Court Rules U.S. Nuclear Weapons Production Plan Violates Federal Law
FOR IMMEDIATE RELEASE, October 3, 2024
Media Contacts:
Ben Cunningham, Esquire, SCELP, 843-527-0078, [email protected]
Tom Clements, Savannah River Site Watch, 803-834-3084, [email protected]
Jay Coghlan, Nuclear Watch New Mexico, 505-989-7342, [email protected]
Scott Yundt, Tri-Valley CAREs, 925-443-7148, [email protected]
Queen Quet, Gullah/Geechee Sea Island Coalition, 843-838-1171, [email protected]
AIKEN, S.C. — On September 30, United States District Court Judge Mary Geiger Lewis ruled that the United States Department of Energy (“DOE”) and its semi-autonomous nuclear weapons agency, the National Nuclear Security Administration (“NNSA”), violated the National Environmental Policy Act (“NEPA”) by failing to properly consider alternatives before proceeding with their plan to produce plutonium pits, a critical component of nuclear weapons, at the Los Alamos National Laboratory (“LANL”) in New Mexico and, for the first time ever, at the Savannah River Site (“SRS”) in South Carolina.
The Court found that the plan’s purpose had fundamentally changed from NNSA’s earlier analyses which had not considered simultaneous pit production at two sites. These changes necessitated a reevaluation of alternatives, including site alternatives, which Defendants failed to undertake prior to moving forward while spending tens of billions of taxpayers’ dollars. Therefore, the Court entered judgment in favor of Plaintiffs, the nonprofit public interest groups Savannah River Site Watch, Nuclear Water New Mexico and Tri-Valley Communities Against a Radioactive Environment (CAREs); the Gullah/Geechee Sea Island Coalition; and Tom Clements as an individual plaintiff.
As a result of this ruling, the Defendants are required to newly assess pit production at a nation-wide programmatic level which will mean undertaking a thorough analysis of the impacts of pit production at DOE sites throughout the United States, including radioactive waste generation and disposal. Under the National Environmental Policy Act (NEPA), this will provide the opportunity for public scrutiny of and formal comment on their assessments.
High Detections of Plutonium in Los Alamos Neighborhood – As We Enter a New Nuclear Arms Race the Last One is Still Not Cleaned Up
FOR IMMEDIATE RELEASE, August 15, 2024
Dr. Michael Ketterer – 928.853.7188 | Email
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – In April Nuclear Watch New Mexico released a map of plutonium contamination based on Lab data. Today, Dr. Michael Ketterer, Professor Emeritus of Chemistry and Biochemistry, Northern Arizona University, is releasing alarmingly high results from samples taken from a popular walking trail in the Los Alamos Town Site, including detections of some of the earliest plutonium produced by humankind.
On July 2 and 17 Dr. Ketterer, with the assistance of Nuclear Watch New Mexico, collected water, soil and plant samples from Acid Canyon in the Los Alamos Town Site and soil and plant samples in Los Alamos Canyon at the Totavi gas station downstream from the Lab. The samples were prepared and analyzed by mass spectrometry at Northern Arizona University to measure concentrations of plutonium, and to ascertain its sources in the environment.
NNSA Delays Urgent Research on Plutonium “Pit” Aging While Spending Tens of Billions on Nuclear Weapons Bomb Core Production
FOR IMMEDIATE RELEASE, April 17, 2024
Tom Clements, SRS Watch – 803.240.7268 | Email
Scott Yundt, TVC – 415.990.2070 | Email
Jay Coghlan – 505.989.7342 | Email
Nearly three years after filing a Freedom of Information Act request, the public interest group Savannah River Site Watch has finally received the National Nuclear Security Administration’s (NNSA’s) congressionally-required “Research Program Plan for Plutonium and Pit Aging.” However, the document is 40% blacked out, including references and acronyms. Plutonium “pits” are the radioactive cores of all U.S. nuclear weapons. The NNSA claims that potential aging effects are justification for a ~$60 billion program to expand production. However, the Plan fails to show that aging is a current problem. To the contrary, it demonstrates that NNSA is delaying urgently needed updated plutonium pit aging research.
In 2006 independent scientific experts known as the JASONs concluded that plutonium pits last at least 85 years without specifying an end date [i] (the average pit age is now around 40 years). A 2012 follow-on study by the Lawrence Livermore nuclear weapons lab concluded:
“This continuing work shows that no unexpected aging issues are appearing in plutonium that has been accelerated to an equivalent of ~ 150 years of age. The results of this work are consistent with, and further reinforce, the Department of Energy Record of Decision to pursue a limited pit manufacturing capability in existing and planned facilities at Los Alamos instead of constructing a new, very large pit manufacturing facility…” [ii]
Since then NNSA has reversed itself. In 2018 the agency decided to pursue the simultaneous production of at least 30 pits per year at the Los Alamos National Laboratory (LANL) in northern New Mexico and at least 50 pits per year at the Savannah River Site (SRS) in South Carolina. Upgrades to plutonium facilities at LANL are slated to cost $8 billion over the next 5 years. The redundant Savannah River Plutonium Processing Facility in South Carolina will cost up to $25 billion, making it the second most expensive building in human history.
NNSA’s Nuclear Weapons Budget Takes Huge Jump
Arms Race Accelerates with MIRVed Warheads
Los Alamos Lab Cleanup Cut
FOR IMMEDIATE RELEASE, March 11, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – Ironically the day after the film Oppenheimer was awarded multiple Oscars, the Department of Energy’s semi-autonomous National Nuclear Security Administration (NNSA) asked Congress for its biggest nuclear weapons budget ever. NNSA’s FY 2025 request for “Total Weapons Activities” is $19.8 billion, $700 million above what Congress recently enacted for FY 2024. It is also a full billion dollars above what President Biden asked for last year, which Congress then added to and will likely do so again.
The Biden Administration states that the $19.8 billion will be used to:
“[P]rioritize implementation of the 2022 National Defense Strategy and Nuclear Posture Review by modernizing the Nation’s nuclear deterrent to keep the American people safe. The Budget supports a safe, secure, reliable, and effective nuclear stockpile and a resilient, responsive nuclear security enterprise necessary to protect the U.S. homeland and allies from growing international threats.” whitehouse.gov/wp-content/uploads/2024/03/budget_fy2025.pdf, page 75.
The 2022 National Defense Strategy and Nuclear Posture Review for the first time posited two nuclear “near peers”, i.e. Russia and China, that need to be simultaneously “deterred.” This hinted at a potentially large nuclear buildup which this budget may now be implementing. That claimed need to deter two nuclear near peers was explicitly taken a step beyond just deterrence in an October 2023 report from the Strategic Posture Commission. It declared:
“Decisions need to be made now in order for the nation to be prepared to address the threats from these two nuclear-armed adversaries arising during the 2027-2035 timeframe. Moreover, these threats are such that the United States and its Allies and partners must be ready to deter and defeat both adversaries simultaneously.” ida.org/research-and-publications/publications/all/a/am/americas-strategic-posture, page vii (bolded emphasis added)
NNSA Suppresses How Taxpayers Money Is Spent
FOR IMMEDIATE RELEASE, January 19, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – The National Nuclear Security Administration (NNSA) has just released cursory two or three page summaries of contractors’ performance paid for by the American taxpayer. For the just ended fiscal year 2023, NNSA gave nothing less than grades of “Excellent” or “Very Good” in six broad mission goals for its major contractors. This is despite the constant cost overruns and schedule delays that are the rule, not the exception, in the nation-wide nuclear weapons complex. NNSA and its parent Department of Energy have been on the Government Accountability Office’s “High Risk List” for project mismanagement ever since GAO started that List in 1991.
A current example is the Uranium Processing Facility (UPF) at the Y-12 Plant near Oak Ridge, Tennessee, originally estimated in 2011 to cost $1.4 to $3.5 billion. After costs started going through the roof, NNSA and Senator Lamar Alexander (R.-TN), then-chair of Senate Energy and Water Appropriations, swore that UPF would never go over $6.5 billion. But even after eliminating non-nuclear weapons production missions and a formal decision to continue operations at two old, unsafe buildings slated for replacement, the Uranium Processing Facility is now estimated to cost $8.5 billion. However, even that is not the final price, as NNSA is still to “rebaseline” UPF costs at some unspecified date.
2023
NukeWatch DNFSB 2022 Hearing Comments 1-20-23
Nuclear Watch New Mexico January 20, 2023 | Email
Defense Nuclear Facilities Safety Board
625 Indiana Avenue NW, Suite 700
Washington, DC 20004
Via email at <[email protected]>
Re: Comments concerning the November 16, 2022 public hearing regarding legacy cleanup activities, nuclear safety, and increased production activities at the Los Alamos National Laboratory
Dear Safety Board:
Nuclear Watch New Mexico (NukeWatch) appreciates the opportunity to provide follow up written comments for the November 16, 2022 public hearing in Santa Fe, NM. We want to thank the Board for its continuing concern over Los Alamos National Laboratory (LANL) safety issues and for having a public hearing to begin with. Further, we are grateful for the DNFSB’s perseverance in the face of the Department of Energy’s arguably illegal attempts to restrict its access. We look forward to many more years of the Safety Board’s insights and recommendations on nuclear facilities at DOE and NNSA sites, for which the DNFSB is uniquely positioned. Your service is invaluable and irreplaceable. Thank you!
Our mission statement: Nuclear Watch New Mexico seeks to promote safety and environmental protection at nuclear facilities; mission diversification away from nuclear weapons programs; greater accountability and cleanup in the nation-wide nuclear weapons complex; and consistent U.S. leadership toward a world free of nuclear weapons.
PLUTONIUM PIT PRODUCTION BRIEFING
Jay Coghlan, Nuclear Watch New Mexico January 17, 2023 | Email
GAO report: NNSA Does Not Have a Comprehensive Schedule or Cost Estimate for Pit Production Capability, January 12, 2023, gao.gov/products/gao-23-104661
- “NNSA’s Plutonium Pit Production Scope of Work Includes Dozens of Programs, Projects, and Other Activities Managed by Multiple NNSA Offices at Multiple Sites.” p. 19
- “NNSA Does Not Have a Comprehensive Schedule or Cost Estimate for Establishing its Pit Production Capability.” p. 40
- They [NNSA officials] said they did not want to introduce uncertainty about dates and wanted to avoid releasing preliminary or unpalatable information that was subject to change.” pp. 40-41
- “NNSA will have spent billions of dollars without having an overall idea of total program costs, or when program objectives, to include the capability to produce 80 pits per year, will be reached.” pp. 55-56
Independent Government Accountability Office Releases Scathing Report on Expanding Plutonium Pit Production; Pressure Mounts on Los Alamos Lab to Increase Production
FOR IMMEDIATE RELEASE, January 12, 2023 | Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – Today, the independent Government Accountability Office (GAO) released a scathing report entitled NNSA Does Not Have a Comprehensive Schedule or Cost Estimate for Pit Production Capability. The National Nuclear Security Administration (NNSA) and its parent Department of Energy have been on the GAO’s High Risk List for project mismanagement since 1991.
Plutonium pits are the essential radioactive cores of nuclear weapons. There has been only limited production at the Los Alamos National Laboratory (LANL) since 1989 when a FBI raid investigating environmental crimes abruptly shut down production at the Rocky Flats Plant near Denver. NNSA now plans to spend $2.9 billion in FY 2023 alone to establish production of at least 30 pits per year at LANL and 50 pits per year at the Savannah River Site (SRS) in South Carolina.
The two main findings of GAO’s report are:
- NNSA’s Plutonium Pit Production Scope of Work Includes Dozens of Programs, Projects, and Other Activities Managed by Multiple NNSA Offices at Multiple Sites (p 19)
RECENT FACT SHEETS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT PRESS RELEASES
Los Alamos Lab: More Plutonium, More Nuclear Weapons
FOR IMMEDIATE RELEASE, April 18, 2022 | Contact: Jay Coghlan, 505.989.7342, [email protected], Scott Kovac, 505.989.7342, [email protected],
Santa Fe, NM – On Good Friday afternoon, just before the Easter weekend, the Department of Energy (DOE) posted its “Laboratory Tables”, the best source for site specific budget information. DOE boosts funding for the Los Alamos National Laboratory (LANL) to $4.6 billion in FY 2023 (+21%), which begins October 1. With another typical $300 million in “Work for Others” (the Defense Department, FBI, CIA, etc.), LANL’s total institutional funding for FY 2023 will be approximately $4.9 billion.
Out of that, $3.6 billion is slated for core nuclear weapons research and production programs. The percentage of nuclear weapons funding at LANL has steadily grown as the Lab increasingly banks its future on plutonium “pit” bomb core production. A decade ago, nuclear weapons programs were 59% of LANL’s total institutional budget. Today it is 73%. Moreover, the remainder of Lab programs (including nonproliferation and cleanup) either directly or indirectly support nuclear weapons programs, for example through a 6% internal tax for “laboratory-directed research and development” that has historically tilted towards nuclear weapons.
LANL’s largest funding increase is for “Plutonium Modernization”, jumping 61% to $1.6 billion in FY 2023. Within that, funding to expand the production of plutonium “pit” bomb cores at LANL’s aging plutonium pit production facility is increased 68% to $588 million.
Biden’s FY 2023 Budget Fuels New Nuclear Arms Race
FOR IMMEDIATE RELEASE, April 12, 2022 | Contact: Jay Coghlan, 505.989.7342, [email protected], Scott Kovac, 505.989.7342, [email protected],
Santa Fe, NM – The Biden Administration is slow rolling its nuclear weapons budget for the federal fiscal year 2023, which will begin October 1, 2022. Top line budget numbers released on March 24 showed that Biden is increasing the National Nuclear Security Administration’s (NNSA’s) budget category for “Total Weapons Activities” by 7.4% to $16.5 billion. That may seem like a relatively modest increase, especially given accelerating inflation.
However, huge increases in specific programs have now been disclosed in an obscure budget chart entitled “Comparative Appropriation by Congressional Control FY 2023.” These NNSA programs are the tip of the spear in the United States’ $1.7 trillion nuclear weapons “modernization” program. It will rebuild every nuclear warhead in the planned stockpile with new military capabilities; design and manufacture new-design nuclear weapons as well; construct new production plants expected to be operational until the 2080’s; and procure at enormous taxpayers’ expense new missiles, subs and bombers to deliver these weapons of mass destruction. It is, in short, a program of nuclear weapons forever.
NukeWatch Lawsuit Settlement Speeds Up Cleanup at Los Alamos Lab
FOR IMMEDIATE RELEASE, March 23, 2022 | Contact: Jay Coghlan, 505.989.7342, [email protected], Scott Kovac, 505.989.7342, [email protected],
Santa Fe, NM – Today, Nuclear Watch New Mexico is announcing successful settlement of a lawsuit it brought against the Department of Energy (DOE) over its slow cleanup of the Los Alamos National Laboratory (LANL). The watchdogs’ lawsuit alleged violations of a 2005 Consent Order, which was a site-wide cleanup agreement between the New Mexico Environment Department (NMED) and DOE to address radioactive and toxic wastes at the Lab. NMED has since sued DOE to terminate a revised 2016 Consent Order issued under the Martinez Administration that is far weaker than the original 2005 Order.
After a six-year court battle, NukeWatch’s settlement agreement requires DOE to:
- Reestablish a surface water flow monitoring station near where the Los Alamos Canyon meets the Rio Grande. This is critical because the Canyon has long been a known pathway for plutonium contaminants to migrate as far as 20 miles south to Cochiti Lake, a popular recreational area. The Buckman Direct Diversion Project (BDDP), three miles south of the Canyon, supplies drinking water directly out of the river to the City and County of Santa Fe. The original monitoring station warned the BDDP to close its intake gates as a precaution during stormwater events and allowed characterization of the radioactive contaminants in the stormwater flows.” However, it was destroyed during a 2013 flood and DOE had refused to reinstall it ever since, despite repeated BDDP requests. Meanwhile, during that same period of time, funding doubled for LANL’s nuclear weapons research and production programs that caused the radioactive and toxic pollution to begin with.
NNSA Whitewashes LANL Performance, Hides Information from Taxpayers
FOR IMMEDIATE RELEASE, February 10, 2022 | Contact: Jay Coghlan, 505.989.7342, [email protected]
Santa Fe, NM – Today the National Nuclear Security Administration (NNSA) released cursory three-page summaries of its FY 2021 Performance Evaluation Reports (PERs) which grade contractor performance at its eight nuclear weapons sites. Out of six missions goals the NNSA gave the Los Alamos National Laboratory (LANL) two “Excellent” and four “Very Good,” thereby awarding 87% of the at-risk award fee of $26 million to Triad National Security, LLC, the Management and Operating Contractor. In all, including the fixed fee of $20.5 million, Triad will receive $46.7 million for its FY 2021 contractor performance.[1]
The NNSA is releasing only summaries of the Performance Evaluation Reports (“Performance Evaluation Summaries”), which provide scant information and essentially whitewash contractor performance. For context, the Department of Energy’s nuclear weapons and cleanup programs have been on the Government Accountability Office’s High Risk List for project and contractor mismanagement for 27 consecutive years. In 2012 Nuclear Watch New Mexico sued to obtain the full and complete Performance Evaluation Reports, after which NNSA caved in and immediately provided them. However, that unfortunately resulted in no legal settlement requiring annual releases of the full and complete PERs, and now the agency is back to suppressing information of contractor performance paid for by the American taxpayer.
Groups Fire Back at Feds’ Move to Dismiss Plutonium Pit Lawsuit
Federal agencies continue to reject a full review of the public safety and environmental risks of producing nuclear bomb cores at multiple DOE sites.
Jay Coghlan, director of Nuclear Watch New Mexico, commented, “The government has yet to explain to American taxpayers why it will spend more than $50 billion to build new plutonium pit bomb cores for new-design nuclear weapons when we already have thousands of existing pits proven to be reliable for a century or more. This has nothing to do with maintaining the safety and reliability of the existing stockpile and everything to do with building up a new nuclear arms race that will threaten the entire world.”
SRS WATCH / EIN PRESSWIRE October 26, 2021
AIKEN, SOUTH CAROLINA — Public interest groups shot back at the U.S. Department of Energy and the National Nuclear Security Administration’s attempt to suppress a lawsuit seeking a comprehensive environmental review of the agencies’ plans to produce large quantities of nuclear bomb cores, or plutonium pits, at DOE sites in New Mexico and South Carolina.
Expanded Plutonium “Pit” Bomb Production Rules Over Genuine Cleanup Los Alamos Lab Plans to Make Existing Nuclear Waste Dumps Permanent Without Eliminating Threat to Groundwater
The Department of Energy (DOE) has submitted a report to the New Mexico Environment Department (NMED) declaring its preferred plan to “cap and cover” radioactive and toxic wastes at one of the Los Alamos National Laboratory’s (LANL’s) oldest dumps. DOE’s $12 million cleanup-on-the-cheap plan for Material Disposal Area C will create a permanent nuclear waste dump above our regional groundwater. In contrast, DOE has asked Congress for one billion dollars for expanded plutonium “pit” bomb core production at LANL for fiscal year 2022 alone.
LANL used to falsely claim that groundwater contamination was impossible and even asked NMED for a waiver from even having to monitor for it. We now know that there is extensive groundwater contamination from hexavalent chromium (the carcinogen in the Erin Brockovich movie) and high explosives. Traces of plutonium have been detected 1,300 feet under Area C in regional groundwater monitoring wells. The dump also has a large toxic gaseous plume of industrial solvents known as volatile organic compounds (VOCs) which threatens nearby facilities.
New Mexico: Number One in Nuclear Weapons and Radioactive Wastes Near Last in Citizen and Child Well-Being
The goal of NNSA programs in New Mexico is to indefinitely extend the service lives of existing nuclear weapons while giving them new military capabilities. This will be followed by completely new nuclear weapons that cannot be tested given the global testing moratorium. Alternatively, it could prompt the U.S. back into nuclear weapons testing, which would have serious international proliferation implications. NNSA’s claimed rationale is “deterrence” which requires only a few hundred nuclear weapons. In reality the U.S. and Russia each have thousands of ready-to-launch weapons for nuclear war-fighting.
Lawsuit Filed Against Biden Administration Over Nuclear Bomb Core Production Plans
Federal agencies’ refusal to review cross-country expansion of plutonium pit production violates the National Environmental Policy Act and the Administrative Procedures Act, groups say.
AIKEN, S.C. – Today, a coalition of community and public interest groups filed a lawsuit against the U.S. Department of Energy (DOE) and the National Nuclear Security Administration (NNSA). This legal action is prompted by the agencies’ failure to take the “hard look” required by the National Environmental Policy Act at their plans to more than quadruple the production of plutonium pits and split their production between the Los Alamos National Laboratory in New Mexico and the Savannah River Site in South Carolina.
Following New Mexico Environment Department Lawsuit DOE Dramatically Increases Funding for Los Alamos Lab Cleanup
Santa Fe, NM – The Biden Administration has finally released budget details for Department of Energy (DOE) programs that clean up Cold War contamination and radioactive and toxic wastes. In January the New Mexico Environment Department sued DOE in order to terminate a 2016 “Consent Order” that subordinated cleanup at the Los Alamos National Laboratory (LANL) to the budget that DOE wants, which is increased nuclear weapons production. The Biden Administration has responded by increasing proposed cleanup funding at the Lab by 33% from $226 million in FY 2021 to $333.5 million proposed for FY 2022 (which begins October 1, 2021).
Biden Continues Trump’s Bloated Nuclear Weapons Budget
Will That Change in Future Years?
Santa Fe, NM – In a classic move that discouraged media coverage, the Department of Energy’s semi-autonomous National Nuclear Security Administration (NNSA) released its long delayed FY 2022 Congressional Budget Request around 7:30 pm EST Friday, May 28, at the very beginning of the long Memorial Day weekend.
Nuclear Watch New Mexico strongly opposed the 25% FY 2021 increase that the Trump Administration bequeathed to NNSA’s nuclear weapons programs. That massive increase was originally sold in testimony to Congress as essential to maintaining the nuclear deterrence but later revealed as necessary to cover NNSA cost overruns and blown schedules.[i]
RECENT NUCLEAR BUDGET GRAPHS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
Past Work Product (2020-2021)
Non-Governmental Organizations Demand Resumption of Los Alamos Nuclear Bomb Plant Public Information Meetings
The NGOs request that the semi-annual public meetings resume by early fall 2020, and the CMRR Project website be updated and maintained until the RLUOB reconfiguration and PF-4 upgrades are completed. All documents and presentations from the previous 13 public meetings must be reposted. The NGOs are also asking that the unilateral decision by the DOE/National Nuclear Security Administration (NNSA) to increase the amount of plutonium equivalent allowed in the RLUOB from 8.4 grams to 400 grams be reviewed by NMED.
Los Alamos Lab Suppresses Data on Negative Economic Impact on Surrounding Counties; Wealthy White Los Alamos County Asks for 3,000 Acres Seized from Hispanics and Native Americans
“This is yet another example of the racial disparity that exists in the wake of communities like Los Alamos, established under the protective umbrella of government sanctioned white privilege. When you take something by force and don’t pay for it, that’s called stealing. So why is land stolen by the US government from the original Hispanic and Native American owners not being given back to them?…As the national reckoning over racial injustice unfolds, let us not forget how Los Alamos Lab came to be and the insult to injury that giving away land stolen from others represents.”
— Chuck Montaño, Nuclear Watch NM Steering Committee member. Mr. Montaño, born and raised in Santa Fe, NM, worked at the Los Alamos National Laboratory for 32 years where he investigated allegations of fraud, waste and abuse.
WATCHDOG GROUPS FILE LEGAL PETITION WITH ENERGY DEPT: Allege Agency is Slow Walking “Record of Decision” Re: Plutonium Bomb Core Production to Prevent Judicial Review; Stage Set for Litigation on Expanded Production
“DOE and NNSA appear to be deliberately slow-walking the issuance of a formal Record of Decision on expanded plutonium pit production in an apparent effort to prevent the federal courts from reviewing the agencies’ failure to comply with the National Environmental Policy Act.”
COLLECTIVE COMMENTS: on the National Nuclear Security Administration’s (NNSA’s) Draft Supplement Analysis of the 2008 Site-Wide Environmental Impact Statement for the Continued Operation of Los Alamos National Laboratory (LANL) for Plutonium Operations
These comments were signed onto by over 100 individuals and organizations.
THANK YOU to all those who participated!
75TH ANNIVERSARY HIROSHIMA DAY ONLINE COMMEMORATION CALLING FOR THE ABOLITION OF NUCLEAR WEAPONS
August 6, 2020
"Jay Coghlan of Nukewatch.org on the history of the Los Alamos labs, where the bomb was designed and fabricated, and how it continues to play the leading role in the creation of most U.S. nuclear weapons since then."
[embeddoc url="https://nukewatch.org/wp-content/uploads/2020/05/plutonium-pit-production-fact-sheet.pdf" download="all" viewer="browser"]
PLUTONIUM PIT PRODUCTION WORKSHOP – NOVEMBER 19, 2019
RADIO INTERVIEW – SCOTT KOVAC & JON LIPSKY
Scott Kovac of Nuclear Watch New Mexico and Jon Lipsky, the FBI agent who led the 1989 raid investigating environmental crimes that shut down the Rocky Flats Nuclear Bomb Plant join Xubi to talk about Nuclear weapons, Nuclear clean up and Pit production plans at LANL.
RADIO INTERVIEW – JAY COGHLAN & JON LIPSKY
PIT Production at LANL with Nuclear Watch New Mexico’s Jay Coghlan and Workshop Speaker, Jon Lipsky
RADIO INTERVIEW – MARYLIA KELLEY, EXECUTIVE DIRECTOR, TRI-VALLEY CARES
Nuclear Watch NM’s Workshop on LANL & PIT Production with Marylia Kelley of Tri-Valley CARES
Pit Production Workshop: View the Presentations
Jon Lipsky, FBI agent that led the 1989 raid investigating environmental crimes that shut down the Rocky Flats bomb plant
Introduction by Jay Coghlan
Jay Coghlan, Executive Director, Nuclear Watch New Mexico, on plutonium pit production at LANL
Marylia Kelly, Executive Director, Tri-Valley CAREs (Livermore, CA) on the new nuclear arms race
https://www.facebook.com/NukeWatch.NM/videos/825812604488302/
Scott Kovac Nuclear Watch New Mexico, on LANL cleanup issues
Blog Posts
Nuclear Weapons Issues & The Accelerating Arms Race: December 2023
Nuclear weapons issues
Final conference by Senate and House Armed Services Committee deleted expansion of the Radiation Exposure Compensation Act that would have covered Trinity Test Downwinders, among others. In contrast, it authorized tens of billions for expanding nuclear weapons programs. So, it’s nothing for those harmed by nuclear weapons testing and production in New Mexico, but radical expansion of those programs that did harm them.
The FY 2024 Defense Authorization Act added money above Biden’s request for pit production at the Savannah River Site and the Sea-Launched Cruise Missile and its new nuclear warhead. The Biden Administration opposed the SLCM, but Congress authorized it anyway.
LANL SWEIS
The 2020 Supplement Analysis that we had robustly critiqued with comprehensive formal comments, which DOE/NNSA have ignored, contains analysis of pit production based solely off the 2008 SWEIS pit analysis. Our single biggest point in the 2020 SA comments was the need for a programmatic environmental impact statement on expanded plutonium pit production.
Homily and Statement by Archbishop Wester to the Parties to the Treaty on the Prohibition of Nuclear Weapons
On November 29, 2023, the 34th anniversary of the death of Dorothy Day, and in conjunction with the Second Meeting of the State Parties to the Treaty on the Prohibition of Nuclear Weapons, the Archbishop of Santa Fe John C. Wester gave a homily on nuclear disarmament at Our Church of the Savior near the United Nations. Dorothy Day was a life-long anti-nuclear weapons activist and is now being considered for canonization by the Catholic Church.
The Second Meeting of States Parties on the Prohibition of Nuclear Weapons
Since the invasion of Ukraine nearly two years ago, to the recent situation in Israel/Gaza, the risk of impending nuclear war has been a reality considered by many for the first time. As stated at a side event during the weeklong meeting of States Parties on the Prohibition of Nuclear Weapons (TPNW) held last week from November 27 to Decmber 1st, Hirotsugu Terasaki, Director General of Peace and Global Issues, Soka Gakkai International (SGI), warned that the wide-scale violence brought by these two events “continue to heighten the risk that nuclear weapons could actually be used.” This fear is made all the more tangible when considering also that earlier this month, the Putin announced Russia would be revoking its ratification of the Comprehensive Test Ban Treaty (CTBT), which Terasaki pointed out is a “serious setback for the cause of nuclear disarmament.”
As stated in the article, The Voices of Victims of Nuclear Weapons Testing, “these realities make convening the current Second Meeting of States Parties of the TPNW, which concludes December 1, all the more important and a crucial opportunity to revive momentum for nuclear disarmament and abolition.”
Nuclear Weapons Issues & The Accelerating Arms Race: November 2023
Nuclear weapons issues
New bomb: The Pentagon has announced a new nuclear bomb, the B61-13. The B61-12 is now in production and will be forward deployed in Europe. But it has a dial-a-yield that maxes out at 50 kilotons. The new B61-13 will max out at 360 kt to get at hardened deeply buried targets (both have limited earth-penetrating capabilities). At one time, production of the B61-12 at least potentially signified retirement of the 1.2 megaton surface burst B83 strategic bomb, but now production of the B61-13 will probably be relatively quick at the tail end of already scheduled B61-12 production.
See: https://www.defense.gov/News/Releases/Release/Article/3571660/department-of-defense-announces-pursuit-of-b61-gravity-bomb-variant/ and https://media.defense.gov/2023/Oct/27/2003329624/-1/-1/1/B61-13-FACT-SHEET.PDF
See excellent analysis by the Federation of American Scientists:
https://fas.org/publication/biden-administration-to-build-a-new-nuclear-bomb/
Strategic Posture Review: Commissioned by Congress,
“The Commission recommends that a strategy to address the two-nuclear-peer threat [Russia and China] environment be a prerequisite for developing U.S. nuclear arms control limits for the 2027-2035 timeframe. The Commission recommends that once a strategy and its related force requirements are established, the U.S. government determine whether and how nuclear arms control limits continue to enhance U.S. security…”
→
U.S. Strategic Posture Commission Ratchets Up Nuclear Arms Race
Today, America’s Strategic Posture, The Final Report was released by the Congressional Commission on the Strategic Posture of the United States. In its own words:
“The Congressional Commission on the Strategic Posture of the United States was established by the Fiscal Year (FY) 2022 National Defense Authorization Act (NDAA), and concludes that America’s defense strategy and strategic posture must change in order to properly defend its vital interests and improve strategic stability with China and Russia. Decisions need to be made now in order for the nation to be prepared to address the threats from these two nuclear-armed adversaries arising during the 2027-2035 timeframe. Moreover, these threats are such that the United States and its Allies and partners must be ready to deter and defeat both adversaries simultaneously.”
The United States has already embarked upon a $2 trillion “modernization” program that is a complete makeover of its nuclear forces. This program will rebuild every warhead in the planned future stockpile while giving them new military capabilities. It will also build new-design nuclear weapons and new missiles, subs and bombers to deliver them, plus new nuclear weapons production plants expected to be operational until the 2080’s.
Los Alamos Lab’s Future at a Crossroads: Cleanup or More Nuclear Weapons? NukeWatch Applauds NM State Rejection of Fake Cleanup
Santa Fe, NM – In an important win for genuine cleanup at the Los Alamos National Laboratory (LANL), the New Mexico Environment Department (NMED) has rejected the Lab’s plans for so-called cleanup through “cap and cover.” LANL’s plan would leave existing radioactive and toxic wastes uncharacterized and forever buried in unlined pits and trenches as a permanent threat to groundwater. At issue is remediation of the Lab’s “Material Disposal Area C” waste dump that has 7 pits and 108 shafts of radioactive and toxic wastes. Area C is located in the heart of nuclear weapons production at LANL, contiguous to the Lab’s main plutonium facility which is expanding production of plutonium “pit” bomb cores.
In a September 7, 2023 “Public Notice of Statement of Basis,” the Environment Department ruled:
“For maximum protection of human health and the environment and to ensure that the drinking water resource can be conservatively protected, NMED has determined that the selected [cleanup] remedy for MDA C must consist of waste excavation, characterization, and appropriate disposal of the buried waste… Excavation will ensure that the source of contamination at MDA C is removed…”
National Nuclear Security Administration: New Assessments of Major Projects from the Government Accountability Office
National Nuclear Security Administration: Assessments of Major Projects
The National Nuclear Security Administration plans to invest over $30 billion in its major projects to modernize the research and production infrastructure supporting the nation’s nuclear weapons stockpile. This is our first biennial assessment of NNSA’s major projects.
As of March 2023, NNSA’s major projects collectively exceeded their cost estimates by over $2 billion. They also surpassed their collective schedules by almost 10 years. Cost growth and schedule delays had multiple causes, such as lower levels of worker productivity than planned.
The Department of Energy has been on the Government Accountability Office’s “High Risk List” for project mismanagement since 1991. A January 2023 GAO report says it all: NNSA Does Not Have a Comprehensive Schedule or Cost Estimate for Pit Production Capability. Congress has made its ongoing concern over the lack of pit aging studies explicit in legislation. The FY 2021 Consolidated Appropriations Act enacted the following provision:
“Pit and Plutonium Aging.-There is concern with the apparent lack of focus on advancing knowledge regarding pit and plutonium aging since the JASONs conducted its first study in 2006. Given the future needs of the nation’s nuclear deterrent, a robust program of research and experimentation is needed. Therefore, NNSA is directed to develop a comprehensive, integrated ten-year research program for pit and plutonium aging that represents a consensus program among the national laboratories and federal sponsors. Such a plan shall include estimated cost of ongoing research, new or upgraded capability needs, and key near-, mid-, and long-range milestones. The plan shall be submitted to the Committees on Appropriations of both Houses of Congress not later than 180 days after enactment of this Act.”
As far as is publicly known no such plan has been submitted to Congress despite its statutory requirement. That said, a ten year plan to have plutonium pit aging studies is not sufficient to begin with when uncertainty over pit aging is being used as the rationale for an aggressive plutonium pit production program costing at least $60 billion over the next thirty years. The recent GAO report states, “…Six projects in the design phase are implementing significant changes that may increase their cost and schedule beyond NNSA’s preliminary estimates. These include a project to modify existing plutonium processing facilities at Los Alamos National Laboratory in New Mexico.”
Furthermore, the entire U.S. $2 Trillion “Modernization” plan includes new intercontinental ballistic missiles, new cruise missiles, heavy stealth bombers and
submarines, which entails rebuilding warheads with new military capabilities plus completely new-design nuclear weapons. This is not just for “deterrence” but instead for nuclear warfighting capabilities. No production of plutonium pits is scheduled to maintain the safety and reliability of the existing nuclear stockpile; instead it is for new-design nuclear weapons. The US is inspiring a new arms race with nuclear weapons forever.
→
Photos from Japan Pilgrimage of Peace
Image Credit: The Archdiocese of Seattle Website (Daily Digests), Leslie M. Radigan & Archdiocese of Santa Fe Official Facebook Page, and Jay Coghlan of NukeWatch New Mexico.
“We are here to see what we can do to advocate for peace and share the gospel,” said AB Etienne. We are here “to invite people to realize that we can have peace by growing relationships with our neighbors and communities. We need to do that as people before we can do so as nations.”
Three Huge New Facilities Rebuild U.S. Nuclear Weapons Production Capacity
Modern nuclear weapons are comprised of three general types of components: plutonium pit primaries, uranium/lithium secondaries that are triggered by the primaries, and the 1,000’s of non-nuclear components that create deliverable weapons of mass destruction (fuzes, radar, bomb cases, etc.). The U.S. is aggressively pursuing major new production facilities for all three types. At the Los Alamos National Laboratory (LANL) in New Mexico, the “Chemistry and Metallurgy Research Replacement (CMRR) Project” will be the keystone to a revived plutonium manufacturing complex. The proposed “Uranium Processing Facility” (UPF) at the Y-12 Site in Oak Ridge, Tennessee, will be the future production plant for warhead secondaries. A new “Kansas City Plant” (KCP) in Missouri for nonnuclear components production is slated for groundbreaking in August 2010. Each of these three major new production facilities is expected to operate for the next half-century, in sharp contradiction to the declared national and global security goal of a nuclear weapons-free world.
A Compromised START
Nuclear Watch New Mexico is a staunch supporter of arms control treaties, particularly since they can be confidence building steps toward the long term goal of creating the nuclear weapons-free world articulated by President Obama.
However, we fear that arms control treaties will be turned on their heads to become in effect armament treaties for the American nuclear weapons complex. We think our fears are now concretely realized by the Obama Administration’s “modernization plan” attached to yesterday’s submittal of New START to the Senate for ratification.
As you probably know, the Obama plan is to increase funding for the NNSA’s nuclear weapons programs from $6.4 billion in FY10 to $9 billion by FY 2018, which is a 76% increase above the Cold War annual average of $5.1 billion. We think that is obviously a serious step backwards on the road to a nuclear weapons-free world, especially when the labs seem intent on introducing new military capabilities to existing types of U.S. nuclear weapons.
There have been calls for unconditional public support of New START. Yet current political realities are that New START will be heavily conditioned by both the Obama Administration and the Senate to include the revitalization of the U.S. nuclear weapons complex.
In concrete terms, this means dramatically increased funding for huge new production plants for plutonium, uranium and nonnuclear components, respectively the Los Alamos CMRR-Nuclear Facility, the Y-12 Uranium Processing Facility and the new Kansas City Plant.
It also means future aggressive Life Extension Programs that will substantially modify the nuclear explosives package, a serious threshold that we have not yet crossed (and which could effectively recreate the Reliable Replacement Warheads that NNSA sought but Congress rejected, but by another name). We also need to remain aware of the failure to ratify the Comprehensive Test Ban Treaty in 1999, but which nevertheless profited the nuclear weapons labs and complex by some $100 billion to date under the Stockpile Stewardship Program to compensate for the loss of underground full-scale testing.
We don’t question that appeals for public support of New START should go forward. But as NGOs we are also entrusted with public responsibility to provide a fuller picture.
We argue that certain conditions for New START ratification, such as increased funding for new production facilities, LEPs and stockpile work, should be publicly explained, and lead to qualified instead of unconditional support of New START ratification.
Obama Bails Out Arms Reduction Treaty by Dramatically Increasing Nuclear Weapons Budgets
Santa Fe, NM – Yesterday President Obama submitted the new bilateral Strategic Arms Reduction Treaty (START) with Russia to the Senate for ratification. At the same time he submitted a modernization plan required by Congress that “includes investments of $80 billion to sustain and modernize the [U.S.] nuclear weapons complex over the next decade.” Given that two-thirds of the Senate is required for treaty ratifications a large political fight was always expected over a second attempt at ratifying the previously rejected Comprehensive Test Ban Treaty (CTBT). However, last December all 40 Republican senators plus one independent wrote to President Obama demanding modernization of both the stockpile and complex as a condition for New START ratification. Meanwhile, the prospects for ratification of the CTBT (first proposed by Prime Minister Nehru of India in 1954) look increasingly dim.
In response to Republican demands, the Obama Administration plans to increase funding for the nuclear weapons research and production programs of the National Nuclear Security Administration (NNSA) by more than 40% from $6.4 billion in FY 2010 to $9 billion by 2018. In turn, $9 billion is 43% above the average annual cost of $5.1 billion during the Cold War for analogous Department of Energy nuclear weapons programs.
The one-page unclassified summary of the modernization plan declares
U.S. nuclear weapons will undergo extensive life extension programs in the coming years to ensure their safety, security and effectiveness. Maintaining a credible nuclear deterrent requires that the United States operates a modern physical infrastructure and sustain a highly capable workforce.
That may seem intuitively logical on the face of it, but NNSA and the nuclear weapons labs are subtly changing the frame of debate to favor their own interests. Independent scientists have repeatedly found that the nuclear weapons stockpile is safe and reliable and can be so maintained by existing life extension programs. Past NNSA budget requests repeatedly invoke a “reliable” stockpile, but its FY 2011 request is full of references to an “effective” stockpile.
NNSA Administrator Tom D’Agostino claimed at a recent presentation to international delegations at the United Nations for the NonProliferation Treaty Review Conference that the U.S. is meeting its disarmament obligations in good faith. At the same time, he repeatedly stated the U.S.’s need to maintain an “effective” stockpile. When asked what effective meant he replied it meant having confidence in the nuclear weapons stockpile underpinned by the right mix of infrastructure and people.
In order to extract increased funding, NNSA and the nuclear weapons labs are trying to shift the debate over maintaining the stockpile from technical arguments over warhead safety and reliability to subjective arguments over maintaining an exorbitant research and production complex and workforce. This will not only cost enormous sums of money, which is what the labs seek, but will also perversely undermine confidence in the stockpile because of planned changes, including new military capabilities, that will be made to existing, previously tested weapons. Giving the nuclear weapons labs a blank check contradicts Obama’s declared national security goal of a future nuclear weapons-free world. Instead, he should be redirecting the labs into dramatically increased nonproliferation programs, cleanup, and meeting today’s national security threats of nuclear terrorism, energy dependence and climate change.
The one-page unclassified summary of the Obama modernization plan for the stockpile and nuclear weapons complex.
The average annual cost of $5.1 billion during the Cold War for DOE defense programs is derived from Atomic Audit, The Costs and Consequences of U.S. Nuclear Weapons Since 1940, Steven Schwartz, et.al., Brooking Institution Press, DC, 1998, Table A-2, p. 561 (adjusted for inflation).
NNSA Administrator Tom D’Agostino’s presentation to the NPT Review Conference
For more background, please see “Labs Seek “Stockpile Modernization” Through Test Ban Ratification – “Updating” of Treaty “Safeguards” to Protect Nuclear Weapons Budgets”
Of particular interest are cited Los Alamos Lab viewgraphs that state “Technically: there is little difference between a ratified CTBT, and the current testing moratorium” and “There are several ways to sustain capabilities… Get more money.” The point is that the nuclear weapons labs are fully aware that treaty ratifications are an opportunity for them to secure more funding, as they did in the build up to the 1999 ratification process that rejected the CTBT.
A Tale of Two Cross-Sections
At the recent LANL Hazardous Waste Permit Hearings, the public was presented with two cross-sections of the current understanding of the geology under the Lab’s largest nuclear waste disposal area, Tech Area 54. These cross sections are important because the NM Environment Department, with public input, will soon have to decide the final disposition of the over 800,000 cubic yards of radioactive and hazardous waste buried there. The options range from leaving the waste in place with some sort of cover to exhuming the waste.
The geology under the site is very complicated and includes layers of lava flows, ash falls, and old stream beds. The waste is buried in unlined pits, shafts and trenches and is perched 800 – 1000 feet above our sole-source aquifer. Some of the more soluble contaminants, such as tritium, perchlorate, explosives, and chromium have already made their way to the aquifer from other parts of the Lab. The cross-sections are needed to understand the contaminant pathways from the dumps to the aquifer.
First, the Lab’s version – (click on image for larger picture)
The MDAs, or Material Disposal Areas or dumps, are across the top. MDA G is the largest by far. The PM-#s are wells where drinking water is drawn. The R-#s are characterization and contaminant sampling wells. The elevation is on each side. The top of the regional aquifer is the horizontal blue line near 5800′. There are some perched aquifers shown, too. The one question is a new structure that the Lab is calling a “dike” discovered by well R-22.
The NM Environment Department’s Version – (click on image for larger picture)
The Environment Department’s version gives a different interpretation of the fractures that could be pathways to the aquifer. It has many question marks, including the “vent” and the perched aquifers.
We appreciate the two versions. With so many unknowns, with so much waste, and with such a potential negative impact to our aquifer, the most protective course would be to remove the waste.
New Nuclear Facility – An Attempt to Divide and Conquer
Coghlan Report from NPT Rev Con
I’m in New York City for the first week of the Non-Proliferation Treaty Review Conference that opened today (Monday May 3). Yesterday global citizens marched from Times Square to the United Nations demanding nuclear weapons abolition. I was very moved to see ~10,000 people from ~25 countries pour into this little park across from the UN, where NukeWatch and some 40 other organizations had information waiting for them.
My main gig here is about the 3 proposed huge nuclear weapons production plants the U.S. is planning to spend some $10 billion on over the next decade. They are the “Nuclear Facility” that will keystone an expanded plutonium complex at Los Alamos; the Uranium Processing Facility (UPF) at the Y-12 Site near Oak Ridge, TN; and the new Kansas City Plant (KCP). These facilities will expand production capability up to 80 new warheads per year. For more, see New US Production Facilities.
When I talked to folks (half from other countries) here for the Conference about these new facilities, most invariably say, “But, but, buuuuuuuut… what about Obama?” Their eyes get big when I tell them Obama doubled FY 2011 funding for the Nuclear Facility and UPF (KCP is privately financed, hence outside the federal budget). I guess they heard the part loud and clear from Obama in Prague about a nuclear weapons-free world, but not so much when he said probably not in my lifetime.
If left just up to him, I suppose that would be the case, given that these production facilities are expected to operate until 2065. But at least there are ~10,000 global citizens here in NYC pushing for sooner than that. We’ll see what concrete results the NPT Review Conference brings.
The CMRR-Nuclear Facility Is All About Expanding Plutonium Pit Production Capacity
In response to a question by Senator Jeff Bingaman at a Senate Armed Services Committee hearing on April 14, 2010, NNSA Administrator Tom D’Agostino stated “We will not make pits in the CMR replacement facility. We’ll make them in the existing older facility.”
That is narrowly true, but highly misleading. In fact, the Chemistry and Metallurgy Research Replacement (CMRR) Project is all about expanding plutonium pit production capabilities at the Los Alamos National Laboratory from the presently sanctioned level of 20 per year to up to 80. [Plutonium pits are the fissile “triggers” that initiate fusion in today’s modern thermonuclear weapons.] Yes, PF-4, LANL’s existing plutonium facility, performs the actual physical manufacturing of pits. However, that production cannot take place without “analytical chemistry” (AC) and “materials characterization” (MC) before production to make sure that the plutonium is weapons-grade, and extensive AC and MC sampling during production for stringent “war reserve” quality control.
It’s a mistake to get hung up on different facilities, when an integrated plutonium complex for expanded pit production capability is being created through proposed construction of the CMRR’s “Nuclear Facility” and upgrades to PF-4. It’s silly to think of them as separate facilities just because they’ll be under two different roofs. PF-4 and the Nuclear Facility will be next door to each other, linked by underground tunnel, with highly integrated operations and much exchange of special nuclear materials between them (especially given the Nuclear Facility’s planned vault for up to six metric tons of “special nuclear materials”).
The CMRR Nuclear Facility is being specifically sized to support pit production capability of 50 – 80 pits per year. An internal NNSA study of planned alternatives advocated for a “baseline version (22,500 ft2 of Pu lab space) of the CMRR-NF…, resulting in a production capacity of 50-80 ppy” [pits per year]. Independent Business Case Analysis of Consolidation Options for the Defense Programs SNM and Weapons Programs, TechSource, Inc, December 2007, p. 5-3, parentheses in the original. This “Business Case” is one of NNSA’s hundreds of reference documents for its 2008 Complex Transformation Supplemental Programmatic Environmental Impact Statement. [To conveniently find it, use “TechSource 2007a.”]
That 22,500 ft2 of Pu lab space is exactly what is being designed for the Nuclear Facility now. “CMRR Project Nuclear Facility… Baseline under development …. 22,500 Net Square Feet Lab Space.” CMRR Project Update, LANL, Public Meeting, Los Alamos, New Mexico March 3, 2010, 7th viewgraph.
Los Alamos National Security, LLC, the for-profit corporation that runs Los Alamos, has already been paid for installing additional equipment in PF-4 that in conjunction with the future CMRR-Nuclear Facility will expand plutonium pit production capability to up to 80 pits per year. “Build Six New W88 Pits & Install Equipment in FY 2008 to Increase Pit Capacity to 80 Pits Per Year by the Operational Date of a CMRR-Nuclear Facility – Available Fee $1,079,915 – Awarded Fee $1,079,915.” FY 2008 Performance Evaluation Report for the Los Alamos National Security, LLC’s Management and Operation of the Los Alamos National Laboratory, NNSA, p. 9.
NNSA echoes this in its FY 2010 Supplemental Stockpile Stewardship Plan. Under Key Recent Accomplishments the agency boasts of “New equipment installed as scheduled for gradual capacity increases to 80 pits per year potential by scheduled operational date for Chemistry and Metallurgy Research Replacement (CMRR) Nuclear Facility.” Table 1-1, NNSA/Office of Defense Programs, FY 2010 – 2014 Supplement to the Stockpile Stewardship Plan, p. 14.
In sum, suggestions or representations by NNSA and LANL that the $4.5 billion CMRR Project is not about pit production are at best half-truths. Its massive proposed “Nuclear Facility” is, in fact, all about expanded pit production capability.
What the New Definition of “New” Is
On March 16 I met with a senior congressional staff members. I raised the issue of what is “new.” I specifically pointed to an earth-penetrating variant of the B61 gravity bomb (the B61-11) that was rushed to the stockpile in 1997, likely because of a perceived threat of an alleged Libyan hardened underground bioweapons facility. B61’s are believed to have selectable yields, ranging from .3 kilotons to 300 kilotons.
The destructive effects of earth-penetrating weapons (even if they penetrate 10 meters or less) rise exponentially due to shock “coupling” with geologic strata. The B61-11, with a yield of up to 300kt, was designed to and did replace the monster 9-megaton surface-burst B53. Earth-penetration is indisputably a new military capability for the B61 bomb. But because the B61-11 has the same military mission as the B53 to destroy hardened deeply buried targets (never mind the extreme differences in yields, while arguably lower yield weapons are more “usable”), this senior HASC staffer asserted that the B61-11 was not a “new” nuclear weapon.
This is not an isolated case. I then went on to raise the current example of the sub-launched W76 that is now being refurbished in an ongoing Life Extension Program (LEP). It is being endowed with a new fuze that gives it selectable heights of burst and a more accurately targetable reentry vehicle. So it not only can hit a smaller target, but the lower the altitude of the burst, the more it can hold hardened bunkers or underground facilities at risk. Pete Nanos, then head of Naval Strategic Systems (and later controversial LANL Director), wrote in 1997 that the refurbished 100kt W76-1Mk4 would be transformed into a hard target killer, one that is a “counterforce” weapon against military assets rather a “countervalue” (“city-buster”) weapon of deterrence.
But because refurbished W76s could replace the hard target killer mission of 450kt. sub-launched W88s, this HASC staffer again maintained that it was not a “new” weapon. Never mind that there are less than an estimated 400 W88s, while the Bush Administration planned to run some 2,000 W76’s through LEP’s, which would radically alter the strategic equation (we don’t yet know how many Obama will refurbish).
To add to my case, now Under Secretary for Arms Control and Nonproliferation Ellen Tauscher (former congresswoman for the CA district that sites Livermore Lab) has also indicated that if a modified existing U.S. nuclear weapon, no matter how profoundly changed, assumes the mission of another existing nuclear weapon, then it is not a “new” nuclear weapon.
Needless to say the specific missions of U.S. nuclear weapons are highly classified. But the bottom line is that our stockpile is enough to kill this planet many times over. The U.S. Government appears poised to run many existing nuclear weapons through extreme makeovers (including plutonium pit triggers) that clearly give them new military capabilities. But because there is little theoretical end to what nuclear weapons can blow up (on this planet anyway) our government will continue to deny that these heavily modified existing nuclear weapons are “new” nuclear weapons as long as they assume the missions of other existing nuclear weapons.
In other words, they think they can do whatever they damn well please, and still not call it a new nuclear weapon.
LANL Installing Equipment for Manufacuring 80 Plutonium Pits Per Year
The question arose at the Alliance for Nuclear Accountability meeting this week over the potential level of future pit production at LANL and the role that the Chemistry and Metallurgy Research Replacement Project – Nuclear Facility will play in it.
See the below from the
FY10-14 Supplement to the Stockpile Stewardship Plan, p. 14, under “Recent Key Accomplishments”: (emphasis added)
“More than six new W88 plutonium pits
manufactured. New equipment installed as
scheduled for gradual capacity increases to
80 pits per year potential by scheduled
operational date for Chemistry and Metallurgy
Research Replacement (CMRR) Nuclear Facility.”
This whole document is worthwhile reading (3.7MB).
Senator Bingaman Supports More Nuclear Plants
In the January/February issue of Mother Jones magazine Mariah Blake writes that New Mexico’s Senator Bingaman aided by Lisa Murkowski (R, Alaska) has introduced legislation likely to be included in the coming climate bill that would create a Clean Energy Development Agency (CEDA) within DOE with authority to extend a ‘virtually unlimited number of loan guarantees—without congressional review—to utilities to build nuclear plants.’ Blake goes on to say that both Bingaman and Mirkowski are ‘top recipients of the nuclear industry’s campaign largesse.’ Interested utilities would have to pay an unspecified fee to get a loan guarantee but, if the historical default rate from the 1st generation of US nuclear power folly is a guide, these fees will not come close to covering defaults. Blake continues: “According to the Union of Concerned Scientists, if 100 new plants are built, as key Republican lawmakers have called for, the price of bad loans could total at least $360 billion—and that’s assuming zero cost overruns.”
So if fellow New Mexicans do not want MORE federal subsidies wasted in nuclear power plant construction they should send a ‘boo and hiss’ email to Senator Bingaman. I had not realized how completely Jeff had donned the pro-nuke mantle of Pete Domenici—and I deplore it!
RECENT FACT SHEETS
RECENT FORMAL COMMENTS
Past NukeWatch Events
March 10, 2020 – Deadline for Comments on Protecting NEPA
The Council on Environmental Quality (CEQ) is proposing to update its regulations for implementing the procedural provisions of the National Environmental Policy Act (NEPA). Sumbit comments HERE by March 10 on how and why the National Environmental Policy Act is our country’s most fundamental environmental law. It is important for the public, Congress and federal agencies to understand that NEPA has provided benefits to government decision-making processes.
Public Event – Rocky Flats Disaster: Red Light for SRS Plutonium Bomb Plant
Speakers: Dr. LeRoy Moore and Patricia Mellen, Esq, who is trying to get grand jury documents about the FBI raid released on behalf of the Rocky Mountain Peace and Justice Center and other groups.
Read LeRoy’s new book: “Plutonium & People Don’t Mix: Rocky Flats: Colorado’s Defunct Nuclear Bomb Factory.”
View article by LeRoy: Rocky Flats refuge opening disregards evidence of risk
Come meet NukeWatch staff.
Ask questions!
6:00 – 8:00 pm
Tuesday Nov. 19
City of Mud Gallery
1114 A Hickox St, Santa Fe,
New Mexico 87505
(straight across from Tune-Up Cafe)
How to Avoid a Nuclear Apocalypse
Join Women’s Action for New Directions (WAND) for a panel with leading experts in nuclear nonproliferation & disarmament
https://schedule.sxsw.com/
→
January 24, 2019
Watch the announcement HERE
Read the 2019 Doomsday Clock Statement.
Past Work Product (2019-)
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
2019
November 26, 2019 Press Release November 24, 2019 Press Release November 19, 2019 Plutonium Pit Production Workshop Presenters:
August 12, 2019 NEPA Comments NukeWatch’s 22-page formal comments on expanded plutonium pit production Until NNSA fully complies with the National Environmental Policy Act through the preparation of a programmatic environmental impact statement on expanded plutonium pit production, Nuclear Watch believes that any irreversible or irretrievable commitment of resources to either the expansion of pit production at the Los Alamos Lab or to the repurposing of the MOX Facility at the Savannah River Site is unlawful. Read/Download the Full Document HERE July 25, 2019 NEPA Comments Scoping comments on NNSA draft EIS for plutonium pit production at the Savannah River Site THE NEED FOR A PROGRAMMATIC ENVIRONMENTAL IMPACT STATEMENT: This is our first and primary concern, that NNSA must first complete a programmatic environmental impact statement (PEIS) on its nation-wide plans for plutonium pit production, in advance of the Savannah River Site-specific environmental impact statement. To get right to the point, we argue that the SRS EIS process should go no further than this scoping period and should resume only after a completed formal Record of Decision for a new or supplemental PEIS. Read/Download the Full Document HERE July 9, 2019 Plutonium Pit Production Fact Sheet Expanding Nuclear Pit Production: The Facts and What You Can Do The Facts Read/Download the Full Document HERE June 10, 2019 News Release In a victory for transparency and legal compliance by the government, the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) today published a “Notice of Intent” in the Federal Register to complete environmental reviews on its controversial proposal to expand plutonium “pit” production for new and refurbished nuclear weapons. [embeddoc url="https://nukewatch.org/wp-content/uploads/2019/06/SRS-plutonium-bomb-plant6-14-19.pptx" download="all" viewer="google"] Read/Download the Full News Release HERE June 4, 2019 Press Release On behalf of three public interest organizations - Nuclear Watch New Mexico, Tri-Valley Communities Against a Radioactive Environment and Savannah River Site Watch – attorneys for the law firm of Meyer Glitzenstein & Eubanks and the Natural Resources Defense Council recently sent a 16-page letter to Lisa Gordon-Hagerty, head of the National Nuclear Security Administration (NNSA). The detailed letter warns the nuclear agency to not proceed with aggressive plans to expand plutonium pit production without first meeting its legal requirements for timely public review and comment under the National Environmental Policy Act. Read/Download the Full Press Release HERE May 31, 2019 Press Release Last Wednesday, facility operations personnel entered a service room and noticed a leak emanating from a valve on the radioactive liquid waste (RLW) system. Upon subsequent visual inspection by a radiological control technician, RLUOB engineers believe that this valve, and 6 similar valves, may be constructed of carbon steel. The RLW system handles radioactive liquid waste streams from chemistry operations that include nitric and hydrochloric acids—carbon steel valves would be incompatible with these solutions. The suspect valves are also in contact with stainless steel piping, which would create another corrosion mechanism. RLUOB management plans to drain the affected piping sections and develop a work package to replace all of the suspect valves. They will also confirm the valve materials and if shown to be incorrect, investigate the cause of this failure in the design, procurement, and installation processes. The valves were installed in 2013 as part of a modification to add straining and sampling capabilities that were not in the included in the original design. [Please note that DNFSB reports are posted a few weeks later than dated.] This immediately raises two crucial issues: 1) the National Nuclear Security Administration’s (NNSA’s) plans for expanded plutonium pit production; and 2) the current attempt by the Department of Energy to restrict Safety Board access to its nuclear weapons facilities. Read/Download the Full Press Release HERE April 26, 2019 Consent Orders Comparison On March 1, 2005, after arduous negotiations and threats of litigation, the New Mexico Environment Department (NMED), Department of Energy (DOE), and Los Alamos National Laboratory (LANL) entered into a Consent Order specifying the schedule for investigation and cleanup of the Lab’s hundreds of contaminated sites. This Consent Order (CO) was LANL’s agreement to fence-to-fence cleanup of Cold War legacy wastes, which NMED began to enforce. Read/Download the Full Comparison HERE March 25, 2019 Press Release More than 25 years after the end of the Cold War, all eight established nuclear weapons powers are “modernizing” their stockpiles. Talks have broken down with North Korea, the new nuclear weapons power. Nuclear-armed India and Pakistan narrowly averted war last month. Russian President Vladmir Putin made new nuclear threats in response to Trump’s announced withdrawal from the Intermediate-Range Nuclear Forces Treaty. This could lead to hair-trigger missile emplacements in the heart of Europe and block extension of the New Strategic Arms Reduction Treaty with Russia. If so, the world will be without any nuclear arms control at all for the first time since 1972. Meanwhile, the U.S. criticizes non-weapons states for signing a nuclear weapons ban treaty, despite the fact there have long been treaties completely banning chemical and biological weapons of mass destruction that the U.S. seeks to enforce. The pending international NonProliferation Treaty (NPT) Preparatory Committee conference at the United Nations is widely expected to collapse in failure because of the nuclear weapons powers’ failure to enter into serious negotiations leading to nuclear disarmament. The NPT’s Article VI mandate for those negotiations has been in effect since 1970, when the Treaty was signed by 189 countries (more than any other treaty). Read/Download the Full Press Release HERE March 26, 2019 NukeWatch Budget Compilation Nuclear Watch New Mexico — Department of Energy FY 2020 Nuclear Weapons Budget Request |
2018
November 16, 2018 Plutonium Pit Production Fact Sheet Plutonium pits are the radioactive cores or “triggers” of nuclear weapons. Their production has always been a chokepoint of resumed industrial-scale U.S. nuclear weapons production ever since a 1989 FBI raid investigating environmental crimes shut down the Rocky Flats Plant near Denver. In 1997 the mission of plutonium pit production was officially transferred to its birthplace, the Los Alamos National Laboratory (LANL) in northern New Mexico, but officially capped at not more than 20 pits per year. However, in 2015 Congress required expanded pit production by 2030 whether or not the existing nuclear weapons stockpile actually needs it. This will support new military capabilities for nuclear weapons and their potential use. Read/Download the full fact sheet pdf HERE October 31, 2018 Nuclear Watch New Mexico, Savannah River Site Watch, and Tri-Valley CAREs sent a letter of demand to the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) to inform the government that its plan to quadruple the production rate of plutonium bomb cores is out of compliance with the National Environmental Policy Act (NEPA). NNSA’s premature plan to quadruple the production rate of plutonium bomb cores (“pits”), the heart of all US nuclear weapons, is out of compliance with requisite environmental law, the groups argue, as NNSA has failed to undertake a legally-mandated programmatic review and hold required public hearings. View/Download the entire press release HERE NukeWatch Comments, September 27, 2018 Nuclear Watch New Mexico is submitted formal comments to express in the strongest possible terms our opposition to DOE Order 140.1 Interface with the Defense Nuclear Facilities Safety Board. We find that the Department of Energy’s (DOE’s) attempt to restrict and suppress DNFSB access is very misguided, arrogant, and likely illegal in that it acts contrary to the Board’s enabling legislation. June 8, 2018 Press Release New Contractors Selected For Expanded Nuclear Weapons Production at Los Alamos Santa Fe, NM. Today the Department of Energy's National Nuclear Security Administration (NNSA) announced its choice for the new management and operating contract for the Los Alamos National Laboratory (LANL).The new contractor, Triad National Security, LLC, is a limited liability company consisting of the Battelle Memorial Institute, the University of California and Texas A&M University. All three are non-profits, and it is unclear how this will affect New Mexico gross receipts taxes. Battelle claims to be the world's largest non-profit technology research and development organization, and manages a number of labs including the Lawrence Livermore and Idaho National Laboratories. Texas A&M was founded in 1876 as the state's first public institution of higher learning and has the largest nuclear engineering program in the country. DOE Secretary Rick Perry is an avid A&M alumnus. May 31, 2018 Press Release Santa Fe, NM & Columbia, SC - "Two key U.S. Department of Energy documents on future production of plutonium "pits" for nuclear weapons, not previously released to the public, fail to justify new and upgraded production facilities at both the Los Alamos National Laboratory (LANL) in New Mexico and the Savannah River Site (SRS) in South Carolina." May 15, 2018 Fact Sheet May 10, 2018 Press Release What's Not in NNSA's Plutonium Pit Production Decision
- NNSA did not mention that up to 15,000 "excess" pits are already stored at the Pantex Plant near Amarillo, TX, with up to another 5,000 in "strategic reserve." The agency did not explain why new production is needed given that immense inventory of already existing plutonium pits. (In 2006 independent experts found that pits last a least a century. Plutonium pits in the existing stockpile now average around 40 years old.) May 2, 2018 Press Release "NNSA should begin nation-wide review of plutonium pit production, why it's needed, and what it will cost the American taxpayer in financial, safety and environmental risks. These are all things that the public should know." -Jay Coghlan, Director, Nuclear Watch New Mexico. April 26, 2018 NukeWatch Comments LANL Rad Lab: Formal Comments Under Nat'l Environmental Policy Act Against raising plutonium limit at LANL Rad Lab View/download Nuclear Watch comments as submitted Excerpt:
- NNSA is planning a 10-fold increase in plutonium at the LANL Rad Lab with a view to ramping up the production of plutonium pits for new nuclear weapons. March 26, 2018 Press Release United States To Begin Construction Of New Nuclear Bomb Plant The National Nuclear Security Administration (NNSA) announced on Friday, March 23, that it was authorizing the start of construction of the Uranium Processing Facility (UPF) and two sub-projects at the Y-12 National Security Complex in Oak Ridge, Tennessee. The UPF is a facility dedicated solely to the manufacture of thermonuclear cores for US nuclear bombs and warheads.
Jay Coghlan of NukeWatch points out that "This project already has a long history, and it is instructive. In 2013, DOE announced it was 85% finished with the UPF design when it ran into the 'space/fit' issue- and more than a half-billion taxpayer dollars were just written off. In private business, that kind of thing gets you fired. In DOE's world of contractors running amok, they not only didn't get fired, not one Congressional hearing was held and the UPF budget went up the next year!" - See full press release for all the details (PDF) March 1, 2018 Press Release The Regional Coalition of LANL Communities: Benefits for the Select Few Santa Fe, NM- According to media reports, Andrea Romero, Executive Director of the Regional Coalition of LANL Communities, is accused of charging some $2,200 dollars of unallowable travel costs, such as alcohol and baseball tickets, while lobbying in Washington, DC for additional funding for the Los Alamos National Laboratory (LANL). She in turn accused the nonprofit group Northern New Mexico Protects of political motivations in revealing these questionable expenses. Romero is running in the Democrat Party primary against incumbent state Rep. Carl Trujillo for Santa Fe County's 46th district in the state House of Representatives. For all the details, see full press release PDF February 28, 2018 Press Release Santa Fe, NM. On December 17, 2017, the Department of Energy (DOE) awarded a separate $1.4 billion contract for cleanup at the Los Alamos National Laboratory (LANL) to Newport News Nuclear BWXT-Los Alamos, LLC (also known as "N3B"). This award followed a DOE decision to pull cleanup from LANL's prime contractor, Los Alamos National Security, LLC (LANS), after it sent an improperly prepared radioactive waste drum that ruptured underground at the Waste Isolation Pilot Plant (WIPP). That incident contaminated 21 workers and closed WIPP for nearly three years, costing taxpayers at least $1.5 billion to reopen. (See all the details in the full press release) February 26, 2018 Press Release Detailed NNSA Budget Documents Accelerates Nuclear Weapons Arms Race Santa Fe, NM. Late Friday February 23, the Trump Administration released the detailed FY 2019 budget for the National Nuclear Security Administration (NNSA), the semi-autonomous nuclear weapons agency within the federal Department of Energy. Overall, NNSA is receiving a $2.2 billion boost to $15.1 billion, a 17% increase above the FY 2018 enacted level. Of that, a full $11 billion is for the budget category [Nuclear] "Weapons Activities", 18% above the FY 2018 level. Of concern to the American taxpayer, DOE and NNSA nuclear weapons programs have been on the congressional Government Accountability Office's High Risk List for project mismanagement, fraud, waste and abuse since its inception in 1990... (See all the details in the full press release) February 22, 2018 Press Release Santa Fe, NM. Today the National Nuclear Security Administration announced an Environmental Assessment to increase the amount of plutonium used in the Radiological Laboratory Utility and Office Building (aka the "Rad Lab") at the Los Alamos National Laboratory from 38.6 grams of plutonium-239 equivalent to 400 grams. This 10-fold increase is significant because it will dramatically expand materials characterization and analytical chemistry capabilities in the Rad Lab in support of expanded plutonium pit production for future nuclear weapons designs. It also re-categorizes the Rad Lab from a "radiological facility" to a "Hazard Category-3" nuclear facility. View/Download full press release February 12, 2018 Press Release Trump's Budget Dramatically Increases Nuclear Weapons Work Santa Fe, NM In keeping with the Trump Administration's recent controversial Nuclear Posture Review, today's just released FY 2019 federal budget dramatically ramps up nuclear weapons research and production. January 12, 2018 Press Release Draft Nuclear Posture Review Degrades National Security Yesterday evening the Huffington Post posted a leaked draft of the Trump Administration's Nuclear Posture Review (NPR). This review is the federal government's highest unclassified nuclear weapons policy document, and the first since the Obama Administration's April 2010 NPR. 2017 |
2017
December 22, 2017 Press Release New Mexico Environment Department Surrendered to DOE Extortion Santa Fe, NM. The New Mexico State Auditor Office recently questioned whether two settlements between the New Mexico Environment Department and the Department of Energy were in the best interests of New Mexico. That Office noted: (View/download full press release) December 20, 2017 Press Release Los Alamos Hires New Contractor - Starts Cleanup On the Cheap Santa Fe, NM- Today the Department of Energy (DOE) announced the award of the new Los Alamos National Laboratory legacy cleanup contract to Newport News Nuclear BWXT-Los Alamos, LLC. The $1.39 billion contract is for ten years, which works out to $139 million per year... View/download the full press release Public Presentation, December 2, 2017 October 31, 2017 Press Release Today, in Washington, DC, the Congressional Budget Office released its new report, "Approaches for Managing the Costs of U.S. Nuclear Forces, 2017 to 2046". The Congressional Budget Office estimates that the most recent detailed plans for nuclear forces, which were incorporated in the Obama Administration's 2017 budget request, would cost $1.2 trillion in 2017 dollars over the 2017-2046 period: more than $800 billion to operate and sustain (that is, incrementally upgrade) nuclear forces and about $400 billion to modernize them.... Driving this astronomical expense is the fact that instead of maintaining just the few hundred warheads needed for the publicly claimed policy of "deterrence," thousands of warheads are being refurbished and improved to fight a potential nuclear war. This is the little known but explicit policy of the U.S. government! October 27, 2017 Press Release Santa Fe, NM. On the evening of Wednesday October 25, the Santa Fe City Council passed a resolution requesting that the New Mexico Environment Department strengthen the revised Los Alamos National Labs cleanup order to call for additional characterization of legacy nuclear wastes, increased cleanup funding, and significant additional safety training. The resolution also called for the suspension of any planned expanded plutonium pit production until safety issues are resolved. (view/download full press release) October 6, 2017 Press Release Santa Fe, NM. Nuclear Watch New Mexico strongly applauds the awarding of the Nobel Peace Prize to the International Campaign to Abolish Nuclear Weapons (disclosure: NukeWatch is one of ICAN's ~400 member groups around the world). This award is especially apt because the peoples of the world are now living at the highest risk for nuclear war since the middle 1980's, when during President Reagan's military buildup the Soviet Union became convinced that the United States might launch a pre-emptive nuclear first strike. Today, we not only have Trump's threats to "totally destroy" North Korea and Kim Jong-un's counter threats, but also renewed Russian fears of a US preemptive nuclear attack... Generally unknown to the American taxpayer, our government has quietly tripled the lethality of the US nuclear weapons stockpile..." (view/download complete press release) NukeWatch fact sheet, September 26, 2017 The National Nuclear Security Administration's own documents have explicitly stated that expanded pit production would have no significant positive effect on job creation and the regional economy of northern New Mexico. Nuclear Watch argues that expanded plutonium pit production could actually have negative effect if it blocks other economic alternatives such as comprehensive cleanup, which could be the real job producer. Moreover, given LANL's poor safety and environmental record, expanded plutonium pit production could have a seriously negative economic impact on northern New Mexico in the event of any major accidents. September 15, 2017 Press Release Santa Fe, NM. The Los Alamos National Laboratory (LANL) has detected far more hexavalent chromium (Cr) contamination than previously estimated in the "sole source" regional groundwater aquifer that serves Los Alamos, Santa Fe and the Espanola Basin. Sampling in July from a new well meant to inject treated groundwater back into the aquifer detected chromium contamination five times greater than the New Mexico groundwater standard of 50 micrograms per liter (ug/L). View/download the full press release September 11, 2017 Press Release Talking Points: The 2016 LANL Cleanup Consent Order Should Be Rescinded The 2005 LANL Cleanup Consent Order was all about the enforceable schedules. It required DOE and LANL to investigate, characterize, and clean up hazardous and mixed radioactive contaminants from 70 years of nuclear weapons research and production. It stipulated a detailed compliance schedule that the Lab was required to meet. Under Gov. Martinez, NMED Secretary Ryan Flynn granted more than 150 compliance milestone extensions at the Lab's request, effectively eviscerating it. View/download the complete talking points July 20, 2017 Press Release Washington, DC Today, the Oak Ridge Environmental Peace Alliance (OREPA), Nuclear Watch New Mexico, and the Natural Resources Defense Council filed a federal lawsuit to stop construction of the problem-plagued Uranium Processing Facility (UPF) until legally required environmental review is completed. The UPF, located at the National Nuclear Security Administration's (NNSA's) Y-12 production plant near Oak Ridge, TN, is slated to produce new thermonuclear weapons components until the year 2080. The UPF is the tip of the spear for the U.S.'s planned one trillion dollar-plus make over of its nuclear weapons arsenal, delivery systems, and production plants. View/download the full press release June 19, 2017 Press Release Some Background on Plutonium Pit Production at the Los Alamos Lab Santa Fe, NM -The Washington Post has published the first in a series of articles on nuclear safety lapses in plutonium pit production at the Los Alamos Lab. Plutonium pits are the fissile cores of nuclear weapons that when imploded initiate the thermonuclear detonation of modern weapons. By the way, did you know? Plutonium facilities at LANL are- in principle- designed to withstand a serious earthquake of a degree expected to occur only once every 10,000 years. The last serious earthquake near the Lab is believed to have occurred 11,500 years ago. View/download the full press release ANA Report 2017: Accountability Audit May 19, 2017 Press Release SA Preview of Trump's Budget: More Nuclear Bombs and Plutonium Pit Production Santa Fe, NM. "The proposed level of funding for the National Nuclear Security Administration's (NNSA)'s Total Weapons Activities is $10.2 billion, a full billion above what was requested for FY 2017. In March, Trump's "skinny budget" stated NNSA's funding priorities as 'moving toward a responsive nuclear infrastructure', and 'advancing the existing warhead life extension programs'. Read the full press release for all the details. March 28, 2017 ANA workshop at UN Ban Treaty Conference Ban Treaty Conference: Alliance for Nuclear Accountability Panel Discussion March 28, 2017, UN, NYC:
March 2017 Fact Sheet Plutonium Pit Production at LANL (Updated March 2017) February 23, 2017 Press Release Costs Jump in Nuclear Weapons vs. Cleanup; Nuclear Weapons Winning over Environmental Protection Santa Fe, NM. America is at a crossroads, having to choose between an unnecessarily large, exorbitant, nuclear weapons stockpile, and cleanup that would protect the environment and water resources for future generations. Expanded nuclear weapons research and production, which will cause yet more contamination, is winning. Read the full press release for all the details. January 5, 2017 Press Release The National Nuclear Security Administration (NNSA) has publicly released its fiscal year 2016 Performance Evaluation Report (PER) for Los Alamos National Security, LLC (LANS), the for-profit contractor that runs the Los Alamos Lab. The Performance Evaluation Report is NNSA's annual report card on contractor performance, and overall the agency awarded LANS $59 million in profit out of a possible $65 million. The grade was 85% for the incentive part of the award. In 2012 Nuclear Watch New Mexico successfully sued NNSA to ensure that the Performance Evaluation Reports detailing taxpayers funds paid to nuclear weapons contractors are publicly available. In 2016 the NNSA decided to put the LANL management contract out for competitive bid, but granted LANS a contract extension until the end of September 2018. |
Media appearances including radio interviews are listed on the internal Media page
See the NukeWatch Channel at YouTube for our extensive playlists of key videos.
See the Nukewatch Twitter feed
See the Nukewatch Tumblr site
WatchBlog Posts:
Over 200 posts published since 2009. See archives at the WatchBlog
Earlier Work Product items are archived here