Court Rules U.S. Nuclear Weapons Production Plan Violates Federal Law
FOR IMMEDIATE RELEASE, October 3, 2024
Media Contacts:
Ben Cunningham, Esquire, SCELP, 843-527-0078, [email protected]
Tom Clements, Savannah River Site Watch, 803-834-3084, [email protected]
Jay Coghlan, Nuclear Watch New Mexico, 505-989-7342, [email protected]
Scott Yundt, Tri-Valley CAREs, 925-443-7148, [email protected]
Queen Quet, Gullah/Geechee Sea Island Coalition, 843-838-1171, [email protected]
AIKEN, S.C. — On September 30, United States District Court Judge Mary Geiger Lewis ruled that the United States Department of Energy (“DOE”) and its semi-autonomous nuclear weapons agency, the National Nuclear Security Administration (“NNSA”), violated the National Environmental Policy Act (“NEPA”) by failing to properly consider alternatives before proceeding with their plan to produce plutonium pits, a critical component of nuclear weapons, at the Los Alamos National Laboratory (“LANL”) in New Mexico and, for the first time ever, at the Savannah River Site (“SRS”) in South Carolina.
The Court found that the plan’s purpose had fundamentally changed from NNSA’s earlier analyses which had not considered simultaneous pit production at two sites. These changes necessitated a reevaluation of alternatives, including site alternatives, which Defendants failed to undertake prior to moving forward while spending tens of billions of taxpayers’ dollars. Therefore, the Court entered judgment in favor of Plaintiffs, the nonprofit public interest groups Savannah River Site Watch, Nuclear Water New Mexico and Tri-Valley Communities Against a Radioactive Environment (CAREs); the Gullah/Geechee Sea Island Coalition; and Tom Clements as an individual plaintiff.
As a result of this ruling, the Defendants are required to newly assess pit production at a nation-wide programmatic level which will mean undertaking a thorough analysis of the impacts of pit production at DOE sites throughout the United States, including radioactive waste generation and disposal. Under the National Environmental Policy Act (NEPA), this will provide the opportunity for public scrutiny of and formal comment on their assessments.
High Detections of Plutonium in Los Alamos Neighborhood – As We Enter a New Nuclear Arms Race the Last One is Still Not Cleaned Up
FOR IMMEDIATE RELEASE, August 15, 2024
Dr. Michael Ketterer – 928.853.7188 | Email
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – In April Nuclear Watch New Mexico released a map of plutonium contamination based on Lab data. Today, Dr. Michael Ketterer, Professor Emeritus of Chemistry and Biochemistry, Northern Arizona University, is releasing alarmingly high results from samples taken from a popular walking trail in the Los Alamos Town Site, including detections of some of the earliest plutonium produced by humankind.
On July 2 and 17 Dr. Ketterer, with the assistance of Nuclear Watch New Mexico, collected water, soil and plant samples from Acid Canyon in the Los Alamos Town Site and soil and plant samples in Los Alamos Canyon at the Totavi gas station downstream from the Lab. The samples were prepared and analyzed by mass spectrometry at Northern Arizona University to measure concentrations of plutonium, and to ascertain its sources in the environment.
NNSA Delays Urgent Research on Plutonium “Pit” Aging While Spending Tens of Billions on Nuclear Weapons Bomb Core Production
FOR IMMEDIATE RELEASE, April 17, 2024
Tom Clements, SRS Watch – 803.240.7268 | Email
Scott Yundt, TVC – 415.990.2070 | Email
Jay Coghlan – 505.989.7342 | Email
Nearly three years after filing a Freedom of Information Act request, the public interest group Savannah River Site Watch has finally received the National Nuclear Security Administration’s (NNSA’s) congressionally-required “Research Program Plan for Plutonium and Pit Aging.” However, the document is 40% blacked out, including references and acronyms. Plutonium “pits” are the radioactive cores of all U.S. nuclear weapons. The NNSA claims that potential aging effects are justification for a ~$60 billion program to expand production. However, the Plan fails to show that aging is a current problem. To the contrary, it demonstrates that NNSA is delaying urgently needed updated plutonium pit aging research.
In 2006 independent scientific experts known as the JASONs concluded that plutonium pits last at least 85 years without specifying an end date [i] (the average pit age is now around 40 years). A 2012 follow-on study by the Lawrence Livermore nuclear weapons lab concluded:
“This continuing work shows that no unexpected aging issues are appearing in plutonium that has been accelerated to an equivalent of ~ 150 years of age. The results of this work are consistent with, and further reinforce, the Department of Energy Record of Decision to pursue a limited pit manufacturing capability in existing and planned facilities at Los Alamos instead of constructing a new, very large pit manufacturing facility…” [ii]
Since then NNSA has reversed itself. In 2018 the agency decided to pursue the simultaneous production of at least 30 pits per year at the Los Alamos National Laboratory (LANL) in northern New Mexico and at least 50 pits per year at the Savannah River Site (SRS) in South Carolina. Upgrades to plutonium facilities at LANL are slated to cost $8 billion over the next 5 years. The redundant Savannah River Plutonium Processing Facility in South Carolina will cost up to $25 billion, making it the second most expensive building in human history.
NNSA’s Nuclear Weapons Budget Takes Huge Jump
Arms Race Accelerates with MIRVed Warheads
Los Alamos Lab Cleanup Cut
FOR IMMEDIATE RELEASE, March 11, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – Ironically the day after the film Oppenheimer was awarded multiple Oscars, the Department of Energy’s semi-autonomous National Nuclear Security Administration (NNSA) asked Congress for its biggest nuclear weapons budget ever. NNSA’s FY 2025 request for “Total Weapons Activities” is $19.8 billion, $700 million above what Congress recently enacted for FY 2024. It is also a full billion dollars above what President Biden asked for last year, which Congress then added to and will likely do so again.
The Biden Administration states that the $19.8 billion will be used to:
“[P]rioritize implementation of the 2022 National Defense Strategy and Nuclear Posture Review by modernizing the Nation’s nuclear deterrent to keep the American people safe. The Budget supports a safe, secure, reliable, and effective nuclear stockpile and a resilient, responsive nuclear security enterprise necessary to protect the U.S. homeland and allies from growing international threats.” whitehouse.gov/wp-content/uploads/2024/03/budget_fy2025.pdf, page 75.
The 2022 National Defense Strategy and Nuclear Posture Review for the first time posited two nuclear “near peers”, i.e. Russia and China, that need to be simultaneously “deterred.” This hinted at a potentially large nuclear buildup which this budget may now be implementing. That claimed need to deter two nuclear near peers was explicitly taken a step beyond just deterrence in an October 2023 report from the Strategic Posture Commission. It declared:
“Decisions need to be made now in order for the nation to be prepared to address the threats from these two nuclear-armed adversaries arising during the 2027-2035 timeframe. Moreover, these threats are such that the United States and its Allies and partners must be ready to deter and defeat both adversaries simultaneously.” ida.org/research-and-publications/publications/all/a/am/americas-strategic-posture, page vii (bolded emphasis added)
NNSA Suppresses How Taxpayers Money Is Spent
FOR IMMEDIATE RELEASE, January 19, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – The National Nuclear Security Administration (NNSA) has just released cursory two or three page summaries of contractors’ performance paid for by the American taxpayer. For the just ended fiscal year 2023, NNSA gave nothing less than grades of “Excellent” or “Very Good” in six broad mission goals for its major contractors. This is despite the constant cost overruns and schedule delays that are the rule, not the exception, in the nation-wide nuclear weapons complex. NNSA and its parent Department of Energy have been on the Government Accountability Office’s “High Risk List” for project mismanagement ever since GAO started that List in 1991.
A current example is the Uranium Processing Facility (UPF) at the Y-12 Plant near Oak Ridge, Tennessee, originally estimated in 2011 to cost $1.4 to $3.5 billion. After costs started going through the roof, NNSA and Senator Lamar Alexander (R.-TN), then-chair of Senate Energy and Water Appropriations, swore that UPF would never go over $6.5 billion. But even after eliminating non-nuclear weapons production missions and a formal decision to continue operations at two old, unsafe buildings slated for replacement, the Uranium Processing Facility is now estimated to cost $8.5 billion. However, even that is not the final price, as NNSA is still to “rebaseline” UPF costs at some unspecified date.
2023
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT FACT SHEETS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT PRESS RELEASES
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT NUCLEAR BUDGET GRAPHS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
Past Work Product (2020-2021)
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
75TH ANNIVERSARY HIROSHIMA DAY ONLINE COMMEMORATION CALLING FOR THE ABOLITION OF NUCLEAR WEAPONS
August 6, 2020
"Jay Coghlan of Nukewatch.org on the history of the Los Alamos labs, where the bomb was designed and fabricated, and how it continues to play the leading role in the creation of most U.S. nuclear weapons since then."
[embeddoc url="https://nukewatch.org/wp-content/uploads/2020/05/plutonium-pit-production-fact-sheet.pdf" download="all" viewer="browser"]
PLUTONIUM PIT PRODUCTION WORKSHOP – NOVEMBER 19, 2019
RADIO INTERVIEW – SCOTT KOVAC & JON LIPSKY
Scott Kovac of Nuclear Watch New Mexico and Jon Lipsky, the FBI agent who led the 1989 raid investigating environmental crimes that shut down the Rocky Flats Nuclear Bomb Plant join Xubi to talk about Nuclear weapons, Nuclear clean up and Pit production plans at LANL.
RADIO INTERVIEW – JAY COGHLAN & JON LIPSKY
PIT Production at LANL with Nuclear Watch New Mexico’s Jay Coghlan and Workshop Speaker, Jon Lipsky
RADIO INTERVIEW – MARYLIA KELLEY, EXECUTIVE DIRECTOR, TRI-VALLEY CARES
Nuclear Watch NM’s Workshop on LANL & PIT Production with Marylia Kelley of Tri-Valley CARES
Pit Production Workshop: View the Presentations
Jon Lipsky, FBI agent that led the 1989 raid investigating environmental crimes that shut down the Rocky Flats bomb plant
Introduction by Jay Coghlan
Jay Coghlan, Executive Director, Nuclear Watch New Mexico, on plutonium pit production at LANL
Marylia Kelly, Executive Director, Tri-Valley CAREs (Livermore, CA) on the new nuclear arms race
https://www.facebook.com/NukeWatch.NM/videos/825812604488302/
Scott Kovac Nuclear Watch New Mexico, on LANL cleanup issues
Blog Posts
LANL Proposes Satellite “Campus” in Santa Fe as Part of Expanded Production of Plutonium Nuclear Weapons Triggers
Santa Fe, NM – Today, the Santa Fe New Mexican newspaper reported:
“Santa Fe city leaders asked for developers’ ideas on what to do with the city-owned midtown campus…The National Nuclear Security Administration [NNSA], which administers the Los Alamos National Laboratory management and operating contract, submitted a master developer proposal to build an open-campus environment with administrative offices, sustainable green spaces, engineering space, light manufacturing, training facilities and research and development…
[A NNSA spokesperson said] “LANL is undergoing unprecedented growth and expects to hire more than 1,000 new personnel annually for the next several years. Having a new campus — midway between New Mexico’s two national laboratories [LANL and Sandia]— to house professional staff, scientists, and engineers in partnership with the city of Santa Fe — would be very beneficial.” ”
LANL’s growing jobs are primarily for expanded production of plutonium pits (the radioactive triggers of nuclear weapons) which helps to fuel the new global arms race. Over the last decade the Santa Fe City Council has passed three different resolutions against expanded plutonium pit production. Seventy percent (and growing) of LANL’s ~$2.6 billion annual budget is for core nuclear weapons research and production programs, while the remainder directly or indirectly supports those programs. In contrast, LANL’s renewable energy budget is .007% of its nuclear weapons budget and the Lab has zero dedicated funding to fight climate change. Moreover, LANL claims that its cleanup is more than half complete, intentionally omitting that it plans to leave ~150,000 cubic meters of toxic and radioactive wastes permanently buried uphill from the Rio Grande and above our common groundwater aquifer.
Just this last Sunday Pope Francis called for the abolition of nuclear weapons while in Japan paying homage to the victims of the Hiroshima and Nagasaki bombings. Those atomic bombs were designed and produced at the Los Alamos Lab.
The City of Santa Fe’s official name is the “La Villa Real de la Santa Fe de San Francisco de Asís” (“The Royal Town of the Holy Faith of Saint Francis of Assisi”), in honor of the beloved saint who preached peace and environmental protection and from whom the present Pope draws his name. It would be supremely ironic if the City of Santa Fe hosted a satellite campus for a massive institution that spends 2 billion dollars (and counting) every year on nuclear weapons of mass destruction.
Jay Coghlan, director of Nuclear Watch New Mexico, commented, “Mayor Webber and the Santa Fe City Council surely know that the institutionalized presence of a nuclear weapons production laboratory in our city would generate a tremendous amount of controversy, a controversy they could well do without. The leaders of the City of Santa Fe should nix LANL’s proposal for a satellite campus in our town as a nonstarter and an affront to St. Francis de Assisi, the saint of peace.”
# # #
The Santa Fe New Mexican article is available at
Pope Frances Calls for Nuclear Weapons Abolition – – Santa Fe Catholic Archdiocese Likely Has Largest Presence of Nuclear Weapons in the World
FOR IMMEDIATE RELEASE, November 24, 2019
Santa Fe, NM – Today, Pope Francis called for the global abolition of nuclear weapons while paying homage to the victims of the bombings of Hiroshima and Nagasaki. Those two cities were both destroyed by atomic weapons designed and produced by the Los Alamos National Laboratory, located in northern New Mexico’s Santa Fe Catholic Archdiocese.
The Holy Father declared:
“With deep conviction I wish once more to declare that the use of atomic energy for purposes of war is today, more than ever, a crime not only against the dignity of human beings but against any possible future for our common home. The use of atomic energy for purposes of war is immoral, just as the possessing of nuclear weapons is immoral, as I already said two years ago. We will be judged on this. Future generations will rise to condemn our failure if we spoke of peace but did not act to bring it about among the peoples of the earth. How can we speak of peace even as we build terrifying new weapons of war?”
Two of the U.S.’ three nuclear weapons laboratories, the Los Alamos and Sandia National Laboratories, are located within the Santa Fe Catholic Archdiocese. Together the two labs spend $4 billion per year on core nuclear weapons design, testing and production programs. In addition, up to 2,500 nuclear weapons are estimated to be held in strategic reserve at the Kirtland Underground Munitions Maintenance and Storage Complex, less than two miles south of the Albuquerque International Airport. That complex is probably the largest repository of intact nuclear weapons in the country and perhaps the world. →
LANL Busted For Losing Control of Controlled Substances
In a recent report, the Department Of Energy’s Office of Inspector General (IG) found issues with the way Los Alamos National Laboratory (LANL) keeps track of controlled substances such as cocaine, fentanyl, and methamphetamine. The IG found that LANL staff had not managed controlled substances in accordance with applicable Federal laws and regulations.
The IG also found that LANL staff had mislabeled procurement records of these drugs, kept inaccurate inventories, and retained controlled substances well beyond the conclusion of experiments. The IG determined that Los Alamos did not have appropriate “processes, procedures, or controls in place to monitor, track, account for, and dispose of controlled substances.”
Help Stop Plans to “Modernize” WIPP
The Waste Isolation Pilot Plant (WIPP), located outside Carlsbad, NM. is the nation’s only geologic repository for defense-generated transuranic waste. The Department of Energy (DOE) is accepting comments on its 2019-2024 “Strategic Plan”, which should be focused on closing WIPP. But the Plan focuses on extending WIPP’s lifetime to 2050 and beyond. WIPP’s disposal phase was extended until 2024 (in 2010), and the last expected year of final closure of the WIPP facility (i.e., date of final closure certification) was to be 2034. There was always a 10-year period for final closure after the disposal operations ceased.
But, instead, the WIPP Strategic Plan is stocked full of new projects that will extend WIPP’s life another 25 years at least. Yet, WIPP officials don’t mention how or when they plan to modify the State Permit with the new proposed date. DOE’s own waste-handling inefficiencies and mistakes have caused this delay that the people of New Mexico are now paying for by having WIPP open longer than planned. We are asking everyone to oppose DOE’s “WIPP Forever” plans by sending in comments. See below.
Help Stop The New Strategic Plan That Would Double WIPP’s Lifespan
DOE Moves Forward With Unneeded New Shaft at WIPP
Originally billed as a replacement exhaust shaft to help WIPP recover from the 2014 exploding drum event that shut down WIPP for three years, a proposed new shaft is now designed to increase WIPP’s capacity. WIPP officials have repeatedly stated that after a new filter building is complete, WIPP will have returned to its pre-2014 capacity without the new shaft. The $75 million new fifth shaft would increase the mining and waste handling capacity by 25% at any given time.
One would think that increasing the annual ability to emplace waste at WIPP would help keep the repository on track to stop receiving waste by its original date of 2024. But along with the annual increased mining and disposal capacity, DOE has also released a Strategic Plan to extend WIPP’s waste disposal deadline to 2052.
Watchdogs Issue Second Demand for Nation-Wide Environmental Review of Expanded Plutonium Pit Production
Today, lawyers for the Natural Resources Defense Council, Nuclear Watch New Mexico, Savannah River Site Watch and Tri-Valley Communities Against a Radioactive Environment sent a second letter to Department of Energy (DOE) Secretary Rick Perry and Lisa Gordon-Hagerty, the head of the semi-autonomous National Nuclear Security Administration (NNSA). The letter demands a nation-wide programmatic environmental impact statement for the agencies’ proposed expanded production of plutonium pits, the fissile cores or “triggers” of nuclear weapons. Invoking the National Environmental Policy Act (NEPA), the letter concludes:
“…we advise the agencies that timely compliance with NEPA is the best means for the agencies to keep these [expanded plutonium pit production] projects on track, as a failure to rigorously comply with NEPA may necessitate litigation, including if necessary motions for injunctive relief, all of which would likely increase the expense of DOE’s and NNSA’s proposed actions and extend their timelines further. Accordingly, we strongly encourage DOE and NNSA to come into compliance with NEPA by preparing a new or supplemental PEIS for its proposals regarding plutonium pit production, and to do so immediately. If the agencies continue on their current trajectory, we will have no choice but to evaluate all our options to enforce compliance with federal environmental laws.”
As background, on May 10, 2018, the Departments of Defense and Energy jointly announced that plutonium pit production would be expanded from the currently sanctioned level of 20 pits per year at the Los Alamos National Laboratory (LANL) in northern New Mexico to at least 30 pits per year, plus redundant production of at least 50 pits per year at the Savannah River Site (SRS) in South Carolina, which would be a completely new mission there.
Lack Of Safety And Health Priorities Continue To Plague Los Alamos Beryllium Program
A new assessment finds that Department of Energy (DOE) is not conducting effective oversight of the Los Alamos National Laboratory (LANL) beryllium program, or of safety and health programs in general. In addition, DOE is not maintaining sufficient technical capability and knowledge of site and contractor activities to make informed decisions about hazards and risks. DOE indicated the lack of sufficient safety and health resources has presented a challenge to achieving effective oversight in this area.
The U.S. should carefully and prudently maintain its nuclear weapons stockpile
Defense News reports that “Nuclear gravity bomb and warhead upgrades face new delays” because of new components used in so-called Life Extension Programs (LEPs) to prolong the service lives of existing nuclear weapons. These programs also give existing nuclear weapons new military capabilities. For example, see How US nuclear force modernization is undermining strategic stability: The burst-height compensating super-fuze
The point of this blog is to raise the question of whether these Life Extension Programs really enhance U.S. national security while maintaining the safety and reliability of the nuclear weapons stockpile. In fact, perhaps the crux issue is prudent and conservative maintenance of the stockpile versus increasingly aggressive LEPs.
Relevant to NNSA biolabs – – C.D.C. Closes Anthrax and Flu Labs After Accidents
Today’s New York Times has a very relevant article for those concerned about biolabs at National Nuclear Security Administration sites (i.e., Los Alamos and Livermore Labs).
The money quote: “Dr. Frieden [Director of the CDC] himself suggested that the accidents had implications for labs beyond his agency, arguing that the world needs to reduce to absolute minimums the number of labs handling dangerous agents, the number of staff members involved and the number of [bio]agents circulating.”
As Marylia Kelley of Tri-Valley CAREs can attest to, Livermore is conducting aerosolized experiments with anthrax and other “select agents.” In its inadequate environmental assessment (a lesser cousin of an “environmental impact statement”) LLNL disingenuously declared a certain amount of pathogens to be at risk during a major event. We discovered only through litigation discovery that ~10 times the amount of pathogens would be permanently kept at the biolab in freezers, which NNSA did not disclose in the EA. This, of course, is near the densely populated, highly seismic Bay Area, which could have its electrical grid destroyed during a major earthquake.
See:
C.D.C. Closes Anthrax and Flu Labs After Accidents
By DONALD G. McNEIL Jr.JULY 11, 2014
Los Alamos Rated Easiest County to Live in
Los Alamos Rated Easiest County to Live in
The team at The Upshot, a NYTimes news and data-analysis venture, compiled six basic metrics to give a picture of the quality and longevity of life in each county of the nation. They were attempting to answer the question, Where are the hardest places to live in the U.S.? To create an overall ranking, they averaged each county’s relative rank in these categories: educational attainment, household income, jobless rate, disability rate, life expectancy and obesity rate.
The #1 ranking, and hence easiest place to live, went to Los Alamos County, home of Los Alamos National Laboratory, which spends 65% of its annual budget on nuclear weapons production and design. “The Lab directly employs one out of every five county residents and has a budget of $2.1 billion, which an enormous economic engine for a county of just 18,000 people,” the article states. A look at surrounding counties shows that this engine does not power the surrounding counties equally.
Rio Arriba is ranked #1966 out of 3,135 counties
Taos County = #1234
Sandoval County = #420
Santa Fe County = #148
Some specific comparisons:
63.2 percent residents have at least a bachelor’s degree in Los Alamos.
Rio Arriba County = 15.9%
Taos County = 28.8%
Sandoval County = 28.1%
Santa Fe County = 39.3%
The median household income in Los Alamos County is $106,426.
Rio Arriba County = $40,791
Taos County = $33,835
Sandoval County = $58,116
Santa Fe County = $53,642
In Rio Arriba County, 8 percent of residents are unemployed, and 1.9 percent are on disability.
The corresponding figures in Los Alamos County are 3.5 percent and 0.3 percent.
Taos County = 9.1%, and 1.2%
Sandoval County = 8%, and 1%
Santa Fe County = 5.5% are unemployed, 1% are on disability
Los Alamos County residents live on average 82.4 years
Rio Arriba County = 75 years
Taos County = 79.3 years
Sandoval County = 79.4 years
Santa Fe County = 80.1 years
And Los Alamos County’s obesity rate is 22.8 percent,
Rio Arriba County = 34%
Taos County = 29%
Sandoval County = 32%
Santa Fe County = 22%
Making nukes and the livin’s easy.
Missed WIPP Deadline May Put Real Cleanup at LANL Back On Track
Missed WIPP Deadline May Put Real Cleanup at LANL Back On Track
Santa Fe, NM – Today the New Mexico Environment Department (NMED) denied extension requests by Los Alamos National Laboratory (LANL) to delay cleanup milestones under a legally enforceable 2005 Consent Order. These denials by NMED counter a trend since January 2012 when NMED and LANL entered into a nonbinding “Framework Agreement” to ship 3706 cubic meters of above-ground transuranic waste from the Lab to the Waste Isolation Pilot Plant (WIPP) for permanent disposal. LANL radioactive wastes are now the main suspect in the February 14 contamination and subsequent shutdown of the multi-billion dollar WIPP.
NMED denied 14 extensions, now available in LANL’s Electronic Public Reading Room. These denials include construction of monitoring wells, and investigation reports for cleanup of contaminated areas. All of them included language that LANL requested an extension based on the Lab’s need to divert resources to remove transuranic waste in accordance with the Framework Agreement. The denials repeatedly state, “Based on the Permittees’ [LANL’s] statement that they will not be able to meet the deadlines that they committed to in the Framework Agreement [to ship TRU wastes to WIPP], the request is hereby denied.”
NMED had previously agreed to over 100 of these extension requests in favor of the so-called 3706 Campaign. The campaign was part of a non-binding agreement with the NM Environment Department so there are no penalties associated with lack of performance. The problem is that much other cleanup at the Lab was delayed while the 3706 Campaign was prioritized.
The Lab will miss the June 30 deadline of shipping 3,706 cubic meters of transuranic waste while the cleanup of over 1,000,000 cubic meters of all types of radioactive waste, hazardous waste, and contaminated backfill buried across the Lab were put on the back burner. These vast amounts of buried wastes, dating back to the Lab’s early days, are covered under the 2005 Consent Order for the “fence-to-fence” cleanup of legacy wastes. The Consent Order is enforceable with financial penalties for missed deliverables.
The Lab has claimed that there is not enough money to address all the Consent Order deliverables, but the original intent behind the Consent Order was that fines or the threat of fines would shake federal cleanup funding from DOE headquarters in Washington, DC. Cleanup without the big stick of possible fines just takes us back to the time when the small budget received annually just gets sprinkled around to where the cleanup “priorities” are perceived to be.
Jay Coghlan, Nuclear Watch New Mexico Executive Director, commented, “After granting more than one hundred extension requests to delay cleanup, we salute the New Mexico Environment Department for denying further requests. We encourage NMED to enforce what it already has, and make LANL comply with its legally mandated cleanup order. This in turn will drive increased federal funding for genuine cleanup at the Lab, creating hundreds of jobs while permanently protecting our precious water and environment.”
Scott Kovac, Nuclear Watch New Mexico Program Director, commented, “We look forward to continuing enforcement of the 2005 Consent Order and the necessary removal of Cold War legacy waste buried in unlined trenches above our aquifer.”
January 2012 Framework Agreement
LANL’s Electronic Public Reading Room
DOE Headquarters Launches an Investigation Into the WIPP Release
DOE Headquarters Launches an Investigation Into the WIPP Release
On June 16, 2014, the U.S. Department of Energy (DOE) DC Office of Independent Enterprise Assessments notified Nuclear Waste Partnership, LLC, the operating contractor for DOE’s Waste Isolation Pilot Plant, of its intent to conduct an investigation. The investigation will look into potential nuclear safety, worker safety, and health programmatic deficiencies associated with the two events in February.
WIPP has been shut down since February 5, 2014, when a salt-hauling truck caught fire, forcing evacuation of 86 workers from underground, 13 of whom were treated for smoke inhalation. Nine days later, an air monitor detected radiation underground where waste had recently been emplaced. The emergency filtration started, but radioactive particles were released to the environment. That resulted in contamination of all 13 people working above ground.
The DOE headquarters’ investigation may be a good start (hopefully), but Nuclear Watch NM, and many other groups, wants a truly independent, public investigation. This investigation should determine the cause of the WIPP radiation release, the extent of underground and surface contamination, the medical and compensation requirements for contaminated workers, and options for cleaning up underground and surface contamination.
In the meantime, TRU must be stored safely and securely at other DOE sites, regardless of how long WIPP is closed. Unnecessary waste shipments should not occur while WIPP is closed. Additional newly-generated TRU waste from nuclear weapons production, which exacerbates existing problems, should not be produced.
Los Alamos Budget is 65% Nuclear Weapons
Los Alamos Budget is 65% Nuclear Weapons
There are people who don’t realize that there still are nuclear weapons in the world. There are those who don’t realize that Los Alamos is still in the nuclear weapons business. I’ve created a chart that illustrates that nuclear weapons activities are 65% of the Lab’s annual $2.1 billion dollar budget. The actual Laboratory table from the Department of Energy’s (DOE’s) budget is included.
First, please remember to add three zeroes to all the numbers in the table because all “Dollars in Thousands”. And remember that the Fiscal Year (FY) 2015 Request numbers are just the President’s request, which Congress then slices and dices to arrive at the final appropriation during the congressional budget process.
Notice the largest FY 2015 Request budget by far is “Total Weapons Activities” at $1,417,502,(000). That’s $1.4 billion. “Total Defense Environmental Cleanup”, which is the remediation of radioactive and hazardous waste, is $222,262,(000). That’s $222 million.
The full budget categories are described in Volume 1 of the DOE budget here.
This page also has the Laboratory Tables on it. In addition, there is a “FY 2015 State Table” that shows all of New Mexico receives a total of $4.6 billion from DOE annually including $3.4 billion for nuclear weapons. Sandia National Laboratory in Albuquerque has a $1.5 billion request for nuclear weapons for FY 2015.
What is not on the Laboratory Tables is “Work For Others”, which is work that Los Alamos performs for government agencies other than DOE. This number is estimated at $250 million for FY 2015.
Let me know if you have any questions.
GAO report on NNSA’s dismantlement program
There are lots of interesting nuggets in the Government Accountability Office’s recent dismantlement report. “Nuclear Weapons: Actions Needed by NNSA to Clarify Dismantlement Performance Goal,” April 2014, GAO-14-449, www.gao.gov/assets/670/662840.pdf
Selected highlights below. Verbatim excerpts follow page numbers (add 5 for PDF page number). General points in italics are mine.
Republican presidents, not Dems, make significant stockpile cuts, and do so unilaterally.
1: …in September 1991, the President announced several unilateral initiatives to reduce the U.S. nonstrategic nuclear weapons arsenal. The following month, the Soviet President responded that the Soviet Union would reduce its nonstrategic nuclear weapons. In addition, as part of the annual presidential stockpile review process, in 2004, the President directed that the U.S. nuclear weapons stockpile be reduced by more than 40 percent by 2012 and, in 2007, he directed an additional reduction of the stockpile, making it roughly one-quarter the size of cold war-era levels.
Dismantlements resulting from New START are being held hostage to construction of the Uranium Processing Facility and the Chemistry and Metallurgy Research Replacement Nuclear Facility at LANL.
29: DOD officials told us that the retirement of additional weapons from the stockpile stemming from New START will be predicated on the successful restoration of the NNSA weapons production infrastructure, including the construction and operation of new NNSA facilities supporting nuclear weapons production—the Chemistry and Metallurgy Research Replacement Nuclear Facility at LANL, and the Uranium Production Facility at Y-12—which they did not believe could be achieved until the late 2020s or early 2030s.
Pantex dismantlement workforce could be lost.
29: …this gap in dismantlement workload in the mid-2020s could result in the loss of certified dismantlement personnel because dismantlement technicians at Pantex lose their certifications if they have not worked on a weapon type within the past year. As a result, Pantex may need to retrain and recertify sufficient numbers of new dismantlement personnel in the late 2020s to resume dismantlement efforts to address retired weapons stemming from New START.
NNSA dismantlement rates have plummeted.
21: According to our analysis of dismantlement data, since the early 1990s, NNSA’s dismantlement rates have generally decreased, with NNSA dismantling about 1,000 fewer weapons annually in recent years than it was dismantling in the mid-1990s. In addition, in some years, only one or two types of retired war reserve weapons were dismantled.
NNSA dismantlement reporting is misleading.
23: How NNSA measures progress toward its performance goal of dismantling all weapons retired prior to fiscal year 2009 by the end of fiscal year 2022 is unclear and may make its reported progress misleading, including its practice of not tracking the actual date of retirement of individual dismantled weapons and its plans to reinstate to the stockpile—rather than dismantle—certain weapons retired prior to fiscal year 2009.
Nine percent of “retired” nuclear weapons may go back to the active stockpile.
25: …how NNSA measures progress toward its dismantlement performance goal is also unclear and may be misleading because some weapons retired prior to fiscal year 2009 are reinstated to the stockpile rather than dismantled. Specifically, in our analysis of NNSA’s dismantlement schedule as of March 2013 for weapons retired prior to fiscal year 2009, we found that approximately 9 percent of the weapons retired prior to fiscal year 2009 are scheduled to be reinstated during fiscal year 2013 through fiscal year 2022 or later.
Long retired weapons may come back to active stockpile.
27: The W84-0s and W80-1s currently in managed retirement may not be available to NNSA for dismantlement prior to fiscal year 2022 because both of these systems are being held in managed retirement as candidates for potential reuse as the warhead on a future long-range standoff missile to replace the Air Force’s current ALCM.
Contrary to NNSA claims Life Extension Programs will not decrease total stockpile size, especially when coupled with slower dismantlement rates.
28: As a hedge against technical problems in the life extension program process and in the refurbished warheads, however, the W76-0s are to remain in managed retirement and be unavailable for dismantlement until the life extension program processes and W76-1 unit reliability are “satisfactorily established,” …creating uncertainty as to whether the W76-0s in managed retirement will be released to NNSA in time for dismantlement by the end of fiscal year 2022.
Inconsistent W76-1 production.
28: These officials stated that it would be difficult to predict the completion of the W76-1 life extension program given inconsistent production, and that it was impossible to say whether the W76-0s in managed retirement could be released for dismantlement prior to fiscal year 2019 without additional confidence in NNSA’s production capability.
New START does not change total stockpile numbers, and as previously stated retired weapons can be pulled back to the active stockpile.
29: DOD officials said that the United States will meet the New START ceiling—1,550 operationally deployed nuclear weapons—to be in force by 2018 by transitioning currently deployed nuclear weapons to nondeployed “hedge” status without any significant change in the total stockpile size.
Interesting allusion to the Navy’s lack of support for the interoperable warhead, which could doom it for good.
32: …potential loss of military interest in a future planned common, or interoperable, warhead to replace the W78 and W88
GAO quotes NNSA estimated amounts for accelerated dismantlements, which might be handy for advocacy purposes. However, perhaps as a matter of its timing, the report fails to note the Obama Administration’s proposed 45% cut for dismantlement funding in FY 2015. Separately, the FY 2015 NNSA Stockpile Stewardship and Management Plan states that dismantlements are only 1% of funding for Direct Stockpile Work.
33: NNSA estimated at the time that approximately $212 million in additional funding on top of the projected baseline budgets… would be needed to achieve the fiscal year 2018 dismantlement scenario. Alternatively, NNSA estimated that $265 million in additional funding on top of the projected baseline budgets… would be needed to achieve the fiscal year 2020 scenario.
Dismantlements save money!
35: According to Navy officials we interviewed, accelerating dismantlement of retired W76-0 warheads allowed the Navy to avoid constructing new weapon storage facilities, saving the Navy approximately $190 million in estimated construction costs.
41: NNSA is retaining two types of CSAs [Canned Subassemblies, AKA secondaries] as options for reuse in a potential future W78 warhead refurbishment… In addition, NNSA is also retaining four types of CSAs as options for reuse in a warhead on the Air Force’s planned long-range standoff missile… NNSA officials told us that CSAs associated with a certain warhead indicated as excess in the 2012 Production and Planning Directive are being retained in an indeterminate state pending a senior-level government evaluation of their use in planetary defense against earthbound asteroids… the national labs’ retention letter has also characterized the CSA associated with this warhead as an “irreplaceable national asset.”
42: Y-12 is projected to disassemble far fewer CSAs than in NNSA’s 2009 Production and Planning Directive.
45: As of May 2013, Pantex was storing 3 million mark quality nonnuclear components as a contingency inventory for potential reuse in maintaining active stockpile or refurbished weapons.
49: Pantex site contractors told us that some of these boxes may contain parts that are up to 60 years old and that may be radiologically contaminated, which makes them difficult to handle and identify.
After a Failed Campaign, the State Must Return to Enforceable Cleanup At LANL
After a Failed Campaign, the State Must Return to Enforceable Cleanup At LANL
The June 30 deadline of the “3706 Campaign” to remove 3706 cubic meters of transuranic waste stored on the surface on Los Alamos Lab will be missed due to the radiation release and shutdown of the Waste Isolation Pilot Plant. The campaign was part of a non-binding agreement with the NM Environment Department so there are no penalties associated with lack of performance. The problem is that much other cleanup at the Lab was delayed while the 3706 Campaign was prioritized.
The Lab missed the low bar of shipping 3,706 cubic meters of transuranic waste while the cleanup of over 1,000,000 cubic meters of all types of radioactive waste, hazardous waste, and contaminated backfill buried across the Lab were put on the back burner. These vast amounts of buried wastes, dating back to the Lab’s early days, are covered under a 2005 Consent Order for the “fence-to-fence” cleanup of legacy waste. The Consent Order is enforceable with stipulated penalties of up to $3000/day for missed deliverables. But NMED has been hesitant to impose fines, because of DOE claims that the fines come out of the cleanup budget. The deadline for the last cleanup under the Consent Order is currently December 2015, which everyone agrees is impossible. But that end date could be extended, and should be extended, especially if the Lab was actually working on the legacy cleanup
NMED, to date, has granted over 95 extensions for Consent Order deliverables in favor of the 3706 Campaign. These extensions allow the Lab to not drill monitoring wells and to not perform cleanup investigations and work plans for sites across the Lab. The Lab claims that there is not enough money to address all the Consent Order deliverables, but the idea behind the Consent Order was that fines and the threat of fines would shake cleanup funding from DOE headquarters in DC. Cleanup without the big stick of possible fines just takes us back to the time when the small budget received annually just gets sprinkled around to where the cleanup “priorities” are perceived to be. Urgency and comprehensiveness go out the window.
The Cold War has been over for twenty years now and we in Northern New Mexico have been patient in removing LANL’s legacy waste.
But now Northern New Mexico has neither a 3706 Campaign that is complete, nor a Consent Order that will be complete by its deadline. NMED officials have stated, upon the successful completion of the 3706 Campaign, that they would consider renegotiating the Consent Order. We are waiting to see how NMED deals with the 3706 failure and we urge NMED to make the Consent Order the priority again. The Campaign approach has now been proven not to work.
In the meantime, we also have contaminated WIPP workers.
We have 707 possibly explosive drums probably created by Los Alamos spread across New Mexico and West Texas.
We have a damaged WIPP, which is shut down for up to three years and missing its deadlines for disposing waste.
We have other impacted DOE sites across the country, which will be missing deadlines for radioactive waste disposal.
We the taxpayers are no doubt going to spend hundreds of millions on this fiasco while the contractors continue to put money in their pockets.
The New Mexico Environment Department is the regulator here. Relying on LANL’s promises and plans to make things better must end. Time to return to the 2005 Consent Order and actually use the enforceable provisions in it.
LANL Management Irregularities Continue
LANL Management Irregularities Continue
Los Alamos National Security (LANS), the private consortium that runs Los Alamos National Laboratory under contract for the federal government will manage $2.1 billion of our taxpayer dollars this year. LANS should remember that they were hired to represent the nation’s interests, not the interests of the for-profit corporations running the Lab.
Scott Sandlin, Albuquerque Journal Staff Writer, reported a $3.64 million judgment against Los Alamos National Laboratory for “breach of implied contract and breach of the duty of good faith and fair dealing.” The plaintiffs claimed that Los Alamos conducted the federally funded bidding process, procurement and subsequent protest “using secret policies and procedures inimical to a fair and open bidding procedure.” The Journal disclosed that, according to the lawsuit, the contract was worth roughly $395 million over the first five years and almost $800 million over the decade.
Despite the judgment, LANS denied that it had departed from procedures and also denied deviating from its customary practices.
This follows the March resignation of Los Alamos National Laboratory Deputy Director Beth Sellers, the second-highest ranking administrator at the Lab, for failure to properly report a potential conflict of interest when her husband received a lab consulting contract in 2012. This was also from the ABQ Journal.
The Lab determined that the consultant agreement did not conform to prescribed LANL procedures and processes.” The consultant/husband charged two hours “for a discussion on environmental matters that never took place” and which was actually a visit to the Santa Fe Opera. Los Alamos National Security (LANS), the private consortium that runs the lab under contract with the federal government, reimbursed the government for over $23,000 for the improper contract.
This comes after the November 2013 revelation that Ex-Congresswoman Heather Wilson was paid by nuclear weapons labs the day after she left office. An Albuquerque Journal article built upon a Department of Energy (DOE) Inspector General investigation, which determined that the Sandia and Los Alamos Labs had made approximately $450,000 in improper payments to Wilson up until March 2011, when she began to campaign for the Senate.
A DOE IG report said that the facts indicate that federal funds were used for prohibited lobbying activities, which that office is still investigating. The Labs were forced to return that money to the government, but not Wilson.
The Albuquerque Journal received the new information concerning the dates of Wilson’s contract with Sandia from Nuclear Watch New Mexico. The watchdog organization obtained the documents by appealing an initially rejected federal Freedom of Information Act (FOIA) request.
Nuclear Watch New Mexico Is A Proud Participant In Give Grande
Give ¡Grande! New Mexico is Tomorrow!
On Tuesday, May 6th, you have the opportunity to support local nonprofits and generate significant funds for causes in New Mexico. Large and small gifts will combine for big impact that will support local efforts!
Just log onto www.givegrandenm.org and give to the nonprofits of your choice. Make a tax-deductible contribution online, and your gifts will be added to those of others as the whole state comes together to support the causes we all care about.
Also, come celebrate with us on Tuesday in Santa Fe! Join us to celebrate New Mexico’s first “Day of Giving” from 3:00-6:00 pm at San Isidro Plaza on the South Side! Print out and bring your Give ¡Grande! receipt to get 10 % off your meal at the Plaza Cafe Southside, the Capitol Bar & Grill, and Pizza Centro.
At 5 p.m. Plaza Cafe Southside will cut a giant cake shaped like the state of New Mexico. We also have invited TV stations to stop by about 5:00 pm to do broadcasts for their evening news.
98.1 Radio Free Santa Fe and 107.5 Outlaw Country will be broadcasting live throughout the celebration, and computers will be available for you to make donations on-site.
The Community Foundation Coalition of New Mexico (Coalition), comprised of the Albuquerque, Taos, Southern New Mexico, New Mexico and Santa Fe Community Foundations, is proud to host Give Grande NM, the biggest online philanthropic event in New Mexico history! Community members will come together to raise as much money as possible for local nonprofits in 24 hours. Every dollar will go directly to nonprofits! It’s a great way to recognize and support the positive work of these local organizations.
Donations will begin being accepted on May 06, 2014 12:00 AM MDT.
Enabled by your contribution Nuclear Watch will continue to work diligently to:
• Oppose so-called “modernization” of the nuclear weapons complex and directly related expanded capabilities for increased nuclear weapons production.
• Oppose modernization of the nuclear weapons stockpile itself, which we believe is substantially about creating new military capabilities through planned “Life Extension Programs.”
• Stop expansion of WIPP.
• Promote comprehensive cleanup at Los Alamos and all DOE sites.
• Promote mission change at LANL. We will continue to redirect the Lab from core nuclear weapons research, testing and production programs to today’s critical national security challenges, such as preventing the proliferation of nuclear weapons, promoting clean national energy independence, and studying global climate changes.
• Strive to be your worthy representative locally and in Washington, DC, on nuclear weapons issues that affect our communities, New Mexico, the nation, and the world.
Thank you!
U.S. Nuclear Weapons Agency Claims Phony Budget Savings
New Report: U.S. Nuclear Weapons Agency Claims Phony Budget Savings;
Misleads Congress and Taxpayers About Real Costs of New Warheads; Nonproliferation and Dismantlement Programs Cut
Santa Fe, NM – The House Armed Services Committee is currently pushing a defense bill that pushes back against the Obama Administration’s plans to delay production of a new air launched cruise missile warhead and new nuclear warheads that would be “interoperable” between land-based ICBMs and sub-launched missiles. Related, the bill also calls for speeding up expanded plutonium pit production at the Los Alamos National Laboratory.
The House Armed Services Committee is objecting to delays, but not the substance, of plans by the Department of Energy (DOE) to heavily modify existing nuclear weapons during “Life Extension Programs” to create the new nuclear warheads. DOE’s FY 2014 “Stockpile Stewardship and Management Plan” (SSMP), which first introduced these new warheads, caused considerable sticker shock in Congress. Now DOE has released a new FY 2015 SSMP that it claims is “generally affordable and more executable than the program proposed in the FY 2014 SSMP.” However, an analysis by Nuclear Watch New Mexico concludes that DOE’s new sales pitch is based on overly optimistic claims and outright omissions that should alarm Congressional budget hawks.
DOE’s nuclear weapons agency, the National Nuclear Security Administration (NNSA), is notorious for cost overruns. Its FY 2015 plan misrepresents reduced costs by:
• Delaying projects and their costs – which almost always results in higher total costs.
• Lowering budget estimates while claiming undocumented improved cost modeling – when NNSA has an abysmal record in cost estimates.
• Claiming $7.5 to $9.5 billion in savings for NOT doing a Life Extension Program – which in fact was never planned.
• Omitting costs of directly related programs – which may exceed the costs of the Life Extension Programs themselves.
• Depicting costs as gradually tapering off – while failing to disclose that even more expensive follow-on programs are planned 20 years after the first round of Life Extension Programs.
• Perhaps most significantly, assuming the armed services will help pay for heavily modified nuclear weapons – when in fact the U.S. Navy does not want them (see internal memo below).
Missing is justification of why an extensively tested, reliable stockpile needs to be heavily modified during Life Extension Programs. According to a recent DOE Inspector General audit report, NNSA failed to diligently keep original “as-built” designs, when that information “is the foundation upon which the NNSA surveillance program assesses the current stockpile. Without it, NNSA loses confidence in its nuclear weapons stockpile assessments.” Changes could possibly erode confidence in nuclear weapons reliability, especially if original design information is lacking as a baseline.
The non-partisan Congressional Budget Office (CBO) recently reported that NNSA and the Pentagon plan to spend $355 billion over the next decade on nuclear weapons and their delivery systems. Meanwhile, the Obama Administration’s FY 2015 budget request cuts funding for nonproliferation, dismantlement and nuclear safety programs, and keeps cleanup funding flat.
Jay Coghlan, Nuclear Watch Director, commented, “Congress should demand that NNSA rigorously justify any proposed changes to existing reliable nuclear weapons. The antidote to exorbitantly expensive, potentially harmful modifications to the reliable stockpile is genuine stewardship that would preserve original weapons designs. This is far less risky and provocative, and would free up money for critically needed nonproliferation, dismantlement, nuclear safety and cleanup programs.”
Strongly recommended: Nuclear Watch’s detailed analysis of NNSA’s FY 2015 Stockpile Stewardship and Management Plan, including sources and key NNSA excerpts https://nukewatch.org/importantdocs/resources/FY2015-SSMP-analysis.pdf
An Executive Summary is available at https://nukewatch.org/importantdocs/resources/FY2015-SSMP-analysis-summary.pdf
# # #
The NNSA FYs 2014 and 2015 Stockpile Stewardship and Management Plans are available at https://web.archive.org/web/20170714130201/https://nnsa.energy.gov/ourmission/managingthestockpile/ssmp
The Congressional Budget Office report Projected Costs of Nuclear Forces 2014 -2023 is available at http://www.cbo.gov/sites/default/files/cbofiles/attachments/12-19-2013-NuclearForces.pdf
For U.S. Navy lack of support for heavily modified nuclear warheads see “Navy Perspective of W78/88 LEP Phase 6.2,” September 27, 2012, https://nukewatch.org/importantdocs/resources/Navy-Memo-W87W88.pdf
Past NukeWatch Events
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
Past Work Product (2019-)
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
2019
November 26, 2019 Press Release November 24, 2019 Press Release November 19, 2019 Plutonium Pit Production Workshop Presenters:
August 12, 2019 NEPA Comments NukeWatch’s 22-page formal comments on expanded plutonium pit production Until NNSA fully complies with the National Environmental Policy Act through the preparation of a programmatic environmental impact statement on expanded plutonium pit production, Nuclear Watch believes that any irreversible or irretrievable commitment of resources to either the expansion of pit production at the Los Alamos Lab or to the repurposing of the MOX Facility at the Savannah River Site is unlawful. Read/Download the Full Document HERE July 25, 2019 NEPA Comments Scoping comments on NNSA draft EIS for plutonium pit production at the Savannah River Site THE NEED FOR A PROGRAMMATIC ENVIRONMENTAL IMPACT STATEMENT: This is our first and primary concern, that NNSA must first complete a programmatic environmental impact statement (PEIS) on its nation-wide plans for plutonium pit production, in advance of the Savannah River Site-specific environmental impact statement. To get right to the point, we argue that the SRS EIS process should go no further than this scoping period and should resume only after a completed formal Record of Decision for a new or supplemental PEIS. Read/Download the Full Document HERE July 9, 2019 Plutonium Pit Production Fact Sheet Expanding Nuclear Pit Production: The Facts and What You Can Do The Facts Read/Download the Full Document HERE June 10, 2019 News Release In a victory for transparency and legal compliance by the government, the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) today published a “Notice of Intent” in the Federal Register to complete environmental reviews on its controversial proposal to expand plutonium “pit” production for new and refurbished nuclear weapons. [embeddoc url="https://nukewatch.org/wp-content/uploads/2019/06/SRS-plutonium-bomb-plant6-14-19.pptx" download="all" viewer="google"] Read/Download the Full News Release HERE June 4, 2019 Press Release On behalf of three public interest organizations - Nuclear Watch New Mexico, Tri-Valley Communities Against a Radioactive Environment and Savannah River Site Watch – attorneys for the law firm of Meyer Glitzenstein & Eubanks and the Natural Resources Defense Council recently sent a 16-page letter to Lisa Gordon-Hagerty, head of the National Nuclear Security Administration (NNSA). The detailed letter warns the nuclear agency to not proceed with aggressive plans to expand plutonium pit production without first meeting its legal requirements for timely public review and comment under the National Environmental Policy Act. Read/Download the Full Press Release HERE May 31, 2019 Press Release Last Wednesday, facility operations personnel entered a service room and noticed a leak emanating from a valve on the radioactive liquid waste (RLW) system. Upon subsequent visual inspection by a radiological control technician, RLUOB engineers believe that this valve, and 6 similar valves, may be constructed of carbon steel. The RLW system handles radioactive liquid waste streams from chemistry operations that include nitric and hydrochloric acids—carbon steel valves would be incompatible with these solutions. The suspect valves are also in contact with stainless steel piping, which would create another corrosion mechanism. RLUOB management plans to drain the affected piping sections and develop a work package to replace all of the suspect valves. They will also confirm the valve materials and if shown to be incorrect, investigate the cause of this failure in the design, procurement, and installation processes. The valves were installed in 2013 as part of a modification to add straining and sampling capabilities that were not in the included in the original design. [Please note that DNFSB reports are posted a few weeks later than dated.] This immediately raises two crucial issues: 1) the National Nuclear Security Administration’s (NNSA’s) plans for expanded plutonium pit production; and 2) the current attempt by the Department of Energy to restrict Safety Board access to its nuclear weapons facilities. Read/Download the Full Press Release HERE April 26, 2019 Consent Orders Comparison On March 1, 2005, after arduous negotiations and threats of litigation, the New Mexico Environment Department (NMED), Department of Energy (DOE), and Los Alamos National Laboratory (LANL) entered into a Consent Order specifying the schedule for investigation and cleanup of the Lab’s hundreds of contaminated sites. This Consent Order (CO) was LANL’s agreement to fence-to-fence cleanup of Cold War legacy wastes, which NMED began to enforce. Read/Download the Full Comparison HERE March 25, 2019 Press Release More than 25 years after the end of the Cold War, all eight established nuclear weapons powers are “modernizing” their stockpiles. Talks have broken down with North Korea, the new nuclear weapons power. Nuclear-armed India and Pakistan narrowly averted war last month. Russian President Vladmir Putin made new nuclear threats in response to Trump’s announced withdrawal from the Intermediate-Range Nuclear Forces Treaty. This could lead to hair-trigger missile emplacements in the heart of Europe and block extension of the New Strategic Arms Reduction Treaty with Russia. If so, the world will be without any nuclear arms control at all for the first time since 1972. Meanwhile, the U.S. criticizes non-weapons states for signing a nuclear weapons ban treaty, despite the fact there have long been treaties completely banning chemical and biological weapons of mass destruction that the U.S. seeks to enforce. The pending international NonProliferation Treaty (NPT) Preparatory Committee conference at the United Nations is widely expected to collapse in failure because of the nuclear weapons powers’ failure to enter into serious negotiations leading to nuclear disarmament. The NPT’s Article VI mandate for those negotiations has been in effect since 1970, when the Treaty was signed by 189 countries (more than any other treaty). Read/Download the Full Press Release HERE March 26, 2019 NukeWatch Budget Compilation Nuclear Watch New Mexico — Department of Energy FY 2020 Nuclear Weapons Budget Request |
2018
November 16, 2018 Plutonium Pit Production Fact Sheet Plutonium pits are the radioactive cores or “triggers” of nuclear weapons. Their production has always been a chokepoint of resumed industrial-scale U.S. nuclear weapons production ever since a 1989 FBI raid investigating environmental crimes shut down the Rocky Flats Plant near Denver. In 1997 the mission of plutonium pit production was officially transferred to its birthplace, the Los Alamos National Laboratory (LANL) in northern New Mexico, but officially capped at not more than 20 pits per year. However, in 2015 Congress required expanded pit production by 2030 whether or not the existing nuclear weapons stockpile actually needs it. This will support new military capabilities for nuclear weapons and their potential use. Read/Download the full fact sheet pdf HERE October 31, 2018 Nuclear Watch New Mexico, Savannah River Site Watch, and Tri-Valley CAREs sent a letter of demand to the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) to inform the government that its plan to quadruple the production rate of plutonium bomb cores is out of compliance with the National Environmental Policy Act (NEPA). NNSA’s premature plan to quadruple the production rate of plutonium bomb cores (“pits”), the heart of all US nuclear weapons, is out of compliance with requisite environmental law, the groups argue, as NNSA has failed to undertake a legally-mandated programmatic review and hold required public hearings. View/Download the entire press release HERE NukeWatch Comments, September 27, 2018 Nuclear Watch New Mexico is submitted formal comments to express in the strongest possible terms our opposition to DOE Order 140.1 Interface with the Defense Nuclear Facilities Safety Board. We find that the Department of Energy’s (DOE’s) attempt to restrict and suppress DNFSB access is very misguided, arrogant, and likely illegal in that it acts contrary to the Board’s enabling legislation. June 8, 2018 Press Release New Contractors Selected For Expanded Nuclear Weapons Production at Los Alamos Santa Fe, NM. Today the Department of Energy's National Nuclear Security Administration (NNSA) announced its choice for the new management and operating contract for the Los Alamos National Laboratory (LANL).The new contractor, Triad National Security, LLC, is a limited liability company consisting of the Battelle Memorial Institute, the University of California and Texas A&M University. All three are non-profits, and it is unclear how this will affect New Mexico gross receipts taxes. Battelle claims to be the world's largest non-profit technology research and development organization, and manages a number of labs including the Lawrence Livermore and Idaho National Laboratories. Texas A&M was founded in 1876 as the state's first public institution of higher learning and has the largest nuclear engineering program in the country. DOE Secretary Rick Perry is an avid A&M alumnus. May 31, 2018 Press Release Santa Fe, NM & Columbia, SC - "Two key U.S. Department of Energy documents on future production of plutonium "pits" for nuclear weapons, not previously released to the public, fail to justify new and upgraded production facilities at both the Los Alamos National Laboratory (LANL) in New Mexico and the Savannah River Site (SRS) in South Carolina." May 15, 2018 Fact Sheet May 10, 2018 Press Release What's Not in NNSA's Plutonium Pit Production Decision
- NNSA did not mention that up to 15,000 "excess" pits are already stored at the Pantex Plant near Amarillo, TX, with up to another 5,000 in "strategic reserve." The agency did not explain why new production is needed given that immense inventory of already existing plutonium pits. (In 2006 independent experts found that pits last a least a century. Plutonium pits in the existing stockpile now average around 40 years old.) May 2, 2018 Press Release "NNSA should begin nation-wide review of plutonium pit production, why it's needed, and what it will cost the American taxpayer in financial, safety and environmental risks. These are all things that the public should know." -Jay Coghlan, Director, Nuclear Watch New Mexico. April 26, 2018 NukeWatch Comments LANL Rad Lab: Formal Comments Under Nat'l Environmental Policy Act Against raising plutonium limit at LANL Rad Lab View/download Nuclear Watch comments as submitted Excerpt:
- NNSA is planning a 10-fold increase in plutonium at the LANL Rad Lab with a view to ramping up the production of plutonium pits for new nuclear weapons. March 26, 2018 Press Release United States To Begin Construction Of New Nuclear Bomb Plant The National Nuclear Security Administration (NNSA) announced on Friday, March 23, that it was authorizing the start of construction of the Uranium Processing Facility (UPF) and two sub-projects at the Y-12 National Security Complex in Oak Ridge, Tennessee. The UPF is a facility dedicated solely to the manufacture of thermonuclear cores for US nuclear bombs and warheads.
Jay Coghlan of NukeWatch points out that "This project already has a long history, and it is instructive. In 2013, DOE announced it was 85% finished with the UPF design when it ran into the 'space/fit' issue- and more than a half-billion taxpayer dollars were just written off. In private business, that kind of thing gets you fired. In DOE's world of contractors running amok, they not only didn't get fired, not one Congressional hearing was held and the UPF budget went up the next year!" - See full press release for all the details (PDF) March 1, 2018 Press Release The Regional Coalition of LANL Communities: Benefits for the Select Few Santa Fe, NM- According to media reports, Andrea Romero, Executive Director of the Regional Coalition of LANL Communities, is accused of charging some $2,200 dollars of unallowable travel costs, such as alcohol and baseball tickets, while lobbying in Washington, DC for additional funding for the Los Alamos National Laboratory (LANL). She in turn accused the nonprofit group Northern New Mexico Protects of political motivations in revealing these questionable expenses. Romero is running in the Democrat Party primary against incumbent state Rep. Carl Trujillo for Santa Fe County's 46th district in the state House of Representatives. For all the details, see full press release PDF February 28, 2018 Press Release Santa Fe, NM. On December 17, 2017, the Department of Energy (DOE) awarded a separate $1.4 billion contract for cleanup at the Los Alamos National Laboratory (LANL) to Newport News Nuclear BWXT-Los Alamos, LLC (also known as "N3B"). This award followed a DOE decision to pull cleanup from LANL's prime contractor, Los Alamos National Security, LLC (LANS), after it sent an improperly prepared radioactive waste drum that ruptured underground at the Waste Isolation Pilot Plant (WIPP). That incident contaminated 21 workers and closed WIPP for nearly three years, costing taxpayers at least $1.5 billion to reopen. (See all the details in the full press release) February 26, 2018 Press Release Detailed NNSA Budget Documents Accelerates Nuclear Weapons Arms Race Santa Fe, NM. Late Friday February 23, the Trump Administration released the detailed FY 2019 budget for the National Nuclear Security Administration (NNSA), the semi-autonomous nuclear weapons agency within the federal Department of Energy. Overall, NNSA is receiving a $2.2 billion boost to $15.1 billion, a 17% increase above the FY 2018 enacted level. Of that, a full $11 billion is for the budget category [Nuclear] "Weapons Activities", 18% above the FY 2018 level. Of concern to the American taxpayer, DOE and NNSA nuclear weapons programs have been on the congressional Government Accountability Office's High Risk List for project mismanagement, fraud, waste and abuse since its inception in 1990... (See all the details in the full press release) February 22, 2018 Press Release Santa Fe, NM. Today the National Nuclear Security Administration announced an Environmental Assessment to increase the amount of plutonium used in the Radiological Laboratory Utility and Office Building (aka the "Rad Lab") at the Los Alamos National Laboratory from 38.6 grams of plutonium-239 equivalent to 400 grams. This 10-fold increase is significant because it will dramatically expand materials characterization and analytical chemistry capabilities in the Rad Lab in support of expanded plutonium pit production for future nuclear weapons designs. It also re-categorizes the Rad Lab from a "radiological facility" to a "Hazard Category-3" nuclear facility. View/Download full press release February 12, 2018 Press Release Trump's Budget Dramatically Increases Nuclear Weapons Work Santa Fe, NM In keeping with the Trump Administration's recent controversial Nuclear Posture Review, today's just released FY 2019 federal budget dramatically ramps up nuclear weapons research and production. January 12, 2018 Press Release Draft Nuclear Posture Review Degrades National Security Yesterday evening the Huffington Post posted a leaked draft of the Trump Administration's Nuclear Posture Review (NPR). This review is the federal government's highest unclassified nuclear weapons policy document, and the first since the Obama Administration's April 2010 NPR. 2017 |
2017
December 22, 2017 Press Release New Mexico Environment Department Surrendered to DOE Extortion Santa Fe, NM. The New Mexico State Auditor Office recently questioned whether two settlements between the New Mexico Environment Department and the Department of Energy were in the best interests of New Mexico. That Office noted: (View/download full press release) December 20, 2017 Press Release Los Alamos Hires New Contractor - Starts Cleanup On the Cheap Santa Fe, NM- Today the Department of Energy (DOE) announced the award of the new Los Alamos National Laboratory legacy cleanup contract to Newport News Nuclear BWXT-Los Alamos, LLC. The $1.39 billion contract is for ten years, which works out to $139 million per year... View/download the full press release Public Presentation, December 2, 2017 October 31, 2017 Press Release Today, in Washington, DC, the Congressional Budget Office released its new report, "Approaches for Managing the Costs of U.S. Nuclear Forces, 2017 to 2046". The Congressional Budget Office estimates that the most recent detailed plans for nuclear forces, which were incorporated in the Obama Administration's 2017 budget request, would cost $1.2 trillion in 2017 dollars over the 2017-2046 period: more than $800 billion to operate and sustain (that is, incrementally upgrade) nuclear forces and about $400 billion to modernize them.... Driving this astronomical expense is the fact that instead of maintaining just the few hundred warheads needed for the publicly claimed policy of "deterrence," thousands of warheads are being refurbished and improved to fight a potential nuclear war. This is the little known but explicit policy of the U.S. government! October 27, 2017 Press Release Santa Fe, NM. On the evening of Wednesday October 25, the Santa Fe City Council passed a resolution requesting that the New Mexico Environment Department strengthen the revised Los Alamos National Labs cleanup order to call for additional characterization of legacy nuclear wastes, increased cleanup funding, and significant additional safety training. The resolution also called for the suspension of any planned expanded plutonium pit production until safety issues are resolved. (view/download full press release) October 6, 2017 Press Release Santa Fe, NM. Nuclear Watch New Mexico strongly applauds the awarding of the Nobel Peace Prize to the International Campaign to Abolish Nuclear Weapons (disclosure: NukeWatch is one of ICAN's ~400 member groups around the world). This award is especially apt because the peoples of the world are now living at the highest risk for nuclear war since the middle 1980's, when during President Reagan's military buildup the Soviet Union became convinced that the United States might launch a pre-emptive nuclear first strike. Today, we not only have Trump's threats to "totally destroy" North Korea and Kim Jong-un's counter threats, but also renewed Russian fears of a US preemptive nuclear attack... Generally unknown to the American taxpayer, our government has quietly tripled the lethality of the US nuclear weapons stockpile..." (view/download complete press release) NukeWatch fact sheet, September 26, 2017 The National Nuclear Security Administration's own documents have explicitly stated that expanded pit production would have no significant positive effect on job creation and the regional economy of northern New Mexico. Nuclear Watch argues that expanded plutonium pit production could actually have negative effect if it blocks other economic alternatives such as comprehensive cleanup, which could be the real job producer. Moreover, given LANL's poor safety and environmental record, expanded plutonium pit production could have a seriously negative economic impact on northern New Mexico in the event of any major accidents. September 15, 2017 Press Release Santa Fe, NM. The Los Alamos National Laboratory (LANL) has detected far more hexavalent chromium (Cr) contamination than previously estimated in the "sole source" regional groundwater aquifer that serves Los Alamos, Santa Fe and the Espanola Basin. Sampling in July from a new well meant to inject treated groundwater back into the aquifer detected chromium contamination five times greater than the New Mexico groundwater standard of 50 micrograms per liter (ug/L). View/download the full press release September 11, 2017 Press Release Talking Points: The 2016 LANL Cleanup Consent Order Should Be Rescinded The 2005 LANL Cleanup Consent Order was all about the enforceable schedules. It required DOE and LANL to investigate, characterize, and clean up hazardous and mixed radioactive contaminants from 70 years of nuclear weapons research and production. It stipulated a detailed compliance schedule that the Lab was required to meet. Under Gov. Martinez, NMED Secretary Ryan Flynn granted more than 150 compliance milestone extensions at the Lab's request, effectively eviscerating it. View/download the complete talking points July 20, 2017 Press Release Washington, DC Today, the Oak Ridge Environmental Peace Alliance (OREPA), Nuclear Watch New Mexico, and the Natural Resources Defense Council filed a federal lawsuit to stop construction of the problem-plagued Uranium Processing Facility (UPF) until legally required environmental review is completed. The UPF, located at the National Nuclear Security Administration's (NNSA's) Y-12 production plant near Oak Ridge, TN, is slated to produce new thermonuclear weapons components until the year 2080. The UPF is the tip of the spear for the U.S.'s planned one trillion dollar-plus make over of its nuclear weapons arsenal, delivery systems, and production plants. View/download the full press release June 19, 2017 Press Release Some Background on Plutonium Pit Production at the Los Alamos Lab Santa Fe, NM -The Washington Post has published the first in a series of articles on nuclear safety lapses in plutonium pit production at the Los Alamos Lab. Plutonium pits are the fissile cores of nuclear weapons that when imploded initiate the thermonuclear detonation of modern weapons. By the way, did you know? Plutonium facilities at LANL are- in principle- designed to withstand a serious earthquake of a degree expected to occur only once every 10,000 years. The last serious earthquake near the Lab is believed to have occurred 11,500 years ago. View/download the full press release ANA Report 2017: Accountability Audit May 19, 2017 Press Release SA Preview of Trump's Budget: More Nuclear Bombs and Plutonium Pit Production Santa Fe, NM. "The proposed level of funding for the National Nuclear Security Administration's (NNSA)'s Total Weapons Activities is $10.2 billion, a full billion above what was requested for FY 2017. In March, Trump's "skinny budget" stated NNSA's funding priorities as 'moving toward a responsive nuclear infrastructure', and 'advancing the existing warhead life extension programs'. Read the full press release for all the details. March 28, 2017 ANA workshop at UN Ban Treaty Conference Ban Treaty Conference: Alliance for Nuclear Accountability Panel Discussion March 28, 2017, UN, NYC:
March 2017 Fact Sheet Plutonium Pit Production at LANL (Updated March 2017) February 23, 2017 Press Release Costs Jump in Nuclear Weapons vs. Cleanup; Nuclear Weapons Winning over Environmental Protection Santa Fe, NM. America is at a crossroads, having to choose between an unnecessarily large, exorbitant, nuclear weapons stockpile, and cleanup that would protect the environment and water resources for future generations. Expanded nuclear weapons research and production, which will cause yet more contamination, is winning. Read the full press release for all the details. January 5, 2017 Press Release The National Nuclear Security Administration (NNSA) has publicly released its fiscal year 2016 Performance Evaluation Report (PER) for Los Alamos National Security, LLC (LANS), the for-profit contractor that runs the Los Alamos Lab. The Performance Evaluation Report is NNSA's annual report card on contractor performance, and overall the agency awarded LANS $59 million in profit out of a possible $65 million. The grade was 85% for the incentive part of the award. In 2012 Nuclear Watch New Mexico successfully sued NNSA to ensure that the Performance Evaluation Reports detailing taxpayers funds paid to nuclear weapons contractors are publicly available. In 2016 the NNSA decided to put the LANL management contract out for competitive bid, but granted LANS a contract extension until the end of September 2018. |
Media appearances including radio interviews are listed on the internal Media page
See the NukeWatch Channel at YouTube for our extensive playlists of key videos.
See the Nukewatch Twitter feed
See the Nukewatch Tumblr site
WatchBlog Posts:
Over 200 posts published since 2009. See archives at the WatchBlog
Earlier Work Product items are archived here