Court Rules U.S. Nuclear Weapons Production Plan Violates Federal Law
FOR IMMEDIATE RELEASE, October 3, 2024
Media Contacts:
Ben Cunningham, Esquire, SCELP, 843-527-0078, [email protected]
Tom Clements, Savannah River Site Watch, 803-834-3084, [email protected]
Jay Coghlan, Nuclear Watch New Mexico, 505-989-7342, [email protected]
Scott Yundt, Tri-Valley CAREs, 925-443-7148, [email protected]
Queen Quet, Gullah/Geechee Sea Island Coalition, 843-838-1171, [email protected]
AIKEN, S.C. — On September 30, United States District Court Judge Mary Geiger Lewis ruled that the United States Department of Energy (“DOE”) and its semi-autonomous nuclear weapons agency, the National Nuclear Security Administration (“NNSA”), violated the National Environmental Policy Act (“NEPA”) by failing to properly consider alternatives before proceeding with their plan to produce plutonium pits, a critical component of nuclear weapons, at the Los Alamos National Laboratory (“LANL”) in New Mexico and, for the first time ever, at the Savannah River Site (“SRS”) in South Carolina.
The Court found that the plan’s purpose had fundamentally changed from NNSA’s earlier analyses which had not considered simultaneous pit production at two sites. These changes necessitated a reevaluation of alternatives, including site alternatives, which Defendants failed to undertake prior to moving forward while spending tens of billions of taxpayers’ dollars. Therefore, the Court entered judgment in favor of Plaintiffs, the nonprofit public interest groups Savannah River Site Watch, Nuclear Water New Mexico and Tri-Valley Communities Against a Radioactive Environment (CAREs); the Gullah/Geechee Sea Island Coalition; and Tom Clements as an individual plaintiff.
As a result of this ruling, the Defendants are required to newly assess pit production at a nation-wide programmatic level which will mean undertaking a thorough analysis of the impacts of pit production at DOE sites throughout the United States, including radioactive waste generation and disposal. Under the National Environmental Policy Act (NEPA), this will provide the opportunity for public scrutiny of and formal comment on their assessments.
High Detections of Plutonium in Los Alamos Neighborhood – As We Enter a New Nuclear Arms Race the Last One is Still Not Cleaned Up
FOR IMMEDIATE RELEASE, August 15, 2024
Dr. Michael Ketterer – 928.853.7188 | Email
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – In April Nuclear Watch New Mexico released a map of plutonium contamination based on Lab data. Today, Dr. Michael Ketterer, Professor Emeritus of Chemistry and Biochemistry, Northern Arizona University, is releasing alarmingly high results from samples taken from a popular walking trail in the Los Alamos Town Site, including detections of some of the earliest plutonium produced by humankind.
On July 2 and 17 Dr. Ketterer, with the assistance of Nuclear Watch New Mexico, collected water, soil and plant samples from Acid Canyon in the Los Alamos Town Site and soil and plant samples in Los Alamos Canyon at the Totavi gas station downstream from the Lab. The samples were prepared and analyzed by mass spectrometry at Northern Arizona University to measure concentrations of plutonium, and to ascertain its sources in the environment.
NNSA Delays Urgent Research on Plutonium “Pit” Aging While Spending Tens of Billions on Nuclear Weapons Bomb Core Production
FOR IMMEDIATE RELEASE, April 17, 2024
Tom Clements, SRS Watch – 803.240.7268 | Email
Scott Yundt, TVC – 415.990.2070 | Email
Jay Coghlan – 505.989.7342 | Email
Nearly three years after filing a Freedom of Information Act request, the public interest group Savannah River Site Watch has finally received the National Nuclear Security Administration’s (NNSA’s) congressionally-required “Research Program Plan for Plutonium and Pit Aging.” However, the document is 40% blacked out, including references and acronyms. Plutonium “pits” are the radioactive cores of all U.S. nuclear weapons. The NNSA claims that potential aging effects are justification for a ~$60 billion program to expand production. However, the Plan fails to show that aging is a current problem. To the contrary, it demonstrates that NNSA is delaying urgently needed updated plutonium pit aging research.
In 2006 independent scientific experts known as the JASONs concluded that plutonium pits last at least 85 years without specifying an end date [i] (the average pit age is now around 40 years). A 2012 follow-on study by the Lawrence Livermore nuclear weapons lab concluded:
“This continuing work shows that no unexpected aging issues are appearing in plutonium that has been accelerated to an equivalent of ~ 150 years of age. The results of this work are consistent with, and further reinforce, the Department of Energy Record of Decision to pursue a limited pit manufacturing capability in existing and planned facilities at Los Alamos instead of constructing a new, very large pit manufacturing facility…” [ii]
Since then NNSA has reversed itself. In 2018 the agency decided to pursue the simultaneous production of at least 30 pits per year at the Los Alamos National Laboratory (LANL) in northern New Mexico and at least 50 pits per year at the Savannah River Site (SRS) in South Carolina. Upgrades to plutonium facilities at LANL are slated to cost $8 billion over the next 5 years. The redundant Savannah River Plutonium Processing Facility in South Carolina will cost up to $25 billion, making it the second most expensive building in human history.
NNSA’s Nuclear Weapons Budget Takes Huge Jump
Arms Race Accelerates with MIRVed Warheads
Los Alamos Lab Cleanup Cut
FOR IMMEDIATE RELEASE, March 11, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – Ironically the day after the film Oppenheimer was awarded multiple Oscars, the Department of Energy’s semi-autonomous National Nuclear Security Administration (NNSA) asked Congress for its biggest nuclear weapons budget ever. NNSA’s FY 2025 request for “Total Weapons Activities” is $19.8 billion, $700 million above what Congress recently enacted for FY 2024. It is also a full billion dollars above what President Biden asked for last year, which Congress then added to and will likely do so again.
The Biden Administration states that the $19.8 billion will be used to:
“[P]rioritize implementation of the 2022 National Defense Strategy and Nuclear Posture Review by modernizing the Nation’s nuclear deterrent to keep the American people safe. The Budget supports a safe, secure, reliable, and effective nuclear stockpile and a resilient, responsive nuclear security enterprise necessary to protect the U.S. homeland and allies from growing international threats.” whitehouse.gov/wp-content/uploads/2024/03/budget_fy2025.pdf, page 75.
The 2022 National Defense Strategy and Nuclear Posture Review for the first time posited two nuclear “near peers”, i.e. Russia and China, that need to be simultaneously “deterred.” This hinted at a potentially large nuclear buildup which this budget may now be implementing. That claimed need to deter two nuclear near peers was explicitly taken a step beyond just deterrence in an October 2023 report from the Strategic Posture Commission. It declared:
“Decisions need to be made now in order for the nation to be prepared to address the threats from these two nuclear-armed adversaries arising during the 2027-2035 timeframe. Moreover, these threats are such that the United States and its Allies and partners must be ready to deter and defeat both adversaries simultaneously.” ida.org/research-and-publications/publications/all/a/am/americas-strategic-posture, page vii (bolded emphasis added)
NNSA Suppresses How Taxpayers Money Is Spent
FOR IMMEDIATE RELEASE, January 19, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – The National Nuclear Security Administration (NNSA) has just released cursory two or three page summaries of contractors’ performance paid for by the American taxpayer. For the just ended fiscal year 2023, NNSA gave nothing less than grades of “Excellent” or “Very Good” in six broad mission goals for its major contractors. This is despite the constant cost overruns and schedule delays that are the rule, not the exception, in the nation-wide nuclear weapons complex. NNSA and its parent Department of Energy have been on the Government Accountability Office’s “High Risk List” for project mismanagement ever since GAO started that List in 1991.
A current example is the Uranium Processing Facility (UPF) at the Y-12 Plant near Oak Ridge, Tennessee, originally estimated in 2011 to cost $1.4 to $3.5 billion. After costs started going through the roof, NNSA and Senator Lamar Alexander (R.-TN), then-chair of Senate Energy and Water Appropriations, swore that UPF would never go over $6.5 billion. But even after eliminating non-nuclear weapons production missions and a formal decision to continue operations at two old, unsafe buildings slated for replacement, the Uranium Processing Facility is now estimated to cost $8.5 billion. However, even that is not the final price, as NNSA is still to “rebaseline” UPF costs at some unspecified date.
2023
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT FACT SHEETS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT PRESS RELEASES
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT NUCLEAR BUDGET GRAPHS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
Past Work Product (2020-2021)
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
75TH ANNIVERSARY HIROSHIMA DAY ONLINE COMMEMORATION CALLING FOR THE ABOLITION OF NUCLEAR WEAPONS
August 6, 2020
"Jay Coghlan of Nukewatch.org on the history of the Los Alamos labs, where the bomb was designed and fabricated, and how it continues to play the leading role in the creation of most U.S. nuclear weapons since then."
[embeddoc url="https://nukewatch.org/wp-content/uploads/2020/05/plutonium-pit-production-fact-sheet.pdf" download="all" viewer="browser"]
PLUTONIUM PIT PRODUCTION WORKSHOP – NOVEMBER 19, 2019
RADIO INTERVIEW – SCOTT KOVAC & JON LIPSKY
Scott Kovac of Nuclear Watch New Mexico and Jon Lipsky, the FBI agent who led the 1989 raid investigating environmental crimes that shut down the Rocky Flats Nuclear Bomb Plant join Xubi to talk about Nuclear weapons, Nuclear clean up and Pit production plans at LANL.
RADIO INTERVIEW – JAY COGHLAN & JON LIPSKY
PIT Production at LANL with Nuclear Watch New Mexico’s Jay Coghlan and Workshop Speaker, Jon Lipsky
RADIO INTERVIEW – MARYLIA KELLEY, EXECUTIVE DIRECTOR, TRI-VALLEY CARES
Nuclear Watch NM’s Workshop on LANL & PIT Production with Marylia Kelley of Tri-Valley CARES
Pit Production Workshop: View the Presentations
Jon Lipsky, FBI agent that led the 1989 raid investigating environmental crimes that shut down the Rocky Flats bomb plant
Introduction by Jay Coghlan
Jay Coghlan, Executive Director, Nuclear Watch New Mexico, on plutonium pit production at LANL
Marylia Kelly, Executive Director, Tri-Valley CAREs (Livermore, CA) on the new nuclear arms race
https://www.facebook.com/NukeWatch.NM/videos/825812604488302/
Scott Kovac Nuclear Watch New Mexico, on LANL cleanup issues
Blog Posts
New Mexico’s Revolving Nuclear Door: Top Environment Officials Sell Out to Nuclear Weapons Labs
As part of a long, ingrained history, senior officials at the New Mexico Environment Department (NMED) have repeatedly resigned to go to work for the nuclear weapons labs, the Department of Energy, or DOE contractors. In a number of cases that is where they came from to begin with.
The hierarchy of leadership at NMED starts with the Secretary, Deputy Secretaries and then Division Directors. The position of Resource Protection Division Director is particularly critical because it oversees the two NMED bureaus most directly involved with DOE facilities in New Mexico, the Hazardous Waste Bureau and the DOE Oversight Bureau.
FULL PRESS RELEASE [PDF]
Biden’s Nuclear Posture Review Fuels the New Nuclear Arms Race
FOR IMMEDIATE RELEASE, October 27, 2022 |
Jay Coghlan, 505.989.7342 [email protected]
Santa Fe, NM– Today, the Biden Administration has released its long awaited unclassified Nuclear Posture Review. It headlines a “Comprehensive, balanced approach to defending vital national security interests and reducing nuclear dangers.” It also declares that “deterrence alone will not reduce nuclear dangers.”
“Deterrence” against others has always been the publicly sold rationale for the United States’ nuclear weapons stockpile. First, there is the inconvenient fact that the U.S. was the first and only to use nuclear weapons in war. But secondly, the United States and the USSR (now Russia) never possessed their huge stockpiles for the sole purpose of deterrence anyway. Instead, their nuclear weapons policies have always been a hybrid of deterrence and nuclear war fighting, which threatens global annihilation to this very day.
FULL PRESS RELEASE [PDF]
The Cuban Missile Crisis 60 Years Ago, Ukraine Today: What, if Anything, Have we Learned?
By: Sophia Stroud | October 27, 2022
The 60th anniversary of the Cuban Missile Crisis this year coincides with a world again in a moment of impeding nuclear conflict with the perilous escalation of the situation in Ukraine. The Cuban Missile Crisis has been viewed as the defining confrontation of the modern age, the world’s closest brush with nuclear annihilation, until now. But “the war in Ukraine presents perils of at least equal magnitude.” The world is again on the brink of nuclear war. Russian Foreign Minister Sergey Lavrov has said bluntly “there are ‘similarities’ [of the Ukraine War] to the Cuban crisis,” mainly because Russia was now threatened by Western weapons in Ukraine. But how can we get a deeper understanding besides this surface comparison? Now seems like a good time to analyze, not what the lessons of the Cuban missile crisis are for us now, but what, if anything, have we learned from these lessons that we have supposedly have already identified by now, far past half a century later? Have these lessons really taught us anything or are “the Lessons of the Cuban Missile Crisis [Actually] Pretty Useless Right Now“?
→
Watchdogs File Suit for NNSA’s Performance Evaluation Reports
Santa Fe, NM – Today, Nuclear Watch New Mexico has once again filed a lawsuit to pry loose the National Nuclear Security Administration’s (NNSA’s) full and complete Performance Evaluation Reports that evaluate contractor performance at its eight nuclear weapons sites. Approximately 57,000 people are employed by NNSA’s nuclear weapons production complex, 95% of them contractor personnel. NNSA and its parent Department of Energy have been on the independent Government Accountability Office’s “High Risk List” for project mismanagement and waste of taxpayers’ dollars since 1992.
NNSA’s Performance Evaluation Reports grade contractor performance, award performance fees and contain no classified information. Nevertheless, NNSA seeks to hide how taxpayers’ money is spent from the public, issuing only terse three page summaries instead of the full and complete Reports. Nuclear Watch sued in 2012 to obtain the full and complete Performance Evaluation Reports, after which NNSA started releasing them within three working days. But NNSA has again been releasing only summaries since 2019, despite a Freedom of Information Act request by Nuclear Watch that the agency never responded to.
To illustrate the importance of these Performance Evaluation Reports, in its FY 2021 Los Alamos Lab summary NNSA noted that the contractor “[s]ucessfully made advances in pit production processes…” Plutonium “pits” are the fissile cores of nuclear weapons whose expanded production the Pentagon has identified as the number one issue in the United States’ $2 trillion nuclear weapons “modernization” program. NNSA has directed the Los Alamos National Laboratory (LANL) to begin producing at least 30 pits per year by 2026 and the Savannah River Site (SRS) in South Carolina to begin producing at least 50 pits per year by 2030.
A Guide to “Scoping” the New LANL SWEIS
“Scoping” means determining the issues that should be included in public analyses required by the National Environmental Policy Act (NEPA) of proposed major actions by the federal government. According to the Department of Energy ‘s own NEPA implementation regulations, DOE must prepare a new or supplemental site-wide environmental impact statement (SWEIS) for its major sites when there are “significant new circumstances or information relevant to environmental concerns.” The last site-wide EIS for the Los Alamos National Laboratory (LANL) was completed in 2008 and is badly outdated. Moreover, since 2018 the National Nuclear Security Administration (NNSA), DOE’s semi-autonomous nuclear weapons agency, has been aggressively expanding the production of plutonium “pit” bomb cores for nuclear weapons at the Lab.
On August 19, 2022, NNSA finally announced its intent to prepare a new LANL SWEIS, but apparently the agency will not address expanded plutonium pit production.1 NNSA’s dubious argument is that it performed the legally required NEPA analysis for expanded plutonium pit production in a 2008 Complex Transformation Programmatic Environmental Impact Statement, the 2008 LANL SWEIS and a woefully inadequate “Supplement Analysis” in 2020 that concluded a new SWEIS was not needed. 2 3
Issues That Must Be Addressed in a New LANL SWEIS
This is meant to be a guide to (or list of) the issues that must be addressed in a new draft LANL SWEIS. It is not completely exhaustive, nor is it a comprehensive fact sheet on the substance of the issues. Nuclear Watch New Mexico will offer suggested scoping comments for interested citizens and submit its own comprehensive formal comments before the October 3 deadline or extended deadline (see “Timing” below).
The Future of Nuclear Nonproliferation and Disarmament is the Treaty PROHIBITING Nuclear Weapons (TPNW)
The Future of Nuclear Nonproliferation and Disarmament is in Danger is the Treaty PROHIBITING Nuclear Weapons (TPNW)
A “Council of Councils” Global Memo titled, “The Future of Nuclear Nonproliferation and Disarmament Is in Danger” highlights the analysis of five experts on analyze the “failure after a month of negotiations of the tenth review conference (RevCon) of the Treaty on the Non-Proliferation of Nuclear Weapons (NPT) concluding on August 26 without a consensus final document, raising concerns about weakening efforts to promote nuclear nonproliferation, disarmament, and the peaceful use of nuclear energy.”
The International Campaign to Abolish Nuclear Weapons recently published an article along the same lines titled, “NPT Review Conference fails to address current security environment.” The final draft outcome document had already been significantly weakened throughout the negotiations, however Russia still refused to accept the final version and the conference ended without an agreement. ICAN: “Although the NPT Review Conference failed, there was a success this year in June. At the First Meeting of States Parties, TPNW states parties committed to the Vienna Action Plan, 50 concrete steps to advance disarmament, help victims of nuclear use and testing, commit to inclusion and progressive steps on gender and disarmament.”
Robin Lloyd of the Women’s International League for Peace and Freedom asks the leading questions, “How can the US consider signing the draft preamble while the House and Senate are finalizing the National Defense Authorization Act which calls for the modernization of our nuclear arsenal? How can our government even take part in this Conference while it is seeking funding for a renewed nuclear edifice of destruction including Modernized Strategic Delivery Systems and Refurbished Nuclear Warheads? Over the next decade, the United States plans to spend $494 billion on its nuclear forces, or about $50 billion a year, according to a 2019 Congressional Budget Office report. Trillions of dollars for submarines and bombers and buried nuclear missiles. Things they are committing to not use. Please, does this make sense?”
Faced with an unacceptable dangerous global situation, the TPNW will do what the NPT failed to: adopt a credible plan to advance disarmament, help victims of nuclear use and testing, and condemn any and all threats to use nuclear weapons.
The NPT is in crisis, but the TPNW is already starting to carry out its role of implementing the nuclear disarmament obligations of the NPT. All other NPT states parties that have failed to make progress during the NPT Review Conference should join this work too.
LANL Gestures to Gas Shortage
In response to statewide natural gas outages across New Mexico, LANL closed February 4th. The gesture may reflect that LANL gas use is roughly the equivalent[1] of 22,310 people, nearly the same as the 25,000 people that media reports are without recent service.
Although shutting down LANL would almost make up for the shortage in gas affecting northern New Mexico, it is not quite that equitable. LANL and the Los Alamos town site have their own dedicated gas pipeline coming from the NW San Juan Basin, in New Mexico. Whereas Albuquerque, Santa Fe, Espanola, Taos etc are fed natural gas from the Permian Basin gas fields in Texas. Therefore it is questionable that curtailing operations (which cost taxpayers ~$6 million/per day) at LANL helps to relieve gas supplies in northern New Mexican communities.
It also begs the question of why aren’t Northern New Mexico gas supplies coming from the plentiful San Juan basin, one of the largest reserves in the nation, which is geographically closer? Espanola and Taos are reportedly suffering in recent subzero temperatures because they are at the “end of the line” of gas coming from Texas. But the privileged Lab and Los Alamos town site would not be subject to the same short supply.
[1] According to the 2006 LANL Site-Wide Environmental Impact Statement the Lab uses an average of 37.4 million cubic meters of natural gas annually, or 1.32 billion cubic feet (1 cubic meter = 35.31 cubic feet). Wikipedia says Americans use 18.4 trillion cubic feet per year. U.S. population is around 311 million people, hence per person use = 59,164 cubic ft/yr. Population of Espanola = ~10,000, hence uses ~ 591,640,000 cubic ft/yr. Population of Taos = 5,550, hence uses ~ 328,360,200 cubic ft/yr. Therefore, LANL uses twice as natural gas as Espanola, 4 times as much as Taos. TA-55 (site of plutonium pit production) alone uses 45 million cubic ft per year.
Nuclear Science Week, by the makers of the “Bomb”
This press release from NNSA is really deceptive. The words “nuclear” and “science” are used quite a bit, but “weapons” only like in “As we continue to turn a Cold War nuclear weapons complex into a 21st century nuclear security enterprise.” The uninformed reader would get the impression that NIF, DARHT and the Z machine are not really about nuclear weapons, when of course they are.
Also, the uninformed might get the impression that the National Ignition Facility has already achieved ignition, which couldn’t be farther from the truth (and it’s doubtful that NIF ever will achieve ignition). Nor is DARHT yet working as advertised, even after more than a decade of operations. And then there are the cost overruns: NIF from ~$1 billion to ~$5 billion and DARHT from ~$35 million to ~$275 million, not including dubious reprogramming of other monies for both projects.
And supercomputers fighting AIDS and bringing “products to market faster” (can you spell j-o-b-s?). It’s a wonderful world, this “21st century nuclear security enterprise.”
I cringe to think that a congressional staffer (or anybody) would read stuff like this and think it true.
NNSA Will Not be “Burdened” by Costs for Clean-Up at New KCP
I found what I think is an interesting quote concerning the new KCP in NNSA’s FY 2011 Stockpile Stewardship and Management Plan (which is the plan that NNSA showboats to Congress).
“Finally, because the new facility [KCP] will be leased, there will be no capital investment and NNSA will not be burdened by costs for legacy disposition should the mission ever be discontinued.” NNSA FY11 SSMP Annex D, p. 44,
This sounds to me like the federal government is walking away from any future obligation to clean up any contamination at the new Kansas City Plant. I think that interesting given how there is no real federal commitment to clean up the old plant which is badly contaminated.
The rest of NNSA’s FY 2011 Stockpile Stewardship and Management Plan (summary and Annex A) can be viewed.
Annex B and C are classified.
If NNSA won’t be burdened for clean-up, who will?
Weight Restrictions for Weapons Workers?
Question: What is the tripping-man impact scenario for a nuclear weapons production technician?
Answer: A 280 lb production technician traveling 2 .5 miles per hour.
We are all familiar with the horrible impacts that nuclear weapons have on humans, but now we have an Analysis of Human Impacts on Weapons. The Defense Nuclear Facilities Safety Board (Board) recently reviewed the Hazard Analysis Reports (HARs) for several nuclear explosive operations at the Pantex Plant and found that Plant could have a weight problem with its production technicians (PTs).
Of concern is that the weapons design agency supplies data on weapons responses for “tripping-man impact scenarios” based on the energy imparted by a 280 lb PT traveling 2.5 miles per hour. Tools and parts could break if someone larger tripped into a warhead while going faster that 2.5 mph. And Pantex has no controls in place to limit these human impact energies.
The DNFSB concluded that the “maximum PT impact energy does not represent an uncontrolled environment, such as lightning, earthquake, or meteorological conditions.” Pantex imposes other physical qualifications for PTs (such as age, sight, speech), as well as other limitations specified by the Human Reliability Program. They believe that weapon responses should be reevaluated for higher impact energies, or that Pantex should limit PT weights.
Once Again – It’ll Cost More and Take Longer
Decades of nuclear materials production at the Department of Energy’s (DOE) Savannah River Site in South Carolina have left 37 million gallons of radioactive liquid waste in 49 underground storage tanks. This is just a small part of DOE’s Cold War cleanup legacy that currently has an estimate of $360+ billion to remediate across the country. This estimate keeps going up.
The United States Government Accountability Office released a September 2010 report about persistent concerns with efforts to cleanup these underground radioactive waste tanks. Like so many GAO reports before, the findings are that it will cost more and take longer:
Emptying, cleaning, and permanently closing the 22 underground liquid radioactive waste tanks at the Savannah River Site is likely to cost significantly more and take longer than estimated in the December 2008 contract between DOE and Savannah River Remediation, LLC (SRR). Originally estimated to cost $3.2 billion, SRR notified DOE in June 2010 that the total cost to close the 22 tanks had increased by more than $1.4 billion or 44 percent. Much of this increase is because DOE’s cost estimate in the September 2007 request for proposals that formed the basis of the December 2008 contract between DOE and SRR was not accurate or comprehensive.
Legacy cleanup at Los Alamos is currently estimated by the Lab to be around $2-3 billion. This is required to be complete by 2015 by a consent Order agreement with the State of NM. This estimate includes the Lab’s version of cleanup, which is leaving most the waste in the ground perched above our aquifer. Actually removing the waste is estimated at $20 billion. The final decision on what type of cleanup will be made by the State, which would like to have you the public’s input.
Cleanup at Los Alamos is one project that needs to cost more.
CMRR is Key to Expanded Plutonium Pit Production
While being narrowly correct, LANL PR man Kevin Roark is misleading when he claims [in a June 25, Letter to the Editor of the Santa Fe New Mexican newspaper] that plutonium pit production will not take place in the new Chemistry and Metallurgy Research Replacement Project (CMRR). What he fails to disclose is that the Lab is not building just one facility, but instead is creating an integrated manufacturing complex for expanded production for which the CMRR is absolutely key. This complex will consist of LANL’s existing production facility “PF-4” with ~$300 million in upgrades; CMRR’s already completed first phase, the $400 million “Rad Lab”; and the future $4 billion CMRR “Nuclear Facility,” now being debated.
The Nuclear Facility will be literally next door to PF-4 and linked to it via underground tunnel. While pits are physically manufactured in PF-4’s glovebox lines, the Nuclear Facility’s central missions of “materials characterization” and “analytical chemistry” are essential operations that ensure “weapons-grade” plutonium and pit production quality control. The National Nuclear Security Administration’s own documents show that the Nuclear Facility is being specifically sized to support expanded production of up to 80 pits per year, quadruple LANL’s currently approved rate. It is also planned to have a vault for up to six metric tons of “special nuclear materials,” capable of storing around 1,000 pits.
Roark must think that New Mexicans are naïve enough to accept the Lab’s claims that the CMRR is all about “science” even as LANL becomes more and more a production site. Sadly, this is only part and parcel of the substantial rebuilding of the U.S. nuclear weapons production complex, which will also include a new $3.5 billion Uranium Processing Facility in Tennessee and a new privately financed Kansas City Plant for production of the 1,000’s of nonnuclear components that go into a nuclear weapon.
Many New Mexicans hoped for serious mission diversification at Los Alamos, which some $5 billion sunk into its plutonium infrastructure will almost certainly shut the door on. Schools in Santa Fe and all across the country are being closed due to lack of funding. Nevertheless, our government is preparing to spend some $10 billion to build new production plants even as we are purportedly working toward the declared long-term national security goal of a nuclear weapons-free world. To get there, citizens need to push the politicians to meet the needs of everyday people, not those of the vested nuclear weaponeers.
Revised Estimates for Safer Gloveboxes Hurt Budget
On the heels of a GAO report made public Monday, which stated that accounting procedures used by various branches of the U.S. nuclear weapons complex are preventing NNSA from pinpointing the exact total cost of maintaining its nuclear deterrent, the Defense Nuclear Facilities Safety Board (DNFSB) has released a weekly report also showing LANL’s inability to accurately estimate even the tiniest of specific costs.
In the June 4th weekly report for Los Alamos Lab, the DNFSB stated that the Lab underestimated the cost of seismically upgrading gloveboxes at its plutonium pit production complex by an order of magnitude. The DNFSB stated, “…the expected cost of seismic upgrades to individual gloveboxes has risen from an original estimate of about $80,000 per glovebox to a current estimate of approximately $850,000.” In addition, the Lab also ended up doubling the number of gloveboxes that need the upgrades as a priority up to 157.
So, in effect, the Labs original estimate for this glovebox work was $6.4 million (80 gloveboxes at $80,000 each), but the revised estimate is now $133.4 million (157 gloveboxes at $850,000 each). It’s hard to understand how new bracing and bolts to upgrade the legs of these gloveboxes could cost $80,000 each, much less $850,000. It’s not rocket science. Maybe the private corporation running the Lab underestimated the profits that they wanted to make for this much-needed work. Make no mistake, there will be performance- based incentive award fees for the work, as well as for the design and even the estimates.
In safety documents, the Lab originally stated that these upgrades would be done by 2011 to mitigate the possible off-site dose of plutonium to the public in the event of a large earthquake and subsequent facility fire. Guess what? The Lab will be behind schedule as well as way over budget. But LANL is already using its commitment for future glovebox seismic upgrades to reduce the mitigated dose consequence for a seismically-induced event in its dose calculations. So the public will be safe, only on paper, until the Lab finds the time and the money to upgrade those glovebox legs.
The Lab should focus on upgrading existing facilities and equipment and prove its ability and desire to protect the public before embarking on unneeded new construction, such as the CMRR – Nuclear Facility.
A Bargain – But At What Cost?
The Government Accounting Office (GAO) released a new report today. Actions Needed to Identify Total Costs of Weapons Complex Infrastructure and Research and Production Capabilities, GAO-10-582, June 2010
I’ll start with the conclusion –
Within the global community, the Administration, and Congress, a bargain is being struck on nuclear weapons policy. Internationally, if the [START] treaty is ratified, significant stockpile reductions [will] have been negotiated between the United States and Russia. Domestically, a new Nuclear Posture Review has provided an updated policy framework for the nation’s nuclear deterrent. To enable this arms reduction agenda, the Administration is requesting from Congress billions of dollars in increased investment in the nuclear security enterprise to ensure that base scientific, technical, and engineering capabilities are sufficiently supported … For its part, NNSA must accurately identify these base capabilities and determine their costs in order to adequately justify future presidential budget requests and show the effects on its programs of potential budget increases. As it now stands, NNSA may not be accurately identifying the costs of base capabilities because … NNSA cannot identify the total costs to operate and maintain essential weapons activities facilities and infrastructure, … Without taking action to identify these costs, NNSA risks being unable to identify the return on investment of planned budget increases on the health of its base capabilities or to identify opportunities for cost saving…NNSA has the opportunity to mitigate these risks by addressing them through the ongoing revision of work breakdown structures and through identifying means of collecting the total costs … Without taking these actions, NNSA will not have the management information it needs to better justify future budget requests by making its justifications more transparent. Additionally, the availability of this information will assist Congress with its oversight function. (Pg. 25)
It looks like NNSA does not know exactly the total costs of its infrastructure budget, but it does know that it wants more. The report tells us that without identifying the total costs of products and capabilities, NNSA will be challenged to explain the effects of funding changes or justify the necessity for increased investment to support or enhance base capabilities. (Pg. 25)
The reduction in nuclear warhead numbers will mean an increase spending. “In such an environment, NNSA is likely to face increased scrutiny of its planning, programming, and budget execution to determine the effect of funding increases on the overall health of base capabilities.” (Pg. 24)
Curating the Stockpile: Remanufacturing Fogbank
I only now happened to run across the article below from the Los Alamos National Laboratory Nuclear Weapons Journal about how the remanufacturing of Fogbank was reestablished. As dated as it is, I think its implication is very important that existing programs are more than sufficient to keep the nuclear weapons stockpile safe and reliable, until eventual disarmament.
You may recall that the loss of Fogbank was a bit of a crisis that seriously delayed the W76 Life Extension Program. It had at various times been used as rationale for why existing LEPs would not work in the long run because of necessary changes to materials, loss of knowledgeable workforce, etc. By extension this was used to argue why Reliable Replacement Warheads should be designed and built.
But this article demonstrates that all that was needed was to simply give some emphasis to reestablishing fogbank production. Plus as an added bonus, it has some pleasing wonky detail. “It’s the impurity, stupid!” [see link below]
LANL Nuclear Weapons Journal, Issue 2 • 2009, pp. 21-22
Fogbank: Lost Knowledge Regained
Power of the Purse over DOE Projects
I was in Washington, DC last week and heard a number of congressional offices express support for the CMRR-Nuclear Facility, indicating what we already know, that it will be very difficult to defeat directly. However, the issue of costs is another matter, and I have some hope that the Nuclear Facility can die a death of 1,000 cuts.
For example, while in DC I met with a staff person knowledgeable about DOE project cost accounting requirements introduced by the Senate Armed Services Committee. I expressed my concern that LANL could implement its first segment of CMRR-Nuclear Facility construction without having come up with total costs, thus steamrolling the project. [Reminder: we are now $4.5 billion for estimated total project costs and climbing.] That staffer said that sort of thing will not be allowed to happen. Further, while being in favor of some advance site prep, that staffer said LANL would not be allowed to construct the concrete batch plant and replace 225,000 cubic yards of weak volcanic ash strata with “lean concrete” until total project costs are in.
The requirements were introduced as SEC. 4713. NOTIFICATION OF COST OVERRUNS FOR CERTAIN DEPARTMENT OF ENERGY PROJECTS.
I realize this is not a showstopper, but it is something. It should slow the CMRR-NF down some, which hopefully we can capitalize on. Further, it may provide us with ammo over the project’s tremendous and escalating costs.
Nick Roth of the Alliance for Nuclear Accountability was instrumental in suggesting this cost accounting requirement to Congress.
Past NukeWatch Events
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
Past Work Product (2019-)
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
2019
November 26, 2019 Press Release November 24, 2019 Press Release November 19, 2019 Plutonium Pit Production Workshop Presenters:
August 12, 2019 NEPA Comments NukeWatch’s 22-page formal comments on expanded plutonium pit production Until NNSA fully complies with the National Environmental Policy Act through the preparation of a programmatic environmental impact statement on expanded plutonium pit production, Nuclear Watch believes that any irreversible or irretrievable commitment of resources to either the expansion of pit production at the Los Alamos Lab or to the repurposing of the MOX Facility at the Savannah River Site is unlawful. Read/Download the Full Document HERE July 25, 2019 NEPA Comments Scoping comments on NNSA draft EIS for plutonium pit production at the Savannah River Site THE NEED FOR A PROGRAMMATIC ENVIRONMENTAL IMPACT STATEMENT: This is our first and primary concern, that NNSA must first complete a programmatic environmental impact statement (PEIS) on its nation-wide plans for plutonium pit production, in advance of the Savannah River Site-specific environmental impact statement. To get right to the point, we argue that the SRS EIS process should go no further than this scoping period and should resume only after a completed formal Record of Decision for a new or supplemental PEIS. Read/Download the Full Document HERE July 9, 2019 Plutonium Pit Production Fact Sheet Expanding Nuclear Pit Production: The Facts and What You Can Do The Facts Read/Download the Full Document HERE June 10, 2019 News Release In a victory for transparency and legal compliance by the government, the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) today published a “Notice of Intent” in the Federal Register to complete environmental reviews on its controversial proposal to expand plutonium “pit” production for new and refurbished nuclear weapons. [embeddoc url="https://nukewatch.org/wp-content/uploads/2019/06/SRS-plutonium-bomb-plant6-14-19.pptx" download="all" viewer="google"] Read/Download the Full News Release HERE June 4, 2019 Press Release On behalf of three public interest organizations - Nuclear Watch New Mexico, Tri-Valley Communities Against a Radioactive Environment and Savannah River Site Watch – attorneys for the law firm of Meyer Glitzenstein & Eubanks and the Natural Resources Defense Council recently sent a 16-page letter to Lisa Gordon-Hagerty, head of the National Nuclear Security Administration (NNSA). The detailed letter warns the nuclear agency to not proceed with aggressive plans to expand plutonium pit production without first meeting its legal requirements for timely public review and comment under the National Environmental Policy Act. Read/Download the Full Press Release HERE May 31, 2019 Press Release Last Wednesday, facility operations personnel entered a service room and noticed a leak emanating from a valve on the radioactive liquid waste (RLW) system. Upon subsequent visual inspection by a radiological control technician, RLUOB engineers believe that this valve, and 6 similar valves, may be constructed of carbon steel. The RLW system handles radioactive liquid waste streams from chemistry operations that include nitric and hydrochloric acids—carbon steel valves would be incompatible with these solutions. The suspect valves are also in contact with stainless steel piping, which would create another corrosion mechanism. RLUOB management plans to drain the affected piping sections and develop a work package to replace all of the suspect valves. They will also confirm the valve materials and if shown to be incorrect, investigate the cause of this failure in the design, procurement, and installation processes. The valves were installed in 2013 as part of a modification to add straining and sampling capabilities that were not in the included in the original design. [Please note that DNFSB reports are posted a few weeks later than dated.] This immediately raises two crucial issues: 1) the National Nuclear Security Administration’s (NNSA’s) plans for expanded plutonium pit production; and 2) the current attempt by the Department of Energy to restrict Safety Board access to its nuclear weapons facilities. Read/Download the Full Press Release HERE April 26, 2019 Consent Orders Comparison On March 1, 2005, after arduous negotiations and threats of litigation, the New Mexico Environment Department (NMED), Department of Energy (DOE), and Los Alamos National Laboratory (LANL) entered into a Consent Order specifying the schedule for investigation and cleanup of the Lab’s hundreds of contaminated sites. This Consent Order (CO) was LANL’s agreement to fence-to-fence cleanup of Cold War legacy wastes, which NMED began to enforce. Read/Download the Full Comparison HERE March 25, 2019 Press Release More than 25 years after the end of the Cold War, all eight established nuclear weapons powers are “modernizing” their stockpiles. Talks have broken down with North Korea, the new nuclear weapons power. Nuclear-armed India and Pakistan narrowly averted war last month. Russian President Vladmir Putin made new nuclear threats in response to Trump’s announced withdrawal from the Intermediate-Range Nuclear Forces Treaty. This could lead to hair-trigger missile emplacements in the heart of Europe and block extension of the New Strategic Arms Reduction Treaty with Russia. If so, the world will be without any nuclear arms control at all for the first time since 1972. Meanwhile, the U.S. criticizes non-weapons states for signing a nuclear weapons ban treaty, despite the fact there have long been treaties completely banning chemical and biological weapons of mass destruction that the U.S. seeks to enforce. The pending international NonProliferation Treaty (NPT) Preparatory Committee conference at the United Nations is widely expected to collapse in failure because of the nuclear weapons powers’ failure to enter into serious negotiations leading to nuclear disarmament. The NPT’s Article VI mandate for those negotiations has been in effect since 1970, when the Treaty was signed by 189 countries (more than any other treaty). Read/Download the Full Press Release HERE March 26, 2019 NukeWatch Budget Compilation Nuclear Watch New Mexico — Department of Energy FY 2020 Nuclear Weapons Budget Request |
2018
November 16, 2018 Plutonium Pit Production Fact Sheet Plutonium pits are the radioactive cores or “triggers” of nuclear weapons. Their production has always been a chokepoint of resumed industrial-scale U.S. nuclear weapons production ever since a 1989 FBI raid investigating environmental crimes shut down the Rocky Flats Plant near Denver. In 1997 the mission of plutonium pit production was officially transferred to its birthplace, the Los Alamos National Laboratory (LANL) in northern New Mexico, but officially capped at not more than 20 pits per year. However, in 2015 Congress required expanded pit production by 2030 whether or not the existing nuclear weapons stockpile actually needs it. This will support new military capabilities for nuclear weapons and their potential use. Read/Download the full fact sheet pdf HERE October 31, 2018 Nuclear Watch New Mexico, Savannah River Site Watch, and Tri-Valley CAREs sent a letter of demand to the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) to inform the government that its plan to quadruple the production rate of plutonium bomb cores is out of compliance with the National Environmental Policy Act (NEPA). NNSA’s premature plan to quadruple the production rate of plutonium bomb cores (“pits”), the heart of all US nuclear weapons, is out of compliance with requisite environmental law, the groups argue, as NNSA has failed to undertake a legally-mandated programmatic review and hold required public hearings. View/Download the entire press release HERE NukeWatch Comments, September 27, 2018 Nuclear Watch New Mexico is submitted formal comments to express in the strongest possible terms our opposition to DOE Order 140.1 Interface with the Defense Nuclear Facilities Safety Board. We find that the Department of Energy’s (DOE’s) attempt to restrict and suppress DNFSB access is very misguided, arrogant, and likely illegal in that it acts contrary to the Board’s enabling legislation. June 8, 2018 Press Release New Contractors Selected For Expanded Nuclear Weapons Production at Los Alamos Santa Fe, NM. Today the Department of Energy's National Nuclear Security Administration (NNSA) announced its choice for the new management and operating contract for the Los Alamos National Laboratory (LANL).The new contractor, Triad National Security, LLC, is a limited liability company consisting of the Battelle Memorial Institute, the University of California and Texas A&M University. All three are non-profits, and it is unclear how this will affect New Mexico gross receipts taxes. Battelle claims to be the world's largest non-profit technology research and development organization, and manages a number of labs including the Lawrence Livermore and Idaho National Laboratories. Texas A&M was founded in 1876 as the state's first public institution of higher learning and has the largest nuclear engineering program in the country. DOE Secretary Rick Perry is an avid A&M alumnus. May 31, 2018 Press Release Santa Fe, NM & Columbia, SC - "Two key U.S. Department of Energy documents on future production of plutonium "pits" for nuclear weapons, not previously released to the public, fail to justify new and upgraded production facilities at both the Los Alamos National Laboratory (LANL) in New Mexico and the Savannah River Site (SRS) in South Carolina." May 15, 2018 Fact Sheet May 10, 2018 Press Release What's Not in NNSA's Plutonium Pit Production Decision
- NNSA did not mention that up to 15,000 "excess" pits are already stored at the Pantex Plant near Amarillo, TX, with up to another 5,000 in "strategic reserve." The agency did not explain why new production is needed given that immense inventory of already existing plutonium pits. (In 2006 independent experts found that pits last a least a century. Plutonium pits in the existing stockpile now average around 40 years old.) May 2, 2018 Press Release "NNSA should begin nation-wide review of plutonium pit production, why it's needed, and what it will cost the American taxpayer in financial, safety and environmental risks. These are all things that the public should know." -Jay Coghlan, Director, Nuclear Watch New Mexico. April 26, 2018 NukeWatch Comments LANL Rad Lab: Formal Comments Under Nat'l Environmental Policy Act Against raising plutonium limit at LANL Rad Lab View/download Nuclear Watch comments as submitted Excerpt:
- NNSA is planning a 10-fold increase in plutonium at the LANL Rad Lab with a view to ramping up the production of plutonium pits for new nuclear weapons. March 26, 2018 Press Release United States To Begin Construction Of New Nuclear Bomb Plant The National Nuclear Security Administration (NNSA) announced on Friday, March 23, that it was authorizing the start of construction of the Uranium Processing Facility (UPF) and two sub-projects at the Y-12 National Security Complex in Oak Ridge, Tennessee. The UPF is a facility dedicated solely to the manufacture of thermonuclear cores for US nuclear bombs and warheads.
Jay Coghlan of NukeWatch points out that "This project already has a long history, and it is instructive. In 2013, DOE announced it was 85% finished with the UPF design when it ran into the 'space/fit' issue- and more than a half-billion taxpayer dollars were just written off. In private business, that kind of thing gets you fired. In DOE's world of contractors running amok, they not only didn't get fired, not one Congressional hearing was held and the UPF budget went up the next year!" - See full press release for all the details (PDF) March 1, 2018 Press Release The Regional Coalition of LANL Communities: Benefits for the Select Few Santa Fe, NM- According to media reports, Andrea Romero, Executive Director of the Regional Coalition of LANL Communities, is accused of charging some $2,200 dollars of unallowable travel costs, such as alcohol and baseball tickets, while lobbying in Washington, DC for additional funding for the Los Alamos National Laboratory (LANL). She in turn accused the nonprofit group Northern New Mexico Protects of political motivations in revealing these questionable expenses. Romero is running in the Democrat Party primary against incumbent state Rep. Carl Trujillo for Santa Fe County's 46th district in the state House of Representatives. For all the details, see full press release PDF February 28, 2018 Press Release Santa Fe, NM. On December 17, 2017, the Department of Energy (DOE) awarded a separate $1.4 billion contract for cleanup at the Los Alamos National Laboratory (LANL) to Newport News Nuclear BWXT-Los Alamos, LLC (also known as "N3B"). This award followed a DOE decision to pull cleanup from LANL's prime contractor, Los Alamos National Security, LLC (LANS), after it sent an improperly prepared radioactive waste drum that ruptured underground at the Waste Isolation Pilot Plant (WIPP). That incident contaminated 21 workers and closed WIPP for nearly three years, costing taxpayers at least $1.5 billion to reopen. (See all the details in the full press release) February 26, 2018 Press Release Detailed NNSA Budget Documents Accelerates Nuclear Weapons Arms Race Santa Fe, NM. Late Friday February 23, the Trump Administration released the detailed FY 2019 budget for the National Nuclear Security Administration (NNSA), the semi-autonomous nuclear weapons agency within the federal Department of Energy. Overall, NNSA is receiving a $2.2 billion boost to $15.1 billion, a 17% increase above the FY 2018 enacted level. Of that, a full $11 billion is for the budget category [Nuclear] "Weapons Activities", 18% above the FY 2018 level. Of concern to the American taxpayer, DOE and NNSA nuclear weapons programs have been on the congressional Government Accountability Office's High Risk List for project mismanagement, fraud, waste and abuse since its inception in 1990... (See all the details in the full press release) February 22, 2018 Press Release Santa Fe, NM. Today the National Nuclear Security Administration announced an Environmental Assessment to increase the amount of plutonium used in the Radiological Laboratory Utility and Office Building (aka the "Rad Lab") at the Los Alamos National Laboratory from 38.6 grams of plutonium-239 equivalent to 400 grams. This 10-fold increase is significant because it will dramatically expand materials characterization and analytical chemistry capabilities in the Rad Lab in support of expanded plutonium pit production for future nuclear weapons designs. It also re-categorizes the Rad Lab from a "radiological facility" to a "Hazard Category-3" nuclear facility. View/Download full press release February 12, 2018 Press Release Trump's Budget Dramatically Increases Nuclear Weapons Work Santa Fe, NM In keeping with the Trump Administration's recent controversial Nuclear Posture Review, today's just released FY 2019 federal budget dramatically ramps up nuclear weapons research and production. January 12, 2018 Press Release Draft Nuclear Posture Review Degrades National Security Yesterday evening the Huffington Post posted a leaked draft of the Trump Administration's Nuclear Posture Review (NPR). This review is the federal government's highest unclassified nuclear weapons policy document, and the first since the Obama Administration's April 2010 NPR. 2017 |
2017
December 22, 2017 Press Release New Mexico Environment Department Surrendered to DOE Extortion Santa Fe, NM. The New Mexico State Auditor Office recently questioned whether two settlements between the New Mexico Environment Department and the Department of Energy were in the best interests of New Mexico. That Office noted: (View/download full press release) December 20, 2017 Press Release Los Alamos Hires New Contractor - Starts Cleanup On the Cheap Santa Fe, NM- Today the Department of Energy (DOE) announced the award of the new Los Alamos National Laboratory legacy cleanup contract to Newport News Nuclear BWXT-Los Alamos, LLC. The $1.39 billion contract is for ten years, which works out to $139 million per year... View/download the full press release Public Presentation, December 2, 2017 October 31, 2017 Press Release Today, in Washington, DC, the Congressional Budget Office released its new report, "Approaches for Managing the Costs of U.S. Nuclear Forces, 2017 to 2046". The Congressional Budget Office estimates that the most recent detailed plans for nuclear forces, which were incorporated in the Obama Administration's 2017 budget request, would cost $1.2 trillion in 2017 dollars over the 2017-2046 period: more than $800 billion to operate and sustain (that is, incrementally upgrade) nuclear forces and about $400 billion to modernize them.... Driving this astronomical expense is the fact that instead of maintaining just the few hundred warheads needed for the publicly claimed policy of "deterrence," thousands of warheads are being refurbished and improved to fight a potential nuclear war. This is the little known but explicit policy of the U.S. government! October 27, 2017 Press Release Santa Fe, NM. On the evening of Wednesday October 25, the Santa Fe City Council passed a resolution requesting that the New Mexico Environment Department strengthen the revised Los Alamos National Labs cleanup order to call for additional characterization of legacy nuclear wastes, increased cleanup funding, and significant additional safety training. The resolution also called for the suspension of any planned expanded plutonium pit production until safety issues are resolved. (view/download full press release) October 6, 2017 Press Release Santa Fe, NM. Nuclear Watch New Mexico strongly applauds the awarding of the Nobel Peace Prize to the International Campaign to Abolish Nuclear Weapons (disclosure: NukeWatch is one of ICAN's ~400 member groups around the world). This award is especially apt because the peoples of the world are now living at the highest risk for nuclear war since the middle 1980's, when during President Reagan's military buildup the Soviet Union became convinced that the United States might launch a pre-emptive nuclear first strike. Today, we not only have Trump's threats to "totally destroy" North Korea and Kim Jong-un's counter threats, but also renewed Russian fears of a US preemptive nuclear attack... Generally unknown to the American taxpayer, our government has quietly tripled the lethality of the US nuclear weapons stockpile..." (view/download complete press release) NukeWatch fact sheet, September 26, 2017 The National Nuclear Security Administration's own documents have explicitly stated that expanded pit production would have no significant positive effect on job creation and the regional economy of northern New Mexico. Nuclear Watch argues that expanded plutonium pit production could actually have negative effect if it blocks other economic alternatives such as comprehensive cleanup, which could be the real job producer. Moreover, given LANL's poor safety and environmental record, expanded plutonium pit production could have a seriously negative economic impact on northern New Mexico in the event of any major accidents. September 15, 2017 Press Release Santa Fe, NM. The Los Alamos National Laboratory (LANL) has detected far more hexavalent chromium (Cr) contamination than previously estimated in the "sole source" regional groundwater aquifer that serves Los Alamos, Santa Fe and the Espanola Basin. Sampling in July from a new well meant to inject treated groundwater back into the aquifer detected chromium contamination five times greater than the New Mexico groundwater standard of 50 micrograms per liter (ug/L). View/download the full press release September 11, 2017 Press Release Talking Points: The 2016 LANL Cleanup Consent Order Should Be Rescinded The 2005 LANL Cleanup Consent Order was all about the enforceable schedules. It required DOE and LANL to investigate, characterize, and clean up hazardous and mixed radioactive contaminants from 70 years of nuclear weapons research and production. It stipulated a detailed compliance schedule that the Lab was required to meet. Under Gov. Martinez, NMED Secretary Ryan Flynn granted more than 150 compliance milestone extensions at the Lab's request, effectively eviscerating it. View/download the complete talking points July 20, 2017 Press Release Washington, DC Today, the Oak Ridge Environmental Peace Alliance (OREPA), Nuclear Watch New Mexico, and the Natural Resources Defense Council filed a federal lawsuit to stop construction of the problem-plagued Uranium Processing Facility (UPF) until legally required environmental review is completed. The UPF, located at the National Nuclear Security Administration's (NNSA's) Y-12 production plant near Oak Ridge, TN, is slated to produce new thermonuclear weapons components until the year 2080. The UPF is the tip of the spear for the U.S.'s planned one trillion dollar-plus make over of its nuclear weapons arsenal, delivery systems, and production plants. View/download the full press release June 19, 2017 Press Release Some Background on Plutonium Pit Production at the Los Alamos Lab Santa Fe, NM -The Washington Post has published the first in a series of articles on nuclear safety lapses in plutonium pit production at the Los Alamos Lab. Plutonium pits are the fissile cores of nuclear weapons that when imploded initiate the thermonuclear detonation of modern weapons. By the way, did you know? Plutonium facilities at LANL are- in principle- designed to withstand a serious earthquake of a degree expected to occur only once every 10,000 years. The last serious earthquake near the Lab is believed to have occurred 11,500 years ago. View/download the full press release ANA Report 2017: Accountability Audit May 19, 2017 Press Release SA Preview of Trump's Budget: More Nuclear Bombs and Plutonium Pit Production Santa Fe, NM. "The proposed level of funding for the National Nuclear Security Administration's (NNSA)'s Total Weapons Activities is $10.2 billion, a full billion above what was requested for FY 2017. In March, Trump's "skinny budget" stated NNSA's funding priorities as 'moving toward a responsive nuclear infrastructure', and 'advancing the existing warhead life extension programs'. Read the full press release for all the details. March 28, 2017 ANA workshop at UN Ban Treaty Conference Ban Treaty Conference: Alliance for Nuclear Accountability Panel Discussion March 28, 2017, UN, NYC:
March 2017 Fact Sheet Plutonium Pit Production at LANL (Updated March 2017) February 23, 2017 Press Release Costs Jump in Nuclear Weapons vs. Cleanup; Nuclear Weapons Winning over Environmental Protection Santa Fe, NM. America is at a crossroads, having to choose between an unnecessarily large, exorbitant, nuclear weapons stockpile, and cleanup that would protect the environment and water resources for future generations. Expanded nuclear weapons research and production, which will cause yet more contamination, is winning. Read the full press release for all the details. January 5, 2017 Press Release The National Nuclear Security Administration (NNSA) has publicly released its fiscal year 2016 Performance Evaluation Report (PER) for Los Alamos National Security, LLC (LANS), the for-profit contractor that runs the Los Alamos Lab. The Performance Evaluation Report is NNSA's annual report card on contractor performance, and overall the agency awarded LANS $59 million in profit out of a possible $65 million. The grade was 85% for the incentive part of the award. In 2012 Nuclear Watch New Mexico successfully sued NNSA to ensure that the Performance Evaluation Reports detailing taxpayers funds paid to nuclear weapons contractors are publicly available. In 2016 the NNSA decided to put the LANL management contract out for competitive bid, but granted LANS a contract extension until the end of September 2018. |
Media appearances including radio interviews are listed on the internal Media page
See the NukeWatch Channel at YouTube for our extensive playlists of key videos.
See the Nukewatch Twitter feed
See the Nukewatch Tumblr site
WatchBlog Posts:
Over 200 posts published since 2009. See archives at the WatchBlog
Earlier Work Product items are archived here