Court Rules U.S. Nuclear Weapons Production Plan Violates Federal Law
FOR IMMEDIATE RELEASE, October 3, 2024
Media Contacts:
Ben Cunningham, Esquire, SCELP, 843-527-0078, [email protected]
Tom Clements, Savannah River Site Watch, 803-834-3084, [email protected]
Jay Coghlan, Nuclear Watch New Mexico, 505-989-7342, [email protected]
Scott Yundt, Tri-Valley CAREs, 925-443-7148, [email protected]
Queen Quet, Gullah/Geechee Sea Island Coalition, 843-838-1171, [email protected]
AIKEN, S.C. — On September 30, United States District Court Judge Mary Geiger Lewis ruled that the United States Department of Energy (“DOE”) and its semi-autonomous nuclear weapons agency, the National Nuclear Security Administration (“NNSA”), violated the National Environmental Policy Act (“NEPA”) by failing to properly consider alternatives before proceeding with their plan to produce plutonium pits, a critical component of nuclear weapons, at the Los Alamos National Laboratory (“LANL”) in New Mexico and, for the first time ever, at the Savannah River Site (“SRS”) in South Carolina.
The Court found that the plan’s purpose had fundamentally changed from NNSA’s earlier analyses which had not considered simultaneous pit production at two sites. These changes necessitated a reevaluation of alternatives, including site alternatives, which Defendants failed to undertake prior to moving forward while spending tens of billions of taxpayers’ dollars. Therefore, the Court entered judgment in favor of Plaintiffs, the nonprofit public interest groups Savannah River Site Watch, Nuclear Water New Mexico and Tri-Valley Communities Against a Radioactive Environment (CAREs); the Gullah/Geechee Sea Island Coalition; and Tom Clements as an individual plaintiff.
As a result of this ruling, the Defendants are required to newly assess pit production at a nation-wide programmatic level which will mean undertaking a thorough analysis of the impacts of pit production at DOE sites throughout the United States, including radioactive waste generation and disposal. Under the National Environmental Policy Act (NEPA), this will provide the opportunity for public scrutiny of and formal comment on their assessments.
High Detections of Plutonium in Los Alamos Neighborhood – As We Enter a New Nuclear Arms Race the Last One is Still Not Cleaned Up
FOR IMMEDIATE RELEASE, August 15, 2024
Dr. Michael Ketterer – 928.853.7188 | Email
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – In April Nuclear Watch New Mexico released a map of plutonium contamination based on Lab data. Today, Dr. Michael Ketterer, Professor Emeritus of Chemistry and Biochemistry, Northern Arizona University, is releasing alarmingly high results from samples taken from a popular walking trail in the Los Alamos Town Site, including detections of some of the earliest plutonium produced by humankind.
On July 2 and 17 Dr. Ketterer, with the assistance of Nuclear Watch New Mexico, collected water, soil and plant samples from Acid Canyon in the Los Alamos Town Site and soil and plant samples in Los Alamos Canyon at the Totavi gas station downstream from the Lab. The samples were prepared and analyzed by mass spectrometry at Northern Arizona University to measure concentrations of plutonium, and to ascertain its sources in the environment.
NNSA Delays Urgent Research on Plutonium “Pit” Aging While Spending Tens of Billions on Nuclear Weapons Bomb Core Production
FOR IMMEDIATE RELEASE, April 17, 2024
Tom Clements, SRS Watch – 803.240.7268 | Email
Scott Yundt, TVC – 415.990.2070 | Email
Jay Coghlan – 505.989.7342 | Email
Nearly three years after filing a Freedom of Information Act request, the public interest group Savannah River Site Watch has finally received the National Nuclear Security Administration’s (NNSA’s) congressionally-required “Research Program Plan for Plutonium and Pit Aging.” However, the document is 40% blacked out, including references and acronyms. Plutonium “pits” are the radioactive cores of all U.S. nuclear weapons. The NNSA claims that potential aging effects are justification for a ~$60 billion program to expand production. However, the Plan fails to show that aging is a current problem. To the contrary, it demonstrates that NNSA is delaying urgently needed updated plutonium pit aging research.
In 2006 independent scientific experts known as the JASONs concluded that plutonium pits last at least 85 years without specifying an end date [i] (the average pit age is now around 40 years). A 2012 follow-on study by the Lawrence Livermore nuclear weapons lab concluded:
“This continuing work shows that no unexpected aging issues are appearing in plutonium that has been accelerated to an equivalent of ~ 150 years of age. The results of this work are consistent with, and further reinforce, the Department of Energy Record of Decision to pursue a limited pit manufacturing capability in existing and planned facilities at Los Alamos instead of constructing a new, very large pit manufacturing facility…” [ii]
Since then NNSA has reversed itself. In 2018 the agency decided to pursue the simultaneous production of at least 30 pits per year at the Los Alamos National Laboratory (LANL) in northern New Mexico and at least 50 pits per year at the Savannah River Site (SRS) in South Carolina. Upgrades to plutonium facilities at LANL are slated to cost $8 billion over the next 5 years. The redundant Savannah River Plutonium Processing Facility in South Carolina will cost up to $25 billion, making it the second most expensive building in human history.
NNSA’s Nuclear Weapons Budget Takes Huge Jump
Arms Race Accelerates with MIRVed Warheads
Los Alamos Lab Cleanup Cut
FOR IMMEDIATE RELEASE, March 11, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – Ironically the day after the film Oppenheimer was awarded multiple Oscars, the Department of Energy’s semi-autonomous National Nuclear Security Administration (NNSA) asked Congress for its biggest nuclear weapons budget ever. NNSA’s FY 2025 request for “Total Weapons Activities” is $19.8 billion, $700 million above what Congress recently enacted for FY 2024. It is also a full billion dollars above what President Biden asked for last year, which Congress then added to and will likely do so again.
The Biden Administration states that the $19.8 billion will be used to:
“[P]rioritize implementation of the 2022 National Defense Strategy and Nuclear Posture Review by modernizing the Nation’s nuclear deterrent to keep the American people safe. The Budget supports a safe, secure, reliable, and effective nuclear stockpile and a resilient, responsive nuclear security enterprise necessary to protect the U.S. homeland and allies from growing international threats.” whitehouse.gov/wp-content/uploads/2024/03/budget_fy2025.pdf, page 75.
The 2022 National Defense Strategy and Nuclear Posture Review for the first time posited two nuclear “near peers”, i.e. Russia and China, that need to be simultaneously “deterred.” This hinted at a potentially large nuclear buildup which this budget may now be implementing. That claimed need to deter two nuclear near peers was explicitly taken a step beyond just deterrence in an October 2023 report from the Strategic Posture Commission. It declared:
“Decisions need to be made now in order for the nation to be prepared to address the threats from these two nuclear-armed adversaries arising during the 2027-2035 timeframe. Moreover, these threats are such that the United States and its Allies and partners must be ready to deter and defeat both adversaries simultaneously.” ida.org/research-and-publications/publications/all/a/am/americas-strategic-posture, page vii (bolded emphasis added)
NNSA Suppresses How Taxpayers Money Is Spent
FOR IMMEDIATE RELEASE, January 19, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – The National Nuclear Security Administration (NNSA) has just released cursory two or three page summaries of contractors’ performance paid for by the American taxpayer. For the just ended fiscal year 2023, NNSA gave nothing less than grades of “Excellent” or “Very Good” in six broad mission goals for its major contractors. This is despite the constant cost overruns and schedule delays that are the rule, not the exception, in the nation-wide nuclear weapons complex. NNSA and its parent Department of Energy have been on the Government Accountability Office’s “High Risk List” for project mismanagement ever since GAO started that List in 1991.
A current example is the Uranium Processing Facility (UPF) at the Y-12 Plant near Oak Ridge, Tennessee, originally estimated in 2011 to cost $1.4 to $3.5 billion. After costs started going through the roof, NNSA and Senator Lamar Alexander (R.-TN), then-chair of Senate Energy and Water Appropriations, swore that UPF would never go over $6.5 billion. But even after eliminating non-nuclear weapons production missions and a formal decision to continue operations at two old, unsafe buildings slated for replacement, the Uranium Processing Facility is now estimated to cost $8.5 billion. However, even that is not the final price, as NNSA is still to “rebaseline” UPF costs at some unspecified date.
2023
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT FACT SHEETS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT PRESS RELEASES
New Mexico Environment Department Takes Legal Action To Terminate Defective LANL Cleanup “Consent Order”
FOR IMMEDIATE RELEASE, February 25, 2021
The New Mexico Environment Department has announced that it is filing a lawsuit against the Department of Energy to terminate a “Consent Order” governing cleanup at the Los Alamos National Laboratory (LANL). Nuclear Watch New Mexico, which has fought against that Consent Order ever since it went into effect nearly five years ago, strongly supports and applauds NMED’s decision.
Much to its credit, in 2005 the State of New Mexico successfully compelled DOE to enter into a strong, enforceable Consent Order after years of tough negotiations and lawsuits brought against it by DOE and the University of California (then LANL’s manager). However, at the Lab’s request the anti-regulation Susanna Martinez Administration eviscerated that Consent Order with more than 150 milestone extensions.
Los Alamos Nuclear Weapons Lab Opens Office in the City of the Santa Fe (“Holy Faith”) of Peace and Environmental Protection
FEBRUARY 10, 2021
Santa Fe, NM – A Lab press release has announced that “[c]onnections between Los Alamos National Laboratory and the City of Santa Fe will be strengthened with the Laboratory’s opening of a new downtown office” after signing a 10-year lease on a 28,000-square-foot building. The Lab’s press release ignores LANL’s $2.9 billion nuclear weapons production budget (up 33% in one year), its proposed 46% cut to cleanup to $120 million, serious groundwater contamination and recent reports how it has neglected wildfire protection. Two catastrophic wildfires in the last 21 years on or near the Lab blanketed a large portion of northern New Mexico with possibly contaminated smoke.
The City of Santa Fe’s official name is the “La Villa Real de la Santa Fe de San Francisco de Asís” (“The Royal Town of the Holy Faith of Saint Francis of Assisi”), in honor of the beloved saint who preached peace and environmental protection and from whom the present Pope draws his name. Pope Francis has repeatedly called for the abolition of nuclear weapons and while in Japan paid homage to the victims of the Hiroshima and Nagasaki bombings. Those atomic bombs were designed and produced at the Los Alamos Lab.
LANL Falls Behind on Wildfire Protection While Expanding Nuclear Weapons Production Watchdog Calls for New Site-Wide Environmental Impact Statement
FEBRUARY 9, 2021
Santa Fe, NM – The Department of Energy’s Inspector General is reporting that the Los Alamos National Laboratory (LANL) is falling seriously behind in wildfire protection. This is despite the fact that the 2000 Cerro Grande Fire forced the mandatory evacuation of both LANL and the Los Alamos townsite, burned 3,500 acres of Lab property and came within a half-mile of Area G, its largest waste dump. At the time Area G stored above ground some 40,000 barrels of plutonium-contaminated radioactive wastes. It could have been catastrophic had they burst and sent respirable airborne plutonium across northern New Mexico (inhaled plutonium is a very serious carcinogen).
In 2011 the Los Conchas Fire raced 13 miles in 24 hours to the Lab’s western boundary, where it was stopped along State Highway 4. Both it and the Cerro Grande Fire sent huge plumes of harmful smoke across northern New Mexico, possibly carrying Lab contaminants as well (operation of radioactive air emissions monitoring equipment was suspended during the Cerro Grande Fire).
RECENT NUCLEAR BUDGET GRAPHS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
Past Work Product (2020-2021)
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
75TH ANNIVERSARY HIROSHIMA DAY ONLINE COMMEMORATION CALLING FOR THE ABOLITION OF NUCLEAR WEAPONS
August 6, 2020
"Jay Coghlan of Nukewatch.org on the history of the Los Alamos labs, where the bomb was designed and fabricated, and how it continues to play the leading role in the creation of most U.S. nuclear weapons since then."
[embeddoc url="https://nukewatch.org/wp-content/uploads/2020/05/plutonium-pit-production-fact-sheet.pdf" download="all" viewer="browser"]
PLUTONIUM PIT PRODUCTION WORKSHOP – NOVEMBER 19, 2019
RADIO INTERVIEW – SCOTT KOVAC & JON LIPSKY
Scott Kovac of Nuclear Watch New Mexico and Jon Lipsky, the FBI agent who led the 1989 raid investigating environmental crimes that shut down the Rocky Flats Nuclear Bomb Plant join Xubi to talk about Nuclear weapons, Nuclear clean up and Pit production plans at LANL.
RADIO INTERVIEW – JAY COGHLAN & JON LIPSKY
PIT Production at LANL with Nuclear Watch New Mexico’s Jay Coghlan and Workshop Speaker, Jon Lipsky
RADIO INTERVIEW – MARYLIA KELLEY, EXECUTIVE DIRECTOR, TRI-VALLEY CARES
Nuclear Watch NM’s Workshop on LANL & PIT Production with Marylia Kelley of Tri-Valley CARES
Pit Production Workshop: View the Presentations
Jon Lipsky, FBI agent that led the 1989 raid investigating environmental crimes that shut down the Rocky Flats bomb plant
Introduction by Jay Coghlan
Jay Coghlan, Executive Director, Nuclear Watch New Mexico, on plutonium pit production at LANL
Marylia Kelly, Executive Director, Tri-Valley CAREs (Livermore, CA) on the new nuclear arms race
https://www.facebook.com/NukeWatch.NM/videos/825812604488302/
Scott Kovac Nuclear Watch New Mexico, on LANL cleanup issues
Blog Posts
Breakthrough Study Bolsters RECA Claims for New Mexicans Exposed to Trinity Test Site Radiation
Plutonium Detections From Trinity Test Discovered 78 years After Test – Confirm RECA Must Be Expanded
Located in the Tularosa Basin in southern New Mexico, the Trinity Test Site marks the location of the first detonation of a nuclear weapon. Christopher Nolan’s “Oppenheimer” would have you believe this area is desolate, inhospitable and uninhabited. Contrary to this narrative and popular opinion, The area where the Trinity test occurred was not uninhabited. There were more than 13,000 New Mexicans living within a 50-mile radius. Many of those children, women and men were not warned before or after the test. The event marking the dawn of the nuclear age in July 1945 ushered in decades of health issues for residents living downwind due to exposure to radioactive fallout. The long-lasting impact of radiation exposure is a painful legacy that the New Mexican communities have had to bear.
New preliminary information strongly supports Radiation Exposure Compensation Act (RECA) status for New Mexicans downwind of the Trinity Test Site. In the past weeks, Michael E. Ketterer, (Professor Emeritus, Chemistry and Biochemistry, Northern Arizona University, Flagstaff, AZ) has completed a short “proof of principle” study that directly investigates where plutonium in soils originates by analyzing isotopic ratios, in a known portion of the Trinity Test plume.
Dr. Ketterer sampled soils along highways NM 42, US 54, NM 55, US 60, and US 380. The isotopes show that there is definitely plutonium from the Trinity Test in the northeast plume, and distinguishes it from global (stratospheric) background and New Mexico regional background from Nevada Test Site fallout. Soils along all five of these highways contain plutonium that reflects mixtures of Trinity Test debris and global/Nevada regional background fallout; in some cases, nearly 100% of the Pu originates from the Trinity Test.
Does New Mexico Deserve Downwinder Status: Definitely Yes, as Evident Via Plutonium Isotopes in 2023 Soil Samples
Michael E. Ketterer, Professor Emeritus, Department of Chemistry and Biochemistry
Northern Arizona University , Flagstaff AZ
Introduction/objective: to investigate whether plutonium from the July 16, 1945 Trinity Test can be identified in contemporary soils and dusts near the Trinity Site. A proof-of concept study was conducted via a small-scale July 2023 collection of soil samples along five public highways transecting the areas reported to be most affected (refer to 239+240Pu deposition inventory map from Beck et al., 2020). More-distant soil samples were obtained from the Carson National Forest near Truchas, New Mexico.
Rest In Peace, Daniel Ellsberg
My dear father, #DanielEllsberg, died this morning June 16 at 1:24 a.m., four months after his diagnosis with pancreatic cancer. His family surrounded him as he took his last breath. He had no pain and died peacefully at home. https://t.co/x5qm73LW3c pic.twitter.com/GTBqgAADYj
— @RobertEllsberg (@RobertEllsberg) June 16, 2023
ICAN: The U.S. Spent $43.7 Billion on Nuclear Weapons Last Year—More Than EVERY Other Nuclear-Armed Nation COMBINED
A new report from the Nobel Peace Prize-winning International Campaign to Abolish Nuclear Weapons shows that the world’s nine nuclear-armed countries spent a total of $82.9 billion on nuclear weapons, “of which the private sector earned at least $29 billion in 2022.” The United States spent more than all of the other nuclear armed states combined, $43.7 billion. Russia spent 22% of what the U.S. did, at $9.6 billion, and China spent just over a quarter of the U.S. total, at $11.7 billion.
ICAN states, “The nine nuclear-armed states may have wasted $157,644 a minute on nuclear weapons in 2022, but no matter how much they spend, their nuclear weapons remain tools of terror and intimidation propped up by a mythical tale of deterrence that is rapidly unravelling.
“Through an ever-changing and challenging security environment, from security threats of climate change to the Covid-19 pandemic to the Russian invasion of Ukraine, nuclear weapons spending has steadily increased, with no resulting measurable improvement on the security environment…If anything, the situation is getting worse.”
“Luck, not reason or strategy, has kept nuclear weapons from being used in warfare for the past 78 years. But we can’t count on our luck to hold in perpetuity.”
If you need any more convincing of this fact, or of how “unacceptably dangerous nine countries’ reliance on nuclear weapons is,” watch this POV video where you’re the President and a nuclear attack is imminent. What do you do?
@kurz_gesagt POV: You’re the President and a nuclear attack is imminent. What do you do? #kurzgesagt #kurzgesagt_inanutshell #inanutshell #kurzgesagt_discover #nuclearwar #nuclearattack #nuclearattackwarning #pov #warzone #atomicbombs #emergency #urgent #decision #now ♬ original sound – Kurzgesagt – In A Nutshell
New Mexico: America’s Nuclear Colony
Money doesn’t talk, it swears. (Bob Dylan)
Quick Facts
Nuclear New Mexico
• DOE FY 2024 budget in NM is $10 billion (double next state).
– 75% core nuclear weapons research and production programs
– 28% life extended and new-design nuclear warheads ($2.65B)
– 20% expanded nuclear weapons production ($2 billion)
– $1.75B expanded plutonium “pit” bomb core production
– 5% for dumping radioactive bomb wastes (WIPP $484 million)
• Expanding nuclear weapons programs sold as jobs, jobs, jobs
• Los Alamos County (LAC) 70.6% non-Hispanic Caucasian
• LAC is 11th richest county in USA, most millionaires per capita
• Los Alamos County median household income $123,677
• Los Alamos County per capita income $64,521
• Los Alamos County persons in poverty 3.7%
• Los Alamos County has least children living in poverty in USA
• Los Alamos County rated best county to live in in USA
• Historically LAC schools subsidized added $8 million/yr from DOE
• LAC receives >$50 million in annual state gross receipts taxes
• Dept of Energy renewable spending in NM is 0.5% of $10B budget
• Indigenous and Hispanic lands unjustly seized for LANL
• World’s first atomic bomb detonated at Trinity Test
• 75 years still no govt tally of sick Navajo/Laguna uranium miners
• At least 8,280 sick Los Alamos and Sandia Labs workers
• Major hexavalent chromium groundwater contamination at LANL
• LANL plans to “cap and cover” and leave >200,000 yd3 of waste
• USA’s largest repository of warheads 2 miles south of ABQ airport
• Nation’s only plutonium “pit” bomb core production site at LANL
• Nation’s only dump for bomb wastes at Waste Isolation Pilot Plant
• NM targeted for all of nation’s lethal radioactive high-level wastes
New Mexico
• NM’s entire FY24 state operating budget is 6% less ($9.4 billion).
– 54% public education K-12 and higher
– 34% public health and safety
• NM per capita income falls from 32nd (1959) to 47th (2022)
• New Mexico 50% Hispanic, 11.2% Native American
• New Mexico 4th poorest state
• Median household income $54,020
• Average per capita income $29,624
• New Mexicans in poverty 18.4% (3rd highest in USA)
• 30% of New Mexican children live in poverty (highest rate in USA).
• New Mexico rated worst in well-being of children
• New Mexico is dead last in quality of public education
• Six surrounding county govts suffer net economic loss from LANL
• New Mexico has very abundant renewable energy resources
• DOE transfers excess land to white, wealthy Los Alamos County
• Generational cancers, Downwinders never compensated
• Chronically delayed remediation of 260 uranium mines and 7 mills
• NM facing decreasing water resources and increasing wildfires
• Lab commonly hires away senior NM Environment Dept officials
• >$5B for plutonium facilities, more than all NM schools & hospitals
• DOE threatens to sue NM over new WIPP state permit conditions
• Federal Nuclear Reg. Comm. grants license despite state opposition
New Mexico: America’s Nuclear Colony
New Mexico is the birthplace place of nuclear weapons. The “Land of Enchantment” has always been the single most important state within the U.S. nuclear weapons complex. The Department of Energy (DOE) will spend $10 billion in NM in FY 2024, 6% more than the operating budget of the entire state government.
Holtec International, the U.S. Federal Government, and the State of New Mexico – What Do We Know?
Nuclear power is a trending topic lately. What’s missing from most of these conversations is the nitty gritty details of the nuclear waste produced from nuclear power plants, and how to handle it. In mainstream and social media, nuclear is often hyped up as a climate solution and the issue of what to do with the waste is promoted as being nearly or already solved. Unfortunately this conception is entirely inaccurate. Most people don’t think about the problem of nuclear waste on a frequent basis, however New Mexicans are often forced to confront it whether we like it or not (spoiler: most of us DON’T).
New Mexico has the Waste Isolation Pilot Plant (WIPP) in the southeastern corner of the state, where radioactive waste is stored in a salt formation repository located deep underground. WIPP has been open since 1999, and now federal regulators are currently considering another facility that would store up to 175,000 metric tons of high-level radioactive nuclear waste. The new repository is called a “HI-STORE Consolidated Interim Storage Facility” by Holtec International, the New Jersey-based company who owns the private waste facility, and the waste would be transported in from nuclear reactors around the nation. The Nuclear Regulatory Commission issued Holtec a license for this project on May 9, 2023.
NNSA Digs Deep To Find A Reason To Give Itself Award
The award for the largest nuclear facility project completed ahead of schedule and under budget by NNSA goes to a project came in only 1% under budget after spending $40 million in contingency.
In an April 2 2014 National Nuclear Security Administration press release titled, NNSA Receives Secretary’s Award for Project Management Excellence, the Chemistry and Metallurgy Research Building Replacement (CMRR) Radiological Laboratory/Utility/Office Building (RLUOB) Equipment Installation (REI) Project was touted for coming in $2 million under budget.
First, the CMRR is the now-deferred project at Los Alamos, whose third phase Nuclear Facility would have enabled increased plutonium pit production. The RLOUB was the first phase of the CMRR project. The second phase REI is only the “equipment” for the RLOUB.
The press release tells us –
“The REI installed glovebox and other enclosure systems, analytical and test instrumentation equipment, and telecommunications and safeguards/security systems within the RLUOB.”
Also included, but not mentioned in the press release, were a fuel oil storage tank, furniture, and the parking lot.
It looks like NNSA gave the award in part because it could have been worse. With one year left in the 3-year the contract, it was estimated that the project was $8 million over budget. So NNSA put a new team in charge and straightened out their mess-ups and turned it around to a $2 million savings.
The press release tells us –
“The CMRR/RLUOB REI Project is the largest nuclear facility capital asset project completed ahead of schedule and under budget by NNSA.”
The press release also neglects to give the total budget. Our documents show that REI had a total budget $199 million. That makes the $2 million that the REI came in under budget equal to 1% of the total budget.
But our documents also show that there was $41.6 million (26%) contingency included in the $199 total budget. After spending untold millions in design and then estimating the cost of the project, NNSA adds in a large contingency to every project so that it does not go over budget and have to go back to Congress for more money.
Is the REI, which spent $40 million in contingency, really $2 million under budget?
I think not. NNSA must give the public all the facts and figures when it gives glowing appraisals of itself.
Here’s what we have on the REI –
WIPP Continues to Show Signs, Town Hall Webcast Tonight, LANL TRU to WCS, More Information
WIPP Continues to Show Signs, Town Hall Webcast tonight, LANL TRU to WCS, More Information
WIPP Underground Continues to Show Signs of Radiological Activity
The Waste Isolation Pilot Plant officials stated that there was another radiological release on March 11. This was outside of the WIPP site exhaust shaft filter. An air sample from the outside of the ventilation exhaust recorded 61 disintegrations per minute of americium on a sample collected the evening of March 11. WIPP stated that, “This is expected given the amount of contamination captured by the WIPP ventilation system during the February 14 radiation release event. Engineers believe the contamination was from previous deposits on the inner surface of the exhaust ductwork.” The engineers did not state why they expected this and did not mention the LARGE amount of contamination captured by the WIPP ventilation system filters. The engineers also did not state why they believed this and not that more contamination was being produced in the underground.
Air sampling results before and after the High Efficiency Particulate Air (HEPA) filters at WIPP are available here. Station A samples air before the filters and Station B samples air after passing through the filters. These samples were analyzed following the detection of airborne radioactivity on February 14, 2014. They are not environmental samples, and are not representative of the public or worker breathing zone air samples.
The 3/11/14 4:19PM increase after the filters is shown here. There were other small releases on 03/02/2014 08:50 AM (38 dpm) and 03/05/2014 08:10 AM (60 dpm, although WIPP claims that the filter was “cross contaminated”)
There was a larger event, before the filters, that occurred 03/13/2014 08:30 AM (368 dpm) that has not been mentioned. All this shows that the underground could still be brewing radiological activity. Perhaps this will be explained better tonight at the Town hall.
Weekly Town Hall Meetings in Carlsbad?
Thursdays at 5:30 – Carlsbad City Council Chambers, City Hall, 101 N. Halagueno St.
Co-hosted by City of Carlsbad and U.S. Department of Energy (DOE) Carlsbad Field Office
Discuss recovery efforts following WIPP’s fire and radiological events in February.
Meetings available live online
The Show Goes On
The Department of Energy (DOE), is proposing to ship transuranic waste currently located at the Los Alamos National Laboratory (LANL) for temporary storage at Waste Control Specialists (WCS), located in western Andrews County, Texas. LANL has another ~546 cubic meters remaining out of the original 3706 cubic meters that was agreed to be moved to WIPP by June 2014.
Let’s be clear, there is no technical reason to store the waste temporarily at WSC. DOE and LANL just want to show that they can meet a deadline. The extra cost of this operation has not been released. And don’t get me wrong, no one wants the waste – all the waste – removed from LANL more than me. Let’s hope that DOE and LANL show the same amount of interest and resources when it comes to removing the rest of the waste at Los Alamos, such as the hundreds of thousands of cubic meters of radioactive and hazardous wastes buried at Area G.
Official Websites
New Mexico Environment Department WIPP website
WIPP Informational Meeting in Santa Fe
A WIPP informational meeting will take place in Santa Fe on Monday, March 31st from 6 to 7:30 pm at the Santa Fe Main Library, located at 145 Washington, in downtown Santa Fe. Please note the new location. Don Hancock, of Southwest Research and Information Center, Scott Kovac, of Nuclear Watch New Mexico, and Sasha Pyle, longtime activist, will give presentations. Opportunities for public involvement will be discussed.
DOE Nuclear Weapons Budget Surpasses Cold War Record
FOR IMMEDIATE RELEASE March 17, 2014
DOE Nuclear Weapons Budget Surpasses Cold War Record
Bomb with New Military Capabilities up 20%
Dismantlements Cut By Nearly Half
Nonproliferation Programs Down 21%
Cleanup Funding Flat
Santa Fe, NM – The Obama Administration has finally released its detailed budget for fiscal year 2015, which starts October 1. By law the president’s proposed budget is required to be released not later than the first Monday of February.
Contrary to President Obama’s rhetoric about a future world free of nuclear weapons, most famously expressed in his April 2009 speech in Prague, the President asks for a 7% increase for nuclear weapons research and production programs under the Department of Energy’s semi-autonomous National Nuclear Security Administration (NNSA). NNSA’s “Total Weapons Activities” are slated to rise to $8.3 billion in FY 2015, and to an astounding $9.7 billion by FY 2019, 24% above this current fiscal year 2014. Obama FY 2015 budget request sets a new record for DOE nuclear weapons spending, even exceeding the Cold War high point in 1985 under President Reagan’s military buildup.
Of particular interest is the hands-on nuclear weapons work in the budget category “Directed Stockpile Work,” increased by $305 million (or 12.5% above FY 2014), whose overwhelming focus is Life Extension Programs (LEPs). President Obama wants $634 million (+20%) for the B61 nuclear bomb LEP, which has already exploded in costs from an originally estimated $4 billion to more than $10 billion. Each bomb will end up costing more than twice its weight in gold.
In addition to extending the service life of the bomb by decades, this Life Extension Program will combine three tactical or “battlefield” variants and one strategic variant together into one all-purpose nuclear bomb. The LEP will also transform the B61 from a simple analogue bomb into a digital bomb that interfaces with future super-stealthy fighter aircraft, which themselves will cost an astronomical $1 trillion (although not all will be assigned to a nuclear mission). A separate $1.8 billion Defense Department program for a new tail fin guidance kit will transform the B61 into the world’s first nuclear smart bomb. Despite all this, the U.S. government denies that it would ever endow existing nuclear weapons with new military capabilities.
While rebuilding nuclear weapons at exorbitant expense, the Obama Administration proposes to slash dismantlements by nearly half (45%), from an already paltry $54.2 million to $30 million. Dismantlement work at the Pantex Plant will be cut by 40%. Ironically, much of the dismantlement work that remains is “to provide parts for the life extension programs (B61 and W80-1).” Dismantlements will continue at the same rate at the Y-12 Plant, but its primary aim is to produce “feedstock [highly enriched uranium] for internal and external customers (e.g. Naval Reactors).” Dismantlements are described as a “a workload leveler across all programs,” indicating that instead of being a prioritized step toward a future world free of nuclear weapons, it is merely filler work in between rebuilding nuclear weapons during Life Extension Programs. NNSA FY15 budget, PDF page 109. [All following page numbers are in the same format.]
The construction of the Uranium Processing Facility at the Y-12 plant is capped at $6.5 billion. A recent study by the Pentagon’s Office of Cost Assessment and Project Evaluation predicted that this exorbitant facility, originally estimated by NNSA at ~$600 million, would cost between $12 to 19 billion. To bring it in at $6.5 billion NNSA has cut out all dismantlement and HEU downblending operations, making it a production-only nuclear weapons plant (pp. 319-323).
NNSA’s budget “Defer[s] the W78/88-1 LEP to some date beyond FY 2019” (p. 84), effectively meaning its cancellation. The W78/88-1 LEP was to produce a proposed “interoperable warhead,” using the plutonium pit from a third warhead, the W87. Nevertheless, the Los Alamos National Laboratory plans to “Build W87-design developmental pits each year to sustaining [sic] fabrication capability” (p. 117). The controversial Chemistry and Metallurgy Research Replacement (CMRR) Project for expanded plutonium pit production remains abandoned, but NNSA plans to raise the amount of plutonium used in the already constructed Rad Lab and pursue “pre-conceptual design efforts for the modular acquisition concept” to substitute for the CMRR (p. 219). NNSA still plans to “Execute a plutonium strategy [at LANL] that achieves a 30 pit per year capacity by 2026,” (p. 70) for which it gives no clear requirement or reason.
Key nonproliferation programs designed to halt the spread of nuclear weapons have been slashed by $300 million (-21%), even though nuclear weapons are recognized as the greatest existential threat to the United States. “Defense Environmental Cleanup”, the nation-wide program to clean up the Cold War legacy of radioactive and toxic contamination, is being cut from $5.8 billion to $5.6 billion, despite the fact that estimated costs keep climbing.
All of this is evidence of a pattern where the U.S. will spend massive amounts on nuclear weapons “modernization,” while nonmilitary domestic services are cut or flat lined. In December 2013 the nonpartisan Congressional Budget Office (CBO) released its study Projected Costs of Nuclear Forces 2014 -2023. Its stunning conclusion was that estimated costs for maintenance and “modernization” of the nuclear weapons stockpile, delivery systems, and research and production complex would total $355 billion over the next decade. The CBO also reported that costs after 2023 would increase yet more rapidly since “modernization” is only now beginning. The report did not attempt to project costs for maintenance and modernization of nuclear forces over the planned period of the next thirty years, but given current trends it will easily exceed one trillion dollars.
In one piece of good news the NNSA is finally putting the Mixed Oxide (MOX) Fuel Fabrication Facility at the Savannah River Site in South Carolina in “cold standby.” The MOX program is a failed attempt in the laudable goal of disposing of 34 metric tons of weapons-grade plutonium. The MOX Program’s life cycle costs have exploded to an estimated $30 billion, and NNSA is now studying cheaper alternatives. This has major positive impacts on the Los Alamos National Laboratory (LANL), which was slated to process 2.5 metric tons of plutonium every year as feedstock for the MOX Fuel Fabrication Facility. It also further undermines the need to build massive new plutonium facilities at LANL.
Jay Coghlan, Nuclear Watch New Mexico Director, commented, “Increased budgets for nuclear weapons are being paid off the back of dismantlements, nonproliferation and cleanup programs, which is just plain wrong. It’s common knowledge that NNSA’s nuclear weapons programs have a staggering track record of cost overruns, schedule delays and security breaches. It’s less well known that these programs may undermine stockpile reliability by introducing unneeded, incredibly expensive changes to existing nuclear weapons that have been extensively tested and are known to be even more reliable than originally thought. Clearly, NNSA’s nuclear weapons programs should be cut to help pay for the expansion of nonproliferation programs that actually enhance national security, cleanup programs that protect the environment while creating jobs, and dismantlement programs that get of nuclear weapons forever.”
# # #
For budget release requirement not later than the first Monday of February see U.S. Code, Title 31, Subtitle II, Chapter 11, § 1105, “Budget contents and submission to Congress.”
The FY 2015 DOE nuclear weapons request is calculated as the highest ever using data from Atomic Audit, Brookings Institute, 1998, Stephen Schwartz editor, Table A-2. It gives 5.494 billion in 1996 dollars as the cost for DOE nuclear weapons research, production and testing programs in 1985. Adjusted for inflation that is $8.259 billion in 2014 dollars.
The NNSA’s FY 2015 budget is available at http://energy.gov/sites/prod/files/2014/03/f12/Volume_1_NNSA.pdf
The Congressional Budget Office report Projected Costs of Nuclear Forces 2014 -2023 is available at http://www.cbo.gov/sites/default/files/cbofiles/attachments/12-19-2013-NuclearForces.pdf
WIPP Update March 14 – Truck Fire Report Is Released
WIPP Underground Fire Investigation Summary Report of Accident on February 5, 2014
The salt haul truck that caught fire was approximately 29 years old.
The investigation of the truck fire did not reveal exactly what started the blaze but did find:
•Maintenance program was ineffective
•Fire protection program was less than adequate
•Emergency management/preparedness and response program were ineffective
Truck Fire Accident Report Summary
Underground Salt Haul Truck Fire at the Waste Isolation Pilot Plant February 5, 2014 Accident Investigation Report
3/13/14 Town Hall Meeting Webcast from Carsbad
WIPP Town Hall Webcast Tonight, Thursday March 13 2014
Weekly Town Hall Meeting Scheduled for Thursday March 13 2014
Carlsbad Mayor Dale Janway and DOE will co?host weekly town hall meetings to update the community on recovery activities at WIPP. The meetings will be held every Thursday at 5:30 p.m. at the Carlsbad City Council Chambers, 101 N. Halagueno Street. If you can’t attend, you can view the meeting on line at https://web.archive.org/web/20140417222404/http://new.livestream.com:80/rrv/wipptownhall.
Here is a video of the March 6 DOE WIPP Town Hall.
DOE releases predicted spread of WIPP contamination
We now have a look at DOE’s predicted contamination spread, available at the Waste Isolation Pilot Plant (WIPP) update page.
This model is based on three air samplers, and no samplers to the Northeast. There are still many questions, including:
What caused this release in the first place?
How contaminated is the underground?
Are soil samples being collected? From where?
Modeling has been done to estimate onsite worker and offsite public dose that may have resulted from the February 14, 2014, event. The results of the modeling indicate that all potential doses were well below the applicable regulatory limits (see results below). The modeling results are consistent with actual worker bioassay results. For modeling data see: (http://www.wipp.energy.gov/Special/Modeling Results.pdf)
Estimated Dose Maximum estimated worker dose 10 mrem Maximum estimated public dose 0.1 < 1 mrem
Natural Background 310 mrem
Applicable Regulatory Limit
5000 mrem per year
DOE all?paths limit (adults) 100 mrem per year
DOE all?paths limit for children/pregnant women 25 mrem per year
EPA Air (NESHAPs) Standard for inhalation is 10 mrem per year
Mine Games – WIPP Update March 10, 2014
Mine Games
In a March 9th press release, the Nuclear Waste Partnership (NWP), the management and operations contractor at the Waste Isolation Pilot Plant (WIPP) for the U.S. Department of Energy (DOE), stated their plans to reenter the ailing salt mine/nuclear waste repository after a radiological release shut down operations over three weeks ago.
The press release tells us that, on March 7 and 8, radiological and air quality instruments were lowered down the Salt Handling and the Air Intake Shafts. The preliminary findings indicated that no “detectable radioactive contamination” in the air or on the equipment. The press release claims that these results were expected because the shafts that were sampled were not in the air flow path coming from the area where the radiation release originated.
But, there are 4 shafts to underground – the Salt Handling, the Air Intake, the Waste Handling, and the Exhaust Shafts. After the detection on a radiologic release, filters move into the Exhaust Shaft and air is drawn to the outside by fans blowing to the outside here. The other three shafts, mainly the Air Intake Shaft because it has no elevator in it, provide intake for the air flow path to the Exhaust Shaft. Strangely missing from the press release is any mention of the Waste Handling Shaft, which contains an elevator to take the waste down into the mine and should also have been out of the air flow path. DOE and NWP must explain why the Waste Handling Shaft was not sampled and, if it was, what are the results. The Waste Handling Shaft provides the normal entry to the underground, so why use the Salt Shaft? Also, the press release did not mention that any “soil” samples were taken from the walls of any of the shafts. Is the Waste Handling Shaft contaminated or presumed contaminated?
As far as the air flow path goes, it’s an elaborate game to get the air to flow where it is needed in the underground of WIPP. Getting the desired path requires blocking off numerous openings in the underground. Bob Martin from KRQE gave a hint of what is involved in his recent report. We have not been given the diagram for the air flow path at the time of the release or even if the path was in place. We don’t have the location of all the monitors in the underground and if they were working. What was the presumed path of the contaminated air to the Exhaust Shaft? Why are so many details left out out of the information released to the public?
Unfortunately, the press release also mentioned that four more WIPP workers had been contaminated. But it was not stated where or when these employees received the dose. Was it Friday night or Saturday? Why was this important information not in the press release?
We also have some new sample findings released. Some of the interesting information here is that the WIPP Laboratory Analyses are so much lower than the Screening Analyses. I will get back to you on that. But don’t forget that it is unlikely that the main release actually hit any of the air monitors dead-on. Also, notice the lack of samplers to the northeast.
We will have to wait for soil samples to come in before we can begin to estimate the main path of the release.
WIPP is not a secret facility. (They even let me down there last year.) Press releases that raise more questions than they answer must stop now.
Great Article form La Jicarita – What’s Wrong with WIPP
What’s Wrong with WIPP by lajicarita
By DON HANCOCK, Southwest Research and Information Center (SRIC)
The world’s first geologic repository for military nuclear waste is making international news because of the radiation leak that was detected late at night on Valentine’s Day. An unknown amount of radioactive and toxic chemical waste was released to the environment from the Waste Isolation Pilot Plant (WIPP). On February 26, the 13 workers at the site when the leak was detected were notified that they tested positive for internal radiation contamination.
Since the Department of Energy (DOE) and Nuclear Waste Partnership (NWP), the operating contractor, have repeatedly stated that WIPP would “start clean, stay clean” and not release any radioactivity for at least 10,000 years, the leak was never supposed to happen. The health danger that persists for thousands of generations is the reason to put the wastes underground so they are not released to the environment. Thus, an obvious question: What’s wrong with WIPP?
Also, what effect does the leak have on DOE plans to expand WIPP and what is the opposition to such proposals?
*Some of the unknowns about the February 2014 radiation leak*
As of March 4, there is much more that is unknown than known:
* What caused the leak?
* How much leaked into the underground salt mine?
* How much leaked into the environment?
* Where are those radioactive and toxic wastes now?
* To what amount of radiation were the workers exposed?
* What are the health effects for those workers?
* What decontamination is necessary in the underground mine?
* What decontamination is necessary on the WIPP site and surrounding area?
* If WIPP reopens, what changes in the operation, monitoring, and safety culture will be implemented?
WIPP Video Story and Congressional Delegation Statements from KRQE
KRQE TV 13 aired a news story last night that included statements from the five members of the NM Congressional Delegation:
On the recent radiation leak: “From my perspective on the (U.S. Senate Energy and Natural Resources) committee, the first priority is making sure that the personnel who actually work at WIPP are safe and that the community and environment around WIPP is safe.”
On whether high-level waste should be stored at WIPP: “WIPP was never designed as a high level facility, and I don’t think we should retrofit it to be a high level facility. There has been talk of moving other transuranic waste there that was generated in different ways than the transuranic waste that’s coming from Los Alamos, for example. That’s something we can have the conversation about, but it should never be a high level facility.”
On any future change in WIPP’s mission: “We have a very long standing and robust conversation in my office with the community in Carlsbad all the time. The input from the community is always critical.” “There is nothing more important than making sure that that community feels like we are doing everything possible to make sure that WIPP is a success, and that the people who work there in the surrounding community and their well-being is our first priority.”
~ U.S. Sen. Martin Heinrich, D-New Mexico
“It’s too early to say whether the leak factors into my thoughts about the future of WIPP because we don’t know what happened. I’m taking the leak very seriously, and our focus right now is on the immediate safety of the community and WIPP personnel and the recovery work. It would be premature to draw any conclusions. This is a very technical issue, and the science is extremely important. My position on expansion now is the same as it has always been. When it comes to proposals that would significantly change WIPP’s mission, I support the provision in the current law that bans high-level waste at WIPP. WIPP was not fully studied for high-level waste, and it does not meet permit requirements for high-level waste. Additionally, New Mexico’s people and state government are the ones who have the power to decide what waste our state will accept and under what terms. Any attempt to alter WIPP’s mission would take many years of study, permitting, and require the state of New Mexico’s full support.”
~ U.S. Sen. Tom Udall, D-New Mexico
On the radiation leak: “Congressman Pearce has introduced legislation to protect New Mexico jobs at WIPP, which has safely disposed of TRU waste for over a decade. Right now, Congressman Pearce is focused on monitoring the present situation closely, ensuring DOE and WIPP continue to make public safety the top priority. To date, all information shared with our office indicates there is no risk or danger to the community. At the appropriate time, the Congressman fully expects and will insist that the Department of Energy conduct a thorough investigation and answer all the public’s questions.”
On whether high-level waste should be stored at WIPP: “Now is not the time to speculate about proposals that are not even on the table. Taking high level waste at WIPP is not on the table. Congressman Pearce’s number one priority right now is public safety, and there are many questions that need to be answered before any changes in WIPP’s mission are discussed.”
~ Eric Layer, Spokesman for U.S. Rep. Steve Pearce, R-NM 2nd District
“Right now, the number one priority is the health and safety of the WIPP employees who were affected by the leak as well as the residents of the surrounding community. As the response effort continues, there must be nothing short of full transparency and accountability to ensure the public that they are safe. This incident further proves that any expansion of WIPP’s mission warrants close scrutiny that’s rooted in science and that includes extensive outreach to and input from all stakeholders and local communities.”
~ U.S. Rep. Michelle Lujan Grisham, D-NM 1st District
“I am very concerned about the recent detection of radiation near WIPP and the health and safety of those exposed to radiation. It will be important that answers are provided detailing the causes of the elevated levels and how this will be prevented in the future. The safety and security of the community must be the top priority.
As far as the larger discussion about changes at WIPP, one aspect that cannot be forgotten or overlooked – especially given the recent incident – is the reality of exposure and what will happen when workers or members of the community are exposed to harmful levels of radiation. Sadly in New Mexico, we are all too familiar with the story of those who worked in uranium mines and other government facilities and suffered exposure to radiation. They contributed to our national security, yet paid a steep cost as many individuals became sick and some paid with their life. I am still fighting in Congress to see that many of these workers are compensated for the health problems they developed as a result of their work. While we hope we never have to face a similar situation in the future, it is important we have these discussions now rather than when it’s too late, especially given the recent reports that 13 workers tested positive for radiation exposure.”
~ U.S. Rep. Ben Ray Lujan, D-NM 3rd District
Nuclear Weapons Budget Increased, Nonproliferation and Cleanup Budgets Cut
FOR IMMEDIATE RELEASE March 4, 2014
Contact: Jay Coghlan, Nuclear Watch NM, 505.989.7342, c. 505.692.5854, [email protected]
Nuclear Weapons Budget Increased
Nonproliferation and Cleanup Budgets Cut
Good News: Wasteful Plutonium Program Shuttered
The Obama Administration has released topline numbers for its FY 2015 budget for the National Nuclear Security Administration (NNSA), which owns the nation’s nuclear weapons complex of design laboratories and production plants. The NNSA’s budget category “Total Weapons Activities” is slated to be increased to $8.3 billion, $534 million above FY 2014 (+ 6.9%). Of particular interest is “Directed Stockpile Work,” increased by $305 million (+12.5%), whose overwhelming focus is Life Extension Programs. These programs not only extend the operational lives of existing nuclear weapons by decades, but also arguably give them new military capabilities, despite denials at the highest levels of government. Details are not yet available, but the increase for Directed Stockpile Work will probably mostly be for the B61 Life Extension Program. Its refurbishment of each nuclear bomb will cost more than twice their weight in gold.
This is the beginning of a pattern where the U.S. will spend massive amounts on nuclear weapons “modernization,” while nonmilitary domestic services are cut or flat lined. In December 2013 the nonpartisan Congressional Budget Office (CBO) released its study Projected Costs of Nuclear Forces 2014 -2023. Its stunning conclusion was that estimated costs for maintenance and “modernization” of the nuclear weapons stockpile, delivery systems, and research and production complex would total $355 billion over the next decade. The CBO also reported that costs after 2023 would increase yet more rapidly since “modernization” is only now beginning. The report did not attempt to project costs for maintenance and modernization of nuclear forces over the planned period of the next thirty years, but given current trends it will easily exceed one trillion dollars.
In stark contrast, key nonproliferation programs designed to halt the spread of nuclear weapons have been slashed by $300 million (-21%), even though nuclear weapons are recognized as the greatest existential threat to the United States. “Defense Environmental Cleanup”, the nation-wide program to clean up the Cold War legacy of radioactive and toxic contamination, is being reduced from $5 billion to $4.87 billion, despite the fact that estimated costs keep climbing.
Jay Coghlan, Nuclear Watch New Mexico Director, noted how Obama’s proposed nuclear weapons budget is upside down. He commented, “It’s common knowledge that NNSA’s nuclear weapons programs have a staggering track record of cost overruns, schedule delays and security breaches. It’s less well known that these programs may undermine stockpile reliability by introducing unneeded, incredibly expensive changes to existing nuclear weapons that have been extensively tested and are known to be even more reliable than originally thought. Clearly, NNSA’s nuclear weapons programs should be cut to help pay for the expansion of nonproliferation programs that actually enhance national security and cleanup programs that actually create jobs.”
In one piece of good news the NNSA is finally putting the MOX Fuel Fabrication Facility at the Savannah River Site in South Carolina on “cold standby.” The MOX program is a failed attempt in the laudable goal of disposing of 34 metric tons of weapons-grade plutonium. The MOX Program’s life cycle costs have exploded to an estimated $30 billion, and NNSA is now studying cheaper alternatives. This has major positive impacts on the Los Alamos National Laboratory (LANL), which was slated to process 2.5 metric tons of plutonium every year as feedstock for the MOX Fuel Fabrication Facility. It also further undermines the need to build massive new plutonium facilities at LANL.
# # #
Department of Energy and National Nuclear Security Administration topline budget numbers are available at
http://www.whitehouse.gov/sites/default/files/omb/budget/fy2015/assets/doe.pdf
and
http://www.energy.gov/sites/prod/files/2014/03/f8/15Highlights.pdf
RECENT FORMAL COMMENTS
Past NukeWatch Events
Past Work Product (2019-)
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
2019
November 26, 2019 Press Release November 24, 2019 Press Release November 19, 2019 Plutonium Pit Production Workshop Presenters:
August 12, 2019 NEPA Comments NukeWatch’s 22-page formal comments on expanded plutonium pit production Until NNSA fully complies with the National Environmental Policy Act through the preparation of a programmatic environmental impact statement on expanded plutonium pit production, Nuclear Watch believes that any irreversible or irretrievable commitment of resources to either the expansion of pit production at the Los Alamos Lab or to the repurposing of the MOX Facility at the Savannah River Site is unlawful. Read/Download the Full Document HERE July 25, 2019 NEPA Comments Scoping comments on NNSA draft EIS for plutonium pit production at the Savannah River Site THE NEED FOR A PROGRAMMATIC ENVIRONMENTAL IMPACT STATEMENT: This is our first and primary concern, that NNSA must first complete a programmatic environmental impact statement (PEIS) on its nation-wide plans for plutonium pit production, in advance of the Savannah River Site-specific environmental impact statement. To get right to the point, we argue that the SRS EIS process should go no further than this scoping period and should resume only after a completed formal Record of Decision for a new or supplemental PEIS. Read/Download the Full Document HERE July 9, 2019 Plutonium Pit Production Fact Sheet Expanding Nuclear Pit Production: The Facts and What You Can Do The Facts Read/Download the Full Document HERE June 10, 2019 News Release In a victory for transparency and legal compliance by the government, the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) today published a “Notice of Intent” in the Federal Register to complete environmental reviews on its controversial proposal to expand plutonium “pit” production for new and refurbished nuclear weapons. [embeddoc url="https://nukewatch.org/wp-content/uploads/2019/06/SRS-plutonium-bomb-plant6-14-19.pptx" download="all" viewer="google"] Read/Download the Full News Release HERE June 4, 2019 Press Release On behalf of three public interest organizations - Nuclear Watch New Mexico, Tri-Valley Communities Against a Radioactive Environment and Savannah River Site Watch – attorneys for the law firm of Meyer Glitzenstein & Eubanks and the Natural Resources Defense Council recently sent a 16-page letter to Lisa Gordon-Hagerty, head of the National Nuclear Security Administration (NNSA). The detailed letter warns the nuclear agency to not proceed with aggressive plans to expand plutonium pit production without first meeting its legal requirements for timely public review and comment under the National Environmental Policy Act. Read/Download the Full Press Release HERE May 31, 2019 Press Release Last Wednesday, facility operations personnel entered a service room and noticed a leak emanating from a valve on the radioactive liquid waste (RLW) system. Upon subsequent visual inspection by a radiological control technician, RLUOB engineers believe that this valve, and 6 similar valves, may be constructed of carbon steel. The RLW system handles radioactive liquid waste streams from chemistry operations that include nitric and hydrochloric acids—carbon steel valves would be incompatible with these solutions. The suspect valves are also in contact with stainless steel piping, which would create another corrosion mechanism. RLUOB management plans to drain the affected piping sections and develop a work package to replace all of the suspect valves. They will also confirm the valve materials and if shown to be incorrect, investigate the cause of this failure in the design, procurement, and installation processes. The valves were installed in 2013 as part of a modification to add straining and sampling capabilities that were not in the included in the original design. [Please note that DNFSB reports are posted a few weeks later than dated.] This immediately raises two crucial issues: 1) the National Nuclear Security Administration’s (NNSA’s) plans for expanded plutonium pit production; and 2) the current attempt by the Department of Energy to restrict Safety Board access to its nuclear weapons facilities. Read/Download the Full Press Release HERE April 26, 2019 Consent Orders Comparison On March 1, 2005, after arduous negotiations and threats of litigation, the New Mexico Environment Department (NMED), Department of Energy (DOE), and Los Alamos National Laboratory (LANL) entered into a Consent Order specifying the schedule for investigation and cleanup of the Lab’s hundreds of contaminated sites. This Consent Order (CO) was LANL’s agreement to fence-to-fence cleanup of Cold War legacy wastes, which NMED began to enforce. Read/Download the Full Comparison HERE March 25, 2019 Press Release More than 25 years after the end of the Cold War, all eight established nuclear weapons powers are “modernizing” their stockpiles. Talks have broken down with North Korea, the new nuclear weapons power. Nuclear-armed India and Pakistan narrowly averted war last month. Russian President Vladmir Putin made new nuclear threats in response to Trump’s announced withdrawal from the Intermediate-Range Nuclear Forces Treaty. This could lead to hair-trigger missile emplacements in the heart of Europe and block extension of the New Strategic Arms Reduction Treaty with Russia. If so, the world will be without any nuclear arms control at all for the first time since 1972. Meanwhile, the U.S. criticizes non-weapons states for signing a nuclear weapons ban treaty, despite the fact there have long been treaties completely banning chemical and biological weapons of mass destruction that the U.S. seeks to enforce. The pending international NonProliferation Treaty (NPT) Preparatory Committee conference at the United Nations is widely expected to collapse in failure because of the nuclear weapons powers’ failure to enter into serious negotiations leading to nuclear disarmament. The NPT’s Article VI mandate for those negotiations has been in effect since 1970, when the Treaty was signed by 189 countries (more than any other treaty). Read/Download the Full Press Release HERE March 26, 2019 NukeWatch Budget Compilation Nuclear Watch New Mexico — Department of Energy FY 2020 Nuclear Weapons Budget Request |
2018
November 16, 2018 Plutonium Pit Production Fact Sheet Plutonium pits are the radioactive cores or “triggers” of nuclear weapons. Their production has always been a chokepoint of resumed industrial-scale U.S. nuclear weapons production ever since a 1989 FBI raid investigating environmental crimes shut down the Rocky Flats Plant near Denver. In 1997 the mission of plutonium pit production was officially transferred to its birthplace, the Los Alamos National Laboratory (LANL) in northern New Mexico, but officially capped at not more than 20 pits per year. However, in 2015 Congress required expanded pit production by 2030 whether or not the existing nuclear weapons stockpile actually needs it. This will support new military capabilities for nuclear weapons and their potential use. Read/Download the full fact sheet pdf HERE October 31, 2018 Nuclear Watch New Mexico, Savannah River Site Watch, and Tri-Valley CAREs sent a letter of demand to the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) to inform the government that its plan to quadruple the production rate of plutonium bomb cores is out of compliance with the National Environmental Policy Act (NEPA). NNSA’s premature plan to quadruple the production rate of plutonium bomb cores (“pits”), the heart of all US nuclear weapons, is out of compliance with requisite environmental law, the groups argue, as NNSA has failed to undertake a legally-mandated programmatic review and hold required public hearings. View/Download the entire press release HERE NukeWatch Comments, September 27, 2018 Nuclear Watch New Mexico is submitted formal comments to express in the strongest possible terms our opposition to DOE Order 140.1 Interface with the Defense Nuclear Facilities Safety Board. We find that the Department of Energy’s (DOE’s) attempt to restrict and suppress DNFSB access is very misguided, arrogant, and likely illegal in that it acts contrary to the Board’s enabling legislation. June 8, 2018 Press Release New Contractors Selected For Expanded Nuclear Weapons Production at Los Alamos Santa Fe, NM. Today the Department of Energy's National Nuclear Security Administration (NNSA) announced its choice for the new management and operating contract for the Los Alamos National Laboratory (LANL).The new contractor, Triad National Security, LLC, is a limited liability company consisting of the Battelle Memorial Institute, the University of California and Texas A&M University. All three are non-profits, and it is unclear how this will affect New Mexico gross receipts taxes. Battelle claims to be the world's largest non-profit technology research and development organization, and manages a number of labs including the Lawrence Livermore and Idaho National Laboratories. Texas A&M was founded in 1876 as the state's first public institution of higher learning and has the largest nuclear engineering program in the country. DOE Secretary Rick Perry is an avid A&M alumnus. May 31, 2018 Press Release Santa Fe, NM & Columbia, SC - "Two key U.S. Department of Energy documents on future production of plutonium "pits" for nuclear weapons, not previously released to the public, fail to justify new and upgraded production facilities at both the Los Alamos National Laboratory (LANL) in New Mexico and the Savannah River Site (SRS) in South Carolina." May 15, 2018 Fact Sheet May 10, 2018 Press Release What's Not in NNSA's Plutonium Pit Production Decision
- NNSA did not mention that up to 15,000 "excess" pits are already stored at the Pantex Plant near Amarillo, TX, with up to another 5,000 in "strategic reserve." The agency did not explain why new production is needed given that immense inventory of already existing plutonium pits. (In 2006 independent experts found that pits last a least a century. Plutonium pits in the existing stockpile now average around 40 years old.) May 2, 2018 Press Release "NNSA should begin nation-wide review of plutonium pit production, why it's needed, and what it will cost the American taxpayer in financial, safety and environmental risks. These are all things that the public should know." -Jay Coghlan, Director, Nuclear Watch New Mexico. April 26, 2018 NukeWatch Comments LANL Rad Lab: Formal Comments Under Nat'l Environmental Policy Act Against raising plutonium limit at LANL Rad Lab View/download Nuclear Watch comments as submitted Excerpt:
- NNSA is planning a 10-fold increase in plutonium at the LANL Rad Lab with a view to ramping up the production of plutonium pits for new nuclear weapons. March 26, 2018 Press Release United States To Begin Construction Of New Nuclear Bomb Plant The National Nuclear Security Administration (NNSA) announced on Friday, March 23, that it was authorizing the start of construction of the Uranium Processing Facility (UPF) and two sub-projects at the Y-12 National Security Complex in Oak Ridge, Tennessee. The UPF is a facility dedicated solely to the manufacture of thermonuclear cores for US nuclear bombs and warheads.
Jay Coghlan of NukeWatch points out that "This project already has a long history, and it is instructive. In 2013, DOE announced it was 85% finished with the UPF design when it ran into the 'space/fit' issue- and more than a half-billion taxpayer dollars were just written off. In private business, that kind of thing gets you fired. In DOE's world of contractors running amok, they not only didn't get fired, not one Congressional hearing was held and the UPF budget went up the next year!" - See full press release for all the details (PDF) March 1, 2018 Press Release The Regional Coalition of LANL Communities: Benefits for the Select Few Santa Fe, NM- According to media reports, Andrea Romero, Executive Director of the Regional Coalition of LANL Communities, is accused of charging some $2,200 dollars of unallowable travel costs, such as alcohol and baseball tickets, while lobbying in Washington, DC for additional funding for the Los Alamos National Laboratory (LANL). She in turn accused the nonprofit group Northern New Mexico Protects of political motivations in revealing these questionable expenses. Romero is running in the Democrat Party primary against incumbent state Rep. Carl Trujillo for Santa Fe County's 46th district in the state House of Representatives. For all the details, see full press release PDF February 28, 2018 Press Release Santa Fe, NM. On December 17, 2017, the Department of Energy (DOE) awarded a separate $1.4 billion contract for cleanup at the Los Alamos National Laboratory (LANL) to Newport News Nuclear BWXT-Los Alamos, LLC (also known as "N3B"). This award followed a DOE decision to pull cleanup from LANL's prime contractor, Los Alamos National Security, LLC (LANS), after it sent an improperly prepared radioactive waste drum that ruptured underground at the Waste Isolation Pilot Plant (WIPP). That incident contaminated 21 workers and closed WIPP for nearly three years, costing taxpayers at least $1.5 billion to reopen. (See all the details in the full press release) February 26, 2018 Press Release Detailed NNSA Budget Documents Accelerates Nuclear Weapons Arms Race Santa Fe, NM. Late Friday February 23, the Trump Administration released the detailed FY 2019 budget for the National Nuclear Security Administration (NNSA), the semi-autonomous nuclear weapons agency within the federal Department of Energy. Overall, NNSA is receiving a $2.2 billion boost to $15.1 billion, a 17% increase above the FY 2018 enacted level. Of that, a full $11 billion is for the budget category [Nuclear] "Weapons Activities", 18% above the FY 2018 level. Of concern to the American taxpayer, DOE and NNSA nuclear weapons programs have been on the congressional Government Accountability Office's High Risk List for project mismanagement, fraud, waste and abuse since its inception in 1990... (See all the details in the full press release) February 22, 2018 Press Release Santa Fe, NM. Today the National Nuclear Security Administration announced an Environmental Assessment to increase the amount of plutonium used in the Radiological Laboratory Utility and Office Building (aka the "Rad Lab") at the Los Alamos National Laboratory from 38.6 grams of plutonium-239 equivalent to 400 grams. This 10-fold increase is significant because it will dramatically expand materials characterization and analytical chemistry capabilities in the Rad Lab in support of expanded plutonium pit production for future nuclear weapons designs. It also re-categorizes the Rad Lab from a "radiological facility" to a "Hazard Category-3" nuclear facility. View/Download full press release February 12, 2018 Press Release Trump's Budget Dramatically Increases Nuclear Weapons Work Santa Fe, NM In keeping with the Trump Administration's recent controversial Nuclear Posture Review, today's just released FY 2019 federal budget dramatically ramps up nuclear weapons research and production. January 12, 2018 Press Release Draft Nuclear Posture Review Degrades National Security Yesterday evening the Huffington Post posted a leaked draft of the Trump Administration's Nuclear Posture Review (NPR). This review is the federal government's highest unclassified nuclear weapons policy document, and the first since the Obama Administration's April 2010 NPR. 2017 |
2017
December 22, 2017 Press Release New Mexico Environment Department Surrendered to DOE Extortion Santa Fe, NM. The New Mexico State Auditor Office recently questioned whether two settlements between the New Mexico Environment Department and the Department of Energy were in the best interests of New Mexico. That Office noted: (View/download full press release) December 20, 2017 Press Release Los Alamos Hires New Contractor - Starts Cleanup On the Cheap Santa Fe, NM- Today the Department of Energy (DOE) announced the award of the new Los Alamos National Laboratory legacy cleanup contract to Newport News Nuclear BWXT-Los Alamos, LLC. The $1.39 billion contract is for ten years, which works out to $139 million per year... View/download the full press release Public Presentation, December 2, 2017 October 31, 2017 Press Release Today, in Washington, DC, the Congressional Budget Office released its new report, "Approaches for Managing the Costs of U.S. Nuclear Forces, 2017 to 2046". The Congressional Budget Office estimates that the most recent detailed plans for nuclear forces, which were incorporated in the Obama Administration's 2017 budget request, would cost $1.2 trillion in 2017 dollars over the 2017-2046 period: more than $800 billion to operate and sustain (that is, incrementally upgrade) nuclear forces and about $400 billion to modernize them.... Driving this astronomical expense is the fact that instead of maintaining just the few hundred warheads needed for the publicly claimed policy of "deterrence," thousands of warheads are being refurbished and improved to fight a potential nuclear war. This is the little known but explicit policy of the U.S. government! October 27, 2017 Press Release Santa Fe, NM. On the evening of Wednesday October 25, the Santa Fe City Council passed a resolution requesting that the New Mexico Environment Department strengthen the revised Los Alamos National Labs cleanup order to call for additional characterization of legacy nuclear wastes, increased cleanup funding, and significant additional safety training. The resolution also called for the suspension of any planned expanded plutonium pit production until safety issues are resolved. (view/download full press release) October 6, 2017 Press Release Santa Fe, NM. Nuclear Watch New Mexico strongly applauds the awarding of the Nobel Peace Prize to the International Campaign to Abolish Nuclear Weapons (disclosure: NukeWatch is one of ICAN's ~400 member groups around the world). This award is especially apt because the peoples of the world are now living at the highest risk for nuclear war since the middle 1980's, when during President Reagan's military buildup the Soviet Union became convinced that the United States might launch a pre-emptive nuclear first strike. Today, we not only have Trump's threats to "totally destroy" North Korea and Kim Jong-un's counter threats, but also renewed Russian fears of a US preemptive nuclear attack... Generally unknown to the American taxpayer, our government has quietly tripled the lethality of the US nuclear weapons stockpile..." (view/download complete press release) NukeWatch fact sheet, September 26, 2017 The National Nuclear Security Administration's own documents have explicitly stated that expanded pit production would have no significant positive effect on job creation and the regional economy of northern New Mexico. Nuclear Watch argues that expanded plutonium pit production could actually have negative effect if it blocks other economic alternatives such as comprehensive cleanup, which could be the real job producer. Moreover, given LANL's poor safety and environmental record, expanded plutonium pit production could have a seriously negative economic impact on northern New Mexico in the event of any major accidents. September 15, 2017 Press Release Santa Fe, NM. The Los Alamos National Laboratory (LANL) has detected far more hexavalent chromium (Cr) contamination than previously estimated in the "sole source" regional groundwater aquifer that serves Los Alamos, Santa Fe and the Espanola Basin. Sampling in July from a new well meant to inject treated groundwater back into the aquifer detected chromium contamination five times greater than the New Mexico groundwater standard of 50 micrograms per liter (ug/L). View/download the full press release September 11, 2017 Press Release Talking Points: The 2016 LANL Cleanup Consent Order Should Be Rescinded The 2005 LANL Cleanup Consent Order was all about the enforceable schedules. It required DOE and LANL to investigate, characterize, and clean up hazardous and mixed radioactive contaminants from 70 years of nuclear weapons research and production. It stipulated a detailed compliance schedule that the Lab was required to meet. Under Gov. Martinez, NMED Secretary Ryan Flynn granted more than 150 compliance milestone extensions at the Lab's request, effectively eviscerating it. View/download the complete talking points July 20, 2017 Press Release Washington, DC Today, the Oak Ridge Environmental Peace Alliance (OREPA), Nuclear Watch New Mexico, and the Natural Resources Defense Council filed a federal lawsuit to stop construction of the problem-plagued Uranium Processing Facility (UPF) until legally required environmental review is completed. The UPF, located at the National Nuclear Security Administration's (NNSA's) Y-12 production plant near Oak Ridge, TN, is slated to produce new thermonuclear weapons components until the year 2080. The UPF is the tip of the spear for the U.S.'s planned one trillion dollar-plus make over of its nuclear weapons arsenal, delivery systems, and production plants. View/download the full press release June 19, 2017 Press Release Some Background on Plutonium Pit Production at the Los Alamos Lab Santa Fe, NM -The Washington Post has published the first in a series of articles on nuclear safety lapses in plutonium pit production at the Los Alamos Lab. Plutonium pits are the fissile cores of nuclear weapons that when imploded initiate the thermonuclear detonation of modern weapons. By the way, did you know? Plutonium facilities at LANL are- in principle- designed to withstand a serious earthquake of a degree expected to occur only once every 10,000 years. The last serious earthquake near the Lab is believed to have occurred 11,500 years ago. View/download the full press release ANA Report 2017: Accountability Audit May 19, 2017 Press Release SA Preview of Trump's Budget: More Nuclear Bombs and Plutonium Pit Production Santa Fe, NM. "The proposed level of funding for the National Nuclear Security Administration's (NNSA)'s Total Weapons Activities is $10.2 billion, a full billion above what was requested for FY 2017. In March, Trump's "skinny budget" stated NNSA's funding priorities as 'moving toward a responsive nuclear infrastructure', and 'advancing the existing warhead life extension programs'. Read the full press release for all the details. March 28, 2017 ANA workshop at UN Ban Treaty Conference Ban Treaty Conference: Alliance for Nuclear Accountability Panel Discussion March 28, 2017, UN, NYC:
March 2017 Fact Sheet Plutonium Pit Production at LANL (Updated March 2017) February 23, 2017 Press Release Costs Jump in Nuclear Weapons vs. Cleanup; Nuclear Weapons Winning over Environmental Protection Santa Fe, NM. America is at a crossroads, having to choose between an unnecessarily large, exorbitant, nuclear weapons stockpile, and cleanup that would protect the environment and water resources for future generations. Expanded nuclear weapons research and production, which will cause yet more contamination, is winning. Read the full press release for all the details. January 5, 2017 Press Release The National Nuclear Security Administration (NNSA) has publicly released its fiscal year 2016 Performance Evaluation Report (PER) for Los Alamos National Security, LLC (LANS), the for-profit contractor that runs the Los Alamos Lab. The Performance Evaluation Report is NNSA's annual report card on contractor performance, and overall the agency awarded LANS $59 million in profit out of a possible $65 million. The grade was 85% for the incentive part of the award. In 2012 Nuclear Watch New Mexico successfully sued NNSA to ensure that the Performance Evaluation Reports detailing taxpayers funds paid to nuclear weapons contractors are publicly available. In 2016 the NNSA decided to put the LANL management contract out for competitive bid, but granted LANS a contract extension until the end of September 2018. |
Media appearances including radio interviews are listed on the internal Media page
See the NukeWatch Channel at YouTube for our extensive playlists of key videos.
See the Nukewatch Twitter feed
See the Nukewatch Tumblr site
WatchBlog Posts:
Over 200 posts published since 2009. See archives at the WatchBlog
Earlier Work Product items are archived here