Court Rules U.S. Nuclear Weapons Production Plan Violates Federal Law
FOR IMMEDIATE RELEASE, October 3, 2024
Media Contacts:
Ben Cunningham, Esquire, SCELP, 843-527-0078, [email protected]
Tom Clements, Savannah River Site Watch, 803-834-3084, [email protected]
Jay Coghlan, Nuclear Watch New Mexico, 505-989-7342, [email protected]
Scott Yundt, Tri-Valley CAREs, 925-443-7148, [email protected]
Queen Quet, Gullah/Geechee Sea Island Coalition, 843-838-1171, [email protected]
AIKEN, S.C. — On September 30, United States District Court Judge Mary Geiger Lewis ruled that the United States Department of Energy (“DOE”) and its semi-autonomous nuclear weapons agency, the National Nuclear Security Administration (“NNSA”), violated the National Environmental Policy Act (“NEPA”) by failing to properly consider alternatives before proceeding with their plan to produce plutonium pits, a critical component of nuclear weapons, at the Los Alamos National Laboratory (“LANL”) in New Mexico and, for the first time ever, at the Savannah River Site (“SRS”) in South Carolina.
The Court found that the plan’s purpose had fundamentally changed from NNSA’s earlier analyses which had not considered simultaneous pit production at two sites. These changes necessitated a reevaluation of alternatives, including site alternatives, which Defendants failed to undertake prior to moving forward while spending tens of billions of taxpayers’ dollars. Therefore, the Court entered judgment in favor of Plaintiffs, the nonprofit public interest groups Savannah River Site Watch, Nuclear Water New Mexico and Tri-Valley Communities Against a Radioactive Environment (CAREs); the Gullah/Geechee Sea Island Coalition; and Tom Clements as an individual plaintiff.
As a result of this ruling, the Defendants are required to newly assess pit production at a nation-wide programmatic level which will mean undertaking a thorough analysis of the impacts of pit production at DOE sites throughout the United States, including radioactive waste generation and disposal. Under the National Environmental Policy Act (NEPA), this will provide the opportunity for public scrutiny of and formal comment on their assessments.
High Detections of Plutonium in Los Alamos Neighborhood – As We Enter a New Nuclear Arms Race the Last One is Still Not Cleaned Up
FOR IMMEDIATE RELEASE, August 15, 2024
Dr. Michael Ketterer – 928.853.7188 | Email
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – In April Nuclear Watch New Mexico released a map of plutonium contamination based on Lab data. Today, Dr. Michael Ketterer, Professor Emeritus of Chemistry and Biochemistry, Northern Arizona University, is releasing alarmingly high results from samples taken from a popular walking trail in the Los Alamos Town Site, including detections of some of the earliest plutonium produced by humankind.
On July 2 and 17 Dr. Ketterer, with the assistance of Nuclear Watch New Mexico, collected water, soil and plant samples from Acid Canyon in the Los Alamos Town Site and soil and plant samples in Los Alamos Canyon at the Totavi gas station downstream from the Lab. The samples were prepared and analyzed by mass spectrometry at Northern Arizona University to measure concentrations of plutonium, and to ascertain its sources in the environment.
NNSA Delays Urgent Research on Plutonium “Pit” Aging While Spending Tens of Billions on Nuclear Weapons Bomb Core Production
FOR IMMEDIATE RELEASE, April 17, 2024
Tom Clements, SRS Watch – 803.240.7268 | Email
Scott Yundt, TVC – 415.990.2070 | Email
Jay Coghlan – 505.989.7342 | Email
Nearly three years after filing a Freedom of Information Act request, the public interest group Savannah River Site Watch has finally received the National Nuclear Security Administration’s (NNSA’s) congressionally-required “Research Program Plan for Plutonium and Pit Aging.” However, the document is 40% blacked out, including references and acronyms. Plutonium “pits” are the radioactive cores of all U.S. nuclear weapons. The NNSA claims that potential aging effects are justification for a ~$60 billion program to expand production. However, the Plan fails to show that aging is a current problem. To the contrary, it demonstrates that NNSA is delaying urgently needed updated plutonium pit aging research.
In 2006 independent scientific experts known as the JASONs concluded that plutonium pits last at least 85 years without specifying an end date [i] (the average pit age is now around 40 years). A 2012 follow-on study by the Lawrence Livermore nuclear weapons lab concluded:
“This continuing work shows that no unexpected aging issues are appearing in plutonium that has been accelerated to an equivalent of ~ 150 years of age. The results of this work are consistent with, and further reinforce, the Department of Energy Record of Decision to pursue a limited pit manufacturing capability in existing and planned facilities at Los Alamos instead of constructing a new, very large pit manufacturing facility…” [ii]
Since then NNSA has reversed itself. In 2018 the agency decided to pursue the simultaneous production of at least 30 pits per year at the Los Alamos National Laboratory (LANL) in northern New Mexico and at least 50 pits per year at the Savannah River Site (SRS) in South Carolina. Upgrades to plutonium facilities at LANL are slated to cost $8 billion over the next 5 years. The redundant Savannah River Plutonium Processing Facility in South Carolina will cost up to $25 billion, making it the second most expensive building in human history.
NNSA’s Nuclear Weapons Budget Takes Huge Jump
Arms Race Accelerates with MIRVed Warheads
Los Alamos Lab Cleanup Cut
FOR IMMEDIATE RELEASE, March 11, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – Ironically the day after the film Oppenheimer was awarded multiple Oscars, the Department of Energy’s semi-autonomous National Nuclear Security Administration (NNSA) asked Congress for its biggest nuclear weapons budget ever. NNSA’s FY 2025 request for “Total Weapons Activities” is $19.8 billion, $700 million above what Congress recently enacted for FY 2024. It is also a full billion dollars above what President Biden asked for last year, which Congress then added to and will likely do so again.
The Biden Administration states that the $19.8 billion will be used to:
“[P]rioritize implementation of the 2022 National Defense Strategy and Nuclear Posture Review by modernizing the Nation’s nuclear deterrent to keep the American people safe. The Budget supports a safe, secure, reliable, and effective nuclear stockpile and a resilient, responsive nuclear security enterprise necessary to protect the U.S. homeland and allies from growing international threats.” whitehouse.gov/wp-content/uploads/2024/03/budget_fy2025.pdf, page 75.
The 2022 National Defense Strategy and Nuclear Posture Review for the first time posited two nuclear “near peers”, i.e. Russia and China, that need to be simultaneously “deterred.” This hinted at a potentially large nuclear buildup which this budget may now be implementing. That claimed need to deter two nuclear near peers was explicitly taken a step beyond just deterrence in an October 2023 report from the Strategic Posture Commission. It declared:
“Decisions need to be made now in order for the nation to be prepared to address the threats from these two nuclear-armed adversaries arising during the 2027-2035 timeframe. Moreover, these threats are such that the United States and its Allies and partners must be ready to deter and defeat both adversaries simultaneously.” ida.org/research-and-publications/publications/all/a/am/americas-strategic-posture, page vii (bolded emphasis added)
NNSA Suppresses How Taxpayers Money Is Spent
FOR IMMEDIATE RELEASE, January 19, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – The National Nuclear Security Administration (NNSA) has just released cursory two or three page summaries of contractors’ performance paid for by the American taxpayer. For the just ended fiscal year 2023, NNSA gave nothing less than grades of “Excellent” or “Very Good” in six broad mission goals for its major contractors. This is despite the constant cost overruns and schedule delays that are the rule, not the exception, in the nation-wide nuclear weapons complex. NNSA and its parent Department of Energy have been on the Government Accountability Office’s “High Risk List” for project mismanagement ever since GAO started that List in 1991.
A current example is the Uranium Processing Facility (UPF) at the Y-12 Plant near Oak Ridge, Tennessee, originally estimated in 2011 to cost $1.4 to $3.5 billion. After costs started going through the roof, NNSA and Senator Lamar Alexander (R.-TN), then-chair of Senate Energy and Water Appropriations, swore that UPF would never go over $6.5 billion. But even after eliminating non-nuclear weapons production missions and a formal decision to continue operations at two old, unsafe buildings slated for replacement, the Uranium Processing Facility is now estimated to cost $8.5 billion. However, even that is not the final price, as NNSA is still to “rebaseline” UPF costs at some unspecified date.
2023
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT FACT SHEETS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT PRESS RELEASES
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT NUCLEAR BUDGET GRAPHS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
Past Work Product (2020-2021)
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
75TH ANNIVERSARY HIROSHIMA DAY ONLINE COMMEMORATION CALLING FOR THE ABOLITION OF NUCLEAR WEAPONS
August 6, 2020
"Jay Coghlan of Nukewatch.org on the history of the Los Alamos labs, where the bomb was designed and fabricated, and how it continues to play the leading role in the creation of most U.S. nuclear weapons since then."
[embeddoc url="https://nukewatch.org/wp-content/uploads/2020/05/plutonium-pit-production-fact-sheet.pdf" download="all" viewer="browser"]
PLUTONIUM PIT PRODUCTION WORKSHOP – NOVEMBER 19, 2019
RADIO INTERVIEW – SCOTT KOVAC & JON LIPSKY
Scott Kovac of Nuclear Watch New Mexico and Jon Lipsky, the FBI agent who led the 1989 raid investigating environmental crimes that shut down the Rocky Flats Nuclear Bomb Plant join Xubi to talk about Nuclear weapons, Nuclear clean up and Pit production plans at LANL.
RADIO INTERVIEW – JAY COGHLAN & JON LIPSKY
PIT Production at LANL with Nuclear Watch New Mexico’s Jay Coghlan and Workshop Speaker, Jon Lipsky
RADIO INTERVIEW – MARYLIA KELLEY, EXECUTIVE DIRECTOR, TRI-VALLEY CARES
Nuclear Watch NM’s Workshop on LANL & PIT Production with Marylia Kelley of Tri-Valley CARES
Pit Production Workshop: View the Presentations
Jon Lipsky, FBI agent that led the 1989 raid investigating environmental crimes that shut down the Rocky Flats bomb plant
Introduction by Jay Coghlan
Jay Coghlan, Executive Director, Nuclear Watch New Mexico, on plutonium pit production at LANL
Marylia Kelly, Executive Director, Tri-Valley CAREs (Livermore, CA) on the new nuclear arms race
https://www.facebook.com/NukeWatch.NM/videos/825812604488302/
Scott Kovac Nuclear Watch New Mexico, on LANL cleanup issues
Blog Posts
LANL Proposes Satellite “Campus” in Santa Fe as Part of Expanded Production of Plutonium Nuclear Weapons Triggers
Santa Fe, NM – Today, the Santa Fe New Mexican newspaper reported:
“Santa Fe city leaders asked for developers’ ideas on what to do with the city-owned midtown campus…The National Nuclear Security Administration [NNSA], which administers the Los Alamos National Laboratory management and operating contract, submitted a master developer proposal to build an open-campus environment with administrative offices, sustainable green spaces, engineering space, light manufacturing, training facilities and research and development…
[A NNSA spokesperson said] “LANL is undergoing unprecedented growth and expects to hire more than 1,000 new personnel annually for the next several years. Having a new campus — midway between New Mexico’s two national laboratories [LANL and Sandia]— to house professional staff, scientists, and engineers in partnership with the city of Santa Fe — would be very beneficial.” ”
LANL’s growing jobs are primarily for expanded production of plutonium pits (the radioactive triggers of nuclear weapons) which helps to fuel the new global arms race. Over the last decade the Santa Fe City Council has passed three different resolutions against expanded plutonium pit production. Seventy percent (and growing) of LANL’s ~$2.6 billion annual budget is for core nuclear weapons research and production programs, while the remainder directly or indirectly supports those programs. In contrast, LANL’s renewable energy budget is .007% of its nuclear weapons budget and the Lab has zero dedicated funding to fight climate change. Moreover, LANL claims that its cleanup is more than half complete, intentionally omitting that it plans to leave ~150,000 cubic meters of toxic and radioactive wastes permanently buried uphill from the Rio Grande and above our common groundwater aquifer.
Just this last Sunday Pope Francis called for the abolition of nuclear weapons while in Japan paying homage to the victims of the Hiroshima and Nagasaki bombings. Those atomic bombs were designed and produced at the Los Alamos Lab.
The City of Santa Fe’s official name is the “La Villa Real de la Santa Fe de San Francisco de Asís” (“The Royal Town of the Holy Faith of Saint Francis of Assisi”), in honor of the beloved saint who preached peace and environmental protection and from whom the present Pope draws his name. It would be supremely ironic if the City of Santa Fe hosted a satellite campus for a massive institution that spends 2 billion dollars (and counting) every year on nuclear weapons of mass destruction.
Jay Coghlan, director of Nuclear Watch New Mexico, commented, “Mayor Webber and the Santa Fe City Council surely know that the institutionalized presence of a nuclear weapons production laboratory in our city would generate a tremendous amount of controversy, a controversy they could well do without. The leaders of the City of Santa Fe should nix LANL’s proposal for a satellite campus in our town as a nonstarter and an affront to St. Francis de Assisi, the saint of peace.”
# # #
The Santa Fe New Mexican article is available at
Pope Frances Calls for Nuclear Weapons Abolition – – Santa Fe Catholic Archdiocese Likely Has Largest Presence of Nuclear Weapons in the World
FOR IMMEDIATE RELEASE, November 24, 2019
Santa Fe, NM – Today, Pope Francis called for the global abolition of nuclear weapons while paying homage to the victims of the bombings of Hiroshima and Nagasaki. Those two cities were both destroyed by atomic weapons designed and produced by the Los Alamos National Laboratory, located in northern New Mexico’s Santa Fe Catholic Archdiocese.
The Holy Father declared:
“With deep conviction I wish once more to declare that the use of atomic energy for purposes of war is today, more than ever, a crime not only against the dignity of human beings but against any possible future for our common home. The use of atomic energy for purposes of war is immoral, just as the possessing of nuclear weapons is immoral, as I already said two years ago. We will be judged on this. Future generations will rise to condemn our failure if we spoke of peace but did not act to bring it about among the peoples of the earth. How can we speak of peace even as we build terrifying new weapons of war?”
Two of the U.S.’ three nuclear weapons laboratories, the Los Alamos and Sandia National Laboratories, are located within the Santa Fe Catholic Archdiocese. Together the two labs spend $4 billion per year on core nuclear weapons design, testing and production programs. In addition, up to 2,500 nuclear weapons are estimated to be held in strategic reserve at the Kirtland Underground Munitions Maintenance and Storage Complex, less than two miles south of the Albuquerque International Airport. That complex is probably the largest repository of intact nuclear weapons in the country and perhaps the world. →
LANL Busted For Losing Control of Controlled Substances
In a recent report, the Department Of Energy’s Office of Inspector General (IG) found issues with the way Los Alamos National Laboratory (LANL) keeps track of controlled substances such as cocaine, fentanyl, and methamphetamine. The IG found that LANL staff had not managed controlled substances in accordance with applicable Federal laws and regulations.
The IG also found that LANL staff had mislabeled procurement records of these drugs, kept inaccurate inventories, and retained controlled substances well beyond the conclusion of experiments. The IG determined that Los Alamos did not have appropriate “processes, procedures, or controls in place to monitor, track, account for, and dispose of controlled substances.”
Help Stop Plans to “Modernize” WIPP
The Waste Isolation Pilot Plant (WIPP), located outside Carlsbad, NM. is the nation’s only geologic repository for defense-generated transuranic waste. The Department of Energy (DOE) is accepting comments on its 2019-2024 “Strategic Plan”, which should be focused on closing WIPP. But the Plan focuses on extending WIPP’s lifetime to 2050 and beyond. WIPP’s disposal phase was extended until 2024 (in 2010), and the last expected year of final closure of the WIPP facility (i.e., date of final closure certification) was to be 2034. There was always a 10-year period for final closure after the disposal operations ceased.
But, instead, the WIPP Strategic Plan is stocked full of new projects that will extend WIPP’s life another 25 years at least. Yet, WIPP officials don’t mention how or when they plan to modify the State Permit with the new proposed date. DOE’s own waste-handling inefficiencies and mistakes have caused this delay that the people of New Mexico are now paying for by having WIPP open longer than planned. We are asking everyone to oppose DOE’s “WIPP Forever” plans by sending in comments. See below.
Help Stop The New Strategic Plan That Would Double WIPP’s Lifespan
DOE Moves Forward With Unneeded New Shaft at WIPP
Originally billed as a replacement exhaust shaft to help WIPP recover from the 2014 exploding drum event that shut down WIPP for three years, a proposed new shaft is now designed to increase WIPP’s capacity. WIPP officials have repeatedly stated that after a new filter building is complete, WIPP will have returned to its pre-2014 capacity without the new shaft. The $75 million new fifth shaft would increase the mining and waste handling capacity by 25% at any given time.
One would think that increasing the annual ability to emplace waste at WIPP would help keep the repository on track to stop receiving waste by its original date of 2024. But along with the annual increased mining and disposal capacity, DOE has also released a Strategic Plan to extend WIPP’s waste disposal deadline to 2052.
Watchdogs Issue Second Demand for Nation-Wide Environmental Review of Expanded Plutonium Pit Production
Today, lawyers for the Natural Resources Defense Council, Nuclear Watch New Mexico, Savannah River Site Watch and Tri-Valley Communities Against a Radioactive Environment sent a second letter to Department of Energy (DOE) Secretary Rick Perry and Lisa Gordon-Hagerty, the head of the semi-autonomous National Nuclear Security Administration (NNSA). The letter demands a nation-wide programmatic environmental impact statement for the agencies’ proposed expanded production of plutonium pits, the fissile cores or “triggers” of nuclear weapons. Invoking the National Environmental Policy Act (NEPA), the letter concludes:
“…we advise the agencies that timely compliance with NEPA is the best means for the agencies to keep these [expanded plutonium pit production] projects on track, as a failure to rigorously comply with NEPA may necessitate litigation, including if necessary motions for injunctive relief, all of which would likely increase the expense of DOE’s and NNSA’s proposed actions and extend their timelines further. Accordingly, we strongly encourage DOE and NNSA to come into compliance with NEPA by preparing a new or supplemental PEIS for its proposals regarding plutonium pit production, and to do so immediately. If the agencies continue on their current trajectory, we will have no choice but to evaluate all our options to enforce compliance with federal environmental laws.”
As background, on May 10, 2018, the Departments of Defense and Energy jointly announced that plutonium pit production would be expanded from the currently sanctioned level of 20 pits per year at the Los Alamos National Laboratory (LANL) in northern New Mexico to at least 30 pits per year, plus redundant production of at least 50 pits per year at the Savannah River Site (SRS) in South Carolina, which would be a completely new mission there.
Lack Of Safety And Health Priorities Continue To Plague Los Alamos Beryllium Program
A new assessment finds that Department of Energy (DOE) is not conducting effective oversight of the Los Alamos National Laboratory (LANL) beryllium program, or of safety and health programs in general. In addition, DOE is not maintaining sufficient technical capability and knowledge of site and contractor activities to make informed decisions about hazards and risks. DOE indicated the lack of sufficient safety and health resources has presented a challenge to achieving effective oversight in this area.
The U.S. should carefully and prudently maintain its nuclear weapons stockpile
Defense News reports that “Nuclear gravity bomb and warhead upgrades face new delays” because of new components used in so-called Life Extension Programs (LEPs) to prolong the service lives of existing nuclear weapons. These programs also give existing nuclear weapons new military capabilities. For example, see How US nuclear force modernization is undermining strategic stability: The burst-height compensating super-fuze
The point of this blog is to raise the question of whether these Life Extension Programs really enhance U.S. national security while maintaining the safety and reliability of the nuclear weapons stockpile. In fact, perhaps the crux issue is prudent and conservative maintenance of the stockpile versus increasingly aggressive LEPs.
Please Help Support NukeWatch
Dear Friends of Nuclear Watch New Mexico:
The Los Alamos and Sandia Labs are the tip of the spear for a one-trillion dollar “modernization” program that will completely rebuild every type of warhead in the nuclear stockpile while giving them new military capabilities. This so-called modernization program will also rebuild the production side of the Department of Energy’s nuclear weapons complex, including the proposal to quadruple production of plutonium pit bomb cores at the Los Alamos National Laboratory (LANL). This so-called modernization will be at enormous cost to the taxpayer and our disappearing middle class, robbing citizens of better schools, highways, hospitals, etc.
Join In Giving Tuesday
Join In Giving Tuesday
We have two days for getting deals – Black Friday and Cyber Monday. On #GivingTuesday, we have a day for giving back. Together, people are creating a new ritual for our annual calendar. #GivingTuesday is the opening day of the giving season.
Founded by the team in the Belfer Center for Innovation & Social Impact at 92nd Street Y, #GivingTuesday is a global giving movement that has been built by individuals, families, organizations, businesses and communities in all 50 states and in countries around the world. This year, #GivingTuesday falls on November 27. #GivingTuesday harnesses the collective power of a unique blend of partners to transform how people think about, talk about, and participate in the giving season. It can inspire people to take collective action to improve their communities, give back in better, smarter ways to the charities and causes they believe in, and help create a better world. #GivingTuesday demonstrates how every act of generosity counts, and that they mean even more when we give together.
Belen passes resolution opposing nuclear waste transportation
Belen passes resolution opposing nuclear waste transportation
NISG (Nuclear Issues Study Group) worked to get a resolution opposing the transportation of High Level Radioactive Waste in front of the City of Belen. The Belen City Council passed the resolution on Nov. 19th! It was 3 votes yes and 1 abstention. Belen is the 18th City or county or chapter house to pass it in New Mexico and Texas.
Read more about it here
Santa Fe County passed a similar resolution – A Resolution in the Interest of Protecting Our Lives, Land and Water From Radioactive Waste Risks.
Read more about it here
LANL Ships Waste Offsite Illegally, Again and Again
LANL Ships Waste Offsite Illegally, Again and Again
Posted by Scott Kovac Nov 14, 2018
New Mexico Environment Department (NMED) issued a Notice of Violation (NOV) to LANL for several problems. The first problem was that the Lab sent a drum to a disposal company offsite that was improperly labeled. It should have been labeled “flammable liquid, corrosive.” The Lab also mislabeled two containers by failing to note that they had lead inside. LANL also sent a container with flammable and toxic liquids with the incorrect container number and label on it. These violations occurred in 2015. The NOV reports several other shipping manifest discrepancies in 2016 and 2017. NMED is happy with the Lab just correcting the manifests. These were mistakes by the old contractor, Los Alamos National Security (LANS).
Possibly more serious violations occurred under DOE’s watch in 2017 and 2018 when LANS failed to characterize waste before shipping it to local landfills, including the Santa Fe landfill.
Citizens Oppose Plans For New Mexico Nuclear Waste Dump
Citizens Oppose New Mexico Nuke Dump
The Nuclear Waste Policy Act of 2018, HR 3053, known as the Shimkus Bill, has passed the House on its way to the Senate.
It calls for restarting the failed Yucca Mountain Project in Nevada, and establishing a system of Consolidated Interim Storage (CIS) sites for radioactive waste around the country until Yucca is operational.
First on the list of possible ‘temporary’ CIS dumps is a site proposed by Holtec International and the local Eddy-Lea Alliance just outside Hobbs, New Mexico. Its just over the border from Andrews, Co., Texas – where another high level nuke waste dump is also proposed.
Proponents tout it as an economic boon. Opponents see as it a public health and environmental disaster.
Planned to eventually hold more metric tons of waste than Yucca itself will be designed for, the Hobbs site could well become America’s de facto national dump site, if Yucca never gets built.
At a recent series of Nuclear Regulatory Commission community meetings on the proposed site, opposition was strong from many of New Mexico and Texas public sectors.
A press conference by local citizens laid out their views.
“We Don’t Want It!” Halt Holtec campaign continues. Opposition to proposed nuke dump is strong and growing.
Principles for Safe Management and Geological Isolation of Irradiated Nuclear Fuel
Summary: The environmental risks posed by irradiated fuel are extreme: As observed by the U.S. Court of Appeals, it has “the capacity to outlast human civilization as we know it and the potential to devastate public health and the environment.” Nuclear Energy Inst., Inc. v. Envtl. Prot. Agency, 373 F.3d 1251 (D.C. Cir. 2004).If irradiated fuel is dispersed into the environment, its radionuclides are sufficiently toxic to cause irreparable contamination of large areas of land and entire river and lake systems and coastal ecosystems.
The risk of nuclear weapons proliferation posed by irradiated fuel is also significant. Each metric ton of spent fuel typically contains more than one Nagasaki-bomb equivalent of plutonium and, as of 2016, well over 70,000 metric tons had already be been created in the United States by the commercial nuclear power reactors. Spent fuel, storage and/or disposal may pose a risk of theft if it is stored or disposed of in a manner that would allow access in a few hundred years when the fission product radiation barrier would have declined to low levels.
Federal District Court Allows Lawsuit to Proceed Against DOE/LANS Potential Penalties Exceed $300,000,000
For Immediate Release
New Mexico Environmental Law Center
Nuclear Watch New Mexico – Santa Fe, NM
A United States District Court judge has ruled that a lawsuit filed by Nuclear Watch New Mexico (NukeWatch) can move forward. The lawsuit is based on thirteen (13) violations of corrective actions Los Alamos National Security, LLC (LANS) and the Department of Energy (DOE) failed to complete under a 2005 Consent Order governing cleanup that the New Mexico Environment Department (NMED) fought for under former Governor Bill Richardson.
Fines for failure to complete the corrective tasks are $37,000 per violation per day. Violations for failing to complete the tasks started as early as June 2014 and now total well over $300 million.
The judge in allowing the lawsuit on civil penalties to move forward stated that DOE/LANS had failed to show in their legal and factual analysis that violations were unlikely to recur.
Jon Block, representing NukeWatch as a staff attorney at the New Mexico Environmental Law Center, said “We are gratified that the Court is allowing the lawsuit on civil penalties to move forward.”
In 2002, the NMED determined that decades of contamination at Los Alamos National Laboratory constituted an “imminent and substantial endangerment to health and the environment” and sought to compel cleanup at the Lab. DOE/LANS counter-sued, and in 2005 the parties agreed to a Consent Order specifying that DOE/LANS would characterize the extent and nature of the contamination, assess alternatives for effective cleanup of the contamination, and implement cleanup. Gov. Martinez came into office in 2011, after which DOE/LANS compliance with the Consent Order effectively stopped.
NukeWatch filed its original complaint in May 2016, followed by an amended complaint in July 2016. That was in response to a June 2016 announcement by NMED and DOE/LANS that they had entered into a new Consent Order that rendered the 2005 Consent Order invalid.
The judge did grant DOE/LANS and NMED’s motions to dismiss that part of NukeWatch’s complaint asking for declaratory and injunctive relief (in general seeking to have the 2016 Consent Order declared invalid). However, the judge specifically noted that the revised 2016 Consent Order replaced enforceable goals in the 2005 Order with unenforceable goals.
Jay Coghlan, NukeWatch director, commented “Susana Martinez’ administration shamefully gave away the store to the Los Alamos Lab, forgiving hundreds of millions of dollars in potential penalties for clear violations of an enforceable cleanup order, at the very time when New Mexico was facing a serious budget crisis. We are very pleased that the issue of penalties can now go forward in court, which should bring some accountability toward achieving comprehensive Lab cleanup that would produce hundreds of high-paying jobs.”
See NukeWatch’s Amended Complaint here
See Judge Judith Herrera’s decision here
Contacts:
Jay Coghlan: Nuclear Watch New Mexico
989.7342
Jon Block, Staff Attorney: New Mexico Environmental Law Center
505.989.9022
New Contractors Selected For Expanded Nuclear Weapons Production at Los Alamos
Santa Fe, NM – Today the Department of Energy’s National Nuclear Security Administration (NNSA) announced its choice for the new management and operating contract for the Los Alamos National Laboratory (LANL).
The new contractor, Triad National Security, LLC, is a limited liability company consisting of the Battelle Memorial Institute, the University of California and Texas A&M University. All three are non-profits, and it is unclear how this will affect New Mexico gross receipts taxes.
Battelle claims to be the world’s largest non-profit technology research and development organization, and manages a number of labs including the Lawrence Livermore and Idaho National Laboratories. Texas A&M was founded in 1876 as the state’s first public institution of higher learning and has the largest nuclear engineering program in the country. DOE Secretary Rick Perry is an avid A&M alumnus.
The new contract includes a five-year base time with five one-year options, for a total of 10 years if all options are exercised. The estimated value of the contract is $2.5 billion annually.
The University of California (UC) ran the Lab from its beginning in 1943 until June 2006, when Los Alamos National Security, LLC (LANS), composed of the University of California (UC), Bechtel, AECOM and BWX Technologies, Inc., took over. That contract had a ten-year base period with ten one-year options, for a total of 20 years if all options were exercised. But LANS was terminated with nine years left of possible options. This was primarily due to LANS improperly preparing a barrel of radioactive wastes that ruptured, closing the Waste Isolation Pilot Plant for nearly three years. NNSA did not clarify why it is now issuing a shorter contract.
This change in contract follows a May 10, 2018 announcement by NNSA that production of plutonium pits, the fissile cores of nuclear weapons, will be expanded to at least 30 pits per year at LANL, and an additional 50 pits per year at the Savannah River Site. The Los Alamos Lab is the birthplace of nuclear weapons, and it is tying its future to increased nuclear weapons production, with the active support of the New Mexico congressional delegation. The Lab proposed, but failed to convince NNSA, to produce all 80 plutonium pits per year. LANL’s core research, testing and production programs for nuclear weapons now comprise 70% of its ~$2.5 billion annual budget, while much of the Lab’s remaining budget indirectly supports those programs.
Lisa E. Gordon-Hagerty, the new NNSA Administrator, testified during her confirmation hearing that expanded plutonium pit production is her number one priority. However, expanded production is NOT needed to maintain the safety and reliability of the existing nuclear weapons stockpile. In fact, no pit production for the existing nuclear weapons stockpile has been scheduled since 2011, and none is scheduled for the future. Up to 15,000 “excess” pits and another 5,000 in “strategic reserve” are already stored at DOE’s Pantex Plant near Amarillo, TX. In 2006 independent experts found that pits last a least a century (they currently average 40 years old). A 2012 follow-on study by the Livermore Lab found that the “graceful aging of plutonium also reduces the immediate need for a modern high-capacity manufacturing facility to replace pits in the stockpile.”
Future pit production is for speculative future new designs being pushed by the nuclear weapons labs, so-called Interoperable Warheads for both land- and sub-launched missiles that the Navy does not want. Moreover, future pits will NOT be exact replicas of existing pits. This could have serious potential consequences because heavily modified plutonium pits cannot be full-scale tested, or alternatively could prompt the U.S. to return to nuclear weapons testing, which would have severe international proliferation consequences.
Jay Coghlan, Nuclear Watch Director, commented, “Regardless of who runs the Lab, LANL will decrease mission diversification and increase nuclear weapons production, while holding cleanup flat at a tenth of its weapons budget. New Mexico been a nuclear weapons colony since WWII, and adding Battelle, Texas A&M, and the University of California is just more of the same. There will be little if any added benefit for New Mexico’s citizens.”
Groups Release Key DOE Documents on Expanded Plutonium Pit Production, DOE Nuclear Weapons Plan Not Supported by Recent Congressional Actions
Santa Fe, NM & Columbia, SC – Two key U.S. Department of Energy documents on future production of plutonium “pits” for nuclear weapons, not previously released to the public, fail to justify new and upgraded production facilities at both the Los Alamos National Laboratory (LANL) in New Mexico and the Savannah River Site (SRS) in South Carolina.
The report reveals that the initial cost estimate for these new and upgraded facilities at both sites is $10 billion by 2030, and around $46 billion in total life cycle costs. Plutonium pits are the fissile cores of nuclear weapons. Cost overruns are the rule for major projects undertaken by the National Security Administration (NNSA), the semi-autonomous nuclear weapons agency within DOE, so the costs are likely to rise yet more, according to Nuclear Watch New Mexico and Savannah River Site Watch.
NNSA’s Pu Pit Production Engineering Assessment, originally marked Unclassified Controlled Nuclear Information, was finalized on April 20, 2018. The 293-page document was obtained by Nuclear Watch and is being released so that the public may be fully informed about the agency’s misguided pursuit of new plutonium pit production facilities for future new-design nuclear weapons. The new NNSA Administrator has called future plutonium pit production her highest priority. But the Engineering Assessment fails to answer the most crucial question: why are at least 80 plutonium pits per year needed to begin with?
As background, on May 10, 2018, NNSA announced in a one-page statement:
To achieve DoD’s [Department of Defense] 80 pits per year requirement by 2030, NNSA’s recommended alternative repurposes the Mixed Oxide Fuel Fabrication Facility at the Savannah River Site in South Carolina to produce plutonium pits while also maximizing pit production activities at Los Alamos National Laboratory in New Mexico. This two-prong approach – with at least 50 pits per year produced at Savannah River and at least 30 pits per year at Los Alamos – is the best way to manage the cost, schedule, and risk of such a vital undertaking.
Nuclear Watch also obtained NNSA’s 14-page Plutonium Pit Production Engineering Assessment (EA) Results. That summary document, dated May 2018, relied on the Trump Administration’s 2018 Nuclear Posture Review for claiming the need for expanded plutonium pit production. However, that high-level review failed to state any concrete justification for the alleged pit need. Moreover, Congress is balking at funding any new pit production facilities at SRS, primarily because Sen Lindsey Graham (R-SC) vociferously opposes repurposing the MOX facility, now undergoing termination, and the New Mexico congressional delegation opposes any pit production outside of the Los Alamos Lab.
The Engineering Assessment details that NNSA analyzed four pit production options, one in the Mixed Oxide (MOX) Fuel Fabrication Facility at SRS and three options at Los Alamos. NNSA chose the most expensive combination, repurposing the MOX facility and increasing pit production at LANL to 30 pits per year. Los Alamos is currently authorized to produce 20 pits per year, but has failed to achieve even that because of ongoing nuclear criticality safety issues (moreover, LANL proposed to produce all 80 pits per year, which NNSA rejected). SRS has never produced pits, raising new nuclear risks at that site and concern about new waste streams.
The Engineering Assessment makes clear that “moderate risks” in the option of repurposing the MOX plant at SRS includes any failure to quickly terminate the MOX project, due to subsequent delays in closing out the project and terminating contracts. Likewise, the report affirms a long-held concern that there is a “very high probability for incomplete construction records/as-built drawings” for the MOX project. On May 10, DOE began congressionally sanctioned termination of the bungled MOX project, but it is being opposed in last-ditch, desperate attempts by Senator Lindsey Graham and the State of South Carolina. The Engineering Assessment makes explicitly clear that terminating the MOX program is the crucial prerequisite for plutonium pit production at SRS and that “some work [on repurposing the MOX plant] can be completed during MOX closeout,” contrary to both the wishes of Congress and requirements of the National Environmental Policy Act.
Expanded plutonium pit production is NOT needed to maintain the safety and reliability of the existing nuclear weapons stockpile, according to Nuclear Watch. In fact, no pit production for the existing nuclear weapons stockpile has been scheduled since 2011, and none is scheduled for the future. Up to 15,000 “excess” pits and another 5,000 in “strategic reserve” are already stored at DOE’s Pantex Plant near Amarillo, TX. In 2006 independent experts found that pits last a least a century[i] (they currently average 40 years old). A 2012 follow-on study by the Livermore Lab found that the “graceful aging of plutonium also reduces the immediate need for a modern high-capacity manufacturing facility to replace pits in the stockpile.” [ii]
Future pit production is for speculative future new designs being pushed by the nuclear weapons labs, so-called Interoperable Warheads for both land- and sub-launched missiles that the Navy does not support.[iii] Moreover, as the Engineering Assessment makes clear, future pits will NOT be exact replicas of existing pits. This could have serious potential consequences because heavily modified plutonium pits cannot be full-scale tested, or alternatively could prompt the U.S. to return to nuclear weapons testing, which would have severe international proliferation consequences.
The Engineering Assessment also explicitly links raising the administrative limit on plutonium at LANL’s “Rad Lab” to expanded pit production. This contradicts a recent draft environmental assessment in which NNSA claimed that re-categorizing the Rad Lab as a Hazard Category-3 nuclear facility was necessary only to maintain basic analytical chemistry capabilities, while omitting any reference whatsoever to expanded plutonium pit production.
The Engineering Assessment briefly outlines what could be a major vulnerability to NNSA’s pit production plans, that is the agency’s future compliance (or not) with the National Environmental Policy Act (NEPA). The Assessment states that if “compliance is delayed, [this] extends the schedule, increases costs, and/or delays production.” Both Nuclear Watch and SRS Watch assert that the law requires that major federal proposals be subject to public review and comment before a formal decision is made. Arguably, a formal decision to raise production to 80 pits or more per year necessitates a new or supplemental nation-wide programmatic environmental impact statement (PEIS), which the new dual-site decision strongly buttresses. Follow-on site-specific NEPA documents will then be necessary, with full public participation and hearings. All of this could introduce substantial delays to NNSA’s plutonium pit production plans.
“While it’s clear that the bungled MOX project is unworkable from technical and cost perspectives and must rapidly be terminated, there is no justification to convert the abandoned facility to a nuclear bomb production plant,” said Tom Clements, director of SRS Watch. “We agree that money must now be spent closing and securing the MOX building, but not on the new, unauthorized pit mission. Spending taxpayer funds to now begin conversion of the MOX plant to pit production, as is indicated in the pit report, is premature and can’t even be considered until Congress approves the NNSA approach for new facilities and an environmental impact review with public participation takes place,” added Clements.
Jay Coghlan, Nuclear Watch Director, commented, “NNSA has already tried four times to expand plutonium pit production, only to be defeated by citizen opposition and its own cost overruns and incompetence. We realize that this fifth attempt at a new pit plant is the most serious yet, but we remain confident it too will fall apart. The enormous financial and environmental costs of new nuclear bomb factories and the fact that expanded plutonium pit production is simply not needed for the existing nuclear weapons stockpile will doom this effort. We think the American public will reject new-design nuclear weapons, which is what this expanded pit production decision is really all about.”
Notes:
NNSA’s Plutonium Pit Production Engineering Assessment (EA) Results (14 slides) is available at
NNSA’s 293-page Pu Pit Production Engineering Assessment is available at
NNSA’s Joint Statement from Ellen M. Lord and Lisa E. Gordon-Hagerty on Recapitalization of Plutonium Pit Production, May 10, 2018, is available at
[i] Pit Lifetime (JSR-06-335), the MITRE Corporation, JASON, January 27, 2007, p. 19, http://www.fas.org/irp/agency/dod/jason/pit.pdf
This pivotal study came about because at Nuclear Watch New Mexico’s request then-Senator Jeff Bingaman (D.-NM) successfully offered an amendment to the FY 2004 Defense Authorization Act requiring it.
[ii] Plutonium at 150 years, Lawrence Livermore National Laboratory, December 2012,
https://www.llnl.gov/news/plutonium-150-years
[iii] See 2012 Navy memo demonstrating its lack of support for the Interoperable Warhead at https://nukewatch.org/importantdocs/resources/Navy-Memo-W87W88.pdf
Past NukeWatch Events
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
Past Work Product (2019-)
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
2019
November 26, 2019 Press Release November 24, 2019 Press Release November 19, 2019 Plutonium Pit Production Workshop Presenters:
August 12, 2019 NEPA Comments NukeWatch’s 22-page formal comments on expanded plutonium pit production Until NNSA fully complies with the National Environmental Policy Act through the preparation of a programmatic environmental impact statement on expanded plutonium pit production, Nuclear Watch believes that any irreversible or irretrievable commitment of resources to either the expansion of pit production at the Los Alamos Lab or to the repurposing of the MOX Facility at the Savannah River Site is unlawful. Read/Download the Full Document HERE July 25, 2019 NEPA Comments Scoping comments on NNSA draft EIS for plutonium pit production at the Savannah River Site THE NEED FOR A PROGRAMMATIC ENVIRONMENTAL IMPACT STATEMENT: This is our first and primary concern, that NNSA must first complete a programmatic environmental impact statement (PEIS) on its nation-wide plans for plutonium pit production, in advance of the Savannah River Site-specific environmental impact statement. To get right to the point, we argue that the SRS EIS process should go no further than this scoping period and should resume only after a completed formal Record of Decision for a new or supplemental PEIS. Read/Download the Full Document HERE July 9, 2019 Plutonium Pit Production Fact Sheet Expanding Nuclear Pit Production: The Facts and What You Can Do The Facts Read/Download the Full Document HERE June 10, 2019 News Release In a victory for transparency and legal compliance by the government, the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) today published a “Notice of Intent” in the Federal Register to complete environmental reviews on its controversial proposal to expand plutonium “pit” production for new and refurbished nuclear weapons. [embeddoc url="https://nukewatch.org/wp-content/uploads/2019/06/SRS-plutonium-bomb-plant6-14-19.pptx" download="all" viewer="google"] Read/Download the Full News Release HERE June 4, 2019 Press Release On behalf of three public interest organizations - Nuclear Watch New Mexico, Tri-Valley Communities Against a Radioactive Environment and Savannah River Site Watch – attorneys for the law firm of Meyer Glitzenstein & Eubanks and the Natural Resources Defense Council recently sent a 16-page letter to Lisa Gordon-Hagerty, head of the National Nuclear Security Administration (NNSA). The detailed letter warns the nuclear agency to not proceed with aggressive plans to expand plutonium pit production without first meeting its legal requirements for timely public review and comment under the National Environmental Policy Act. Read/Download the Full Press Release HERE May 31, 2019 Press Release Last Wednesday, facility operations personnel entered a service room and noticed a leak emanating from a valve on the radioactive liquid waste (RLW) system. Upon subsequent visual inspection by a radiological control technician, RLUOB engineers believe that this valve, and 6 similar valves, may be constructed of carbon steel. The RLW system handles radioactive liquid waste streams from chemistry operations that include nitric and hydrochloric acids—carbon steel valves would be incompatible with these solutions. The suspect valves are also in contact with stainless steel piping, which would create another corrosion mechanism. RLUOB management plans to drain the affected piping sections and develop a work package to replace all of the suspect valves. They will also confirm the valve materials and if shown to be incorrect, investigate the cause of this failure in the design, procurement, and installation processes. The valves were installed in 2013 as part of a modification to add straining and sampling capabilities that were not in the included in the original design. [Please note that DNFSB reports are posted a few weeks later than dated.] This immediately raises two crucial issues: 1) the National Nuclear Security Administration’s (NNSA’s) plans for expanded plutonium pit production; and 2) the current attempt by the Department of Energy to restrict Safety Board access to its nuclear weapons facilities. Read/Download the Full Press Release HERE April 26, 2019 Consent Orders Comparison On March 1, 2005, after arduous negotiations and threats of litigation, the New Mexico Environment Department (NMED), Department of Energy (DOE), and Los Alamos National Laboratory (LANL) entered into a Consent Order specifying the schedule for investigation and cleanup of the Lab’s hundreds of contaminated sites. This Consent Order (CO) was LANL’s agreement to fence-to-fence cleanup of Cold War legacy wastes, which NMED began to enforce. Read/Download the Full Comparison HERE March 25, 2019 Press Release More than 25 years after the end of the Cold War, all eight established nuclear weapons powers are “modernizing” their stockpiles. Talks have broken down with North Korea, the new nuclear weapons power. Nuclear-armed India and Pakistan narrowly averted war last month. Russian President Vladmir Putin made new nuclear threats in response to Trump’s announced withdrawal from the Intermediate-Range Nuclear Forces Treaty. This could lead to hair-trigger missile emplacements in the heart of Europe and block extension of the New Strategic Arms Reduction Treaty with Russia. If so, the world will be without any nuclear arms control at all for the first time since 1972. Meanwhile, the U.S. criticizes non-weapons states for signing a nuclear weapons ban treaty, despite the fact there have long been treaties completely banning chemical and biological weapons of mass destruction that the U.S. seeks to enforce. The pending international NonProliferation Treaty (NPT) Preparatory Committee conference at the United Nations is widely expected to collapse in failure because of the nuclear weapons powers’ failure to enter into serious negotiations leading to nuclear disarmament. The NPT’s Article VI mandate for those negotiations has been in effect since 1970, when the Treaty was signed by 189 countries (more than any other treaty). Read/Download the Full Press Release HERE March 26, 2019 NukeWatch Budget Compilation Nuclear Watch New Mexico — Department of Energy FY 2020 Nuclear Weapons Budget Request |
2018
November 16, 2018 Plutonium Pit Production Fact Sheet Plutonium pits are the radioactive cores or “triggers” of nuclear weapons. Their production has always been a chokepoint of resumed industrial-scale U.S. nuclear weapons production ever since a 1989 FBI raid investigating environmental crimes shut down the Rocky Flats Plant near Denver. In 1997 the mission of plutonium pit production was officially transferred to its birthplace, the Los Alamos National Laboratory (LANL) in northern New Mexico, but officially capped at not more than 20 pits per year. However, in 2015 Congress required expanded pit production by 2030 whether or not the existing nuclear weapons stockpile actually needs it. This will support new military capabilities for nuclear weapons and their potential use. Read/Download the full fact sheet pdf HERE October 31, 2018 Nuclear Watch New Mexico, Savannah River Site Watch, and Tri-Valley CAREs sent a letter of demand to the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) to inform the government that its plan to quadruple the production rate of plutonium bomb cores is out of compliance with the National Environmental Policy Act (NEPA). NNSA’s premature plan to quadruple the production rate of plutonium bomb cores (“pits”), the heart of all US nuclear weapons, is out of compliance with requisite environmental law, the groups argue, as NNSA has failed to undertake a legally-mandated programmatic review and hold required public hearings. View/Download the entire press release HERE NukeWatch Comments, September 27, 2018 Nuclear Watch New Mexico is submitted formal comments to express in the strongest possible terms our opposition to DOE Order 140.1 Interface with the Defense Nuclear Facilities Safety Board. We find that the Department of Energy’s (DOE’s) attempt to restrict and suppress DNFSB access is very misguided, arrogant, and likely illegal in that it acts contrary to the Board’s enabling legislation. June 8, 2018 Press Release New Contractors Selected For Expanded Nuclear Weapons Production at Los Alamos Santa Fe, NM. Today the Department of Energy's National Nuclear Security Administration (NNSA) announced its choice for the new management and operating contract for the Los Alamos National Laboratory (LANL).The new contractor, Triad National Security, LLC, is a limited liability company consisting of the Battelle Memorial Institute, the University of California and Texas A&M University. All three are non-profits, and it is unclear how this will affect New Mexico gross receipts taxes. Battelle claims to be the world's largest non-profit technology research and development organization, and manages a number of labs including the Lawrence Livermore and Idaho National Laboratories. Texas A&M was founded in 1876 as the state's first public institution of higher learning and has the largest nuclear engineering program in the country. DOE Secretary Rick Perry is an avid A&M alumnus. May 31, 2018 Press Release Santa Fe, NM & Columbia, SC - "Two key U.S. Department of Energy documents on future production of plutonium "pits" for nuclear weapons, not previously released to the public, fail to justify new and upgraded production facilities at both the Los Alamos National Laboratory (LANL) in New Mexico and the Savannah River Site (SRS) in South Carolina." May 15, 2018 Fact Sheet May 10, 2018 Press Release What's Not in NNSA's Plutonium Pit Production Decision
- NNSA did not mention that up to 15,000 "excess" pits are already stored at the Pantex Plant near Amarillo, TX, with up to another 5,000 in "strategic reserve." The agency did not explain why new production is needed given that immense inventory of already existing plutonium pits. (In 2006 independent experts found that pits last a least a century. Plutonium pits in the existing stockpile now average around 40 years old.) May 2, 2018 Press Release "NNSA should begin nation-wide review of plutonium pit production, why it's needed, and what it will cost the American taxpayer in financial, safety and environmental risks. These are all things that the public should know." -Jay Coghlan, Director, Nuclear Watch New Mexico. April 26, 2018 NukeWatch Comments LANL Rad Lab: Formal Comments Under Nat'l Environmental Policy Act Against raising plutonium limit at LANL Rad Lab View/download Nuclear Watch comments as submitted Excerpt:
- NNSA is planning a 10-fold increase in plutonium at the LANL Rad Lab with a view to ramping up the production of plutonium pits for new nuclear weapons. March 26, 2018 Press Release United States To Begin Construction Of New Nuclear Bomb Plant The National Nuclear Security Administration (NNSA) announced on Friday, March 23, that it was authorizing the start of construction of the Uranium Processing Facility (UPF) and two sub-projects at the Y-12 National Security Complex in Oak Ridge, Tennessee. The UPF is a facility dedicated solely to the manufacture of thermonuclear cores for US nuclear bombs and warheads.
Jay Coghlan of NukeWatch points out that "This project already has a long history, and it is instructive. In 2013, DOE announced it was 85% finished with the UPF design when it ran into the 'space/fit' issue- and more than a half-billion taxpayer dollars were just written off. In private business, that kind of thing gets you fired. In DOE's world of contractors running amok, they not only didn't get fired, not one Congressional hearing was held and the UPF budget went up the next year!" - See full press release for all the details (PDF) March 1, 2018 Press Release The Regional Coalition of LANL Communities: Benefits for the Select Few Santa Fe, NM- According to media reports, Andrea Romero, Executive Director of the Regional Coalition of LANL Communities, is accused of charging some $2,200 dollars of unallowable travel costs, such as alcohol and baseball tickets, while lobbying in Washington, DC for additional funding for the Los Alamos National Laboratory (LANL). She in turn accused the nonprofit group Northern New Mexico Protects of political motivations in revealing these questionable expenses. Romero is running in the Democrat Party primary against incumbent state Rep. Carl Trujillo for Santa Fe County's 46th district in the state House of Representatives. For all the details, see full press release PDF February 28, 2018 Press Release Santa Fe, NM. On December 17, 2017, the Department of Energy (DOE) awarded a separate $1.4 billion contract for cleanup at the Los Alamos National Laboratory (LANL) to Newport News Nuclear BWXT-Los Alamos, LLC (also known as "N3B"). This award followed a DOE decision to pull cleanup from LANL's prime contractor, Los Alamos National Security, LLC (LANS), after it sent an improperly prepared radioactive waste drum that ruptured underground at the Waste Isolation Pilot Plant (WIPP). That incident contaminated 21 workers and closed WIPP for nearly three years, costing taxpayers at least $1.5 billion to reopen. (See all the details in the full press release) February 26, 2018 Press Release Detailed NNSA Budget Documents Accelerates Nuclear Weapons Arms Race Santa Fe, NM. Late Friday February 23, the Trump Administration released the detailed FY 2019 budget for the National Nuclear Security Administration (NNSA), the semi-autonomous nuclear weapons agency within the federal Department of Energy. Overall, NNSA is receiving a $2.2 billion boost to $15.1 billion, a 17% increase above the FY 2018 enacted level. Of that, a full $11 billion is for the budget category [Nuclear] "Weapons Activities", 18% above the FY 2018 level. Of concern to the American taxpayer, DOE and NNSA nuclear weapons programs have been on the congressional Government Accountability Office's High Risk List for project mismanagement, fraud, waste and abuse since its inception in 1990... (See all the details in the full press release) February 22, 2018 Press Release Santa Fe, NM. Today the National Nuclear Security Administration announced an Environmental Assessment to increase the amount of plutonium used in the Radiological Laboratory Utility and Office Building (aka the "Rad Lab") at the Los Alamos National Laboratory from 38.6 grams of plutonium-239 equivalent to 400 grams. This 10-fold increase is significant because it will dramatically expand materials characterization and analytical chemistry capabilities in the Rad Lab in support of expanded plutonium pit production for future nuclear weapons designs. It also re-categorizes the Rad Lab from a "radiological facility" to a "Hazard Category-3" nuclear facility. View/Download full press release February 12, 2018 Press Release Trump's Budget Dramatically Increases Nuclear Weapons Work Santa Fe, NM In keeping with the Trump Administration's recent controversial Nuclear Posture Review, today's just released FY 2019 federal budget dramatically ramps up nuclear weapons research and production. January 12, 2018 Press Release Draft Nuclear Posture Review Degrades National Security Yesterday evening the Huffington Post posted a leaked draft of the Trump Administration's Nuclear Posture Review (NPR). This review is the federal government's highest unclassified nuclear weapons policy document, and the first since the Obama Administration's April 2010 NPR. 2017 |
2017
December 22, 2017 Press Release New Mexico Environment Department Surrendered to DOE Extortion Santa Fe, NM. The New Mexico State Auditor Office recently questioned whether two settlements between the New Mexico Environment Department and the Department of Energy were in the best interests of New Mexico. That Office noted: (View/download full press release) December 20, 2017 Press Release Los Alamos Hires New Contractor - Starts Cleanup On the Cheap Santa Fe, NM- Today the Department of Energy (DOE) announced the award of the new Los Alamos National Laboratory legacy cleanup contract to Newport News Nuclear BWXT-Los Alamos, LLC. The $1.39 billion contract is for ten years, which works out to $139 million per year... View/download the full press release Public Presentation, December 2, 2017 October 31, 2017 Press Release Today, in Washington, DC, the Congressional Budget Office released its new report, "Approaches for Managing the Costs of U.S. Nuclear Forces, 2017 to 2046". The Congressional Budget Office estimates that the most recent detailed plans for nuclear forces, which were incorporated in the Obama Administration's 2017 budget request, would cost $1.2 trillion in 2017 dollars over the 2017-2046 period: more than $800 billion to operate and sustain (that is, incrementally upgrade) nuclear forces and about $400 billion to modernize them.... Driving this astronomical expense is the fact that instead of maintaining just the few hundred warheads needed for the publicly claimed policy of "deterrence," thousands of warheads are being refurbished and improved to fight a potential nuclear war. This is the little known but explicit policy of the U.S. government! October 27, 2017 Press Release Santa Fe, NM. On the evening of Wednesday October 25, the Santa Fe City Council passed a resolution requesting that the New Mexico Environment Department strengthen the revised Los Alamos National Labs cleanup order to call for additional characterization of legacy nuclear wastes, increased cleanup funding, and significant additional safety training. The resolution also called for the suspension of any planned expanded plutonium pit production until safety issues are resolved. (view/download full press release) October 6, 2017 Press Release Santa Fe, NM. Nuclear Watch New Mexico strongly applauds the awarding of the Nobel Peace Prize to the International Campaign to Abolish Nuclear Weapons (disclosure: NukeWatch is one of ICAN's ~400 member groups around the world). This award is especially apt because the peoples of the world are now living at the highest risk for nuclear war since the middle 1980's, when during President Reagan's military buildup the Soviet Union became convinced that the United States might launch a pre-emptive nuclear first strike. Today, we not only have Trump's threats to "totally destroy" North Korea and Kim Jong-un's counter threats, but also renewed Russian fears of a US preemptive nuclear attack... Generally unknown to the American taxpayer, our government has quietly tripled the lethality of the US nuclear weapons stockpile..." (view/download complete press release) NukeWatch fact sheet, September 26, 2017 The National Nuclear Security Administration's own documents have explicitly stated that expanded pit production would have no significant positive effect on job creation and the regional economy of northern New Mexico. Nuclear Watch argues that expanded plutonium pit production could actually have negative effect if it blocks other economic alternatives such as comprehensive cleanup, which could be the real job producer. Moreover, given LANL's poor safety and environmental record, expanded plutonium pit production could have a seriously negative economic impact on northern New Mexico in the event of any major accidents. September 15, 2017 Press Release Santa Fe, NM. The Los Alamos National Laboratory (LANL) has detected far more hexavalent chromium (Cr) contamination than previously estimated in the "sole source" regional groundwater aquifer that serves Los Alamos, Santa Fe and the Espanola Basin. Sampling in July from a new well meant to inject treated groundwater back into the aquifer detected chromium contamination five times greater than the New Mexico groundwater standard of 50 micrograms per liter (ug/L). View/download the full press release September 11, 2017 Press Release Talking Points: The 2016 LANL Cleanup Consent Order Should Be Rescinded The 2005 LANL Cleanup Consent Order was all about the enforceable schedules. It required DOE and LANL to investigate, characterize, and clean up hazardous and mixed radioactive contaminants from 70 years of nuclear weapons research and production. It stipulated a detailed compliance schedule that the Lab was required to meet. Under Gov. Martinez, NMED Secretary Ryan Flynn granted more than 150 compliance milestone extensions at the Lab's request, effectively eviscerating it. View/download the complete talking points July 20, 2017 Press Release Washington, DC Today, the Oak Ridge Environmental Peace Alliance (OREPA), Nuclear Watch New Mexico, and the Natural Resources Defense Council filed a federal lawsuit to stop construction of the problem-plagued Uranium Processing Facility (UPF) until legally required environmental review is completed. The UPF, located at the National Nuclear Security Administration's (NNSA's) Y-12 production plant near Oak Ridge, TN, is slated to produce new thermonuclear weapons components until the year 2080. The UPF is the tip of the spear for the U.S.'s planned one trillion dollar-plus make over of its nuclear weapons arsenal, delivery systems, and production plants. View/download the full press release June 19, 2017 Press Release Some Background on Plutonium Pit Production at the Los Alamos Lab Santa Fe, NM -The Washington Post has published the first in a series of articles on nuclear safety lapses in plutonium pit production at the Los Alamos Lab. Plutonium pits are the fissile cores of nuclear weapons that when imploded initiate the thermonuclear detonation of modern weapons. By the way, did you know? Plutonium facilities at LANL are- in principle- designed to withstand a serious earthquake of a degree expected to occur only once every 10,000 years. The last serious earthquake near the Lab is believed to have occurred 11,500 years ago. View/download the full press release ANA Report 2017: Accountability Audit May 19, 2017 Press Release SA Preview of Trump's Budget: More Nuclear Bombs and Plutonium Pit Production Santa Fe, NM. "The proposed level of funding for the National Nuclear Security Administration's (NNSA)'s Total Weapons Activities is $10.2 billion, a full billion above what was requested for FY 2017. In March, Trump's "skinny budget" stated NNSA's funding priorities as 'moving toward a responsive nuclear infrastructure', and 'advancing the existing warhead life extension programs'. Read the full press release for all the details. March 28, 2017 ANA workshop at UN Ban Treaty Conference Ban Treaty Conference: Alliance for Nuclear Accountability Panel Discussion March 28, 2017, UN, NYC:
March 2017 Fact Sheet Plutonium Pit Production at LANL (Updated March 2017) February 23, 2017 Press Release Costs Jump in Nuclear Weapons vs. Cleanup; Nuclear Weapons Winning over Environmental Protection Santa Fe, NM. America is at a crossroads, having to choose between an unnecessarily large, exorbitant, nuclear weapons stockpile, and cleanup that would protect the environment and water resources for future generations. Expanded nuclear weapons research and production, which will cause yet more contamination, is winning. Read the full press release for all the details. January 5, 2017 Press Release The National Nuclear Security Administration (NNSA) has publicly released its fiscal year 2016 Performance Evaluation Report (PER) for Los Alamos National Security, LLC (LANS), the for-profit contractor that runs the Los Alamos Lab. The Performance Evaluation Report is NNSA's annual report card on contractor performance, and overall the agency awarded LANS $59 million in profit out of a possible $65 million. The grade was 85% for the incentive part of the award. In 2012 Nuclear Watch New Mexico successfully sued NNSA to ensure that the Performance Evaluation Reports detailing taxpayers funds paid to nuclear weapons contractors are publicly available. In 2016 the NNSA decided to put the LANL management contract out for competitive bid, but granted LANS a contract extension until the end of September 2018. |
Media appearances including radio interviews are listed on the internal Media page
See the NukeWatch Channel at YouTube for our extensive playlists of key videos.
See the Nukewatch Twitter feed
See the Nukewatch Tumblr site
WatchBlog Posts:
Over 200 posts published since 2009. See archives at the WatchBlog
Earlier Work Product items are archived here