Court Rules U.S. Nuclear Weapons Production Plan Violates Federal Law
FOR IMMEDIATE RELEASE, October 3, 2024
Media Contacts:
Ben Cunningham, Esquire, SCELP, 843-527-0078, [email protected]
Tom Clements, Savannah River Site Watch, 803-834-3084, [email protected]
Jay Coghlan, Nuclear Watch New Mexico, 505-989-7342, [email protected]
Scott Yundt, Tri-Valley CAREs, 925-443-7148, [email protected]
Queen Quet, Gullah/Geechee Sea Island Coalition, 843-838-1171, [email protected]
AIKEN, S.C. — On September 30, United States District Court Judge Mary Geiger Lewis ruled that the United States Department of Energy (“DOE”) and its semi-autonomous nuclear weapons agency, the National Nuclear Security Administration (“NNSA”), violated the National Environmental Policy Act (“NEPA”) by failing to properly consider alternatives before proceeding with their plan to produce plutonium pits, a critical component of nuclear weapons, at the Los Alamos National Laboratory (“LANL”) in New Mexico and, for the first time ever, at the Savannah River Site (“SRS”) in South Carolina.
The Court found that the plan’s purpose had fundamentally changed from NNSA’s earlier analyses which had not considered simultaneous pit production at two sites. These changes necessitated a reevaluation of alternatives, including site alternatives, which Defendants failed to undertake prior to moving forward while spending tens of billions of taxpayers’ dollars. Therefore, the Court entered judgment in favor of Plaintiffs, the nonprofit public interest groups Savannah River Site Watch, Nuclear Water New Mexico and Tri-Valley Communities Against a Radioactive Environment (CAREs); the Gullah/Geechee Sea Island Coalition; and Tom Clements as an individual plaintiff.
As a result of this ruling, the Defendants are required to newly assess pit production at a nation-wide programmatic level which will mean undertaking a thorough analysis of the impacts of pit production at DOE sites throughout the United States, including radioactive waste generation and disposal. Under the National Environmental Policy Act (NEPA), this will provide the opportunity for public scrutiny of and formal comment on their assessments.
High Detections of Plutonium in Los Alamos Neighborhood – As We Enter a New Nuclear Arms Race the Last One is Still Not Cleaned Up
FOR IMMEDIATE RELEASE, August 15, 2024
Dr. Michael Ketterer – 928.853.7188 | Email
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – In April Nuclear Watch New Mexico released a map of plutonium contamination based on Lab data. Today, Dr. Michael Ketterer, Professor Emeritus of Chemistry and Biochemistry, Northern Arizona University, is releasing alarmingly high results from samples taken from a popular walking trail in the Los Alamos Town Site, including detections of some of the earliest plutonium produced by humankind.
On July 2 and 17 Dr. Ketterer, with the assistance of Nuclear Watch New Mexico, collected water, soil and plant samples from Acid Canyon in the Los Alamos Town Site and soil and plant samples in Los Alamos Canyon at the Totavi gas station downstream from the Lab. The samples were prepared and analyzed by mass spectrometry at Northern Arizona University to measure concentrations of plutonium, and to ascertain its sources in the environment.
NNSA Delays Urgent Research on Plutonium “Pit” Aging While Spending Tens of Billions on Nuclear Weapons Bomb Core Production
FOR IMMEDIATE RELEASE, April 17, 2024
Tom Clements, SRS Watch – 803.240.7268 | Email
Scott Yundt, TVC – 415.990.2070 | Email
Jay Coghlan – 505.989.7342 | Email
Nearly three years after filing a Freedom of Information Act request, the public interest group Savannah River Site Watch has finally received the National Nuclear Security Administration’s (NNSA’s) congressionally-required “Research Program Plan for Plutonium and Pit Aging.” However, the document is 40% blacked out, including references and acronyms. Plutonium “pits” are the radioactive cores of all U.S. nuclear weapons. The NNSA claims that potential aging effects are justification for a ~$60 billion program to expand production. However, the Plan fails to show that aging is a current problem. To the contrary, it demonstrates that NNSA is delaying urgently needed updated plutonium pit aging research.
In 2006 independent scientific experts known as the JASONs concluded that plutonium pits last at least 85 years without specifying an end date [i] (the average pit age is now around 40 years). A 2012 follow-on study by the Lawrence Livermore nuclear weapons lab concluded:
“This continuing work shows that no unexpected aging issues are appearing in plutonium that has been accelerated to an equivalent of ~ 150 years of age. The results of this work are consistent with, and further reinforce, the Department of Energy Record of Decision to pursue a limited pit manufacturing capability in existing and planned facilities at Los Alamos instead of constructing a new, very large pit manufacturing facility…” [ii]
Since then NNSA has reversed itself. In 2018 the agency decided to pursue the simultaneous production of at least 30 pits per year at the Los Alamos National Laboratory (LANL) in northern New Mexico and at least 50 pits per year at the Savannah River Site (SRS) in South Carolina. Upgrades to plutonium facilities at LANL are slated to cost $8 billion over the next 5 years. The redundant Savannah River Plutonium Processing Facility in South Carolina will cost up to $25 billion, making it the second most expensive building in human history.
NNSA’s Nuclear Weapons Budget Takes Huge Jump
Arms Race Accelerates with MIRVed Warheads
Los Alamos Lab Cleanup Cut
FOR IMMEDIATE RELEASE, March 11, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – Ironically the day after the film Oppenheimer was awarded multiple Oscars, the Department of Energy’s semi-autonomous National Nuclear Security Administration (NNSA) asked Congress for its biggest nuclear weapons budget ever. NNSA’s FY 2025 request for “Total Weapons Activities” is $19.8 billion, $700 million above what Congress recently enacted for FY 2024. It is also a full billion dollars above what President Biden asked for last year, which Congress then added to and will likely do so again.
The Biden Administration states that the $19.8 billion will be used to:
“[P]rioritize implementation of the 2022 National Defense Strategy and Nuclear Posture Review by modernizing the Nation’s nuclear deterrent to keep the American people safe. The Budget supports a safe, secure, reliable, and effective nuclear stockpile and a resilient, responsive nuclear security enterprise necessary to protect the U.S. homeland and allies from growing international threats.” whitehouse.gov/wp-content/uploads/2024/03/budget_fy2025.pdf, page 75.
The 2022 National Defense Strategy and Nuclear Posture Review for the first time posited two nuclear “near peers”, i.e. Russia and China, that need to be simultaneously “deterred.” This hinted at a potentially large nuclear buildup which this budget may now be implementing. That claimed need to deter two nuclear near peers was explicitly taken a step beyond just deterrence in an October 2023 report from the Strategic Posture Commission. It declared:
“Decisions need to be made now in order for the nation to be prepared to address the threats from these two nuclear-armed adversaries arising during the 2027-2035 timeframe. Moreover, these threats are such that the United States and its Allies and partners must be ready to deter and defeat both adversaries simultaneously.” ida.org/research-and-publications/publications/all/a/am/americas-strategic-posture, page vii (bolded emphasis added)
NNSA Suppresses How Taxpayers Money Is Spent
FOR IMMEDIATE RELEASE, January 19, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – The National Nuclear Security Administration (NNSA) has just released cursory two or three page summaries of contractors’ performance paid for by the American taxpayer. For the just ended fiscal year 2023, NNSA gave nothing less than grades of “Excellent” or “Very Good” in six broad mission goals for its major contractors. This is despite the constant cost overruns and schedule delays that are the rule, not the exception, in the nation-wide nuclear weapons complex. NNSA and its parent Department of Energy have been on the Government Accountability Office’s “High Risk List” for project mismanagement ever since GAO started that List in 1991.
A current example is the Uranium Processing Facility (UPF) at the Y-12 Plant near Oak Ridge, Tennessee, originally estimated in 2011 to cost $1.4 to $3.5 billion. After costs started going through the roof, NNSA and Senator Lamar Alexander (R.-TN), then-chair of Senate Energy and Water Appropriations, swore that UPF would never go over $6.5 billion. But even after eliminating non-nuclear weapons production missions and a formal decision to continue operations at two old, unsafe buildings slated for replacement, the Uranium Processing Facility is now estimated to cost $8.5 billion. However, even that is not the final price, as NNSA is still to “rebaseline” UPF costs at some unspecified date.
2023
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT FACT SHEETS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT PRESS RELEASES
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT NUCLEAR BUDGET GRAPHS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
Past Work Product (2020-2021)
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
75TH ANNIVERSARY HIROSHIMA DAY ONLINE COMMEMORATION CALLING FOR THE ABOLITION OF NUCLEAR WEAPONS
August 6, 2020
"Jay Coghlan of Nukewatch.org on the history of the Los Alamos labs, where the bomb was designed and fabricated, and how it continues to play the leading role in the creation of most U.S. nuclear weapons since then."
[embeddoc url="https://nukewatch.org/wp-content/uploads/2020/05/plutonium-pit-production-fact-sheet.pdf" download="all" viewer="browser"]
PLUTONIUM PIT PRODUCTION WORKSHOP – NOVEMBER 19, 2019
RADIO INTERVIEW – SCOTT KOVAC & JON LIPSKY
Scott Kovac of Nuclear Watch New Mexico and Jon Lipsky, the FBI agent who led the 1989 raid investigating environmental crimes that shut down the Rocky Flats Nuclear Bomb Plant join Xubi to talk about Nuclear weapons, Nuclear clean up and Pit production plans at LANL.
RADIO INTERVIEW – JAY COGHLAN & JON LIPSKY
PIT Production at LANL with Nuclear Watch New Mexico’s Jay Coghlan and Workshop Speaker, Jon Lipsky
RADIO INTERVIEW – MARYLIA KELLEY, EXECUTIVE DIRECTOR, TRI-VALLEY CARES
Nuclear Watch NM’s Workshop on LANL & PIT Production with Marylia Kelley of Tri-Valley CARES
Pit Production Workshop: View the Presentations
Jon Lipsky, FBI agent that led the 1989 raid investigating environmental crimes that shut down the Rocky Flats bomb plant
Introduction by Jay Coghlan
Jay Coghlan, Executive Director, Nuclear Watch New Mexico, on plutonium pit production at LANL
Marylia Kelly, Executive Director, Tri-Valley CAREs (Livermore, CA) on the new nuclear arms race
https://www.facebook.com/NukeWatch.NM/videos/825812604488302/
Scott Kovac Nuclear Watch New Mexico, on LANL cleanup issues
Blog Posts
76 Years After the First Nuclear Bomb Test, the U.S. is Still Dead Set on Building New Weapons of Mass Destruction
Last week, July 16 2021, marked the 76th anniversary of the world’s first nuclear bomb explosion. Within another month, memorials and commemorations will be held for the Japanese cities of Hiroshima and Nagasaki, which the U.S. bombed on 6 and 9 August 1945, respectively. Although it was unknown to most residents of New Mexico until after the United States’ atomic bombing of Japan, the citizens and communities in the southern region of the state were in fact the first nuclear victims.
When the U.S. Army detonated an atomic bomb on July 16, 1945 at 5:29 a.m., “its thunderous roar during the rainy season knocked people from breakfast tables in Tularosa and sent others on the Mescalero Apache reservation into hiding.” (axios.com) Hispanics and Mescalero Apache tribal members in New Mexico are working to pressure lawmakers to compensate those who have suffered extremely because of the experiment. Rare forms of cancer and other health problems have been discovered in those living near the site of the Trinity Test, and the vast, noxious consequences of this experiment have had lasting impact on now multiple, entire generations.
South Carolina Environmental Law Project and Nuclear Watchdogs Virtual Press Conference
Nuclear Watch New Mexico, along with other watchdog groups, has announced a lawsuit against the Biden administration over its expanded production of plutonium cores for the U.S. nuclear weapons “modernization” plans. There has been inadequate environmental review by federal agencies, who have failed to detail potential impacts of the projects around communities in New Mexico and South Carolina.
The lawsuit was filed against the Energy Department and the National Nuclear Security Administration demanding the federal agency that oversees U.S. nuclear research and bombmaking must “take a legally required ‘hard look’ at impacts on local communities and possible alternatives before expanding manufacturing of the plutonium cores used to trigger nuclear weapons.”
The push from U.S. officials to “modernize” the country’s nuclear arsenal cites only general global security concerns that do not justify the science and brand new, untested technology that will be necessary to the task. citing global security concerns. Although “most of the plutonium cores currently in the stockpile date back to the 1970s and 1980s,” scientific experts estimate that plutonium pits will last 100 years or more., and on warhead type, the best estimate of minimum pit life is 85–100 years.minimum.
Los Alamos National Laboratory in northern New Mexico and the Savannah River Site near Aiken, South Carolina face enormous (and, frankly, unrealistic) deadlines to produce a massive number of plutonium cores in coming years – 50 or more cores at South Carolina and 30 or more at Los Alamos National Lab. The Savannah River Site location now has estimated costs up to $11.1 billion, with a completion date ranging from 2032 to 2035. The U.S. doesn’t need the new plutonium cores with the taxpayer bearing the burden for the expense of lagging deadlines and bloated budgets.
“The watchdog groups said Tuesday that the agency took a piecemeal approach to decide on locating the production at Los Alamos and the Savannah River Site, where nearby communities are already underrepresented and underserved.”
Tom Clements of Savannah River Site Watch said the South Carolina location was picked for political reasons following the failure of a facility designed to convert weapons-grade plutonium into commercial nuclear fuel. As the Savannah River Site has never served as a storage or production site for the pits in its history, establishing pit construction there would be “a daunting technical challenge that has not been properly reviewed,” Clements said.
With very real, current threats the U.S. is facing right now, we don’t need another Rocky Flats situation in New Mexico or South Carolina where a $7 billion, yearslong cleanup is required after the facilities fail due to leaks, fires and environmental violations, doing irreparable damage to the earth and placing communities there in unequivocal peril.
Cleanup Funding Request at Los Alamos Would Be Needed Increase
DOE Environmental Management released the Fiscal Year 2022 (FY22) Congressional Budget Request and asked for a $107.5 million increase over last year for legacy cleanup at Los Alamos National Laboratory (LANL). The FY22 EM funding request for cleanup at LANL totaled $333.5 million, which was a record request for cleanup at the Lab.
The Budget Request gives lifecycle costs. LANL has spent $3.8 billion on cleanup from 1997 to 2020. The high estimate is $4.6 billion for FY21 to FY90. This gives a total lifecycle cost of $8.4 billion from 1997 through 2090. The assumption included with these estimates is that most of the waste will remain buried at LANL. This is the first time DOE has mentioned legacy cleanup lasting until 2090. Last year the completion date was given as 2036.
Is legacy cleanup completion being pushed back to prioritize pit production? If DOE starts spending more on cleanup like this year in the future, shouldn’t cleanup take less time? The numbers work out to DOE only spending an average of $50 million between now and 2090, so DOE must not have plans to spend $330 million annually through 2090.
Modernization: The Mainspring of NNSA FY 2022 Budget Request in the Form of Ballooning SRS Pit Costs
The National Nuclear Security Administration’s detailed fiscal year 2022 budget request was (partially) unveiled last week on Friday, May 28, in the evening before a long holiday weekend. The Biden Administration’s total NNSA FY22 budget request is just under $20 billion, requesting of $15.48 billion for NNSA “Total Weapons Activities” and following suit with Trump’s excessive nuclear weapons budget of $15.35 billion that Congress appropriated for FY 2021.
Of particular note in the budget request is that it will cost more than double what the National Nuclear Security Administration had previously estimated for the total of DOE’s Plutonium Bomb Plant construction at Savannah River Site in South Carolina. The facility would be a converted production plant for the fabrication of plutonium “pits,” the triggers for nuclear warheads. The cost for the plant has ballooned from the previous estimate of $4.6 billion to a now staggering $11.1 billion. What’s more, the schedule for the facility’s initial operation has slipped up to five years. The plans for the SRS Plutonium Bomb Plant have already run far over budget and fallen behind schedule, and “these troubling and potentially debilitating developments foreshadow problems to come to the challenging pit-production project,” according to the public interest group Savannah River Site Watch.
MEDIA ADVISORY: WHAT TO LOOK FOR IN THE U.S. DEPARTMENT OF ENERGY’S FY 2022 NUCLEAR WEAPONS AND CLEANUP BUDGET REQUEST
For use with DOE’s scheduled budget release on Friday May 28, 2021
For more information, key contacts are listed below.
The White House is releasing its detailed Fiscal Year 2022 budget on Friday, May 28. A so-called “skinny budget” was released on April 9 that increased Department of Energy (DOE) funding to $46.1 billion, which reportedly includes major new investments in clean energy and climate change abatement. That said, historically roughly 60% of DOE’s funding has been earmarked for nuclear weapons production and cleanup of Cold War wastes and contamination. The pending budget release will finally provide details on those programs.
Because the budget release is so late Congress has already announced that it can’t consider the annual Defense Authorization Act until September. Related appropriations bills will no doubt be delayed too. This means that the government will probably have to run on a Continuing Resolution(s) for much of FY 2022 (which begins October 1, 2021).
The Alliance for Nuclear Accountability strongly opposed the massive 25% FY 2021 increase that the Trump Administration gave to the National Nuclear Security Administration’s (NNSA’s) nuclear weapons programs and proposed cuts to Department of Energy cleanup. In addition, DOE’s nuclear weapons and environmental management programs have been on the Government Accountability Office’s “High Risk List” for project mismanagement and waste of taxpayers’ dollars for 28 consecutive years. Related, the Congressional Budget Office (CBO) has just released a report that projects a 28% increase in costs for so-called “modernization” of U.S. nuclear forces that between the Defense Department and DOE is expected to cost around $1.7 trillion over 30 years.
The Alliance for Nuclear Accountability, a 34-year-old network of groups from communities downwind and downstream of U.S. nuclear weapons sites, will be analyzing the following critical issues. For details, contact the ANA leaders listed at the end of this Advisory.
Virtual Advocacy for “Safety, Security, and Savings” at ANA DC Days:
May 26, 2021
Nuclear Watch New Mexico virtually visited Washington, DC this month to participate in the Alliance for Nuclear Accountability’s “DC Days,” an annual event where organizations from across the nation, whose members are directly affected by nuclear weapons production and the incidental health and environmental consequences, make their voice heard to federal policy makers.
Nuclear Watch NM was focused on opposing new plutonium pit production at Savannah River Site and Los Alamos, pushing for safe and secure toxic cleanup and prioritizing public health while saving billions by terminating ill-conceived new nuclear weapons programs. View more information on these issues in the Alliance for Nuclear Accountability’s new report, “Safety, Security, and Savings,” which describes in detail the foundation of our 2021 advocacy. The report includes a series of fact sheets and recommendations covering new warheads, bomb plants, nuclear waste, cleanup, and more.
Notice of Impending Lawsuit to DOE & NNSA Over Nuclear Bomb Core Plans from Environmental Groups
Nuclear Watch New Mexico, as part of a larger coalition of environmental groups, has threatened the federal government with a lawsuit over cross-country plans to produce plutonium pits, the cores at the heart of modern nuclear weapons.
A more comprehensive review should have been done on the plans to produce plutonium cores at Los Alamos and at the Savannah River Site in South Carolina. This lack of review violates the National Environmental Policy Act (NEPA) and would saddle already-burdened communities nearby the two DOE sites with significant quantities of toxic and radioactive waste, contravening President Biden’s executive order of making environmental justice a part of the mission of every agency. Here in New Mexico, we are well aware of how much our local community has already have been burdened with legacy contamination from previous defense work. While the budget continues to be cut and slashed for cleanup funding, the astronomical cost of modernizing the U.S. nuclear weapons arsenal continues to balloon out of proportion without NNSA or DOE batting an eyelash. The federal government’s plans are unnecessary and provocative – more plutonium pit production will result in more waste and help to fuel a new arms race.
10 Years Since Fukushima Nuclear Disaster
11 March 2021 marks the 10th anniversary of the triple catastrophe which marked the life of many residents of Eastern Japan: a powerful earthquake, deadly tsunami and nuclear meltdown that left almost 18,500 people killed or missing. Much has been achieved in disaster-hit areas but they are still seriously recovering, and the staggering loss of life and community is still being felt by the nation today. The impacts on communities from the ongoing dispersal of radioactive contamination released from the explosions at the Daiichi nuclear power plant in Fukushima have been disastrous. Tokyo will probably face a massive earthquake in the next 30 years, and Japan must prepare for this next big quake while the Fukushima nuclear meltdown on Japan’s north-eastern coast remains firmly in the minds of everyone there.
Since the disaster, tens of thousands of people have been displaced from their ancestral lands. The harm extends far beyond the immediate threat to health – as well as destroying livelihoods, it has destroyed an entire way of life.
TIME TO TAKE SENATOR BINGAMAN TO TASK!
When Jeff Bingaman replaced Pete Domenici as New Mexico’s senior Senator, environmentalists were pleased. But is Bingaman the new Domenici? Is he stepping into Pete’s radioactive shoes as chief procurer of pork for nuclear contractors, the environment be damned?
Consider this: Bingaman’s so-called “Clean Energy” legislation sticks taxpayers with a huge financial burden to cover unlimited loan guarantees for new nuclear power plants– yet another bailout for fat-cats who’ve already bankrupted us, just like the banks, insurance execs and military contractors. No nuclear plant has ever been built on schedule or within budget. And with no remotely viable solution to the nasty spent-fuel-rod problem, all eyes will be on NM’s sadly flawed WIPP repository as a place to stick the waste out of sight and out of mind. New Mexicans were promised that power-plant waste would never come to WIPP, but with Yucca Mountain in Nevada getting the red light, how long can we trust in that long-ago promise?
Now how about the weapons side of the nuclear equation? Talking out of both sides of his mouth like a true US Senator, Bingaman has weakly endorsed mission diversification at the national weapons Labs, then backed the fat increases for bomb facilities and new designs in Obama’s ghastly proposed federal budget for 2011. Bingaman lamely says this tragic misuse of tax dollars is “good for our state.” Hey, Jeff! If something is bad for the nation and bad for the world, it is not good for our state. And those new radioactive and chemical wastes from cranking out H-bombs will all become a permanent feature here in New Mexico. Thanks for drowning us in nuclear waste from all sides, Senator!!! You’re dooming us to an abusive relationship with a couple of dead-end industries whose profits end up elsewhere, when we could be creating a much brighter and cleaner future for our lovely state. Nuclear waste is permanent. The handful of jobs we get out of it are temporary–the way a Senate seat should be.
Friends, if this makes you as mad as it makes me, give Bingaman a trip to the woodshed. His toll-free NM # is 800-443-8658 and his DC office is 202-224-5521.
New Plutonium Facility Estimate Embraces $4.5 Billion
Buried in Volume 1 of the Department of Energy’s FY 2011 Congressional Budget Request are the Details of Project Cost Estimate for LANL’s proposed Chemistry and Metallurgy Research Building Replacement (CMRR) Project. (Pg.226 & 227)
The Details –
$164 million – The cost of the Radiological Laboratory/Utility/Office Building (RLUOB) recently finished with construction
$199 million – The estimated cost of equipment for the RLUOB scheduled to be installed by 2013.
$3.4 billion – The current estimate of the Proposed Nuclear Facility due to be completed in 2018.
$782 million – “Contingency”
$4.5 Billion – Total
This does not D&D of the existing CMR (estimated at $500 million).
DOE Fails to Make Minimum Payment on Environmental Cleanup
Last I looked, the Cold War ended 18 years ago. We won. OK, I used to think we won, but there is still a big debt that needs to be paid off before any victory party.
The Department of Energy’s Agency Financial Report for Fiscal Year 2009 (Pg.52) gives some sobering figures. Even with extra Recovery funding ($5.1 billion) and all the usual appropriations (about $6 billion) the Department’s “total unfunded environmental cleanup and disposal liabilities” still increased by over $1 billion in 2009. The current estimate for the cleanup of environmental contamination resulting from past operations of the nuclear weapons complex is $262.7 billion. Given that this estimate will surely increase yearly, at this rate, DOE will pay off its existing Cold War environmental liability, well…never.
Yet the Department continues on a shopping spree and rings up new $4 billion facilities that will generate new wastes. DOE must stop creating new waste when the legacy waste is still posing a threat, and should greatly increase the annual cleanup funding at least until it starts to make a dent in the amount owed. Until then, somebody please, cut up the credit card.
More from the Agency Financial Report for Fiscal Year 2009 –
“At all sites where these activities took place, some environmental contamination occurred. This contamination was caused by the production, storage, and use of radioactive materials and hazardous chemicals, which resulted in contamination of soil, surface water, and groundwater. The environmental legacy of nuclear weapons production also includes thousands of contaminated buildings and large volumes of waste and special nuclear materials requiring treatment, stabilization, and disposal. Approximately one-half million cubic meters of radioactive high-level, mixed, and low-level wastes must be stabilized, safeguarded, and dispositioned, including a quantity of plutonium sufficient to fabricate thousands of nuclear weapons. “ (Pg.52)
Mother of Nuclear Weapons Complex Modernization speaks at Global Zero Summit
Re : Ellen Tauscher, Under Secretary for Arms Control and International Security, addressing Global Zero Summit, Paris, February 3, 2010
The good news is there is no bad news in her speech… she basically goes rhetorical using standard mountain climbing analogy language of journeying to the summit of a world free of nuclear weapons.
But it’s an ironic speech given that Tauscher is the Mother of Nuclear Weapons Complex Modernization. As chairwoman of the Strategic Forces Subcommittee of House Armed Services she saw to it that the Perry-Schlesinger Strategic Posture Commission was legislatively created in the 2009 Defense Authorization Act. At the time, she represented the California congressional district that is home to the Lawrence Livermore nuclear weapons laboratory. In May 2009 that Commission came out with recommendations to modernize the complex. Tauscher then saw to it that the FY2010 Defense Authorization Act required “a report on the plan… to modernize the nuclear weapons complex” as a condition for ratification of the new Strategic Arms Reduction Treaty (START) with Russia.
Meanwhile, Sen. Kyl in part used the Commission’s recommendations as the basis for a letter from 40 Republican senators + Lieberman telling Obama there’s no way he’s going to get START ratification without complex modernization. His letter also moved the fight up over complex modernization to START ratification, previously considered a bit of a no-brainer, instead of the expected fight over ratification of the long-sought-for Comprehensive Test Ban Treaty. On Monday, February 1, President Obama released a federal budget that dramatically increased funding for new US nuclear weapons production facilities. So it’s strange to hear Tauscher, now State Undersecretary for Arms Control and International Security, play to the crowd at the summit for Global Zero, whose purpose is to abolish nuclear weapons in 20 years.
She had nary a word to say on how under “modernization” the US is designing and building three new production plants for plutonium, uranium and nonnuclear components for nuclear weapons. In fact, groundbreaking for one of them, the Kansas City Plant, just might occur just before the NonProliferation Treaty Review Conference that begins May 3. Let’s see how Obama and Tauscher explain that to the international delegations at the United Nations!
Despite Non-Proliferation Pledge – $7B for Nuclear Arsenal
February 2, 2010 – Democracy Now!’s Amy Goodman interviews Jay Coghlan of Nuclear Watch
AMY GOODMAN: All forty Republican senators, as well as Joseph Lieberman, implied in a letter to Obama last month that they would block ratification of the new treaty with Russia unless he funds a, quote, “modern” warhead and new facilities at the Los Alamos National Lab, where you’re near right now in New Mexico, and the Y-12 plant in Oak Ridge, Tennessee. Jay?
JAY COGHLAN: You’re absolutely right. They’re playing muscle, and they’re rolling Obama and Biden. The Democrats are now surrendering. The executive administration is now surrendering to that demand.
…how is the US now going to walk in with a straight face, walk into the UN, and claim that it’s leading towards a world free of nuclear weapons, when in fact we are starting up a plutonium facility in Los Alamos, a uranium facility in Tennessee, but also a major new production plant in Kansas City for all of the non-nuclear components that go into a weapon?
So, basically, the US is revitalizing its nuclear weapons production base. And again, the laboratories, mark my words, and as the Republicans already wrote, they’re calling for or attempting to demand a, quote, “modern” warhead, that means new designs.
Obama’s New Budget Increases Funding for Nuclear Weapons Production Facilities; Cuts Dismantlements
In the new budget request for 2011 the Obama Administration proposes to freeze discretionary domestic spending for programs such as education, nutrition, air traffic control and national parks for three years while dramatically increasing funding for new US nuclear weapons production facilities. Meanwhile the proposed budget for dismantling warheads retired from the stockpile is down by 40%. Funding for a new nuclear facility at Los Alamos National Laboratory to be used in direct support of plutonium pit production, the CMRR-NF, is increased to $225 million requested from $97M in FY10 (+132%). After FY11, funding is proposed to triple the FY10 amount to $300 million for each of the following four consecutive years.
Funding for a new “Uranium Processing Facility” (UPF) at the Y12 production plant near Oak Park Ridge, TN, is proposed to increase to $115M from $94M in FY10 (+22%). However, its big money is in the following four consecutive years, climbing to $320 million by 2015 (in all a 240% increase from FY10 funding). Totals costs for both the CMRR and UPF are still “TBD” [To Be Determined], meaning they don’t know, but each will probably cost $3 billion or more.
Outside of the federal budget, groundbreaking is expected this Spring on a new privately-financed ~$700 million Kansas City Plant for nonnuclear components production for US nuclear weapons, subsidized by Kansas City municipal bonds. This pretty well spans the spectrum of future US nuclear weapons production, with big increases for new facilities for plutonium, uranium and nonnuclear components. At the same time, the Obama budget proposes to cut dismantlement from $96.1 million in FY 2010 to $58 million.
Obama is preemptively surrendering to the nuclear weapons labs, the for-profit private corporations running those labs, and the 2/3rd’s Senate majority including Republicans needed for treaty ratifications. All of these special interests explicitly seek to extract more taxpayer funding for nuclear weapons programs in exchange for ratification of a renewed bilateral arms control treaty with Russia and a long-sought-for Test Ban Treaty.
We went through this a decade ago, when the nuclear weapons complex got billions of dollars and but ratification of the Comprehensive Test Ban Treaty failed. History is getting ready to repeat itself, this time with the nuclear weapons labs seeking the capability to produce future new-design weapons. Obama’s new budget begins to give them just that, welfare for warheads that can’t be used while American public needs are not adequately met.
Meet the Nuke Boss, Just Like the Old Boss!
While Obama’s rhetoric soars toward a grand nuclear weapons-free world, his Office of Management and Budget is getting ready to ask Congress for a 10% increase in research and production?
Apparently our president is preemptively surrendering to the 40 Republican senators +1 (“independent” Lieberman) that demanded linkage of ratification of a new Strategic Arms Reduction Treaty (START) with Russia to “modernization” of the nuclear weapons research and production complex, along with a “modern warhead,” whatever that is. A huge fight was always expected over a second round of attempted ratification of the Comprehensive Test Ban Treaty (CTBT. However, the Republicans +1 cunningly chose to move that fight up to START ratification in order to leverage Obama’s proposed FY 2011 federal budget slated for release on February 1. They apparently have succeeded: he has caved into them.
The Republicans seek to mandate the construction of two controversial new production facilities, the plutonium “Nuclear Facility” at Los Alamos and the Uranium Processing Facility at Y-12 near Oak Ridge, TN, both designed for production levels of up to 125 nuclear weapons per year. Additionally, groundbreaking for the new privately financed Kansas City Plant for nonnuclear components production, responsible for 85% of all components that go into U.S. nuclear weapons, will occur soon. Ironically, that may be just before the NonProliferation Treaty Review Conference that begins May 3 at the United Nations. We can expect Obama’s oratory to again excel at the UN while claiming that the U.S. is indeed working toward a nuclear weapons-free world. He will be contradicted by these new plutonium, uranium and nonnuclear nuclear weapons components production plants, together costing $7 billion or more.
Obama should put his money where his mouth is, not give it to the nuclear weaponeers. A decade ago Clinton and Congress delivered bucket loads of money to the nuclear weapons labs, only to have their directors damn the Test Ban Treaty through faint praise before the Senate in 1999 which killed it (and they got to keep the money!).
Today, the Labs internally state that there is little technical difference between a ratified Test Ban Treaty and the current testing moratorium in effect since 1992. Their real concern is to leverage treaty ratifications to ensure expanded design and production capabilities for both existing weapons and possible “replacement designs,” which they have not given up on despite previous congressional rejections of “Reliable Replacement Warheads.” They want to “Get more money” for expanded capabilities through Treaty “Safeguards.” They are apparently succeeding. ( more ).
Studies by independent nuclear weapons experts have concluded that the all important plutonium pit triggers last a century or more, and existing nuclear weapons can be reliably maintained under existing programs for many decades. In pending budget and treaty ratification processes our New Mexican Senators should be pushing for increased funding for alternative missions and cleanup at our Sandia and Los Alamos national labs, instead of supporting Obama’s preemptive surrender that will further entrench our state in the nuclear weapons business. That is the right thing to do for both the long-term creation of jobs in New Mexico and working consistently toward a nuclear weapons-free world.
Given exploding national debt the American taxpayer should not be further burdened with unneeded and provocative nuclear weapons production facilities. The labs want to pervert disarmament treaties into armament treaties by enshrining expanded nuclear weapons design and production capabilities for themselves as treaty “Safeguards.” Hope we don’t get fooled again!
Kansas City (Nuke Plant) Blues
Some pertinent points on the new Kansas City Plant, prompted by the Kansas
City Star article:
• Groundbreaking will probably be sometime after March given that final
private financing still has to be found.
• However, groundbreaking for a major new U.S. nuclear weapons production
plant, costing $4.76 billion to build and operate over its first 20 years,
is still likely to occur just before the May 2010 NonProliferation Treaty
Review Conference. It would be nice if the U.S. had some explaining to do at
the UN over that.
• Originally reported construction cost was $500 million. Now we’re up to
$673 million.
• Previously projected tax abatements to be granted by the Kansas City
municipal government were $41 million. Now we’re up to $65 million ($2.6
million/year over 25 years).
• Infrastructure improvements (roads and utilities) enabled by the tax
abatements will benefit the private developers in their other nearby
business ventures, including a planned intermodal,international
transportation hub (part of the so-called “NAFTA Superhighway”).
• Kansas City’s Planned Industrial Expansion Authority (PIEA), enabled by
Missouri state law to fight urban blight, will issue bonds to private
investors. The PIEA declared a producing soy bean field blighted in order to
provide the basis for this (hardly urban blight).
• Through the PIEA, a municipal government (Kansas City, MO) will hold fee
simple to this new federal nuclear weapons production plant (i.e., own it).
The PIEA will grant the private developers a 20-year or more
lease-to-purchase, after which the private developers will own this new
federal nuclear weapons production plant.
• Guaranteed subleases to the National Nuclear Security Administration
(NNSA) via the General Services Administration (GSA) effectively guarantee
the profits of the private developers and their ability to pay the bonds
off. “Coincidentally,” one of the two private development partners happened
to own the land that the new Plant is to be built upon before GSA/NNSA
selected it.
• GSA/NNSA put out a solicitation for bids to private developers a good
month or so before they issued public notice of an environmental assessment
for the new Kansas City Plant under the National Environmental Policy Act.
Nevertheless, the two agencies have always denied any predetermination.
Sandia Claims Technology Supports the CTBT While Modernizing Weapons
Above its masthead the hard copy 12/4/09 Sandia Lab News has a cool NNSA/DoD “W76-1/MK4A” badge with a black submarine and a vertical warhead above it with a slanted trident across it. MK4A is the reentry vehicle for the W76. The sub, of course, is a Trident submarine.
To summarize some points:
• It states that Life Extension Programs (LEPs) can extend warhead life up to 60 years. That’s significant, especially given the continuing push by some for new-design replacement warheads. Previously I had heard only up to 30 years.
• Please note the pending resumption of broad-scale nuclear weapons production with this W76 LEP.
• Please note “reinventing the weapon’s AF&F [arming, fuzing & firing] system” …. which “provides packaging and performance enhancements. Though the W76-1 is emphatically not a new weapon system, the scope of the LEP effort was very demanding.”
Maybe it’s not a new “system,” but the W76-1 has new military characteristics. That new AF&F system being produced now at the Kansas City Plant is believed to endow the warhead with a selectable height of burst.
In 1997 Navy Admiral George “Pete” Nanos wrote :
The demonstrated capability of the D5 [the new Trident II missile] is excellent. Our capability for Mk 4 [reentry vehicle with W76 warhead], however, is not very impressive by today’s standards, largely because the Mk 4 was never given a fuse that made it capable of placing the burst at the right height to hold other than urban industrial targets at risk. With the accuracy of D5 and Mk 4, just by changing the fuze in the Mk 4 reentry body, you get a significant improvement. The Mk 4, with a modified fuze and Trident II accuracy, can meet the original D5 hard target requirement. Why is this important? Because in the START II regime, of course, the ICBM hard target killers are going out of the inventory and that cuts back our ability to hold hard targets at risk.
“Strategic Systems Update,” Rear Admiral G.P. Nanos, The Submarine Review, April 1997
In other words, with a new fuze and increased missile accuracy the military characteristics of the refurbished W76-1 are transformed from being a countervalue weapon of deterrence (“city buster”) into a counterforce weapon (“hard target killer”). This directly contradicts the constantly repeated statements by senior U.S. Government officials that military characteristics won’t be changed and that “new” nuclear weapons will not be created.
For more, please Hans Kristensen’s excellent 2007 “Administration Increases Submarine Warhead Protection Plan”
(Side note: Adm. Pete Nanos later became LANL Director, didn’t quite get along, and at one point famously called Lab scientists “cowboys” and “buttheads”).
The article ends by noting that the W76 LEP has laid the foundation for a future B61 LEP, which itself is an issue of current controversy.
Separately it was recently revealed that Sandia manager Lockheed Martin pays Sandia Director Tom Hunter $1.7 million a year. Lockheed Martin is also the dominant corporate partner running the U.K’s Atomic Weapons Establishment (AWE) at Aldermaston. On December 4 the Obama Administration nominated Donald Cook to be NNSA Deputy Administrator for Defense Programs. Cook is an American who worked at Sandia for 28 years and was the Managing Director of the UK’s AWE from 2006 to 2009. The W76 is the U.K’s main (if not only) currently operational nuclear weapon.
I find the overarching headline in this e-version of Sandia Lab News announcing that Sandia technology “comprehensively” supports the CTBT to be ironic while it then goes on into an article about broad-scale nuclear weapons production of the W76-1. I understood the original intent of the CTBT to be a disarmament treaty cutting off the further advancement of nuclear weapons by any country.
Update – Lab Shipment Scare at Sunport
Phil Parker at the Journal gives an update.
The package was labeled “explosives” on the inside, so the cargo handlers were rightfully concerned when their alarms went off. The cargo facility was closed for about four hours during the incident.
It was reported that , “The containers are usually shipped via ground transportation but sometimes, he [LANL spokesperson] said, they’re sent by air.” I’m guessing that it costs more to send it by air, not to mention the extra cost of wasting time of the Albuquerque Police Department bomb squad, the cargo handlers, and Lab personnel.
The Journal reported, “Security at the airport didn’t know about the arrangement. “Apparently it was just a misunderstanding,” said airport spokesperson Daniel Jiron.” Once again, the Lab deflects any responsibility.
RECENT FORMAL COMMENTS
Past NukeWatch Events
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
Past Work Product (2019-)
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
2019
November 26, 2019 Press Release November 24, 2019 Press Release November 19, 2019 Plutonium Pit Production Workshop Presenters:
August 12, 2019 NEPA Comments NukeWatch’s 22-page formal comments on expanded plutonium pit production Until NNSA fully complies with the National Environmental Policy Act through the preparation of a programmatic environmental impact statement on expanded plutonium pit production, Nuclear Watch believes that any irreversible or irretrievable commitment of resources to either the expansion of pit production at the Los Alamos Lab or to the repurposing of the MOX Facility at the Savannah River Site is unlawful. Read/Download the Full Document HERE July 25, 2019 NEPA Comments Scoping comments on NNSA draft EIS for plutonium pit production at the Savannah River Site THE NEED FOR A PROGRAMMATIC ENVIRONMENTAL IMPACT STATEMENT: This is our first and primary concern, that NNSA must first complete a programmatic environmental impact statement (PEIS) on its nation-wide plans for plutonium pit production, in advance of the Savannah River Site-specific environmental impact statement. To get right to the point, we argue that the SRS EIS process should go no further than this scoping period and should resume only after a completed formal Record of Decision for a new or supplemental PEIS. Read/Download the Full Document HERE July 9, 2019 Plutonium Pit Production Fact Sheet Expanding Nuclear Pit Production: The Facts and What You Can Do The Facts Read/Download the Full Document HERE June 10, 2019 News Release In a victory for transparency and legal compliance by the government, the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) today published a “Notice of Intent” in the Federal Register to complete environmental reviews on its controversial proposal to expand plutonium “pit” production for new and refurbished nuclear weapons. [embeddoc url="https://nukewatch.org/wp-content/uploads/2019/06/SRS-plutonium-bomb-plant6-14-19.pptx" download="all" viewer="google"] Read/Download the Full News Release HERE June 4, 2019 Press Release On behalf of three public interest organizations - Nuclear Watch New Mexico, Tri-Valley Communities Against a Radioactive Environment and Savannah River Site Watch – attorneys for the law firm of Meyer Glitzenstein & Eubanks and the Natural Resources Defense Council recently sent a 16-page letter to Lisa Gordon-Hagerty, head of the National Nuclear Security Administration (NNSA). The detailed letter warns the nuclear agency to not proceed with aggressive plans to expand plutonium pit production without first meeting its legal requirements for timely public review and comment under the National Environmental Policy Act. Read/Download the Full Press Release HERE May 31, 2019 Press Release Last Wednesday, facility operations personnel entered a service room and noticed a leak emanating from a valve on the radioactive liquid waste (RLW) system. Upon subsequent visual inspection by a radiological control technician, RLUOB engineers believe that this valve, and 6 similar valves, may be constructed of carbon steel. The RLW system handles radioactive liquid waste streams from chemistry operations that include nitric and hydrochloric acids—carbon steel valves would be incompatible with these solutions. The suspect valves are also in contact with stainless steel piping, which would create another corrosion mechanism. RLUOB management plans to drain the affected piping sections and develop a work package to replace all of the suspect valves. They will also confirm the valve materials and if shown to be incorrect, investigate the cause of this failure in the design, procurement, and installation processes. The valves were installed in 2013 as part of a modification to add straining and sampling capabilities that were not in the included in the original design. [Please note that DNFSB reports are posted a few weeks later than dated.] This immediately raises two crucial issues: 1) the National Nuclear Security Administration’s (NNSA’s) plans for expanded plutonium pit production; and 2) the current attempt by the Department of Energy to restrict Safety Board access to its nuclear weapons facilities. Read/Download the Full Press Release HERE April 26, 2019 Consent Orders Comparison On March 1, 2005, after arduous negotiations and threats of litigation, the New Mexico Environment Department (NMED), Department of Energy (DOE), and Los Alamos National Laboratory (LANL) entered into a Consent Order specifying the schedule for investigation and cleanup of the Lab’s hundreds of contaminated sites. This Consent Order (CO) was LANL’s agreement to fence-to-fence cleanup of Cold War legacy wastes, which NMED began to enforce. Read/Download the Full Comparison HERE March 25, 2019 Press Release More than 25 years after the end of the Cold War, all eight established nuclear weapons powers are “modernizing” their stockpiles. Talks have broken down with North Korea, the new nuclear weapons power. Nuclear-armed India and Pakistan narrowly averted war last month. Russian President Vladmir Putin made new nuclear threats in response to Trump’s announced withdrawal from the Intermediate-Range Nuclear Forces Treaty. This could lead to hair-trigger missile emplacements in the heart of Europe and block extension of the New Strategic Arms Reduction Treaty with Russia. If so, the world will be without any nuclear arms control at all for the first time since 1972. Meanwhile, the U.S. criticizes non-weapons states for signing a nuclear weapons ban treaty, despite the fact there have long been treaties completely banning chemical and biological weapons of mass destruction that the U.S. seeks to enforce. The pending international NonProliferation Treaty (NPT) Preparatory Committee conference at the United Nations is widely expected to collapse in failure because of the nuclear weapons powers’ failure to enter into serious negotiations leading to nuclear disarmament. The NPT’s Article VI mandate for those negotiations has been in effect since 1970, when the Treaty was signed by 189 countries (more than any other treaty). Read/Download the Full Press Release HERE March 26, 2019 NukeWatch Budget Compilation Nuclear Watch New Mexico — Department of Energy FY 2020 Nuclear Weapons Budget Request |
2018
November 16, 2018 Plutonium Pit Production Fact Sheet Plutonium pits are the radioactive cores or “triggers” of nuclear weapons. Their production has always been a chokepoint of resumed industrial-scale U.S. nuclear weapons production ever since a 1989 FBI raid investigating environmental crimes shut down the Rocky Flats Plant near Denver. In 1997 the mission of plutonium pit production was officially transferred to its birthplace, the Los Alamos National Laboratory (LANL) in northern New Mexico, but officially capped at not more than 20 pits per year. However, in 2015 Congress required expanded pit production by 2030 whether or not the existing nuclear weapons stockpile actually needs it. This will support new military capabilities for nuclear weapons and their potential use. Read/Download the full fact sheet pdf HERE October 31, 2018 Nuclear Watch New Mexico, Savannah River Site Watch, and Tri-Valley CAREs sent a letter of demand to the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) to inform the government that its plan to quadruple the production rate of plutonium bomb cores is out of compliance with the National Environmental Policy Act (NEPA). NNSA’s premature plan to quadruple the production rate of plutonium bomb cores (“pits”), the heart of all US nuclear weapons, is out of compliance with requisite environmental law, the groups argue, as NNSA has failed to undertake a legally-mandated programmatic review and hold required public hearings. View/Download the entire press release HERE NukeWatch Comments, September 27, 2018 Nuclear Watch New Mexico is submitted formal comments to express in the strongest possible terms our opposition to DOE Order 140.1 Interface with the Defense Nuclear Facilities Safety Board. We find that the Department of Energy’s (DOE’s) attempt to restrict and suppress DNFSB access is very misguided, arrogant, and likely illegal in that it acts contrary to the Board’s enabling legislation. June 8, 2018 Press Release New Contractors Selected For Expanded Nuclear Weapons Production at Los Alamos Santa Fe, NM. Today the Department of Energy's National Nuclear Security Administration (NNSA) announced its choice for the new management and operating contract for the Los Alamos National Laboratory (LANL).The new contractor, Triad National Security, LLC, is a limited liability company consisting of the Battelle Memorial Institute, the University of California and Texas A&M University. All three are non-profits, and it is unclear how this will affect New Mexico gross receipts taxes. Battelle claims to be the world's largest non-profit technology research and development organization, and manages a number of labs including the Lawrence Livermore and Idaho National Laboratories. Texas A&M was founded in 1876 as the state's first public institution of higher learning and has the largest nuclear engineering program in the country. DOE Secretary Rick Perry is an avid A&M alumnus. May 31, 2018 Press Release Santa Fe, NM & Columbia, SC - "Two key U.S. Department of Energy documents on future production of plutonium "pits" for nuclear weapons, not previously released to the public, fail to justify new and upgraded production facilities at both the Los Alamos National Laboratory (LANL) in New Mexico and the Savannah River Site (SRS) in South Carolina." May 15, 2018 Fact Sheet May 10, 2018 Press Release What's Not in NNSA's Plutonium Pit Production Decision
- NNSA did not mention that up to 15,000 "excess" pits are already stored at the Pantex Plant near Amarillo, TX, with up to another 5,000 in "strategic reserve." The agency did not explain why new production is needed given that immense inventory of already existing plutonium pits. (In 2006 independent experts found that pits last a least a century. Plutonium pits in the existing stockpile now average around 40 years old.) May 2, 2018 Press Release "NNSA should begin nation-wide review of plutonium pit production, why it's needed, and what it will cost the American taxpayer in financial, safety and environmental risks. These are all things that the public should know." -Jay Coghlan, Director, Nuclear Watch New Mexico. April 26, 2018 NukeWatch Comments LANL Rad Lab: Formal Comments Under Nat'l Environmental Policy Act Against raising plutonium limit at LANL Rad Lab View/download Nuclear Watch comments as submitted Excerpt:
- NNSA is planning a 10-fold increase in plutonium at the LANL Rad Lab with a view to ramping up the production of plutonium pits for new nuclear weapons. March 26, 2018 Press Release United States To Begin Construction Of New Nuclear Bomb Plant The National Nuclear Security Administration (NNSA) announced on Friday, March 23, that it was authorizing the start of construction of the Uranium Processing Facility (UPF) and two sub-projects at the Y-12 National Security Complex in Oak Ridge, Tennessee. The UPF is a facility dedicated solely to the manufacture of thermonuclear cores for US nuclear bombs and warheads.
Jay Coghlan of NukeWatch points out that "This project already has a long history, and it is instructive. In 2013, DOE announced it was 85% finished with the UPF design when it ran into the 'space/fit' issue- and more than a half-billion taxpayer dollars were just written off. In private business, that kind of thing gets you fired. In DOE's world of contractors running amok, they not only didn't get fired, not one Congressional hearing was held and the UPF budget went up the next year!" - See full press release for all the details (PDF) March 1, 2018 Press Release The Regional Coalition of LANL Communities: Benefits for the Select Few Santa Fe, NM- According to media reports, Andrea Romero, Executive Director of the Regional Coalition of LANL Communities, is accused of charging some $2,200 dollars of unallowable travel costs, such as alcohol and baseball tickets, while lobbying in Washington, DC for additional funding for the Los Alamos National Laboratory (LANL). She in turn accused the nonprofit group Northern New Mexico Protects of political motivations in revealing these questionable expenses. Romero is running in the Democrat Party primary against incumbent state Rep. Carl Trujillo for Santa Fe County's 46th district in the state House of Representatives. For all the details, see full press release PDF February 28, 2018 Press Release Santa Fe, NM. On December 17, 2017, the Department of Energy (DOE) awarded a separate $1.4 billion contract for cleanup at the Los Alamos National Laboratory (LANL) to Newport News Nuclear BWXT-Los Alamos, LLC (also known as "N3B"). This award followed a DOE decision to pull cleanup from LANL's prime contractor, Los Alamos National Security, LLC (LANS), after it sent an improperly prepared radioactive waste drum that ruptured underground at the Waste Isolation Pilot Plant (WIPP). That incident contaminated 21 workers and closed WIPP for nearly three years, costing taxpayers at least $1.5 billion to reopen. (See all the details in the full press release) February 26, 2018 Press Release Detailed NNSA Budget Documents Accelerates Nuclear Weapons Arms Race Santa Fe, NM. Late Friday February 23, the Trump Administration released the detailed FY 2019 budget for the National Nuclear Security Administration (NNSA), the semi-autonomous nuclear weapons agency within the federal Department of Energy. Overall, NNSA is receiving a $2.2 billion boost to $15.1 billion, a 17% increase above the FY 2018 enacted level. Of that, a full $11 billion is for the budget category [Nuclear] "Weapons Activities", 18% above the FY 2018 level. Of concern to the American taxpayer, DOE and NNSA nuclear weapons programs have been on the congressional Government Accountability Office's High Risk List for project mismanagement, fraud, waste and abuse since its inception in 1990... (See all the details in the full press release) February 22, 2018 Press Release Santa Fe, NM. Today the National Nuclear Security Administration announced an Environmental Assessment to increase the amount of plutonium used in the Radiological Laboratory Utility and Office Building (aka the "Rad Lab") at the Los Alamos National Laboratory from 38.6 grams of plutonium-239 equivalent to 400 grams. This 10-fold increase is significant because it will dramatically expand materials characterization and analytical chemistry capabilities in the Rad Lab in support of expanded plutonium pit production for future nuclear weapons designs. It also re-categorizes the Rad Lab from a "radiological facility" to a "Hazard Category-3" nuclear facility. View/Download full press release February 12, 2018 Press Release Trump's Budget Dramatically Increases Nuclear Weapons Work Santa Fe, NM In keeping with the Trump Administration's recent controversial Nuclear Posture Review, today's just released FY 2019 federal budget dramatically ramps up nuclear weapons research and production. January 12, 2018 Press Release Draft Nuclear Posture Review Degrades National Security Yesterday evening the Huffington Post posted a leaked draft of the Trump Administration's Nuclear Posture Review (NPR). This review is the federal government's highest unclassified nuclear weapons policy document, and the first since the Obama Administration's April 2010 NPR. 2017 |
2017
December 22, 2017 Press Release New Mexico Environment Department Surrendered to DOE Extortion Santa Fe, NM. The New Mexico State Auditor Office recently questioned whether two settlements between the New Mexico Environment Department and the Department of Energy were in the best interests of New Mexico. That Office noted: (View/download full press release) December 20, 2017 Press Release Los Alamos Hires New Contractor - Starts Cleanup On the Cheap Santa Fe, NM- Today the Department of Energy (DOE) announced the award of the new Los Alamos National Laboratory legacy cleanup contract to Newport News Nuclear BWXT-Los Alamos, LLC. The $1.39 billion contract is for ten years, which works out to $139 million per year... View/download the full press release Public Presentation, December 2, 2017 October 31, 2017 Press Release Today, in Washington, DC, the Congressional Budget Office released its new report, "Approaches for Managing the Costs of U.S. Nuclear Forces, 2017 to 2046". The Congressional Budget Office estimates that the most recent detailed plans for nuclear forces, which were incorporated in the Obama Administration's 2017 budget request, would cost $1.2 trillion in 2017 dollars over the 2017-2046 period: more than $800 billion to operate and sustain (that is, incrementally upgrade) nuclear forces and about $400 billion to modernize them.... Driving this astronomical expense is the fact that instead of maintaining just the few hundred warheads needed for the publicly claimed policy of "deterrence," thousands of warheads are being refurbished and improved to fight a potential nuclear war. This is the little known but explicit policy of the U.S. government! October 27, 2017 Press Release Santa Fe, NM. On the evening of Wednesday October 25, the Santa Fe City Council passed a resolution requesting that the New Mexico Environment Department strengthen the revised Los Alamos National Labs cleanup order to call for additional characterization of legacy nuclear wastes, increased cleanup funding, and significant additional safety training. The resolution also called for the suspension of any planned expanded plutonium pit production until safety issues are resolved. (view/download full press release) October 6, 2017 Press Release Santa Fe, NM. Nuclear Watch New Mexico strongly applauds the awarding of the Nobel Peace Prize to the International Campaign to Abolish Nuclear Weapons (disclosure: NukeWatch is one of ICAN's ~400 member groups around the world). This award is especially apt because the peoples of the world are now living at the highest risk for nuclear war since the middle 1980's, when during President Reagan's military buildup the Soviet Union became convinced that the United States might launch a pre-emptive nuclear first strike. Today, we not only have Trump's threats to "totally destroy" North Korea and Kim Jong-un's counter threats, but also renewed Russian fears of a US preemptive nuclear attack... Generally unknown to the American taxpayer, our government has quietly tripled the lethality of the US nuclear weapons stockpile..." (view/download complete press release) NukeWatch fact sheet, September 26, 2017 The National Nuclear Security Administration's own documents have explicitly stated that expanded pit production would have no significant positive effect on job creation and the regional economy of northern New Mexico. Nuclear Watch argues that expanded plutonium pit production could actually have negative effect if it blocks other economic alternatives such as comprehensive cleanup, which could be the real job producer. Moreover, given LANL's poor safety and environmental record, expanded plutonium pit production could have a seriously negative economic impact on northern New Mexico in the event of any major accidents. September 15, 2017 Press Release Santa Fe, NM. The Los Alamos National Laboratory (LANL) has detected far more hexavalent chromium (Cr) contamination than previously estimated in the "sole source" regional groundwater aquifer that serves Los Alamos, Santa Fe and the Espanola Basin. Sampling in July from a new well meant to inject treated groundwater back into the aquifer detected chromium contamination five times greater than the New Mexico groundwater standard of 50 micrograms per liter (ug/L). View/download the full press release September 11, 2017 Press Release Talking Points: The 2016 LANL Cleanup Consent Order Should Be Rescinded The 2005 LANL Cleanup Consent Order was all about the enforceable schedules. It required DOE and LANL to investigate, characterize, and clean up hazardous and mixed radioactive contaminants from 70 years of nuclear weapons research and production. It stipulated a detailed compliance schedule that the Lab was required to meet. Under Gov. Martinez, NMED Secretary Ryan Flynn granted more than 150 compliance milestone extensions at the Lab's request, effectively eviscerating it. View/download the complete talking points July 20, 2017 Press Release Washington, DC Today, the Oak Ridge Environmental Peace Alliance (OREPA), Nuclear Watch New Mexico, and the Natural Resources Defense Council filed a federal lawsuit to stop construction of the problem-plagued Uranium Processing Facility (UPF) until legally required environmental review is completed. The UPF, located at the National Nuclear Security Administration's (NNSA's) Y-12 production plant near Oak Ridge, TN, is slated to produce new thermonuclear weapons components until the year 2080. The UPF is the tip of the spear for the U.S.'s planned one trillion dollar-plus make over of its nuclear weapons arsenal, delivery systems, and production plants. View/download the full press release June 19, 2017 Press Release Some Background on Plutonium Pit Production at the Los Alamos Lab Santa Fe, NM -The Washington Post has published the first in a series of articles on nuclear safety lapses in plutonium pit production at the Los Alamos Lab. Plutonium pits are the fissile cores of nuclear weapons that when imploded initiate the thermonuclear detonation of modern weapons. By the way, did you know? Plutonium facilities at LANL are- in principle- designed to withstand a serious earthquake of a degree expected to occur only once every 10,000 years. The last serious earthquake near the Lab is believed to have occurred 11,500 years ago. View/download the full press release ANA Report 2017: Accountability Audit May 19, 2017 Press Release SA Preview of Trump's Budget: More Nuclear Bombs and Plutonium Pit Production Santa Fe, NM. "The proposed level of funding for the National Nuclear Security Administration's (NNSA)'s Total Weapons Activities is $10.2 billion, a full billion above what was requested for FY 2017. In March, Trump's "skinny budget" stated NNSA's funding priorities as 'moving toward a responsive nuclear infrastructure', and 'advancing the existing warhead life extension programs'. Read the full press release for all the details. March 28, 2017 ANA workshop at UN Ban Treaty Conference Ban Treaty Conference: Alliance for Nuclear Accountability Panel Discussion March 28, 2017, UN, NYC:
March 2017 Fact Sheet Plutonium Pit Production at LANL (Updated March 2017) February 23, 2017 Press Release Costs Jump in Nuclear Weapons vs. Cleanup; Nuclear Weapons Winning over Environmental Protection Santa Fe, NM. America is at a crossroads, having to choose between an unnecessarily large, exorbitant, nuclear weapons stockpile, and cleanup that would protect the environment and water resources for future generations. Expanded nuclear weapons research and production, which will cause yet more contamination, is winning. Read the full press release for all the details. January 5, 2017 Press Release The National Nuclear Security Administration (NNSA) has publicly released its fiscal year 2016 Performance Evaluation Report (PER) for Los Alamos National Security, LLC (LANS), the for-profit contractor that runs the Los Alamos Lab. The Performance Evaluation Report is NNSA's annual report card on contractor performance, and overall the agency awarded LANS $59 million in profit out of a possible $65 million. The grade was 85% for the incentive part of the award. In 2012 Nuclear Watch New Mexico successfully sued NNSA to ensure that the Performance Evaluation Reports detailing taxpayers funds paid to nuclear weapons contractors are publicly available. In 2016 the NNSA decided to put the LANL management contract out for competitive bid, but granted LANS a contract extension until the end of September 2018. |
Media appearances including radio interviews are listed on the internal Media page
See the NukeWatch Channel at YouTube for our extensive playlists of key videos.
See the Nukewatch Twitter feed
See the Nukewatch Tumblr site
WatchBlog Posts:
Over 200 posts published since 2009. See archives at the WatchBlog
Earlier Work Product items are archived here