice for the new management and operating contract for the Los Alamos National Laboratory (LANL).

The new contractor, Triad National Security, LLC, is a limited liability company consisting of the Battelle Memorial Institute, the University of California and Texas A&M University. All three are non-profits, and it is unclear how this will affect New Mexico gross receipts taxes.

Battelle claims to be the world’s largest non-profit technology research and development organization, and manages a number of labs including the Lawrence Livermore and Idaho National Laboratories. Texas A&M was founded in 1876 as the state’s first public institution of higher learning and has the largest nuclear engineering program in the country. DOE Secretary Rick Perry is an avid A&M alumnus.

The new contract includes a five-year base time with five one-year options, for a total of 10 years if all options are exercised. The estimated value of the contract is $2.5 billion annually.

The University of California (UC) ran the Lab from its beginning in 1943 until June 2006, when Los Alamos National Security, LLC (LANS), composed of the University of California (UC), Bechtel, AECOM and BWX Technologies, Inc., took over. That contract had a ten-year base period with ten one-year options, for a total of 20 years if all options were exercised. But LANS was terminated with nine years left of possible options. This was primarily due to LANS improperly preparing a barrel of radioactive wastes that ruptured, closing the Waste Isolation Pilot Plant for nearly three years. NNSA did not clarify why it is now issuing a shorter contract.

This change in contract follows a May 10, 2018 announcement by NNSA that production of plutonium pits, the fissile cores of nuclear weapons, will be expanded to at least 30 pits per year at LANL, and an additional 50 pits per year at the Savannah River Site. The Los Alamos Lab is the birthplace of nuclear weapons, and it is tying its future to increased nuclear weapons production, with the active support of the New Mexico congressional delegation. The Lab proposed, but failed to convince NNSA, to produce all 80 plutonium pits per year. LANL’s core research, testing and production programs for nuclear weapons now comprise 70% of its ~$2.5 billion annual budget, while much of the Lab’s remaining budget indirectly supports those programs.

Lisa E. Gordon-Hagerty, the new NNSA Administrator, testified during her confirmation hearing that expanded plutonium pit production is her number one priority.  However, expanded production is NOT needed to maintain the safety and reliability of the existing nuclear weapons stockpile. In fact, no pit production for the existing nuclear weapons stockpile has been scheduled since 2011, and none is scheduled for the future. Up to 15,000 “excess” pits and another 5,000 in “strategic reserve” are already stored at DOE’s Pantex Plant near Amarillo, TX. In 2006 independent experts found that pits last a least a century (they currently average 40 years old). A 2012 follow-on study by the Livermore Lab found that the “graceful aging of plutonium also reduces the immediate need for a modern high-capacity manufacturing facility to replace pits in the stockpile.”

Future pit production is for speculative future new designs being pushed by the nuclear weapons labs, so-called Interoperable Warheads for both land- and sub-launched missiles that the Navy does not want. Moreover, future pits will NOT be exact replicas of existing pits. This could have serious potential consequences because heavily modified plutonium pits cannot be full-scale tested, or alternatively could prompt the U.S. to return to nuclear weapons testing, which would have severe international proliferation consequences.

Jay Coghlan, Nuclear Watch Director, commented, “Regardless of who runs the Lab, LANL will decrease mission diversification and increase nuclear weapons production, while holding cleanup flat at a tenth of its weapons budget. New Mexico been a nuclear weapons colony since WWII, and adding Battelle, Texas A&M, and the University of California is just more of the same. There will be little if any added benefit for New Mexico’s citizens.”

What’s Not in NNSA’s Plutonium Pit Production Decision

 Today the National Nuclear Security Administration (NNSA) announced:

To achieve DoD’s [the Defense Department] 80 pits per year requirement by 2030, NNSA’s recommended alternative repurposes the Mixed Oxide Fuel Fabrication Facility at the Savannah River Site in South Carolina to produce plutonium pits while also maximizing pit production activities at Los Alamos National Laboratory in New Mexico.  This two-prong approach – with at least 50 pits per year produced at Savannah River and at least 30 pits per year at Los Alamos – is the best way to manage the cost, schedule, and risk of such a vital undertaking.

First, in Nuclear Watch’s view, this decision is in large part a political decision, designed to keep the congressional delegations of both New Mexico and South Carolina happy. New Mexico Senators Tom Udall and Martin Heinrich are adamantly against relocating plutonium pit production to South Carolina. On the other hand, South Carolina Senator Lindsay Graham was keeping the boondoggle Mixed Oxide (MOX) program on life support, and this pit production decision may help to mollify him. This could also perhaps help assuage the State of South Carolina, which is suing the Department of Energy for failing to remove plutonium from the Savannah River Site as promised.

But as important is what is NOT in NNSA’s plutonium pit production decision:

  There is no explanation why the Department of Defense requires at least 80 pits per year, and no justification to the American taxpayer why the enormous expense of expanded production is necessary.

•  NNSA avoided pointing out that expanded plutonium pit production is NOT needed to maintain the safety and reliability of the existing nuclear weapons stockpile. In fact, no production of plutonium pits for the existing stockpile has been scheduled since 2011, and none is scheduled for the future.

•  NNSA did not mention that in 2006 independent experts found that pits last a least a century. Plutonium pits in the existing stockpile now average around 40 years old. The independent expert study did not find any end date for reliable pit lifetimes, indicating that plutonium pits could last far beyond just a century.

• NNSA did not mention that up to 15,000 “excess” pits are already stored at the Pantex Plant near Amarillo, TX, with up to another 5,000 in “strategic reserve.” The agency did not explain why new production is needed given that immense inventory of already existing plutonium pits.

•  Related, NNSA did not explain how to dispose of all of that plutonium, given that the MOX program is an abysmal failure. Nor is it made clear where future plutonium wastes from expanded pit production will go since operations at the troubled Waste Isolation Pilot Plant are already constrained from a ruptured radioactive waste barrel, and its capacity is already overcommitted to existing radioactive wastes.

•  NNSA did not make clear that expanded plutonium pit production is for a series of speculative future “Interoperable Warheads.” The first IW is meant to replace nuclear warheads for both the Air Force’s land-based and the Navy’s sub-launched ballistic missiles. The Obama Administration delayed “IW-1” because the Navy does not support it. However, the Trump Administration is restarting it, with annual funding ballooning to $448 million by 2023, and “IW-2” starting in that same year. Altogether the three planned Interoperable Warheads will cost at least $40 billion, despite the fact that the Navy doesn’t support them.[1]

•  NNSA’s expanded plutonium pit production decision did not mention that exact replicas of existing pits will NOT be produced. The agency has selected the W87 pit for the Interoperable Warhead, but its FY 2019 budget request repeatedly states that the pits will actually be “W87-like.” This could have serious potential consequences because any major modifications to plutonium pits cannot be full-scale tested, or alternatively could prompt the U.S. to return to nuclear weapons testing, which would have severe international proliferation consequences.

•  The State of South Carolina is already suing the Department of Energy for its failure to begin removing the many tons of plutonium at the Savannah River Site (SRS). NNSA’s pit production decision will not solve that problem, even as it will likely bring more plutonium to SRS.

•  The independent Defense Nuclear Facilities Safety Board has expressed strong concerns about the safety of plutonium operations at both the Los Alamos National Laboratory (LANL) LANL and SRS, particularly regarding potential nuclear criticality incidents.[2] NNSA did not address those safety concerns in its plutonium pit production decision.

•  Politicians in both New Mexico and South Carolina trumpet how many jobs expanded plutonium pit production will create. Yet NNSA’s expanded plutonium pit production decision does not have any solid data on jobs produced. One indicator that job creation will be limited is that the environmental impact statement for a canceled $6 billion plutonium facility at LANL stated that it would not produce a single new Lab job because it would merely relocate existing jobs. Concerning SRS, it is doubtful that pit production could fully replace the jobs lost as the MOX program dies a slow death. In any event, there certainly won’t be any data on the greater job creation that cleanup and renewable energy programs would create. Funding for those programs is being cut or held flat, in part to help pay for nuclear weapons programs.

•  Finally, the National Environmental Policy Act (NEPA) requires that major federal proposals be subject to public review and comment before a formal decision is made. NNSA’s decision does not mention its NEPA obligations at all. In 1996 plutonium pit production was capped at 20 pits per year in a nation-wide Stockpile Stewardship and Management Programmatic Environmental Impact Statement (PEIS). NNSA failed to raise that production limit in any subsequent NEPA process, despite repeated attempts. Arguably a decision to produce 80 pits or more per year requires a new or supplemental nation-wide programmatic environmental impact statement to raise the production limit, which the new dual-site decision would strongly augment. This then should be followed by whatever site-specific NEPA documents might be necessary.

Jay Coghlan, Nuclear Watch Director, commented, “NNSA has already tried four times to expand plutonium pit production, only to be defeated by citizen opposition and its own cost overruns and incompetence. But we realize that this fifth attempt is the most serious. However, we remain confident it too will fall apart, because of its enormous financial and environmental costs and the fact that expanded plutonium pit production is simply not needed for the existing nuclear weapons stockpile. We think the American public will reject new-design nuclear weapons, which is what this expanded pit production decision is really all about.”

# # #

[1]     See 2012 Navy memo demonstrating its lack of support for the Interoperable Warhead at https://nukewatch.org/importantdocs/resources/Navy-Memo-W87W88.

[2]     For example, see Safety concerns plague key sites proposed for nuclear bomb production, Patrick Malone, Center for Public Integrity, May 2, 2108, https://www.usatoday.com/story/news/nation/2018/05/02/safety-concerns-nuclear-bomb-manufacture-sites/572697002/

 

Expanded Plutonium Pit Production at LANL Will Not Result in Significant Positive Effect On Job Creation and the Regional Economy

Abstract: Expanded production of plutonium pits, the fissile cores of modern thermonuclear weapons, is cynically being justified as a source of job creation. Precise data on employment in plutonium pit production at the Los Alamos National Laboratory (LANL) and the number of additional jobs if expanded is not publicly available to our knowledge. However, the National Nuclear Security Administration’s own documents quoted below explicitly state that expanded pit production would not have any significant positive effect on job creation and the regional economy of northern New Mexico. Further, Nuclear Watch argues that expanded plutonium pit production could actually have negative effect if expanded pit production blocks other economic alternatives such as comprehensive cleanup, which could be the real job producer. Moreover, given LANL’s poor safety and environmental record, expanded plutonium pit production could have a seriously negative economic effect on northern New Mexico in the event of any major accidents or additional contamination.

Final Supplemental Environmental Impact Statement for the Nuclear Facility Portion of the Chemistry and Metallurgy Research Building Replacement Project at Los Alamos National Laboratory, Los Alamos, New Mexico

https://energy.gov/nepa/eis-0350-s1-supplemental-environmental-impact-statement-nuclear-facility-portion-chemistry-and

Bolded emphasis added

Note: The CMRR-Nuclear Facility was the up to $6.5 billion dollar plutonium facility NNSA proposed to build at LANL in direct support of expanded plutonium pit production. The Obama Administration cancelled it in 2012 after costs rose so high. Nevertheless, the 2011 CMRR-Nuclear Facility supplemental environmental impact statement remains the most relevant source of publically available socioeconomic information concerning expanded plutonium pit production that we know of.

Volume 1, p. 2-43, Socioeconomics

Under the Modified CMRR-NF Alternative, an increase in construction-related jobs and businesses in the region surrounding LANL is also expected. Construction employment would be needed over the course of a 9-year construction period under either the Deep or Shallow Excavation Option. Construction employment under either option is projected to peak at about 790 workers, which is expected to generate about 450 indirect jobs in the region. Operation of the Modified CMRR-NF and RLUOB would involve about 550 workers at LANL, with additional workers using the facility on a part-time basis. The personnel working in the Modified CMRR-NF and RLUOB, when fully operational, would relocate from other buildings at LANL, including the existing CMR Building, so an increase in the overall number of workers at LANL is not expected.

Note: The first phase of the Chemistry and Metallurgy Research Replacement Project, the Radiological Laboratory Utility and Office Building (RLUOB), is already built. It is now being retrofitted to handle up to 400 grams of plutonium-239 equivalent instead of the original 8.4 grams. This will greatly increase its special nuclear materials analytical chemistry and materials characterization capabilities in direct support of expanded plutonium pit production.

Under the Continued Use of CMR Building Alternative, about 210 employees would continue to work in the CMR Building until safety concerns force additional reductions in facility operations. In addition, about 140 employees would be employed at RLUOB. A total of about 350 personnel would have their offices relocated to RLUOB. The personnel working in the CMR Building and RLUOB, when fully operational, would not result in an increase in the overall number of workers at LANL.

Pg. 4-12

4.2.9 Socioeconomics

Construction Impacts—Construction of new buildings at TA-55 to house CMR activities would require a peak construction employment level of 300 workers. This level of employment would generate about 852 indirect jobs in the region around LANL. The potential total employment increase of 1,152 direct and indirect jobs represents an approximate 1.3 percent increase in the workforce and would occur over the proposed construction period. This small increase would have little or no noticeable impact on the socioeconomic conditions of the region of influence (ROI).

 Operations Impacts—CMRR Facility operations would require a workforce of approximately 550 workers. As evaluated in the CMRR EIS, this would be an increase of about 340 workers over currently restricted CMR Building operational requirements. Nevertheless, the increase in the number of workers in support of expanded CMRR Facility operations would have little or no noticeable impact on socioeconomic conditions in the LANL ROI (region of influence). New LANL employees hired to support the CMRR Facility would compose a small fraction of the LANL workforce and an even smaller fraction of the regional workforce.

4.3.9 Socioeconomics

Construction Impacts – Deep Excavation Option—Construction of the Modified CMRR-NF under the Deep Excavation Option would require a peak construction employment level of about 790 workers (LANL 2011a:Data Call Tables, 002). This level of employment would generate about 450 indirect jobs in the region around LANL. The potential total peak employment of 1,240 direct and indirect jobs represents an increase in the ROI workforce of approximately 0.8 percent. Direct construction employment would average 420 workers annually over this time, approximately half of the estimated peak employment. The average direct construction employment would result in about 240 indirect jobs in the region around LANL. This total of 660 direct and indirect jobs represents an approximate 0.4 percent increase in the ROI workforce. These small increases would have little or no noticeable impact on the socioeconomic conditions of the ROI.

Pg. 4-54

Chapter 4 – Environmental Consequences

Construction Impacts – Shallow Excavation Option—The impacts under the Shallow Excavation Option from construction of the Modified CMRR-NF would be similar to the Deep Excavation Option. The peak employment number of about 790 construction workers would be the same as under the Deep Excavation Option, and the annual average would be 410 workers over the life of the project. The average direct construction employment would result in about 240 indirect jobs in the region around LANL. This total of 650 direct and indirect jobs represents an approximate 0.4 percent increase in the ROI workforce. Therefore, there would be little or no noticeable impact on the socioeconomic conditions of the ROI.

Operations Impacts—Operations at the Modified CMRR-NF and RLUOB would require a workforce of approximately 550 workers, including workers that would come from other locations at LANL to use the Modified CMRR-NF laboratory capabilities. The number of workers in support of Modified CMRR-NF operations would cause no change to socioeconomic conditions in the LANL four-county ROI (region of influence). Workers assigned to the Modified CMRR-NF and RLUOB would be drawn from existing LANL facilities, including the CMR Building. The number of LANL employees supporting the Modified CMRR-NF and RLUOB operations would represent only a small fraction of the LANL workforce (approximately 13,500 in 2010) and an even smaller fraction of the regional workforce (approximately 165,000 in 2010).

Volume 2, p. 2-13: As discussed in this CMRR-NF SEIS, operation of the new CMRR-NF, if built, is not expected to result in any increase in LANL employment. The people expected to work in the new facility would be transferred from other facilities at LANL where CMR-related activities are currently being accomplished (such as the CMR Building).

– End of NNSA quotes –

Note: The CMRR-Nuclear Facility was expected to cost up to $6.5 billion. It’s pathetic that the largest construction project ever in New Mexico (with the exception of the interstate highways) was going to create no new Lab jobs.

 Comprehensive cleanup at LANL would be a win-win for northern New Mexicans, permanently protecting the environment while providing hundreds of high paying jobs.

  • When DOE wants to do something, it lowballs the cost. When DOE doesn’t want to do something, it highballs the cost. LANL has estimated that comprehensive cleanup of Area G would cost $29 billion. Using actual costs of cleaning up smaller dumps, Nuclear Watch has extrapolated that cleanup of Area G would cost $7 to 8 billion. See https://nukewatch.org/facts/nwd/Area_G_Comparison_Costs-11-14-12.pdf
  • But of that $29 billion, DOE estimated that labor costs would be $13 billion. Applying that 45% proportion to Nuclear Watch’s estimate, that would be around $3.5 billion in jobs, jobs that northern New Mexico sorely needs.
  • Comprehensive cleanup could be the real job producer. It has the additional advantage of being more conducive to regional economic development in that more locally based contractors could possibly do the cleanup work, instead nuclear weapons work such as expanded plutonium pit production conducted by huge out-of-state defense contractors such as Bechtel and Lockheed Martin.

New nuclear ‘pit’ production at LANL is unnecessary

From the Albuquerque Journal
New nuclear ‘pit’ production at LANL is unnecessary
By Jay Coghlan
Friday, July 21st, 2017 at 12:02am

SANTA FE, N.M. — The Center for Public Integrity recently published a series of articles on nuclear safety lapses in plutonium pit production at the Los Alamos lab that captured a lot of national attention.

Plutonium pits are the fissile cores of nuclear weapons that initiate the thermonuclear detonation of modern weapons. The articles were largely based on the National Nuclear Security Administration’s annual contractor Performance Evaluation Reports. Those reports are publicly available only because Nuclear Watch New Mexico successfully sued for them in 2012.

The former plutonium pit production site, the Rocky Flats Plant near Denver, was shut down by a 1989 FBI raid investigating environmental crimes. A special grand jury indicted both Department of Energy (DOE) officials and the contractor, but a federal judge quashed the indictments at the urging of the local federal attorney general. It was only by sheer luck that a major plutonium fire on Mother’s Day 1969 didn’t contaminate Denver with highly carcinogenic plutonium.

I specifically recall senior DOE officials promising New Mexicans 20 years ago that serious lessons were learned from Rocky Flats and that re-established plutonium pit production at the Los Alamos National Laboratory (LANL) would always be safe. Since then, the lab has spent billions of taxpayers’ money on plutonium pit production but, as the recent articles document, LANL still can’t do it safely.

As the articles reported, a serious nuclear criticality accident was narrowly averted in July 2011, which resulted in the three-year shutdown of LANL’s main plutonium facility. Nevertheless, according to the fiscal year 2011 LANL Performance Evaluation Report, the lab contractor was paid $50 million in pure profit for that year.

In 2014, a radioactive waste barrel improperly prepared by LANL ruptured underground at the Waste Isolation Pilot Plant (WIPP), shutting down that multi-billion-dollar facility for nearly three years. Radioactive waste disposal at WIPP will remain constrained for years, raising the question of where future LANL bomb-making wastes will go.

Congress has required the Los Alamos lab to quadruple plutonium pit production, regardless of the technical needs of the stockpile. The requirement was drafted by professional staff on the House Armed Services Committee, one of whom was originally from the Sandia nuclear weapons lab.

That the existing stockpile doesn’t need pit production is demonstrated by the fact that none has been scheduled since 2011 when LANL finished up the production run that was stopped when Rocky Flats was shut down.

At NukeWatch’s request, former U.S. Sen. Jeff Bingaman (D-NM) required an independent study of the lifetimes of pits. The expert conclusion was that plutonium pits last at least a century, more than double government estimates (the oldest pits in the stockpile are now around 45 years old). Moreover, there are some 20,000 existing plutonium pits stored at the Pantex Plant near Amarillo, Texas.

Future plutonium pit production is for a new so-called “Interoperable Warhead” that is supposed to function both as a land-based ICBM and a sub-launched nuclear warhead. The nuclear weapons labs are pushing this $13 billion make-work project that the Navy doesn’t want.

Ironically, new-design pits for the Interoperable Warhead may hurt national security because they cannot be tested in a full-scale nuclear weapons test or, alternatively, testing them would have severe international proliferation consequences.

Given all this, why expand plutonium pit production when apparently it can’t be done safely and may decrease, not increase, our national security? One strong reason is the huge contractor profits to be had under the $1 trillion-plus “modernization” of the nuclear weapons stockpile and production complex started under Obama, which Trump promises to expand. Far from just “modernization,” existing nuclear weapons are being given new military capabilities, despite denials at the highest levels of government.

The directors of the Livermore, Sandia and Los Alamos nuclear weapons labs in truth wear two hats – the first as lab directors, the second as presidents of the for-profit limited liability corporations running the labs. This inherent conflict of interest skews U.S. nuclear weapons policy and should be brought to an end.

The New Mexico congressional delegation kowtows to the nuclear weapons industry in our state. I specifically call upon Senators Tom Udall and Martin Heinrich to certify within this calendar year that future plutonium pit production at the Los Alamos Lab will be safe, or otherwise end their support for it.

Jay Coghlan is the director of Nuclear Watch New Mexico.

The pit is in the primary
From pogo.org

Los Alamos Cleanup At the Crossroads: Treat All Los Alamos Lab Radioactive Wastes Consistently

Los Alamos Cleanup At the Crossroads:

Treat All Los Alamos Lab Radioactive Wastes Consistently

The Defense Nuclear Facilities Safety Board’s role and responsibility includes gathering information regarding the hazards to the public and workers posed by the management of transuranic (TRU) wastes at Los Alamos National Laboratory (LANL), as well as the Department of Energy’s (DOE) plans to address those hazards. The Board will examine DOE’s actions taken or inadequacies addressed in the current safety policies of the various facilities that manage or store TRU wastes at LANL. The Board is also interested in understanding actions taken to improve TRU waste management at LANL after the improper handling and treatment of TRU wastes that resulted in a ruptured barrel that shut down the Waste Isolation Pilot Plant (WIPP).

Continue reading

GAO Seeks Broader Analysis For Proposed Liquid Waste Facility at LANL

GAO Seeks Broader Analysis For Proposed Liquid Waste Facility at LANL

The Government Accounting Office (GAO) was mandated to review the  “analysis of alternatives” (AOA) process applied by NNSA. The process entails identifying, analyzing, and selecting a preferred alternative to best meet the mission need by comparing the operational effectiveness, costs, and risks of potential alternatives. GAO developed a set of practices by reviewing AOA policies and guidance used by seven public and private-sector entities with experience in the AOA process. GAO’s review of DOE’s requirements for AOAs found that they conform to only 1 of the 24 best practices: the practice of defining functional requirements based on mission need.

DOE and NNSA officials acknowledge that unreliable AOAs are a risk factor for major cost increases and schedule delays for NNSA projects. As GAO has previously reported, NNSA has spent billions of dollars designing and partially constructing projects with an estimated cost of $750 million or more, only to later reassess alternatives. NNSA may continue on this path and continue to have limited assurance that it is selecting alternatives that best meet its mission needs and will not result in major cost increases and schedule delays in the future.

Overall, the National Nuclear Security Administration’s (NNSA) analysis of alternatives (AOA) conducted for the Radioactive Liquid Waste Treatment Facility (RLWTF) project only partially met best AOA practices. The mission need for this project—to replace the current, aging facility—was approved in October 2004. NNSA approved an initial AOA for this project in 2006, and after substantial cost increases, conducted a second AOA (analyzed here) in 2013. NNSA currently estimates the project will cost between $168 million and $220 million.

The GAO compared the AOA conducted at the Radioactive Liquid Waste Treatment Facility at LANL with AOA best practices in 24 areas.

For instance in best practices, the team or the decision maker defines selection criteria based on the mission need. What LANL actually did only partially met best practices because the Lab included in the project documentation brief summaries of the selection criteria used but did not describe how these were based on the mission need. LANL included only one of these selection criteria—the scope—in the mission need statement.

In another case, the team or the decision maker is supposed to weigh the selection criteria to reflect the relative importance of each criterion. Here best practices were not met because LANL did not include weighting selection criteria in project documentation.

The ailing facility is still operating.

During 2013, all treated water from the RLWTF was fed to the effluent evaporator. The evaporator was operated 3654 hours on 201 days during 2013, in both one-burner and two-burner mode. A total of 2.64 million liters of treated water were fed to the evaporator, and 2.55 million liters were discharged to the environment as steam from the evaporator stack.

Curies of radioactive materials fed to the effluent evaporator during 2013 were calculated by multiplying the evaporator feed volume (2,638,330 liters) times the flow-weighted average concentration of each radionuclide. Feed to the effluent evaporator in 2013 contained approximately 4.9E-04 curie alpha radioactivity, 3.35E-04 curie beta radioactivity, and 1.7E-02 curie of tritium.

This RLWTF is vital to nuclear weapons production operations at the Lab. But equipment failures could pose a risk to facility workers.

 

DOE AND NNSA PROJECT MANAGEMENT: Analysis of Alternatives Could Be Improved by Incorporating Best Practices

GAO-15-37: Published: Dec 11, 2014. Publicly Released: Dec 11, 2014.

 

Authors: Del Signore, John C. [Los Alamos National Laboratory]

2014-11-25, LA-UR-14-29097

NNSA Considers Stuffing More Plutonium Into New Facility

Despite the fact that no one has come up with a good reason to increase plutonium pit production for the nation’s nuclear weapons stockpile, officials want to study the possibility of radically increasing the amount of plutonium allowed in a recently completed laboratory at the Los Alamos National Laboratory.

The Deputy Administrator for National Nuclear Security Administration (NNSA) Defense Programs, Don Cook, has requested an analysis to increase the radioactive materials inventory in the recently completed Radiological Laboratory Utility Office Building (RLUOB) to up to 400 grams of plutonium-239, the isotope used in nuclear weapons. The RLUOB, which originally was limited to 8.4 grams of Pu 239, was built as Phase 1 of the Chemistry and Metallurgy Research Replacement Project at LANL that would have expanded plutonium pit production to 50 – 80 pits per year (pits are the radioactive cores of nuclear weapons). LANL’s current capacity is 20 pits per year. Phase 2 of the CMRR project, the “Nuclear Facility,” was canceled because of lack of clear need and a bulging ten-fold increase in costs.

This RLUOB, along with some floor space in the existing Plutonium Facility (PF-4), will replace the old Chemistry and Metallurgy Research Building, which is slated for closure in 2019. The Laboratory was working on a plutonium strategy to move out of CMR and maintain the current plutonium capability.

But NNSA recently increased the maximum amount of radiological materials allowed in the RLOUB, and all “radiological” facilities, from 8.4 grams to 38.6 grams. Internal Lab documents floated plans that could have increased the limit again by two or three times by treating each little laboratory in the RLUOB as its own radiological facility. This could have increased the limit to 115.8 grams of Pu239.

But NNSA apparently wants to go big. The new analysis is to consider the RLUOB as a Hazard Category 3 nuclear facility, which is a huge step up from its current designation as a radiological facility.

Scott Kovac, Research and Operations Director for Nuclear Watch New Mexico, said, “This turkey of a plan is stuffed with bad ideas – The RLUOB is not seismically qualified for that amount of plutonium. A new supplemental environmental impact statement will be needed. There is no need for more plutonium pits, except for new nuclear weapons, because they last for around 100 years and nuclear weapons stockpiles are decreasing. And apparently LANL can’t safely handle plutonium anyway, as major operations with plutonium have been paused since June 2013 because of nuclear criticality safety issues. Finally, it was LANL’s improper handling of plutonium waste that contaminated 21 workers at the Waste Isolation Pilot Plant, causing it to close with at least a half billion dollars in costs to reopen. We say no to more plutonium at Los Alamos!”

# # #

Read the Defense Nuclear Facilities Safety Board report here.

 

Report Reveals That Little is Known About Lab’s Future Plutonium Needs

Report Reveals That Little is Known About Lab’s Future Plutonium Needs
Except LANL Contractor Needs Money

A Government Accountability Office (GAO) report reveals how the future of expanded nuclear weapon component production at Los Alamos is unknown. The public has had enough of half-baked billion-dollar plans for nuclear facilities that do nothing but line contractors’ pockets. Congress must put away the check book and realize that the Lab’s plutonium future is unknown because it is unneeded.

Let’s get some details out of the way –

Los Alamos National Laboratory (LANL) houses most of the nation’s capabilities for plutonium research and development in support of the nuclear weapons mission. In addition, LANL’s scientists and technicians also perform research on plutonium to support other missions, such as conducting research on recycling plutonium for use as fuel in commercial nuclear reactors (MOX).

The National Nuclear Security Administration (NNSA), a separately organized agency within the Department of Energy (DOE), is responsible for the management of the nation’s nuclear weapons.

Plutonium pits are the fissile cores of modern nuclear weapons (fissile means capable of sustaining a nuclear reaction). When a nuclear weapon is detonated the pit is explosively compressed into a critical mass that rapidly begins atomic fission. In modern two-stage weapons the plutonium pit acts as the primary (or “trigger”) that initiates fusion in the thermonuclear secondary. Each pit is an atomic bomb in its own right, similar to the Trinity and Nagasaki bombs, both of which were plutonium bombs. In thermonuclear or hydrogen bombs the plutonium pit serves as the trigger that detonates the far more powerful fusion explosion characteristic of hydrogen bombs.

(The need for any more nuclear weapons production ever is actually zero.)

NNSA claims that the need is unknown –
Because of public participation, lack of need, and budget concerns, construction of the Lab’s $6 billion Chemistry and Metallurgy Research Replacement (CMRR) nuclear facility was deferred for at least five years starting in 2012. The CMRR would have enabled a production capacity of 50-80 pits per year. Theoretically, the Lab is currently capable of producing 10-20 pits per year, maybe. But it produced zero this year.

It is now unclear when or if the CMRR nuclear facility will be built, which the Lab claims may lead to insufficient capabilities to meet LANL’s plutonium research requirements. But no one really can say what these requirements are.

The report states the uncertainty–

The Nuclear Weapons Council is still evaluating specifications for nuclear weapons and their corresponding life extension program schedules, and it may take another year or two before final decisions are made, according to NNSA officials. Since the schedule has not been finalized, the number of pits that will be needed is uncertain as well. (Pg. 10)

Officials have announced that they are seeking alternatives to the CMRR that would provide the capabilities planned for the CMRR nuclear facility using existing facilities. This would be replacing deferred unneeded capabilities with unneeded capabilities. Instead of trying to replace the lacking capabilities of the CMRR, NNSA should first describe the actual pit needs, which are none.

Meanwhile, “NNSA has estimated that it needs to be able to ramp up its capabilities to manufacture about 30 pits each year by 2021” to meet expected life extension program requirements. (Life extension programs are intended to lengthen the lives of existing nuclear weapons by 20 to 30 years by repairing or replacing nuclear weapons components as needed.)

But the 30 number is just a guess “for planning purposes”.
For planning purposes, NNSA is studying the possibility of manufacturing about 30 pits per year… (Pg.10)
“Studying the possibility” is not a need.

NNSA now believes that LANL can support the manufacture of 30 pits per year just by upgrading its radiological laboratory and by repurposing available space in its existing plutonium facility. (Pg. 12)

Also,
Costs are unknown –
The cost estimates were characterized as “high-level and a rough order of magnitude and noted that the estimates should be viewed as preliminary and preconceptual that would not be useful for program definition or scoping.” (pg.15)

Staffing is unknown.

NNSA and LANL officials told us that recruiting additional staff for plutonium-related research necessarily takes years of advance planning, but that the uncertainty of where the new capabilities will be located or what the level of capacity is needed has complicated planning efforts. (Pg. 17)

What is know is the public is a problem –

Plans for transporting plutonium or other radioactive materials from LANL to facilities at other sites could also spur public opposition that may cause schedule delays or create other impediments…

Other impediments?
Like speaking up?

Excellence Unfulfilled at the LANL’s Plutonium Facility

A Los Alamos National Laboratory fact sheet touts the Lab as a plutonium “center of excellence”. However, the Laboratory Director paused operations in the Plutonium Facility on June 27, 2013. (The Plutonium Facility, called PF-4, is located at Technical Area 55 at Los Alamos National Laboratory (LANL). PF-4 is home for the Lab’s plutonium work, including nuclear weapons component production.) The pause was based on issues identified during safety reviews and findings from recent assessments. For one, the Defense Nuclear Facilities Safety Board (Board) performed a review of the Criticality Safety Program at Los Alamos National Laboratory (LANL) in May 2013. (The Board is an independent organization within the executive branch chartered with the responsibility of providing recommendations and advice to the President and the Secretary of Energy regarding public health and safety issues at Department of Energy (DOE) defense nuclear facilities.) This review identified significant non-compliances with DOE requirements and industry standards in the Lab’s Criticality Safety Program (CSP). In addition, this review identified criticality safety concerns around operations at the Plutonium Facility. The Board noted that some of these deficiencies are long standing and indicated flaws in federal oversight and contractor assurance. Much plutonium work, especially work with a high potential for criticality, will be stopped through the rest of 2013.

Nuclear criticality safety is defined as “protection against the consequences of an inadvertent nuclear chain reaction, preferably by prevention of the reaction.” The most potentially dangerous aspect of a criticality accident is the release of nuclear radiation if it maintains a self-sustaining nuclear chain reaction.

To date, the only thing self-sustaining is the Lab’s inability to address its criticality issues and yet still convince Congress to keep funding plutonium work there. To prevent bad things from happening, DOE’s regulations and directives require contractors to evaluate potential accident conditions and put in place appropriate controls and safety measures. History shows that the Los Alamos Laboratory just cannot do this, even though much of the work is performed on plutonium pits, the primaries of nuclear weapons. Even though actual need for this work has not been proven, the Lab has entrenched itself as the only place in the country where plutonium pits can be made, developed, and tested.

For fiscal year 2014, the budget request for nuclear ‘weapons activities’ at LANL was $1.4 billion. The exact amount that is spent on plutonium operations in PF-4 is unknown to us, but the budget request for 2014 for Directed Stockpile Work, which is where major parts of the plutonium operations are located, was $460 million. This is a 23% increase over last year’s budget. The funding pours into the Lab regardless of whether the Lab is actually doing any work, which is frequently stopped.

Here’s history of criticality problems and work stoppages at Los Alamos Laboratory:
In 2005, an assessment determined that LANL’s expert-based Criticality Safety Program (CSP) was not compliant with applicable DOE requirements and industry standards.

In 2006, LANS developed a Nuclear Criticality Safety Program Improvement Plan.

In 2007, in response to concerns raised by the Board’s staff, LANL determined that the authorized loading of vault storage rooms in PF-4 could lead to a critical configuration.

In 2008, the Government Accountability Office reported concerns about nuclear safety at LANL are long-standing. Problems included 19 occasions since 2003 where criticality safety requirements were violated, such as storing materials in quantities higher than safety limits allow, 17 of 19 of the site’s nuclear facilities operating without proper safety documentation, reported inadequacies in safety systems, radiological releases, and four enforcement actions for significant violations of nuclear safety rules.

Los Alamos Report for Week Ending April 3, 2009
LANL management placed the facility in stand-by mode until roughly 125 safety evaluations could be re-evaluated.

Los Alamos Report for Week Ending October 2, 2009
The Plutonium Facility was placed in standby mode because management declared the fire suppression system inoperable based on recent hydraulic calculations that concluded the system was not able to achieve the water coverage required. LANL had performed a system adequacy analysis in 2008. The hydraulic calculation completed for the system identified that 13 of approximately 100 hydraulic areas did not meet the requirement.

Los Alamos Report for Week Ending October 16, 2009
A general evacuation alarm was caused by a Criticality Alarm System signal because of a loss of all facility ventilation and failure of the Facility Control System at the Plutonium Facility. The facility was in standby mode during this event due to previously identified issues with the fire suppression system and, therefore, limited personnel were in the facility.

Los Alamos Report for Week Ending September 10, 2010
Operations in Plutonium Facility were suspended because potentially explosive ammonium nitrate was discovered in two filter ducts.

Los Alamos Report for Week Ending December 3, 2010
It was revealed that greater than 1000 items, or about 20%, of the total vault holdings are items packaged in potentially vulnerable containers with taped slip-top lids rather than in robust safety-significant containers that include a HEPA-filtered vent. The presence of these slip-top containers requires respirator use whenever operators access the vault. In FY10, LANL made meaningful progress in addressing these legacy materials.

In 2011, an event occurred at PF-4 in which fissile material handlers violated procedural requirements and criticality safety controls while moving and photographing plutonium rods.

Beginning in 2012, LANS experienced an 18-month exodus of criticality safety professionals from its criticality safety group. LANS currently employs 2 full-time and 2 part-time qualified criticality safety analysts, in addition to 3 part-time subcontractors—far fewer than the 17 criticality safety analysts it has determined to be necessary to support operations, meet mission goals, and maintain the CSP.

Los Alamos Report for Week Ending April 20, 2012
Plutonium Facility personnel use a software program called MAR Tracker to track plutonium that is used in the facility. A system engineer discovered an error in
MAR Tracker that caused only a small subset of applicable facility containers (roughly 1700 out of 13000 containers) to be checked during the required annual MAR surveillance. The Plutonium Facility was placed in Standby Mode.

Los Alamos Report for Week Ending June 15, 2012
LANL identified a number of fuel rods in TA-35 Building 27 that were not consistent with the criticality safety evaluation for the facility. Operations at this building had previously been suspended in late-May due to the discovery of three fuel rods that were not in the facility or institutional tracking systems.

Los Alamos Report for Week Ending December 14, 2012
LANL identified that the Criticality Safety Evaluations (CSEs) for two rooms did not adequately address the potential for interaction effects between storage locations. Plutonium Facility management suspended operations in these two vault rooms.

Los Alamos Report for Week Ending February 15, 2013
LANL began a focused training program (“boot camp”) to provide an intensive learning environment for new criticality safety staff. The program consisted of nine modules including: nuclear theory; criticality safety calculation methods; ANSI/ANS, DOE and LANL criticality safety standards and requirements; criticality safety evaluations; and criticality alarm and detection systems. This program along with on-the-job training and performance demonstrations was to provide a mechanism for achieving full qualification as a LANL criticality safety analyst. Conduct of the boot camp was part of the LANL corrective action plan for improving the nuclear criticality safety program.

Los Alamos Report for Week Ending May 3, 2013
The laboratory completed criticality safety assessments at LANL nuclear facilities. The review teams identified 3, 4, and 6 findings for TA-55, CMR, and Area G, respectively. In all cases, the assessments concluded adequate implementation of the Criticality Safety Program with the exception of identified findings. Notably, one of the findings at Area G identified that supervisors and operations center personnel did not have an adequate understanding of criticality safety requirements. Area G management paused operations based on this finding and conducted appropriate training to resolve this issue.

In May 2013, the staff of the Defense Nuclear Facilities Safety Board (Board) performed a review of the Criticality Safety Program at Los Alamos National Laboratory. This review identified significant non-compliances with applicable Department of Energy requirements and industry standards in the implementation of the Criticality Safety Program. The Board’s staff identified the following non-compliances during its review:
• Most criticality safety controls are not incorporated into operating procedures.
• Operators typically do not utilize written procedures when performing work.
• Fissile material labels do not list parameters relevant to criticality safety (e.g., mass).
• Some fissile material operations lack Criticality Safety Evaluations (CSEs).
• Some CSEs do not analyze all credible abnormal conditions.

Los Alamos Report for Week Ending June 28, 2013
The Laboratory Director paused programmatic activities at the Plutonium Facility. The pause was directed based on issues identified during procedural and criticality safety reviews and findings from recent assessments. Reviews at PF-4 have identified a number of procedural issues and the need for clarification and improvement of criticality safety controls.

Los Alamos Report for Week Ending July 26, 2013
Plutonium Facility personnel identified several criticality safety issues associated with recent construction activity. Even though plutonium work was paused, the Laboratory Director and the Facility Operations Director (FOD) approved construction activities that had the potential to affect nuclear materials.

For more information, please read the LAMonitor article By John Severance
Safety board visits LANL

New Mexico Members of Congress Vote for Exorbitant Nuclear Bomb While State Is Ranked as the Worst for Children

Yesterday all three House members of the New Mexican congressional delegation voted against an amendment that would cut money added to a wasteful nuclear weapons program. In April the Obama Administration asked for $537 million in fiscal year 2014 for a “Life Extension Program” for the B61 Cold War nuclear bomb, 45% above the 2013 level. The House Appropriations Committee added $23.7 million to that bloated request, which the amendment would have cut. Overall, the B61 Life Extension Program has exploded in estimated costs to where each warhead will cost twice their weight in gold just to “refurbish” (which does not include original production and ongoing maintenance costs).

 The sponsor of the amendment, Rep. Mike Quigley, D-Ill., testified during floor debate:

At a time when we are slashing funds for disease research at the NIH [National Institute of Health], failing to fund our crumbling infrastructure, and underinvesting in our children¹s education, we are increasing funding to keep hundreds of nuclear bombs in operation that we will never use. The Cold War is over.

The Albuquerque Journal reported that Rep. Ben Ray Luján, D-N.M.,

…supported the full $551 million for the B61 Life Extension Program because it is a national security priority. “This funding is important for Los Alamos and Sandia labs’ effort to ensure the safety of the nuclear weapons stockpile, and cuts to that funding impact the ability to keep it secure,” Luján said.

Rather just ensuring safety and security the program will radically improve the bomb, giving it new military capabilities by turning it into a precisely targeted smart bomb and mating it to future bombers for supersonic stealthy delivery. Currently the main mission of B61 bombs is as tactical nuclear weapons in NATO countries, a relic of the Cold War. Improved B61’s fly in the face of Obama’s newly declared goal of reducing the presence of battlefield nuclear weapons in Europe, even as he proposes to negotiate with the Russians for further arms reductions. Moreover, if security is really the issue, the sure solution that saves taxpayers money and encourages nonproliferation is to withdraw the nuclear bombs from forward deployment in Europe, where a few years ago protesting peace activists were able to infiltrate within a few hundred yards of them.

Ironically, the B61 Life Extension Program may actually undermine our own national security by introducing major changes to existing bombs. Our stockpile has been extensively full-scale tested, and repeated studies have found our nuclear weapons to be even more reliable than previously believed. The Los Alamos and Sandia Labs propose to create a “frankenbomb” by mixing and matching four variants of the B61 bomb into a single new modification. Common sense dictates that the last thing we should do while seeking to maintain confidence in our reliable nuclear weapons stockpile is to introduce major changes that can’t be tested.

Our New Mexican congressional delegation represents a state that was just ranked as the worst of all fifty for the well-being of its children, where more than 25% live in poverty. In stark contrast, Los Alamos County, dominated by the lab, is the second richest county in the entire USA. Nuclear weapons programs are a poor producer of jobs, where for example according to the government’s own documents a new $6 billion plutonium facility was not going to produce a single new permanent job at Los Alamos Lab.

Contrary to the claimed economic benefits of the Los Alamos and Sandia Labs, New Mexico as a whole continues to fall from 37th in per capita personal income in 1959 to 44th in 2011. Nevertheless, the Labs have always had inordinate influence over New Mexican politicians. One extreme example is the recent starling revelation that in between unsuccessful Senate campaigns former Rep. Heather Wilson was paid more than $450,000 by the Los Alamos and Sandia Labs for “consulting” contracts that had no written work requirements.

The nuclear weapons labs have voracious appetites for federal funding, with their directors simultaneously acting as the presidents of the executive board of the for-profit limited liability corporations that run the labs (those private LLCs pay 2/3’s of the directors’ annual compensation of around one million dollars). Business will boom with never-ending Life Extension Programs, and Sandia and Los Alamos are not satisfied with just one Life Extension Program for the B61. They already plan yet another one 20 years from now that initial figures indicate would be even more expensive. In fact, the labs plan a never-ending cycle of Life Extension Programs that intentionally seek to implement major design changes for all existing types of nuclear weapons in our stockpile, costing at least $60 billion (while the doubling of costs has so far been the rule).

Jay Coghlan, director of Nuclear Watch New Mexico, commented, “Congressman Ben Ray Luján should ask himself the question what good does a Cold War nuclear bomb that the for-profit labs want to endlessly tinker with do for New Mexican children? Pork for the labs should not drive nuclear weapons policies, especially when it’s of little if any tangible benefit to average New Mexicans. Luján should, instead, dedicate himself to boosting funding for programs that would really help our children but are facing painful sequester cuts, such as education, medical care and food assistance. Those investments would really brighten their future, and help raise New Mexico from its shameful position as the worst state for kids.”

# # # 

See House rejects effort to trim $23.7M in funding for B61, Michael Coleman, Albuquerque Journal, July 11, 2013.

For New Mexico’s ranking as the worst state for kids see Kids Count Data Center http://datacenter.kidscount.org/updates/show/20-2013-data-book-rankings
For the scope and schedule of perpetual Life Extension Programs for existing nuclear weapons see NNSA’s FY 2014 Stockpile Stewardship and Management Plan
https://nukewatch.org/importantdocs/resources/SSMP-FY2014.pdf

Obama Calls For Further Nuclear Weapons Reductions While Increased Production and New Facilities at Los Alamos Are Still On the Table

Obama Calls For Further Nuclear Weapons Reductions
While Increased Production and New Facilities at Los Alamos Are Still On the Table

On June 19, in Berlin, President Barack Obama declared that, in concert with Russia, he plans to seek to cut the deployed strategic nuclear arsenal by up to one-third. He also said he will pursue significant bilateral cuts in tactical or battlefield nuclear weapons in Europe. In contrast, Obama’s National Nuclear Security Administration (NNSA) recently released plans for unneeded upgrades and dangerous improvements to existing nuclear weapons, which could force expanded nuclear component production and construction of new facilities at Los Alamos.

In the just released “FY 2014 Stockpile Stewardship and Management Plan” (SSMP), NNSA proposes perpetual Life Extension Programs for nuclear warheads that will result in three types of ballistic missile warheads and two types of nuclear air bombs. Although it’s still vague, the three so-called interoperable warheads would replace four types of existing warheads, which make little sense given the staggering estimated costs. These radical upgrades, if implemented, could not be full-scale tested, which would undermine confidence in their reliability. Our existing nuclear weapons designs have been extensively tested and subsequent studies have found them to be even more reliable and long-lived than originally thought.

The President’s speech is also incongruous with the SSMP in the area of plutonium pit production, and states “Preliminary plans call for pit production of potentially up to 80 pits per year starting as early as FY 2030.” (SSMP Pg. 62) With Obama’s further proposed arsenal reductions, any planned increase in weapons production is only a concession the nuclear weapons contractors profits. The alleged need for more plutonium pits cascades into a misplaced call for more production facilities. NNSA is “…evaluating the feasibility of constructing small laboratory modules connected to existing nuclear facilities…” (SSMP Pg. 8) to meet future claimed plutonium-manufacturing requirements. The SSMP states that Los Alamos can produce up to 30 pits per year without new facilities.

The need for increased pit production has never been explained adequately to the public, but the claim likely is centered on one of the interoperable warhead plans – the W78/88. In a May 7, 2013 testimony to the Senate Subcommittee on Strategic Forces, Dr. Penrose C. Albright, Director, Lawrence Livermore National Laboratory claimed that the W78/88 would require increased pit production at Los Alamos. He goes on to try to scare the Committee by saying that without construction funding for new pit facilities now, the W78/88 warhead upgrade could cost even more. He stated, “without going into the detail, the most likely option for the primary on the 78/88 does require the stand-up and operation of plutonium pit production capabilities at Los Alamos. And so any delay by the Government—any delay in funding to get that stood up—and that really has to start now—is going to add significant schedule risks to the program.” (Hearing Pg. 17)

The President should adopt the more fiscally prudent and technically sound alternative of replacing limited life components while he actually works to eliminate nukes altogether. This unending cycle of proposed Life Extension Program will waste huge sums of taxpayers money and is in direct conflict with the President’s own long-term goal of a future world free of nuclear weapons.

The full text of President’s Obama’s speech is available at http://www.whitehouse.gov/the-press-office/2013/06/19/remarks-president-obam

NNSA’s FY 2014 Stockpile Stewardship and Management Plan (SSMP) is available at https://nukewatch.org/importantdocs/resources/SSMP-FY2014.pdf

Hearing To Receive Testimony On National Nuclear Security Administration Management Of Its National Security Laboratories In Review Of The Defense Authorization Request For Fiscal Year 2014 And The Future Years Defense Program, Tuesday, May 7, 2013, U.S. Senate Subcommittee On Strategic Forces, Committee On Armed Services, Washington, DC.
http://www.armed-services.senate.gov/Transcripts/2013/05%20May/13-36%20-%205-7-13.pdf

Lab lacks ability to estimate emergency response as it also underestimates risk

Lab lacks ability to estimate emergency response as it also underestimates risk

There has been much in the recent news about Los Alamos National Laboratory underestimating how much radiation could leak from the nuclear weapons production plutonium lab after a major earthquake and fire. Read the POGO article here.

The Defense Nuclear Facilities Safety Board Report is here.

Among other problems, LANL computer models credited sheetrock walls with surviving an earthquake.

In a recently released May report, the Department of Energy’s very own oversight Department finished a separate review titled, “Independent Oversight Review of Site Preparedness for Severe Natural Phenomena Events at the Los Alamos National Laboratory”, that also questions the Lab’s safety procedures.

The Health Safety and Security Office (HSS) of Safety and Emergency Management Evaluations performed this independent review to evaluate emergency response capabilities at the Lab and how the Lab maintained them in a state of readiness in case of a severe natural phenomena event. The review showed that LANL would have trouble responding quickly with the appropriate emergency response in the case of a serious natural event.

As one of the conclusions states – “LANL does not have an adequate means for determining quickly whether an event occurring at the CMR facility, a criticality event at TA-55 PF-4 facility, or a severe natural phenomena event at either facility involves a significant quantity of HAZMAT and requires implementation of corresponding onsite protective actions or issuance of appropriate offsite protective action recommendations.” (Pg. 38)

For example, the Emergency Action Levels currently in the Lab’s Emergency Plan Procedure:

•            Do not reflect the CMR Emergency Planning Hazards Assessment isolation and downwind protective action distances for the majority of the events

•            Do not provide Emergency Action Levels for two severe natural phenomena events (earthquake and wildland fire) in the CMR Emergency Planning Hazards Assessment

•            Use a criticality alarm system as an Emergency Action Level entry indicator for a criticality event at CMR, even though CMR is not equipped with a criticality alarm system

•            Do not use the PF-4 criticality alarm system as an Emergency Action Level entry indicator for the criticality event analyzed in the TA-55 Emergency Planning Hazards Assessment.

 

In addition, the Lab’s generic natural disaster Emergency Action Levels do not provide sufficient information to accurately categorize and/or classify a severe natural phenomena event.

And LANL’s planning for onsite protective actions and offsite protective action recommendations provided in the Emergency Action Levels did not fully consider facility or site conditions for the analyzed events.

The report continues. The Independent Oversight observed outdated and incorrect information in the current set of CMR and TA-55 PF-4 Emergency Action Levels. Further, the generic Emergency Action Levels for severe natural phenomena events were not based on the potential for or an actual uncontrolled release of HAZMAT and are not linked to protective actions or protective action recommendations.

Additionally, the pre-planned protective actions for a TA-55 PF-4 seismic event are limited to shelter-in-place when there could be high radiation levels, and no effective shelters are available.

So, we have two different government agencies questioning safety after the Lab received a record $83 million in award bonuses.

These reports are another example of why the Lab must shut down plutonium operations now.

LANL loses track of nuclear materials

LANL loses track of nuclear materials

Plutonium operations placed in standby mode

 

In an April 20, 2012 report, the Safety Board charged with oversight of defense nuclear facilities reported that the system used to track nuclear materials in the Plutonium Facility at Los Alamos National Laboratory was operating erroneously. The system apparently only kept track of 1,700 out of 13,000 containers of nuclear “materials at risk” (MAR). This omission caused the facility to exceed its limits for MAR located in individual containers and outside of gloveboxes at least 15 times.

If one is operating a facility with large quantities of fissionable nuclear materials it is very important to know where the materials are at all times because stacking too much plutonium in one place can cause a criticality event or worse. After the error was noticed, the Lab manually started to verify container MAR amounts manually.  “To date, fifteen containers, all housed in the facility’s vault, have been identified with contents that exceed the MAR limit of 7500 g WG-Pu [Weapons Grade Plutonium] equivalent.” That’s a lot to lose track of because these limits help the facility to comply with the seismic requirements of operations in the Lab’s earthquake fault zone.

Normal operations have been terminated in the 150,000 square foot Plutonium Facility and the facility has been placed in “Standby Mode.” How much does a shutdown cost taxpayers?

How long has the Lab violated these limits? The report states that the tracking error was introduced during software development, apparently due to a “miscommunication” between the software developers and the security personnel. The MAR tracker program performs other required MAR limit surveillances in the facility. Are these other surveillances reliable? This incident also calls into question other Lab software, such as programs that model contaminant transport.

It is unclear if the plutonium facility has restarted operations. The Safety Board reports usually are released about a month after they are written.new green atom

 

 

 

 

 

The Defense Nuclear Facility Safety Board Report is here.

CMRR is Key to Expanded Plutonium Pit Production

While being narrowly correct, LANL PR man Kevin Roark is misleading when he claims [in a June 25, Letter to the Editor of the Santa Fe New Mexican  newspaper] that plutonium pit production will not take place in the new Chemistry and Metallurgy Research Replacement Project (CMRR). What he fails to disclose is that the Lab is not building just one facility, but instead is creating an integrated manufacturing complex for expanded production for which the CMRR is absolutely key. This complex will consist of LANL’s existing production facility “PF-4” with ~$300 million in upgrades; CMRR’s already completed first phase, the $400 million “Rad Lab”; and the future $4 billion CMRR “Nuclear Facility,” now being debated.

The Nuclear Facility will be literally next door to PF-4 and linked to it via underground tunnel. While pits are physically manufactured in PF-4’s glovebox lines, the Nuclear Facility’s central missions of “materials characterization” and “analytical chemistry” are essential operations that ensure “weapons-grade” plutonium and pit production quality control. The National Nuclear Security Administration’s own documents show that the Nuclear Facility is being specifically sized to support expanded production of up to 80 pits per year, quadruple LANL’s currently approved rate. It is also planned to have a vault for up to six metric tons of “special nuclear materials,” capable of storing around 1,000 pits.

Roark must think that New Mexicans are naïve enough to accept the Lab’s claims that the CMRR is all about “science” even as LANL becomes more and more a production site. Sadly, this is only part and parcel of the substantial rebuilding of the U.S. nuclear weapons production complex, which will also include a new $3.5 billion Uranium Processing Facility in Tennessee and a new privately financed Kansas City Plant for production of the 1,000’s of nonnuclear components that go into a nuclear weapon.

Many New Mexicans hoped for serious mission diversification at Los Alamos, which some $5 billion sunk into its plutonium infrastructure will almost certainly shut the door on. Schools in Santa Fe and all across the country are being closed due to lack of funding. Nevertheless, our government is preparing to spend some $10 billion to build new production plants even as we are purportedly working toward the declared long-term national security goal of a nuclear weapons-free world. To get there, citizens need to push the politicians to meet the needs of everyday people, not those of the vested nuclear weaponeers.

The CMRR-Nuclear Facility Is All About Expanding Plutonium Pit Production Capacity

In response to a question by Senator Jeff Bingaman at a Senate Armed Services Committee hearing on April 14, 2010, NNSA Administrator Tom D’Agostino stated “We will not make pits in the CMR replacement facility. We’ll make them in the existing older facility.”

That is narrowly true, but highly misleading. In fact, the Chemistry and Metallurgy Research Replacement (CMRR) Project is all about expanding plutonium pit production capabilities at the Los Alamos National Laboratory from the presently sanctioned level of 20 per year to up to 80. [Plutonium pits are the fissile “triggers” that initiate fusion in today’s modern thermonuclear weapons.] Yes, PF-4, LANL’s existing plutonium facility, performs the actual physical manufacturing of pits. However, that production cannot take place without “analytical chemistry” (AC) and “materials characterization” (MC) before production to make sure that the plutonium is weapons-grade, and extensive AC and MC sampling during production for stringent “war reserve” quality control.

It’s a mistake to get hung up on different facilities, when an integrated plutonium complex for expanded pit production capability is being created through proposed construction of the CMRR’s “Nuclear Facility” and upgrades to PF-4. It’s silly to think of them as separate facilities just because they’ll be under two different roofs. PF-4 and the Nuclear Facility will be next door to each other, linked by underground tunnel, with highly integrated operations and much exchange of special nuclear materials between them (especially given the Nuclear Facility’s planned vault for up to six metric tons of “special nuclear materials”).

The CMRR Nuclear Facility is being specifically sized to support pit production capability of 50 – 80 pits per year. An internal NNSA study of planned alternatives advocated for a “baseline version (22,500 ft2 of Pu lab space) of the CMRR-NF…, resulting in a production capacity of 50-80 ppy” [pits per year]. Independent Business Case Analysis of Consolidation Options for the Defense Programs SNM and Weapons Programs, TechSource, Inc, December 2007, p. 5-3, parentheses in the original. This “Business Case” is one of NNSA’s hundreds of reference documents for its 2008 Complex Transformation Supplemental Programmatic Environmental Impact Statement. [To conveniently find it, use “TechSource 2007a.”]

That 22,500 ft2 of Pu lab space is exactly what is being designed for the Nuclear Facility now. “CMRR Project Nuclear Facility… Baseline under development …. 22,500 Net Square Feet Lab Space.” CMRR Project Update, LANL, Public Meeting, Los Alamos, New Mexico March 3, 2010, 7th viewgraph.

Los Alamos National Security, LLC, the for-profit corporation that runs Los Alamos, has already been paid for installing additional equipment in PF-4 that in conjunction with the future CMRR-Nuclear Facility will expand plutonium pit production capability to up to 80 pits per year. “Build Six New W88 Pits & Install Equipment in FY 2008 to Increase Pit Capacity to 80 Pits Per Year by the Operational Date of a CMRR-Nuclear Facility – Available Fee $1,079,915 – Awarded Fee $1,079,915.” FY 2008 Performance Evaluation Report for the Los Alamos National Security, LLC’s Management and Operation of the Los Alamos National Laboratory, NNSA, p. 9.

NNSA echoes this in its FY 2010 Supplemental Stockpile Stewardship Plan. Under Key Recent Accomplishments the agency boasts of “New equipment installed as scheduled for gradual capacity increases to 80 pits per year potential by scheduled operational date for Chemistry and Metallurgy Research Replacement (CMRR) Nuclear Facility.” Table 1-1, NNSA/Office of Defense Programs, FY 2010 – 2014 Supplement to the Stockpile Stewardship Plan, p. 14.

In sum, suggestions or representations by NNSA and LANL that the $4.5 billion CMRR Project is not about pit production are at best half-truths. Its massive proposed “Nuclear Facility” is, in fact, all about expanded pit production capability.