Court Rules U.S. Nuclear Weapons Production Plan Violates Federal Law
FOR IMMEDIATE RELEASE, October 3, 2024
Media Contacts:
Ben Cunningham, Esquire, SCELP, 843-527-0078, [email protected]
Tom Clements, Savannah River Site Watch, 803-834-3084, [email protected]
Jay Coghlan, Nuclear Watch New Mexico, 505-989-7342, [email protected]
Scott Yundt, Tri-Valley CAREs, 925-443-7148, [email protected]
Queen Quet, Gullah/Geechee Sea Island Coalition, 843-838-1171, [email protected]
AIKEN, S.C. — On September 30, United States District Court Judge Mary Geiger Lewis ruled that the United States Department of Energy (“DOE”) and its semi-autonomous nuclear weapons agency, the National Nuclear Security Administration (“NNSA”), violated the National Environmental Policy Act (“NEPA”) by failing to properly consider alternatives before proceeding with their plan to produce plutonium pits, a critical component of nuclear weapons, at the Los Alamos National Laboratory (“LANL”) in New Mexico and, for the first time ever, at the Savannah River Site (“SRS”) in South Carolina.
The Court found that the plan’s purpose had fundamentally changed from NNSA’s earlier analyses which had not considered simultaneous pit production at two sites. These changes necessitated a reevaluation of alternatives, including site alternatives, which Defendants failed to undertake prior to moving forward while spending tens of billions of taxpayers’ dollars. Therefore, the Court entered judgment in favor of Plaintiffs, the nonprofit public interest groups Savannah River Site Watch, Nuclear Water New Mexico and Tri-Valley Communities Against a Radioactive Environment (CAREs); the Gullah/Geechee Sea Island Coalition; and Tom Clements as an individual plaintiff.
As a result of this ruling, the Defendants are required to newly assess pit production at a nation-wide programmatic level which will mean undertaking a thorough analysis of the impacts of pit production at DOE sites throughout the United States, including radioactive waste generation and disposal. Under the National Environmental Policy Act (NEPA), this will provide the opportunity for public scrutiny of and formal comment on their assessments.
High Detections of Plutonium in Los Alamos Neighborhood – As We Enter a New Nuclear Arms Race the Last One is Still Not Cleaned Up
FOR IMMEDIATE RELEASE, August 15, 2024
Dr. Michael Ketterer – 928.853.7188 | Email
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – In April Nuclear Watch New Mexico released a map of plutonium contamination based on Lab data. Today, Dr. Michael Ketterer, Professor Emeritus of Chemistry and Biochemistry, Northern Arizona University, is releasing alarmingly high results from samples taken from a popular walking trail in the Los Alamos Town Site, including detections of some of the earliest plutonium produced by humankind.
On July 2 and 17 Dr. Ketterer, with the assistance of Nuclear Watch New Mexico, collected water, soil and plant samples from Acid Canyon in the Los Alamos Town Site and soil and plant samples in Los Alamos Canyon at the Totavi gas station downstream from the Lab. The samples were prepared and analyzed by mass spectrometry at Northern Arizona University to measure concentrations of plutonium, and to ascertain its sources in the environment.
NNSA Delays Urgent Research on Plutonium “Pit” Aging While Spending Tens of Billions on Nuclear Weapons Bomb Core Production
FOR IMMEDIATE RELEASE, April 17, 2024
Tom Clements, SRS Watch – 803.240.7268 | Email
Scott Yundt, TVC – 415.990.2070 | Email
Jay Coghlan – 505.989.7342 | Email
Nearly three years after filing a Freedom of Information Act request, the public interest group Savannah River Site Watch has finally received the National Nuclear Security Administration’s (NNSA’s) congressionally-required “Research Program Plan for Plutonium and Pit Aging.” However, the document is 40% blacked out, including references and acronyms. Plutonium “pits” are the radioactive cores of all U.S. nuclear weapons. The NNSA claims that potential aging effects are justification for a ~$60 billion program to expand production. However, the Plan fails to show that aging is a current problem. To the contrary, it demonstrates that NNSA is delaying urgently needed updated plutonium pit aging research.
In 2006 independent scientific experts known as the JASONs concluded that plutonium pits last at least 85 years without specifying an end date [i] (the average pit age is now around 40 years). A 2012 follow-on study by the Lawrence Livermore nuclear weapons lab concluded:
“This continuing work shows that no unexpected aging issues are appearing in plutonium that has been accelerated to an equivalent of ~ 150 years of age. The results of this work are consistent with, and further reinforce, the Department of Energy Record of Decision to pursue a limited pit manufacturing capability in existing and planned facilities at Los Alamos instead of constructing a new, very large pit manufacturing facility…” [ii]
Since then NNSA has reversed itself. In 2018 the agency decided to pursue the simultaneous production of at least 30 pits per year at the Los Alamos National Laboratory (LANL) in northern New Mexico and at least 50 pits per year at the Savannah River Site (SRS) in South Carolina. Upgrades to plutonium facilities at LANL are slated to cost $8 billion over the next 5 years. The redundant Savannah River Plutonium Processing Facility in South Carolina will cost up to $25 billion, making it the second most expensive building in human history.
NNSA’s Nuclear Weapons Budget Takes Huge Jump
Arms Race Accelerates with MIRVed Warheads
Los Alamos Lab Cleanup Cut
FOR IMMEDIATE RELEASE, March 11, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – Ironically the day after the film Oppenheimer was awarded multiple Oscars, the Department of Energy’s semi-autonomous National Nuclear Security Administration (NNSA) asked Congress for its biggest nuclear weapons budget ever. NNSA’s FY 2025 request for “Total Weapons Activities” is $19.8 billion, $700 million above what Congress recently enacted for FY 2024. It is also a full billion dollars above what President Biden asked for last year, which Congress then added to and will likely do so again.
The Biden Administration states that the $19.8 billion will be used to:
“[P]rioritize implementation of the 2022 National Defense Strategy and Nuclear Posture Review by modernizing the Nation’s nuclear deterrent to keep the American people safe. The Budget supports a safe, secure, reliable, and effective nuclear stockpile and a resilient, responsive nuclear security enterprise necessary to protect the U.S. homeland and allies from growing international threats.” whitehouse.gov/wp-content/uploads/2024/03/budget_fy2025.pdf, page 75.
The 2022 National Defense Strategy and Nuclear Posture Review for the first time posited two nuclear “near peers”, i.e. Russia and China, that need to be simultaneously “deterred.” This hinted at a potentially large nuclear buildup which this budget may now be implementing. That claimed need to deter two nuclear near peers was explicitly taken a step beyond just deterrence in an October 2023 report from the Strategic Posture Commission. It declared:
“Decisions need to be made now in order for the nation to be prepared to address the threats from these two nuclear-armed adversaries arising during the 2027-2035 timeframe. Moreover, these threats are such that the United States and its Allies and partners must be ready to deter and defeat both adversaries simultaneously.” ida.org/research-and-publications/publications/all/a/am/americas-strategic-posture, page vii (bolded emphasis added)
NNSA Suppresses How Taxpayers Money Is Spent
FOR IMMEDIATE RELEASE, January 19, 2024
Jay Coghlan – 505.989.7342 | Email
Santa Fe, NM – The National Nuclear Security Administration (NNSA) has just released cursory two or three page summaries of contractors’ performance paid for by the American taxpayer. For the just ended fiscal year 2023, NNSA gave nothing less than grades of “Excellent” or “Very Good” in six broad mission goals for its major contractors. This is despite the constant cost overruns and schedule delays that are the rule, not the exception, in the nation-wide nuclear weapons complex. NNSA and its parent Department of Energy have been on the Government Accountability Office’s “High Risk List” for project mismanagement ever since GAO started that List in 1991.
A current example is the Uranium Processing Facility (UPF) at the Y-12 Plant near Oak Ridge, Tennessee, originally estimated in 2011 to cost $1.4 to $3.5 billion. After costs started going through the roof, NNSA and Senator Lamar Alexander (R.-TN), then-chair of Senate Energy and Water Appropriations, swore that UPF would never go over $6.5 billion. But even after eliminating non-nuclear weapons production missions and a formal decision to continue operations at two old, unsafe buildings slated for replacement, the Uranium Processing Facility is now estimated to cost $8.5 billion. However, even that is not the final price, as NNSA is still to “rebaseline” UPF costs at some unspecified date.
2023
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT FACT SHEETS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT PRESS RELEASES
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
RECENT NUCLEAR BUDGET GRAPHS
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
Past Work Product (2020-2021)
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
75TH ANNIVERSARY HIROSHIMA DAY ONLINE COMMEMORATION CALLING FOR THE ABOLITION OF NUCLEAR WEAPONS
August 6, 2020
"Jay Coghlan of Nukewatch.org on the history of the Los Alamos labs, where the bomb was designed and fabricated, and how it continues to play the leading role in the creation of most U.S. nuclear weapons since then."
[embeddoc url="https://nukewatch.org/wp-content/uploads/2020/05/plutonium-pit-production-fact-sheet.pdf" download="all" viewer="browser"]
PLUTONIUM PIT PRODUCTION WORKSHOP – NOVEMBER 19, 2019
RADIO INTERVIEW – SCOTT KOVAC & JON LIPSKY
Scott Kovac of Nuclear Watch New Mexico and Jon Lipsky, the FBI agent who led the 1989 raid investigating environmental crimes that shut down the Rocky Flats Nuclear Bomb Plant join Xubi to talk about Nuclear weapons, Nuclear clean up and Pit production plans at LANL.
RADIO INTERVIEW – JAY COGHLAN & JON LIPSKY
PIT Production at LANL with Nuclear Watch New Mexico’s Jay Coghlan and Workshop Speaker, Jon Lipsky
RADIO INTERVIEW – MARYLIA KELLEY, EXECUTIVE DIRECTOR, TRI-VALLEY CARES
Nuclear Watch NM’s Workshop on LANL & PIT Production with Marylia Kelley of Tri-Valley CARES
Pit Production Workshop: View the Presentations
Jon Lipsky, FBI agent that led the 1989 raid investigating environmental crimes that shut down the Rocky Flats bomb plant
Introduction by Jay Coghlan
Jay Coghlan, Executive Director, Nuclear Watch New Mexico, on plutonium pit production at LANL
Marylia Kelly, Executive Director, Tri-Valley CAREs (Livermore, CA) on the new nuclear arms race
https://www.facebook.com/NukeWatch.NM/videos/825812604488302/
Scott Kovac Nuclear Watch New Mexico, on LANL cleanup issues
Blog Posts
Where to Store the Nation’s Nuclear Waste? No One Has the Answer, Exactly. But It’s Probably Not “In a High-Risk Seismic Zone.”
It seems obvious that “when assessing the aptitude of a site to receive a deep nuclear-waste repository, seismic activity should be taken into account.” (IAEA). At the moment, the only repository of this kind in the U.S. is the Waste Isolation Pilot Plant (WIPP), the nation’s main nuclear weapons waste storage site. WIPP lies a half mile underground in a salt formation in southeastern New Mexico. Additional nuclear waste storage facilities are planned to be built nearby, along the border between southeastern New Mexico and west Texas, where risks of quakes caused by oil and gas fracking operations in the area are rising.
“The occurrence of smaller earthquakes began to increase in 2017, when oil and gas boomed in the region, up to about three per day recently. In 2021, records show the region was on track for more than 1,200 earthquakes with magnitudes of 1 to 4.” KRQE
In New Mexico in July, a 4.0 temblor shook the southeast corner of the state. Meanwhile, just over the border on the Texas side, the U.S. Nuclear Regulatory Commission approved a high-level waste facility, and Holtec International is trying to put their share of the nation’s commercial nuclear waste there as well, on the New Mexico side.. Holtec, with support from the Nuclear Regulatory Commission, wants to build a nuclear waste storage facility for up to 100,000 tons of spent nuclear fuel rods 12 miles north of WIPP, a plan opposed by New Mexico Gov. Michelle Lujan Grisham and others in state government.
“All of these nuclear sites are surrounded by brine injection wells, the likely cause of the increased seismicity in the basin.” Source NM
LANL Plans to Address Possibly Exploding Drums Shipped to Texas in 2014
Los Alamos National Laboratory (LANL) has given itself a Categorical Exclusion (CX) under National Environmental Policy Act (NEPA) for the removal, relocation, and examination of transuranic (TRU) waste drums at Waste Control Specialists (WCS). These drums are similar to the ones that forced WIPP to close in 2014. LANL officials decided that formal environmental assessments, with public input, of the movement of the possibly exploding waste drums are not needed.
Guest Blog: Associate Director of Physicians for Social Responsibility-Los Angeles, Denise Duffield, on the Fight to Clean up California’s Contaminated Santa Susana Field Laboratory (SSFL)
Dear Friends and Colleagues:
Tonight, MSNBC will air a powerful documentary called “In the Dark of the Valley” at 7 p.m. PST/ 10 p.m. EST. The film follows the story of Melissa Bumstead, a mother whose search for answers about her young daughter’s cancer leads her to the contaminated Santa Susana Field Laboratory (SSFL), a former nuclear and rocket engine testing site near Los Angeles. I have been involved in the fight to clean up SSFL for 15 years, and PSR-LA has been involved for over 30 years. PSR-LA Board President Dr. Bob Dodge and I are featured in the film, along with our longtime ally Dan Hirsch, President of Committee to Bridge the Gap; generations of SSFL cleanup activists, and many others.
I urge you to watch the documentary tonight or record it to watch later. Not only is the film masterfully done and visually stunning, it manages to capture the heart of one of the longest and most intensely fought battles to clean up a contaminated site in the US. That’s a big deal.
I’m writing to you all today because as I reflect on the fight to cleanup SSFL — the struggles, the hard work, the heartache, the setbacks, the frustration, the power of the forces we’re up against, the greenwashing, the gaslighting,the personal sacrifices made by so many, the folks we’ve lost along the way — the fact that this film was made so well and is going to be broadcast nationally is more than a big deal. It’s a victory. And victories, especially in these troubled times, should be shared and savored. Particularly for those of you who don’t know as much about SSFL, understanding just how brutal SSFL cleanup advocacy is, and how amazing the community and cleanup advocates are, makes this film — this victory — even sweeter.
Current U.S. Nuclear Weapons Issues Updates — November 15, 2021
The current Continuing Resolution keeping the government running expires 12/3. Another Continuing Resolution is likely.
The Pentagon has released a major threat assessment of China at https://media.defense.gov/2021/Nov/03/2002885874/-1/-1/0/2021-CMPR-FINAL.PDF.
Under “Nuclear Capabilities” it concludes:
► Over the next decade, the PRC [People’s Republic of China] aims to modernize, diversify, and expand its nuclear forces.
► The PRC is investing in, and expanding, the number of its land-, sea-, and air-based nuclear delivery platforms and constructing the infrastructure necessary to support this major expansion of its nuclear forces.
► The PRC is also supporting this expansion by increasing its capacity to produce and separate plutonium by constructing fast breeder reactors and reprocessing facilities.
► The accelerating pace of the PRC’s nuclear expansion may enable the PRC to have up to 700 deliverable nuclear warheads by 2027. The PRC likely intends to have at least 1,000 warheads by 2030, exceeding the pace and size the DoD projected in 2020.
► The PRC has possibly already established a nascent “nuclear triad” with the development of a nuclear capable air-launched ballistic missile (ALBM) and improvement of its ground and sea-based nuclear capabilities.
► New developments in 2020 further suggest that the PRC intends to increase the peacetime readiness of its nuclear forces by moving to a launch-on-warning (LOW) posture with an expanded silo-based force.
This is bound to have a major influence on Biden’s Nuclear Posture Review, to be released in early 2022. China’s expansion of its nuclear weapons capabilities, along with U.S. and Russian “modernization” programs, may also be big issues at the January 2022 NonProliferation Treaty Review Conference.
An Environmental & Nuclear Disaster in LA’s Backyard: How Much Contamination Really Fell on Top of Communities from Thousand Oaks to Simi Valley from the Woolsey Fire?
The Santa Susana Field Laboratory (SSFL) is a 3,000 acre site sitting on top of the San Fernando and Simi Valleys in California, located less than 30 miles from Malibu. In 1947 the site was developed as a central location for U.S. rocket engine testing and space exploration, and in the 1950’s SSFL began experimenting with constructing nuclear reactors.
Ten nuclear reactors were built in total, and tens of thousands of rocket, energy, and weapons tests took place there from when the laboratory went into operation in 1947 until it’s closure in 2006. The rocket engine tests specifically produced numerous toxic spills and releases. The nuclear reactors built include a “Hot Lab” to “cut up irradiated reactor fuel from around the country,” “plutonium and uranium-carbide fuel fabrication facilities,” and a “sodium burn pit in which open-air burning of contaminated reactor components took place.” One of the reactors, the Sodium Reactor Experiment, experienced a partial nuclear meltdown in 1959, and two other reactors experienced accidents with fuel damage as well.
Current U.S. Nuclear Weapons Issues Updates — October 15, 2021
Congress passed a continuing resolution that keeps the government running until December 3. It freezes funding at 2021 levels which at least prevents short-term budget increases for nuclear weapons modernization programs and has no “anomalies” (i.e. exceptions) for these programs. That said, Biden passed on most of Trump’s nuclear weapons excesses forward in his FY 2022 budget, so it’s not like it makes a whole lot of difference.
Mitch McConnell agreed to let the Democrats raise the national debt ceiling, thereby averting national and international economic disaster. How gracious of him.
Democrats and Republicans joined together to roll Biden on the money in the FY 2023 Defense Authorization Act for the entire military (including the National Nuclear Security Administration (NNSA). These bipartisan porkmeisters added $23.9 billion for $768 billion in total defense spending. The new bogeyman China was repeatedly invoked as the rationale (in comparison China now spends around $250 billion annually on its military).
→
International Day for the Total Elimination of Nuclear Weapons 2021
Today, Sunday, September 26, 2021, marks the United Nations International Day for the Total Elimination of Nuclear Weapons. The United Nations has been working toward achieving global nuclear disarmament since the organization’s inception; it was the subject of the General Assembly’s first resolution in 1946, with a mandate to make specific proposals for the elimination of atomic weapons and all other major weapons adaptable to mass destruction. The International Day for the Total Elimination of Nuclear Weapons has been observed annually since 2014, serving as a tool to enhance public awareness and education about the threat posed to humanity by nuclear weapons and the necessity for their total elimination. In 2013, the year the International Day for the Total Elimination of Nuclear Weapons was introduced, the President of the General Assembly noted that a “renewed international focus on the catastrophic consequences of nuclear weapons has led to a reinvigoration of international nuclear disarmament efforts.”
This is OUR Neighborhood: Expanding the Capacity of New Mexico’s Nuclear Waste Repository Affects Communities across the Country.
The original mission of the Waste Isolation Pilot Plant (WIPP) in southeastern New Mexico had two specific stipulations: it was to be the FIRST and only operating underground nuclear waste repository in U.S; and it is ONLY authorized to take a certain kind of nuclear weapons waste – legacy transuranic (TRU) waste. In December of last year, the U.S. Department of Energy published a notice of intent to expand WIPP. The notice details expansion of the plant in two ways: capacities and types of waste permissible, as well as extended storage/operation timelines. The federal government’s plans would expand the size of the nuclear weapons dump to more than twice its current size and more than is allowed: Federal law and legal agreements with New Mexico clearly limit the amount of waste at WIPP, but the expansion would allow more than that capacity (as described in the April 2020 National Academy of Sciences Report “Review of the Department of Energy’s Plans for Disposal of Surplus Plutonium in the Waste Isolation Pilot Plant.”) This means an increased volume of waste, as well as an increased number of shipments travelling to WIPP over the entire rest of the century.
University of New Mexico’s growing involvement in nuclear weapons prograns
See Honeywell, UNM sign accord to pursue joint research
This is more evidence of the University of New Mexico’s deepening involvement in nuclear weapons programs. UNM recently announced that with Boeing, the U. of Texas and others that it was going to bid on the Sandia Labs management contract.
Honeywell runs the new Kansas City Plant, which is manufacturing and/or procuring ~100,000 nonnuclear nuclear weapons components every year for increasingly aggressive Life Extension Programs. These programs not only extend the service lives of nuclear weapons for up to 60 years, but also give them new military capabilities, despite denials at the highest levels of the U.S. government.
UNM is also the host site for the June 21 Strategic Deterrence Symposium featuring top military and Energy Dept. nuclear brass. Nuclear Watch NM will be there to see what they are to.
Obama’s Speech in Hiroshima
Obama’s speech is beautiful and very moving.
But he’ll be gone soon while the one trillion dollar modernization of U.S. nuclear forces that begins under him will go on for 30 years and then some (unless we stop it, that is).
Text of President Obama’s Speech in Hiroshima, Japan
MAY 27, 2016
Sign the Petition – No Loopholes, No Excuses – Full Cleanup at Los Alamos!
Dear Friends,
Thanks to those who made it to the meeting last night!
NukeWatch has a new petition –
The New Mexico Environment Department (NMED) has issued a proposed new “Consent Order” governing cleanup at the Los Alamos National Laboratory, the birthplace of nuclear weapons.
We demand NMED close the giant loophole in the proposed Consent Order that would allow Los Alamos Lab and DOE to get out of cleanup by simply saying that they don’t have enough money.
And we demand NMED hold a public hearing on the proposed Consent Order, given the intense public interest in cleaning up the Lab.
https://www.change.org/p/kathryn-roberts-no-excuses-no-loopholes-full-cleanup-at-los-alamos-lab
AND WE HAVE EXPANDED OUR SAMPLE COMMENTS FOR YOU TO USE AS YOU SEE FIT
Please let your voice be heard and turn in public comments.
Copy the sample comments below and paste into an email.
Please modify as you see fit, then email to the address below.
If you don’t mind, please cc: us at: info(at)nukewatch(dot)org
[date]
Ms. Kathryn Roberts
New Mexico Environment Department
Post Office Box 5469
Santa Fe, New Mexico 87502
Via email to [email protected]
Dear Ms. Roberts,
I urge the New Mexico Environment Department (NMED) to abandon the proposed 2016 Compliance Order on Consent, or Consent Order, for Los Alamos National Laboratory (LANL), released for public comment on March 30, 2016. It creates serious problems and represents a giant step backwards in achieving the goal of genuine cleanup of the Laboratory.
The Environment Department should keep the existing Consent Order that went into effect March 1, 2005, while modifying and updating a cleanup schedule that includes a realistic final compliance date. I also formally request that NMED provide the opportunity for a public hearing on the revised cleanup schedule and new completion date, in accordance with the New Mexico Hazardous Waste Act and the 2005 Consent Order.
GENERAL COMMENTS
The opportunity for a public hearing must be provided
- Any extension of a final compliance date must be treated as a Class 3 permit modification to the 2005 Consent Order and therefore requires a 60-day public comment period.
- Any extension of a final compliance date under the 2005 Consent Order can be implemented only after the opportunity for public comment and a public hearing, including formal testimony and cross-examination of witnesses.
- The Environment Department is legally required to follow these public participation requirements that explicitly incorporated into the 2005 Consent Order.
Withdraw the proposed draft 2016 Consent Order
- The proposed draft represents a big step backwards in achieving the goal of genuine cleanup of the Laboratory.
- The Environment Department should keep the current 2005 Consent Order and revise the Section XII cleanup schedule and final compliance date.
- I request that the Environment Department withdraw the proposed draft 2016 Consent Order.
The public deserves the opportunity to comment on all following drafts
- It seems likely that a later draft – after the Lab’s and public comments are incorporated into a revised draft – and after closed-door negotiations between the Environment Department and the Laboratory – could be substantially different from the current draft.
- I request that the public have the opportunity to review and comment on any further drafts of a revised proposed 2016 Consent Order.
Public participation provisions in the existing 2005 Consent Order must be incorporated into the proposed draft 2016 Consent Order
- The proposed draft 2016 Consent Order explicitly limits public participation requirements incorporated into the existing 2005 Consent Order.
- I request that all notices, milestones, targets, annual negotiations, and modifications require public review and comment, and the opportunity for a public hearing.
The current state of cleanup must be updated and next steps scheduled
- Work under the existing 2005 Consent Order needs to be subject to public review. In 2005 DOE agreed to complete cleanup under the Consent Order by December 6, 2015, which did not happen. In order for the public to understand where the work under the existing Consent Order stands, LANL should be required to provide a current, publicly available list of the status of all cleanup projects under the 2005 Consent Order.
- Further, I request that next steps for cleanup at every site listed in the 2005 Consent Order be documented in detail and given a scheduled completion date, or alternatively verified as already completed.
- All documents submitted under the 2005 Consent Order must be incorporated into any revised Consent Order.
All documents must be made public as required in the 2005 Consent Order
- The State and the Lab must make all communications, documents, submittals, approvals, notices of deficiencies and denials under any revised Consent Order readily and electronically available to the public.
- The State and the Lab must notify individuals by e-mail of all submittals, as required in the 2005 Consent Order.
The Environment Department must respond in writing to all public comments
- I request that the State reply individually to each and every comment submitted.
- The Lab’s comments and NMED’s response to comments must be made public.
All future work must have enforceable deadlines
- The proposed draft 2016 Consent Order proposes a “Campaign” approach with enforceable cleanup deadlines limited to the work scheduled only for that year.
- I request that all anticipated cleanup projects have scheduled, enforceable cleanup deadlines from the beginning of any revised Consent Order.
The Consent Order cannot be open-ended
- Any Consent Order for LANL cleanup must have a final compliance date to which the State and the Lab agree to and are so bound.
- The public should be given an opportunity for a public hearing on the new final compliance date as required by New Mexico’s hazardous waste regulations.
SPECIFIC COMMENTS
The Proposed 2016 Consent Order Must Not Extend the Original Final Compliance Date Without Required Public Participation
The proposed 2016 consent order would indefinitely extend the final compliance date for completing corrective action at the Laboratory, without the opportunity for a public hearing with formal testimony and cross-examination of witnesses. Any extension of a final compliance date under the 2005 Consent Order requires a 60-day public comment period and the opportunity for a public hearing, including formal testimony and cross-examination. The Environment Department is legally required to follow these procedural requirements.
The legal requirements that mandate a public hearing are clear. Section XII of the 2005 Consent Order establishes the compliance schedule for implementation and completion of corrective actions at specific sites at the Laboratory. This schedule is mandatory. The final report that was to be submitted under the 2005 Consent Order – therefore, the final compliance date – was the remedy completion report for the huge Area G waste dump, required to be submitted by December 6, 2015. The proposed 2016 Consent Order would indefinitely extend this final compliance date by not designating a specific final compliance date.
But this revision must be treated as a major Class 3 permit modification. Section III.W.5 of the 2005 Consent Order explicitly provides for the preservation of full procedural rights for the public as follows:
This Consent Order hereby incorporates all rights, procedures and other protections afforded the Respondents [DOE and UC, now LANS] and the public pursuant to the regulations at 20.4.1.900 NMAC (incorporating 40 C.F.R. § 270.42) and 20.4.1.901 NMAC, including, but not limited to, opportunities for public participation, including public notice and comment, administrative hearings, and judicial appeals concerning, for example, remedy selection decisions of the [Environment] Department.
Thus, extension of a final compliance date under the 2005 Consent Order requires a 60-day public comment period and the opportunity for a public hearing, including formal testimony and cross-examination.
The Proposed New Consent Order Must Not Limit Other Public Participation Procedures
The proposed 2016 Consent Order expressly limits public participation requirements in a way that completely diverges from those provided in the 2005 Consent Order. As explained above, the 2005 Consent Order explicitly protects procedural due process rights available to the public. The proposed 2016 Consent Order explicitly removes these protections, as follows:
The Parties agree that the rights, procedures and other protections set forth at 20.4.1.900 NMAC (incorporating 40 C.F.R. § 270.42), 20.4.1.901 NMAC, and 20.4.1.902 NMAC, including, but not limited to, opportunities for public participation, including public notice and comment, administrative hearings, and judicial appeals, do not apply to modification of the Consent Order itself. [Emphasis added]
Thus, as proposed in the above language, the Parties (the Environment Department, Department of Energy and Los Alamos National Security, LLC) have inappropriately agreed to remove the due process rights, procedures and other protections provided to the public under the Resource Conservation and Recovery Act (RCRA) and the New Mexico Hazardous Waste Act. This provision must be stripped from the proposed 2016 Consent Order.
The Proposed New Consent Order Must Not Eliminate Enforceable Deadlines
The proposed 2016 consent order would eliminate all the deadlines for completing cleanup under the 2005 Consent Order, and replace them with an open-ended and vague scheduling process, with limited enforcement opportunities.
The 2005 Consent Order, in Section XII, established dozens of deadlines for the completion of corrective action tasks, including completion of investigations at individual sites, installation of groundwater monitoring wells, submittal of groundwater monitoring reports, evaluation of remedial alternatives for individual sites, and completion of final remedies. These deadlines are enforceable under section III.G.
The proposed 2016 Consent Order would abandon the 2005 Consent Order provisions and replace them with a so-called “Campaign Approach” under Section VIII. Under Section VIII.A.3, it would be up to the DOE, not the regulator at the New Mexico Environment Department, to select the timing and scope of each “campaign.”
Enforceable deadlines for cleanup tasks would apply no more than one year into the future. Deadlines would be based on “Campaigns” negotiated each year with DOE with no public participation and opportunity to comment on the schedule. To add insult to injury, the annual schedule would be determined by funding at DOE’s discretion, rather than the schedule driving the funding, which was the fundamental approach of the 2005 Consent Order.
All cleanup projects must mandatory completion dates scheduled from the beginning date of any revised Consent Order, and must be fully enforceable.
Existing Violations Must Not Be Eliminated
Section II.A of the proposed 2016 Consent Order would “settle any outstanding violations of the 2005 Consent Order.” This is a get out of jail free card. Without enforceable schedules from the beginning, any consent order is not truly unenforceable, and the Environment Department would be abdicating its responsibility to protect human health and the environment as required by the federal Resource Conservation and Recovery Act (RCRA) and the New Mexico Hazardous Waste Act. NMED must not surrender its regulatory and enforcement powers!
Attorney General Approval Must Be Obtained
The 2005 Consent Order was signed by the Attorney General of New Mexico for purposes of the Covenant Not to Sue (section III.) and the Reservation of Rights (section III.). As indicated on the draft signature page, there is no indication of the NM Attorney General plans to sign the proposed 2016 Consent Order. Yet it would provide the State of New Mexico with a covenant not to sue DOE on behalf of the State of New Mexico, not merely on behalf of the Environment Department. The Attorney General was an active participant, representing the People of New Mexico, in the 2005 Consent Order. The Environment Department has a responsibility to ensure that the NM Attorney General is consulted, and his approval obtained, before any consent order is adopted.
The Proposed 2016 Consent Order Must Not Omit Detailed Requirements Found in the 2005 Consent Order
The 2005 Consent Order includes numerous detailed requirements for such things as well installation, sample collection, and preparation of work plans and reports. These ensure that the cleanup work is done properly, consistently, and according to standard industry practices. They also ensured that work plans and reports were consistent, easy for the Environment Department to review, and easy for the public to understand. The proposed 2016 Consent Order omits many such requirements, which should be corrected.
The Proposed 2016 Consent Order Must Not Allow Budget To Dictate Cleanup
The proposed 2016 Consent Order allows DOE to provide cleanup priorities based on anticipated budget, which is backwards. . By the time NMED receives an estimated annual cleanup budget from DOE, the horse has left the barn. The original purpose of the 2005 Consent Order was to compel DOE and LANL to ask Congress for additional funds to accelerate cleanup. The giant loophole in the proposed 2016 Consent Order that allows DOE and LANL to say that they don’t have sufficient funding and therefore can choose to exempt themselves from cleanup should be eliminated.
Cleanup Levels Must Remain Strict
Section IX Cleanup Objectives and Cleanup Levels of the proposed 2016 Consent Order would allow DOE to “develop site specific ecological cleanup levels” to mitigate unacceptable ecological risk due to release of site-related contaminants. There is no mention of NMED’s role in this process. DOE would be allowed to demonstrate to NMED that any particular “cleanup objective is impracticable.” To do this, DOE may consider such things as technical difficulty, the cost of the project, hazards to workers or to the public, and any other basis that may support a finding of impracticability. If NMED approves the impracticability request, DOE can then propose alternative cleanup methods using site-specific risk assessments. All of this could take place behind closed doors, as there are no public participation requirements in this section. Please clarify what cleanup levels will be used and when and where they will be applied.
New Mexico deserves better
In closing, the Environment Department’s proposed 2016 Consent Order allows the federal government to leave Northern New Mexico contaminated if DOE believes that cleanup is too difficult or costly– a sorry situation indeed for a nuclear weapons facility that receives over 2 billion taxpayer dollars a year. Instead, the New Mexico Environment Department should implement a new revised Consent Order that is aggressive and enforceable and in which the State of New Mexico stays in the driver’s seat, not LANL and DOE. That would be a real win-win for New Mexicans, helping to permanently protect the environment and our precious water resources while creating hundreds of high-paying cleanup jobs. .
Sincerely,
Name
City
The new draft Consent Order is available at
https://www.env.nm.gov/HWB/lanlperm.html#COOC
NMED’s public notice for the draft Consent Order is available at
https://www.env.nm.gov/HWB/documents/PublicNotice__English.pdf
The public comment period ends 5:00 pm May 31, 2016.
Comments should be submitted to [email protected]
Public Meeting: Los Alamos Cleanup at the Crossroads
Dear Friends,
Please join us for an informal public meeting Tuesday, May 24 at 6pm.
Main Library Community Room, 145 Washington Ave, Santa Fe, NM
Please remember that no refreshments are allowed at the Library.
See you there!
Los Alamos Cleanup at the Crossroads
A Discussion on the Future of Cleanup at Los Alamos
We have opportunities to take new directions
How do we get to the Northern New Mexico we want leave for future generations?
Learn how your input can help make better cleanup decisions at Los Alamos National Laboratory
Join us for a
Public Meeting: Tuesday May 24, 2016, 6 – 7:30pm
at the
Main Library Community Room, 145 Washington Ave, Santa Fe
Topics to be Addressed
Los Alamos Cleanup Order
- For “fence-to-fence” cleanup of legacy Cold War wastes
- The 10-year trip since the original Consent Order was signed in 2005
- New “Consent Order” Proposed by the NM Environment Department
- Proposed changes from the existing
- What can be improved?
- Who is in the driver’s seat?
- Just along for the ride, or will the public have real input?
- Public comments due May 31
Department of Energy’s new Environmental Management at Los Alamos
- Cleanup work no longer under nuclear weapons work
- Looking for a new contractor
- Can cleanup accelerate?
Nuclear Watch’s lawsuit
- Alleging violations of the 2005 Consent Order
Questions, answers, and discussion
- What’s on your mind
- Your comments are important
Brought to you by Nuclear Watch New Mexico
(505) 989-7342
www.nukewatch.org
Public Meeting, Los Alamos Cleanup at the Crossroads, 6:00 pm Tuesday May 24
Los Alamos Cleanup at the Crossroads
Public Meeting
6 – 7:30pm, Tuesday May 24, 2016
Community Room, Main Library, 145 Washington Ave, Santa Fe
Presentation on the Future of Cleanup at Los Alamos:
What the public needs to know and how to get involved and be informed
• Focus on new cleanup order proposed by the NM Environment Dept. and its lack of enforceability.
• Public comments due May 31
• New Energy Dept. Environmental Management at the Lab – same as the old boss?
• Nuclear Watch’s lawsuit
• Questions and answers
Brought to you by Nuclear Watch New Mexico
(505) 989-7342 [email protected]
www.nukewatch.org <https://nukewatch.org>
Nuclear Watch NM Files Lawsuit Over Lack of Cleanup at the Los Alamos Lab
May 17, 2016
Nuclear Watch NM Files Lawsuit
Over Lack of Cleanup at the Los Alamos Lab;
NM Environment Dept. Forgoes Nearly $300 Million in Penalties
Santa Fe, NM – Nuclear Watch New Mexico has filed a lawsuit in federal court against the Department of Energy and Los Alamos National Security LLC (LANS), the for-profit operator of the Los Alamos National Laboratory, over their failure to meet cleanup milestones under a 2005 “Consent Order” they agreed to with the New Mexico Environment Department. The New Mexico Environmental Law Center is representing NukeWatch in this legal action to enforce cleanup at LANL.
The suit was filed under the citizen suit provisions of the federal Resource Conservation and Recovery Act (RCRA), which the 2005 Consent Order explicitly incorporated. The law provides that any person who violates any requirement of RCRA is liable for a civil penalty up to $37,500 for each day of violation. Our suit claims twelve violations, which range in length of time of up to 675 days each. Our current cost estimate of the alleged violations approaches 300 million dollars and counting.
Jay Coghlan, NukeWatch Executive Director, commented, “The federal government plans to spend a trillion dollars over the next 30 years completely rebuilding U.S. nuclear forces. Meanwhile, cleanup at the Los Alamos Lab, the birthplace of nuclear weapons, continues to be delayed, delayed, delayed. We seek to make the for-profit nuclear weaponeers cleanup their radioactive and toxic mess first before making another one for a nuclear weapons stockpile that is already bloated far beyond what we need. Real cleanup would be a win-win for New Mexicans, permanently protecting our water and environment while creating hundreds of high paying jobs.”
In 2005 the New Mexico Environment Department compelled DOE and the University of California (LANL’s manager at the time) to enter into a detailed Consent Order that mapped the way toward comprehensive cleanup at LANL. However, beginning in 2011 with Governor Martinez’s administration, the New Mexico Environment Department allowed LANL’s new contractor, the for-profit Los Alamos National Security, LLC, to stop virtually all cleanup, instead engaging in a “campaign” to move above ground, monitored radioactive transuranic wastes to the Waste Isolation Pilot Plant (WIPP). That campaign ended in disaster when an improperly treated radioactive waste drum from LANL ruptured, contaminating 21 workers and indefinitely closing that multi-billion dollar facility.
The 2005 Consent Order required DOE and LANL to investigate, characterize, and clean up hazardous and mixed radioactive contaminants from 70 years of nuclear weapons research and production. It also stipulated a detailed compliance schedule that the Lab was required to meet. Ironically, the last milestone, due December 6, 2015, required a report from LANL on how it successfully cleaned up Area G, its largest waste dump. However, real cleanup remains decades away, if ever. The Lab plans to “cap and cover” Area G, thereby creating a permanent nuclear waste dump in unlined pits and shafts, with an estimated 200,000 cubic yards of toxic and radioactive wastes buried above the regional groundwater aquifer, four miles uphill from the Rio Grande.
Scott Kovac, NukeWatch Research Director, noted, “DOE and NMED agreed to all parts of the 2005 Consent Order, including the schedule. Then under the Martinez administration NMED granted more than 150 extensions requests, and DOE and LANS have still missed many of those deadlines. NukeWatch has taken this necessary step to enforce cleanup at LANL, to hold DOE accountable for protecting New Mexicans and make cleanup of legacy wastes the top priority. It’s ridiculous that we have to have this cleanup debate after 70 years of contamination from nuclear weapons research and production.”
The New Mexico Environment Department has issued a draft revised proposed Consent Order, for which the public comment period expires on May 31. The proposed new Consent Order specifically states that it “supersedes the 2005 Compliance Order on Consent (2005 Consent Order) and settles any outstanding alleged violations under the 2005 Consent Order.” (Sec. II.A.) This then would absolve DOE and LANS of nearly $300 million in potential penalties.
Moreover, the new draft Order puts DOE in the driver’s seat instead of New Mexico. It explicitly states that, “DOE’s project plans and tools will be used to identify proposed milestones and targets” (p. 27) and “DOE shall define the use of screening levels and cleanup levels” (p. 31) Moreover, DOE can opt out of any cleanup because of “impracticability” or cost of cleanup (p. 34) and that “DOE shall update the milestones…. [according to] changes in anticipated funding levels.” (p. 28). So the new Consent Order is made subordinate to DOE’s budget, which has been cutting cleanup while increasing funding for nuclear weapons programs that caused the mess to begin with. This is the opposite of the original Consent Order, whose intent was to make DOE and LANL get increased funding for cleanup.
The relief or remedy that Nuclear Watch New Mexico seeks through its lawsuit is simple, asking the Court to enter a judgment “Enjoining the Defendants [DOE and LANS] to take action to come into compliance with the March 1, 2005 Consent Order, as amended on October 29, 2012, according to a reasonable but aggressive schedule ordered by this Court…”
With that, Nuclear Watch New Mexico hopes to get real, comprehensive cleanup back on track at the Los Alamos National Laboratory.
# # #
Nuclear Watch New Mexico’s lawsuit complaint is available at https://nukewatch.org/importantdocs/resources/NukeWatch-Complaint-Filed-20160512.pdf
Our complaint alleges twelve counts of milestone compliance violations where NMED did not grant extensions. From there we calculate 7,853 total days of noncompliance at $37,500.00 per day, equal to $294,487,500, with the clock still ticking.
Our May 5, 2016 second notice of intent to sue (which is a good summary of our complaint) is available at https://nukewatch.org/importantdocs/resources/NukeWatch-2nd-NOI-DOE-LANS-5-5-16.pdf
Our January 20, 2016 notice of intent to sue is available at https://nukewatch.org/importantdocs/resources/NukeWatch-NM-NOI-to-DOE-and-LANS-20160120.pdf
NMED’s revised Consent Order is available at http://energy.gov/em/nnmcab/downloads/nmed-revised-lanl-consent-order-draft-march-2016
Consolidated Nuclear Security LLC Performance Evaluation Report – Wrong B61-12 tail case?
Buried in the just released NNSA FY 2015 Performance Evaluation Report (PER) for Consolidated Nuclear Security LLC (the combined contract for Pantex and Y-12 run by Lockheed Martin and Bechtel) is the remarkable note that Pantex sent to the Defense Department a Joint Test Assembly (JTA) of the B61-12 nuclear smart bomb with the wrong tail case. Generally, a JTA is a full scale mock up of the nuclear weapon (just not nuclear armed), in this case for a real life drop test from an Air Force fighter at the Tonapah Test Range in Nevada (which is run by the Sandia Labs).
P. 5: “CNS experienced several issues with the builds of the new B61 JTA Modernization configurations. CNS experienced quality issues on five of the six First Production Units. The most severe of which was the installation of an incorrect tail case on the JTA S/N 602 that was delivered to Department of Defense (DoD). The DoD chose not to proceed with the flight test and returned the unit to Pantex.” [S/N is the serial number of the particular unit.] – End –
How do you put the wrong tail case on the mock bomb, especially given all the hoopla we’ve heard about the B61-12 and the rush to get it into production? Did this involve the now-well known tail fin kit that turns the “dumb” B61 bomb into the precision-guided B61-12?
A few other worthy items from the CNS PER:
• p. 5: Pantex is falling behind in dismantlements, and this is before the announced planned 20% increase in dismantlements. “CNS achieved 101% of dismantlements related to secondaries and 66% of the revised Production Control Document (PCD) baseline schedule. The low performance against the revised PCD baseline schedule resulted in NNSA falling below the trajectory to achieve the 2022 dismantlement goal.”
Secondaries are dismantled at Y-12, with all of the rest of the nuclear weapon dismantled at Pantex. The 2022 dismantlement goal is to dismantle the ~2,500 nuclear weapons scheduled by 2009 for dismantlement. This does not include any weapons retired since then.
• p. 7: “CNS did not meet the majority of the expectations for scheduled surveillance activities, deliverables, and requirements as documented within each applicable weapons system approved Integrated Weapon Evaluation Team (IWET) Plans and associated directive documents.”
Rigorous surveillance is the prerequisite for maintaining stockpile safety and reliability (the claimed rationale for the Stockpile Stewardship Program), but has chronically suffered lower prioritization.
• p. 10: “W76-1 LEP: CNS achieved 101% of the secondary production schedule, met the military shipment schedule, but only achieved 85% of the total FY15 delivery commitment to the Department of Defense.”
This doesn’t bode well for future Life Extension Programs that are growing only more complex and ambitious.
• p. 11: “CNS is behind schedule on pit recertification projects and is working on recovery plans. The CNS delays have not adversely impacted the B61-12 schedule. However, if delays continue the impacts to the B61-12 schedule are certain.”
• p. 14: The future uranium casting process for the Uranium Processing Facility is still unproven.
“CNS did not fully meet expectations on the use of the production microwave caster in [Building] 9212 [at Y12]. This is partially due to equipment issues including the stack 11 filter issues and a failure in the microwave’s bottom lift assembly. Unfortunately, CNS was unable to recover the schedule. Running the microwave caster early and often is valuable since this technology represents the future Uranium Processing Facility (UPF) casting capability.”
• p. 24: Pantex and Y-12 are beginning “additive manufacturing” (3-D printing) of nuclear weapons components. What are the future proliferation consequences of this?
“CNS began advancing manufacturing capabilities through additive manufacturing initiatives. CNS procured and received a Connex 500-UV Resin multi-color, large-scale plastic machine. This machine will be used for prototyping, proof of principle, displays and cutaways, and training aids. CNS also procured its first metal additive machine and installation will begin at Y-12 in July. Once R&D material testing is complete, the first area of focus will be tooling applications. A second, identical machine has been procured for Pantex and will be delivered late summer for similar applications.”
• p. 35: CNS, composed of Lockheed Martin and Bechtel, gave the construction contract for the Uranium Processing Facility at Y-12 to Bechtel. There was no competition that I heard about.
Concerning Bechtel’s track record, it took the Chemistry and Metallurgy Research Replacement Project at LANL from an original $600 million to $6 billion, and the Waste Treatment Facility at Hanford from $3.5 billion to $13 billion, and it may still never work.
• p. 42: “While NNSA has noted the CAS [Contractor Assurance System] reports have gotten more self-critical over FY15, the CNS end of year self-assessment was not self-critical. Given all the issues this year that impacted mission, it was unusual that the report was not more introspective.”
In fact, CNS gave itself a glowing self-assessment, which NNSA did not agree with. In all, NNSA awarded CNS $11.3 million out of a possible $20 million in incentive fees, along with a fixed fee of $31 million. For NNSA, that’s a pretty big slap on the wrist.
The Performance Evaluations Reports are available at https://nnsa.energy.gov/aboutus/ouroperations/apm/perfevals
NukeWatch successfully sued in 2012 to get the reports publicly released, but NNSA was misbehaving again and did not release the FY 2015 PERs until now. These reports are invaluable for insight into what NNSA sites actually do and related contractor performance. The reports are also becoming increasingly critical of contractor performance ever since the major security incident at Y-12 and the closure of the Waste Isolation Pilot Plant caused by an errant radioactive waste drum from Los Alamos.
Comment Period Extended for Proposed Los Alamos Cleanup Order
The New Mexico Environment Department’s Hazardous Waste Bureau is extending the public comment period on the proposed changes to the Draft Consent Order which governs legacy clean-up at Los Alamos National Laboratory.
The public comment period now continues through May 31. To obtain a copy of the documents or a portion thereof, visit the NMED website at https://web.archive.org/web/20170109131949/https://www.env.nm.gov/HWB/lanlperm.html under Consent Order.
Written comments must be based on information available for review and include, to the extent practicable, all referenced factual materials.
NMED is scheduled to present on the public comments received to date at the May 18 Northern New Mexico Citizens’ Advisory Committee meeting at the Cities of Gold Hotel, 10-A Cities of Gold Road, Santa Fe, New Mexico from 1:00 P.M. to 5:00 P.M.
AND WE HAVE EXPANDED OUR COMMENTS
Please let your voice be heard and turn in public comments. Copy the sample comments below and paste into an email. Please modify as you see fit, then email to the address below. If you don’t mind, please cc: us at: info(at)nukewatch(dot)org
[date]
Ms. Kathryn Roberts
New Mexico Environment Department
Post Office Box 5469
Santa Fe, New Mexico 87502
Via email to [email protected]
Dear Ms. Roberts,
I urge the New Mexico Environment Department (NMED) to abandon the proposed 2016 Compliance Order on Consent, or Consent Order, for Los Alamos National Laboratory (LANL), released for public comment on March 30, 2016. It creates serious problems and represents a giant step backwards in achieving the goal of genuine cleanup of the Laboratory.
The Environment Department should keep the existing Consent Order that went into effect March 1, 2005, while modifying and updating a cleanup schedule that includes a realistic final compliance date. I also formally request that NMED provide the opportunity for a public hearing on the revised cleanup schedule and new completion date, in accordance with the New Mexico Hazardous Waste Act and the 2005 Consent Order.
GENERAL COMMENTS
The opportunity for a public hearing must be provided
- Any extension of a final compliance date must be treated as a Class 3 permit modification to the 2005 Consent Order and therefore requires a 60-day public comment period.
- Any extension of a final compliance date under the 2005 Consent Order can be implemented only after the opportunity for public comment and a public hearing, including formal testimony and cross-examination of witnesses.
- The Environment Department is legally required to follow these public participation requirements that explicitly incorporated into the 2005 Consent Order.
Withdraw the proposed draft 2016 Consent Order
- The proposed draft represents a big step backwards in achieving the goal of genuine cleanup of the Laboratory.
- The Environment Department should keep the current 2005 Consent Order and revise the Section XII cleanup schedule and final compliance date.
- I request that the Environment Department withdraw the proposed draft 2016 Consent Order.
The public deserves the opportunity to comment on all following drafts
- It seems likely that a later draft – after the Lab’s and public comments are incorporated into a revised draft – and after closed-door negotiations between the Environment Department and the Laboratory – could be substantially different from the current draft.
- I request that the public have the opportunity to review and comment on any further drafts of a revised proposed 2016 Consent Order.
Public participation provisions in the existing 2005 Consent Order must be incorporated into the proposed draft 2016 Consent Order
- The proposed draft 2016 Consent Order explicitly limits public participation requirements incorporated into the existing 2005 Consent Order.
- I request that all notices, milestones, targets, annual negotiations, and modifications require public review and comment, and the opportunity for a public hearing.
The current state of cleanup must be updated and next steps scheduled
- Work under the existing 2005 Consent Order needs to be subject to public review. In 2005 DOE agreed to complete cleanup under the Consent Order by December 6, 2015, which did not happen. In order for the public to understand where the work under the existing Consent Order stands, LANL should be required to provide a current, publicly available list of the status of all cleanup projects under the 2005 Consent Order.
- Further, I request that next steps for cleanup at every site listed in the 2005 Consent Order be documented in detail and given a scheduled completion date, or alternatively verified as already completed.
- All documents submitted under the 2005 Consent Order must be incorporated into any revised Consent Order.
All documents must be made public as required in the 2005 Consent Order
- The State and the Lab must make all communications, documents, submittals, approvals, notices of deficiencies and denials under any revised Consent Order readily and electronically available to the public.
- The State and the Lab must notify individuals by e-mail of all submittals, as required in the 2005 Consent Order.
The Environment Department must respond in writing to all public comments
- I request that the State reply individually to each and every comment submitted.
- The Lab’s comments and NMED’s response to comments must be made public.
All future work must have enforceable deadlines
- The proposed draft 2016 Consent Order proposes a “Campaign” approach with enforceable cleanup deadlines limited to the work scheduled only for that year.
- I request that all anticipated cleanup projects have scheduled, enforceable cleanup deadlines from the beginning of any revised Consent Order.
The Consent Order cannot be open-ended
- Any Consent Order for LANL cleanup must have a final compliance date to which the State and the Lab agree to and are so bound.
- The public should be given an opportunity for a public hearing on the new final compliance date as required by New Mexico’s hazardous waste regulations.
SPECIFIC COMMENTS
The Proposed 2016 Consent Order Must Not Extend the Original Final Compliance Date Without Required Public Participation
The proposed 2016 consent order would indefinitely extend the final compliance date for completing corrective action at the Laboratory, without the opportunity for a public hearing with formal testimony and cross-examination of witnesses. Any extension of a final compliance date under the 2005 Consent Order requires a 60-day public comment period and the opportunity for a public hearing, including formal testimony and cross-examination. The Environment Department is legally required to follow these procedural requirements.
The legal requirements that mandate a public hearing are clear. Section XII of the 2005 Consent Order establishes the compliance schedule for implementation and completion of corrective actions at specific sites at the Laboratory. This schedule is mandatory. The final report that was to be submitted under the 2005 Consent Order – therefore, the final compliance date – was the remedy completion report for the huge Area G waste dump, required to be submitted by December 6, 2015. The proposed 2016 Consent Order would indefinitely extend this final compliance date by not designating a specific final compliance date.
But this revision must be treated as a major Class 3 permit modification. Section III.W.5 of the 2005 Consent Order explicitly provides for the preservation of full procedural rights for the public as follows:
This Consent Order hereby incorporates all rights, procedures and other protections afforded the Respondents [DOE and UC, now LANS] and the public pursuant to the regulations at 20.4.1.900 NMAC (incorporating 40 C.F.R. § 270.42) and 20.4.1.901 NMAC, including, but not limited to, opportunities for public participation, including public notice and comment, administrative hearings, and judicial appeals concerning, for example, remedy selection decisions of the [Environment] Department.
Thus, extension of a final compliance date under the 2005 Consent Order requires a 60-day public comment period and the opportunity for a public hearing, including formal testimony and cross-examination.
The Proposed New Consent Order Must Not Limit Other Public Participation Procedures
The proposed 2016 Consent Order expressly limits public participation requirements in a way that completely diverges from those provided in the 2005 Consent Order. As explained above, the 2005 Consent Order explicitly protects procedural due process rights available to the public. The proposed 2016 Consent Order explicitly removes these protections, as follows:
The Parties agree that the rights, procedures and other protections set forth at 20.4.1.900 NMAC (incorporating 40 C.F.R. § 270.42), 20.4.1.901 NMAC, and 20.4.1.902 NMAC, including, but not limited to, opportunities for public participation, including public notice and comment, administrative hearings, and judicial appeals, do not apply to modification of the Consent Order itself. [Emphasis added]
Thus, as proposed in the above language, the Parties (the Environment Department, Department of Energy and Los Alamos National Security, LLC) have inappropriately agreed to remove the due process rights, procedures and other protections provided to the public under the Resource Conservation and Recovery Act (RCRA) and the New Mexico Hazardous Waste Act. This provision must be stripped from the proposed 2016 Consent Order.
The Proposed New Consent Order Must Not Eliminate Enforceable Deadlines
The proposed 2016 consent order would eliminate all the deadlines for completing cleanup under the 2005 Consent Order, and replace them with an open-ended and vague scheduling process, with limited enforcement opportunities.
The 2005 Consent Order, in Section XII, established dozens of deadlines for the completion of corrective action tasks, including completion of investigations at individual sites, installation of groundwater monitoring wells, submittal of groundwater monitoring reports, evaluation of remedial alternatives for individual sites, and completion of final remedies. These deadlines are enforceable under section III.G.
The proposed 2016 Consent Order would abandon the 2005 Consent Order provisions and replace them with a so-called “Campaign Approach” under Section VIII. Under Section VIII.A.3, it would be up to the DOE, not the regulator at the New Mexico Environment Department, to select the timing and scope of each “campaign.”
Enforceable deadlines for cleanup tasks would apply no more than one year into the future. Deadlines would be based on “Campaigns” negotiated each year with DOE with no public participation and opportunity to comment on the schedule. To add insult to injury, the annual schedule would be determined by funding at DOE’s discretion, rather than the schedule driving the funding, which was the fundamental approach of the 2005 Consent Order.
All cleanup projects must mandatory completion dates scheduled from the beginning date of any revised Consent Order, and must be fully enforceable.
Existing Violations Must Not Be Eliminated
Section II.A of the proposed 2016 Consent Order would “settle any outstanding violations of the 2005 Consent Order.” This is a get out of jail free card. Without enforceable schedules from the beginning, any consent order is not truly unenforceable, and the Environment Department would be abdicating its responsibility to protect human health and the environment as required by the federal Resource Conservation and Recovery Act (RCRA) and the New Mexico Hazardous Waste Act. NMED must not surrender its regulatory and enforcement powers!
Attorney General Approval Must Be Obtained
The 2005 Consent Order was signed by the Attorney General of New Mexico for purposes of the Covenant Not to Sue (section III.) and the Reservation of Rights (section III.). As indicated on the draft signature page, there is no indication of the NM Attorney General plans to sign the proposed 2016 Consent Order. Yet it would provide the State of New Mexico with a covenant not to sue DOE on behalf of the State of New Mexico, not merely on behalf of the Environment Department. The Attorney General was an active participant, representing the People of New Mexico, in the 2005 Consent Order. The Environment Department has a responsibility to ensure that the NM Attorney General is consulted, and his approval obtained, before any consent order is adopted.
The Proposed 2016 Consent Order Must Not Omit Detailed Requirements Found in the 2005 Consent Order
The 2005 Consent Order includes numerous detailed requirements for such things as well installation, sample collection, and preparation of work plans and reports. These ensure that the cleanup work is done properly, consistently, and according to standard industry practices. They also ensured that work plans and reports were consistent, easy for the Environment Department to review, and easy for the public to understand. The proposed 2016 Consent Order omits many such requirements, which should be corrected.
The Proposed 2016 Consent Order Must Not Allow Budget To Dictate Cleanup
The proposed 2016 Consent Order allows DOE to provide cleanup priorities based on anticipated budget, which is backwards. . By the time NMED receives an estimated annual cleanup budget from DOE, the horse has left the barn. The original purpose of the 2005 Consent Order was to compel DOE and LANL to ask Congress for additional funds to accelerate cleanup. The giant loophole in the proposed 2016 Consent Order that allows DOE and LANL to say that they don’t have sufficient funding and therefore can choose to exempt themselves from cleanup should be eliminated.
Cleanup Levels Must Remain Strict
Section IX Cleanup Objectives and Cleanup Levels of the proposed 2016 Consent Order would allow DOE to “develop site specific ecological cleanup levels” to mitigate unacceptable ecological risk due to release of site-related contaminants. There is no mention of NMED’s role in this process. DOE would be allowed to demonstrate to NMED that any particular “cleanup objective is impracticable.” To do this, DOE may consider such things as technical difficulty, the cost of the project, hazards to workers or to the public, and any other basis that may support a finding of impracticability. If NMED approves the impracticability request, DOE can then propose alternative cleanup methods using site-specific risk assessments. All of this could take place behind closed doors, as there are no public participation requirements in this section. Please clarify what cleanup levels will be used and when and where they will be applied.
New Mexico deserves better
In closing, the Environment Department’s proposed 2016 Consent Order allows the federal government to leave Northern New Mexico contaminated if DOE believes that cleanup is too difficult or costly– a sorry situation indeed for a nuclear weapons facility that receives over 2 billion taxpayer dollars a year. Instead, the New Mexico Environment Department should implement a new revised Consent Order that is aggressive and enforceable and in which the State of New Mexico stays in the driver’s seat, not LANL and DOE. That would be a real win-win for New Mexicans, helping to permanently protect the environment and our precious water resources while creating hundreds of high-paying cleanup jobs. .
Sincerely,
Name
City
The new draft Consent Order is available at
https://www.env.nm.gov/HWB/lanlperm.html#COOC
NMED’s public notice for the draft Consent Order is available at
https://www.env.nm.gov/HWB/documents/PublicNotice__English.pdf
The public comment period ends 5:00 pm May 31, 2016.
Comments should be submitted to [email protected]
Sample General Comments on the proposed new Los Alamos Cleanup Agreement
The New Mexico Environment Department (NMED) has issued a draft revised Consent Order (CO), which was the agreement in 2005 between the State and the federal Department of Energy (DOE) for fence-to-fence cleanup of legacy Cold War wastes at the Los Alamos National Laboratory (LANL). The Consent Order was designed as a plan-to-make-a-plan with investigations of contaminated sites followed by cleanup decisions and remediation. Milestones and penalties were included to keep funding and cleanup on track.
Serious investigation and cleanup began under the 2005 Consent Order. From 2005 through 2010, DOE and its contractors, under NMED oversight, accomplished significant progressed towards cleanup of the Laboratory. Much investigation work was completed. A large plume of hexavalent chromium was discovered in groundwater. Remedies were completed at dozens of individual sites.
Little cleanup has been accomplished in the last few years. We fear that the new Consent Order, if adopted, would continue that downward trend. It does not have enforceable milestones for all cleanup projects from the beginning. Instead the new plan is for NMED and DOE to decide every 1 to 3 years which sites will be addressed for cleanup “Campaigns”. This may allow Los Alamos to never address all the sites, and revert cleanup back to the way it was done before the 2005 Consent Order with budget driving cleanup. This is contrary to the original purpose of the CO, which was to compel DOE and LANL to get additional money from Congress for cleanup.
NMED’s public notice for the draft Consent Order is available at
https://www.env.nm.gov/HWB/documents/PublicNotice__English.pdf
The new draft Consent Order is available at
https://www.env.nm.gov/HWB/lanlperm.html#COOC
Please let your voice be heard and turn in public comments. Copy the sample comments below and paste into an email. Please modify as you see fit, then email to the address below. If you don’t mind, please cc: us at: info(at)nukewatch(dot)org
The 45-day public comment period ends 5:00 pm May 16, 2016.
Comments should be submitted to:
Ms. Katherine Roberts
Division Director
New Mexico Environment Department
Post Office Box 5469
Santa Fe, New Mexico 87502
Comments on the proposed new Consent Order
Withdraw this draft
- This draft represents a big step backwards in achieving the goal of genuine, comprehensive cleanup of the Laboratory.
- The Environment Department should keep the current 2005 Consent Order with necessary revisions to the cleanup schedule.
- I request that the Environment Department withdraw this draft Consent Order.
A 45-day comment period on this first draft is inadequate
- The March 30, 2016 draft document is a new Consent Order and, as such, thoroughly reviewing the document is a big task.
- I request that at least another 15 days be added to the public comment period.
The public deserves the opportunity to comment on all following drafts
- It seems likely that a later draft – after the Lab’s and the public’s comments are incorporated – could be substantially different from the current draft.
- I request that the public have the opportunity to comment on any further drafts of the new Consent Order.
Public participation must be put back into the new Consent Order
- The new Consent Order would expressly limit public participation requirements which would be opposite from the 2005 Consent Order.
- I request that all milestones, targets, annual negotiations, and modifications require the opportunity for public review and comment.
The current status of all areas of cleanup must be updated
- A current list of the status of all cleanup at Los Alamos must be included in the new Consent Order.
- I request that the next step for cleanup at every site be documented in detail.
- All previous 2005 Consent Order documents must be incorporated in to the new Consent Order.
All documents must be made public
- The State and the Lab must make all communications, documents, and submittals specified in this Consent Order readily available to the public.
- The State and the Lab shall notify individuals by e-mail of all submittals as specified in this Consent Order.
All future work must have enforceable deadlines
- The new Consent Order would institute a “Campaign” approach with enforceable cleanup deadlines for only one year at a time.
- I request that all cleanup work items have scheduled, enforceable dates.
- The new revised Consent Order creates a giant loophole for DOE and LANL to plead that they don’t have enough funding and therefore don’t have to do the cleanup. The original intent of the Consent Order was to make DOE and LANL get more funding for cleanup from Congress. The “I’m too poor” excuse should be eliminated from any final Consent Order.
The revised Consent Order cannot be open-ended
- Any new Consent Order must have a detailed, enforceable schedule of genuine cleanup milestones.
- I request that the public be given an opportunity for a hearing on the new Consent Order.
Sincerely,
Your name
City
State
NukeWatch NM Heads to DC To Stop U.S. Nuclear Weapons “Trillion Dollar Trainwreck”
NukeWatch NM Heads to Washington to Press Congress, Obama Officials
To Stop U.S. Nuclear Weapons “Trillion Dollar Trainwreck” —
LANL Whistleblower Chuck Montaño to Be Honored
Three members of Nuclear Watch New Mexico will visit Washington, DC from April 17 to April 20 to oppose U.S. Department of Energy (DOE) nuclear weapons projects, which they say will lead to a “trillion dollar trainwreck” through out-of control spending, more radioactive waste generation, and weapons proliferation. The group will meet with the New Mexican congressional delegation, committee staffers, and administration officials with responsibility for U. S. nuclear policies to press for new funding priorities.
The Nuclear Watch NM delegation will be working with more than 50 colleagues from two dozen other states who are participating in the 28th annual Alliance for Nuclear Accountability “DC Days.” They will distribute copies of the ANA’s new report “Trillion Dollar Trainwreck” a detailed analysis of the Obama Administration’s latest plans to spend more money on nuclear weapons without truly enhancing U.S. security.
Jay Coghlan, NukeWatch director and president of the ANA Board of Directors, said, “Massive spending on nuclear weapons ‘modernization’ creates potential catastrophic risks for U.S. taxpayers, the environment and world peace. We will press policy-makers to cut programs that fund dangerous DOE boondoggles. The money saved should be redirected to dismantling weapons and cleaning up the legacy of nuclear weapons research, testing and production.”
NukeWatch NM Steering Committee member Chuck Montaño will receive recognition during DC Days from the Alliance for Nuclear Accountability (ANA) at a reception on April 19, 2015, at the Hart Senate Office Building. He, along with California’s senior U.S. Senator Diane Feinstein and ranking member of the House Armed Services Committee Rep. Adam Smith (D.-WA), will be among those honored by ANA for their efforts to hold the nuclear weapons military-industrial complex accountable. Montaño is being recognized for his advocacy confronting whistleblower and employee abuse, managerial malfeasance and fraudulent activity, all of which he documents in his recently released book detailing the chain of events that led to him becoming a federally protected whistleblower.
Montaño commented that he wrote Los Alamos: Secret Colony, Hidden Truths, “so people can appreciate the Lab’s full impact and legacy, not just what institutional leaders want the public to remember. There are important events I document for posterity, which may otherwise be hidden or erased from memory, and I didn’t want that to happen.”
Jay Coghlan, NukeWatch director, said, “I am very proud of Chuck Montaño, especially since he’s a Nuke Watch Steering Committee member as well. We depend on people like him with the inside story to help keep the Lab safe for communities and workers alike. It’s gratifying to see that the Alliance for Nuclear Accountability and its many member organizations appreciate his efforts.”
Mr. Montaño, a lifelong Santa Fe area resident, was employed at the Los Alamos National Laboratory for 32 years, until his forced retirement from the lab in 2010. He is also the former Director of Fraud and Special Audits for the Office of the New Mexico State Auditor.
The Alliance for Nuclear Accountability (ANA) is a network of three-dozen local, regional and national organizations representing the concerns of communities downwind and downstream from U.S. nuclear weapons production and radioactive waste disposal sites.
# # #
Chuck Montaño’s book Los Alamos: Secret Colony, Hidden Truths
is available at www.losalamosdiary.com
Past NukeWatch Events
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
Past Work Product (2019-)
Nothing Found
It seems we can’t find what you’re looking for. Perhaps searching can help.
2019
November 26, 2019 Press Release November 24, 2019 Press Release November 19, 2019 Plutonium Pit Production Workshop Presenters:
August 12, 2019 NEPA Comments NukeWatch’s 22-page formal comments on expanded plutonium pit production Until NNSA fully complies with the National Environmental Policy Act through the preparation of a programmatic environmental impact statement on expanded plutonium pit production, Nuclear Watch believes that any irreversible or irretrievable commitment of resources to either the expansion of pit production at the Los Alamos Lab or to the repurposing of the MOX Facility at the Savannah River Site is unlawful. Read/Download the Full Document HERE July 25, 2019 NEPA Comments Scoping comments on NNSA draft EIS for plutonium pit production at the Savannah River Site THE NEED FOR A PROGRAMMATIC ENVIRONMENTAL IMPACT STATEMENT: This is our first and primary concern, that NNSA must first complete a programmatic environmental impact statement (PEIS) on its nation-wide plans for plutonium pit production, in advance of the Savannah River Site-specific environmental impact statement. To get right to the point, we argue that the SRS EIS process should go no further than this scoping period and should resume only after a completed formal Record of Decision for a new or supplemental PEIS. Read/Download the Full Document HERE July 9, 2019 Plutonium Pit Production Fact Sheet Expanding Nuclear Pit Production: The Facts and What You Can Do The Facts Read/Download the Full Document HERE June 10, 2019 News Release In a victory for transparency and legal compliance by the government, the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) today published a “Notice of Intent” in the Federal Register to complete environmental reviews on its controversial proposal to expand plutonium “pit” production for new and refurbished nuclear weapons. [embeddoc url="https://nukewatch.org/wp-content/uploads/2019/06/SRS-plutonium-bomb-plant6-14-19.pptx" download="all" viewer="google"] Read/Download the Full News Release HERE June 4, 2019 Press Release On behalf of three public interest organizations - Nuclear Watch New Mexico, Tri-Valley Communities Against a Radioactive Environment and Savannah River Site Watch – attorneys for the law firm of Meyer Glitzenstein & Eubanks and the Natural Resources Defense Council recently sent a 16-page letter to Lisa Gordon-Hagerty, head of the National Nuclear Security Administration (NNSA). The detailed letter warns the nuclear agency to not proceed with aggressive plans to expand plutonium pit production without first meeting its legal requirements for timely public review and comment under the National Environmental Policy Act. Read/Download the Full Press Release HERE May 31, 2019 Press Release Last Wednesday, facility operations personnel entered a service room and noticed a leak emanating from a valve on the radioactive liquid waste (RLW) system. Upon subsequent visual inspection by a radiological control technician, RLUOB engineers believe that this valve, and 6 similar valves, may be constructed of carbon steel. The RLW system handles radioactive liquid waste streams from chemistry operations that include nitric and hydrochloric acids—carbon steel valves would be incompatible with these solutions. The suspect valves are also in contact with stainless steel piping, which would create another corrosion mechanism. RLUOB management plans to drain the affected piping sections and develop a work package to replace all of the suspect valves. They will also confirm the valve materials and if shown to be incorrect, investigate the cause of this failure in the design, procurement, and installation processes. The valves were installed in 2013 as part of a modification to add straining and sampling capabilities that were not in the included in the original design. [Please note that DNFSB reports are posted a few weeks later than dated.] This immediately raises two crucial issues: 1) the National Nuclear Security Administration’s (NNSA’s) plans for expanded plutonium pit production; and 2) the current attempt by the Department of Energy to restrict Safety Board access to its nuclear weapons facilities. Read/Download the Full Press Release HERE April 26, 2019 Consent Orders Comparison On March 1, 2005, after arduous negotiations and threats of litigation, the New Mexico Environment Department (NMED), Department of Energy (DOE), and Los Alamos National Laboratory (LANL) entered into a Consent Order specifying the schedule for investigation and cleanup of the Lab’s hundreds of contaminated sites. This Consent Order (CO) was LANL’s agreement to fence-to-fence cleanup of Cold War legacy wastes, which NMED began to enforce. Read/Download the Full Comparison HERE March 25, 2019 Press Release More than 25 years after the end of the Cold War, all eight established nuclear weapons powers are “modernizing” their stockpiles. Talks have broken down with North Korea, the new nuclear weapons power. Nuclear-armed India and Pakistan narrowly averted war last month. Russian President Vladmir Putin made new nuclear threats in response to Trump’s announced withdrawal from the Intermediate-Range Nuclear Forces Treaty. This could lead to hair-trigger missile emplacements in the heart of Europe and block extension of the New Strategic Arms Reduction Treaty with Russia. If so, the world will be without any nuclear arms control at all for the first time since 1972. Meanwhile, the U.S. criticizes non-weapons states for signing a nuclear weapons ban treaty, despite the fact there have long been treaties completely banning chemical and biological weapons of mass destruction that the U.S. seeks to enforce. The pending international NonProliferation Treaty (NPT) Preparatory Committee conference at the United Nations is widely expected to collapse in failure because of the nuclear weapons powers’ failure to enter into serious negotiations leading to nuclear disarmament. The NPT’s Article VI mandate for those negotiations has been in effect since 1970, when the Treaty was signed by 189 countries (more than any other treaty). Read/Download the Full Press Release HERE March 26, 2019 NukeWatch Budget Compilation Nuclear Watch New Mexico — Department of Energy FY 2020 Nuclear Weapons Budget Request |
2018
November 16, 2018 Plutonium Pit Production Fact Sheet Plutonium pits are the radioactive cores or “triggers” of nuclear weapons. Their production has always been a chokepoint of resumed industrial-scale U.S. nuclear weapons production ever since a 1989 FBI raid investigating environmental crimes shut down the Rocky Flats Plant near Denver. In 1997 the mission of plutonium pit production was officially transferred to its birthplace, the Los Alamos National Laboratory (LANL) in northern New Mexico, but officially capped at not more than 20 pits per year. However, in 2015 Congress required expanded pit production by 2030 whether or not the existing nuclear weapons stockpile actually needs it. This will support new military capabilities for nuclear weapons and their potential use. Read/Download the full fact sheet pdf HERE October 31, 2018 Nuclear Watch New Mexico, Savannah River Site Watch, and Tri-Valley CAREs sent a letter of demand to the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) to inform the government that its plan to quadruple the production rate of plutonium bomb cores is out of compliance with the National Environmental Policy Act (NEPA). NNSA’s premature plan to quadruple the production rate of plutonium bomb cores (“pits”), the heart of all US nuclear weapons, is out of compliance with requisite environmental law, the groups argue, as NNSA has failed to undertake a legally-mandated programmatic review and hold required public hearings. View/Download the entire press release HERE NukeWatch Comments, September 27, 2018 Nuclear Watch New Mexico is submitted formal comments to express in the strongest possible terms our opposition to DOE Order 140.1 Interface with the Defense Nuclear Facilities Safety Board. We find that the Department of Energy’s (DOE’s) attempt to restrict and suppress DNFSB access is very misguided, arrogant, and likely illegal in that it acts contrary to the Board’s enabling legislation. June 8, 2018 Press Release New Contractors Selected For Expanded Nuclear Weapons Production at Los Alamos Santa Fe, NM. Today the Department of Energy's National Nuclear Security Administration (NNSA) announced its choice for the new management and operating contract for the Los Alamos National Laboratory (LANL).The new contractor, Triad National Security, LLC, is a limited liability company consisting of the Battelle Memorial Institute, the University of California and Texas A&M University. All three are non-profits, and it is unclear how this will affect New Mexico gross receipts taxes. Battelle claims to be the world's largest non-profit technology research and development organization, and manages a number of labs including the Lawrence Livermore and Idaho National Laboratories. Texas A&M was founded in 1876 as the state's first public institution of higher learning and has the largest nuclear engineering program in the country. DOE Secretary Rick Perry is an avid A&M alumnus. May 31, 2018 Press Release Santa Fe, NM & Columbia, SC - "Two key U.S. Department of Energy documents on future production of plutonium "pits" for nuclear weapons, not previously released to the public, fail to justify new and upgraded production facilities at both the Los Alamos National Laboratory (LANL) in New Mexico and the Savannah River Site (SRS) in South Carolina." May 15, 2018 Fact Sheet May 10, 2018 Press Release What's Not in NNSA's Plutonium Pit Production Decision
- NNSA did not mention that up to 15,000 "excess" pits are already stored at the Pantex Plant near Amarillo, TX, with up to another 5,000 in "strategic reserve." The agency did not explain why new production is needed given that immense inventory of already existing plutonium pits. (In 2006 independent experts found that pits last a least a century. Plutonium pits in the existing stockpile now average around 40 years old.) May 2, 2018 Press Release "NNSA should begin nation-wide review of plutonium pit production, why it's needed, and what it will cost the American taxpayer in financial, safety and environmental risks. These are all things that the public should know." -Jay Coghlan, Director, Nuclear Watch New Mexico. April 26, 2018 NukeWatch Comments LANL Rad Lab: Formal Comments Under Nat'l Environmental Policy Act Against raising plutonium limit at LANL Rad Lab View/download Nuclear Watch comments as submitted Excerpt:
- NNSA is planning a 10-fold increase in plutonium at the LANL Rad Lab with a view to ramping up the production of plutonium pits for new nuclear weapons. March 26, 2018 Press Release United States To Begin Construction Of New Nuclear Bomb Plant The National Nuclear Security Administration (NNSA) announced on Friday, March 23, that it was authorizing the start of construction of the Uranium Processing Facility (UPF) and two sub-projects at the Y-12 National Security Complex in Oak Ridge, Tennessee. The UPF is a facility dedicated solely to the manufacture of thermonuclear cores for US nuclear bombs and warheads.
Jay Coghlan of NukeWatch points out that "This project already has a long history, and it is instructive. In 2013, DOE announced it was 85% finished with the UPF design when it ran into the 'space/fit' issue- and more than a half-billion taxpayer dollars were just written off. In private business, that kind of thing gets you fired. In DOE's world of contractors running amok, they not only didn't get fired, not one Congressional hearing was held and the UPF budget went up the next year!" - See full press release for all the details (PDF) March 1, 2018 Press Release The Regional Coalition of LANL Communities: Benefits for the Select Few Santa Fe, NM- According to media reports, Andrea Romero, Executive Director of the Regional Coalition of LANL Communities, is accused of charging some $2,200 dollars of unallowable travel costs, such as alcohol and baseball tickets, while lobbying in Washington, DC for additional funding for the Los Alamos National Laboratory (LANL). She in turn accused the nonprofit group Northern New Mexico Protects of political motivations in revealing these questionable expenses. Romero is running in the Democrat Party primary against incumbent state Rep. Carl Trujillo for Santa Fe County's 46th district in the state House of Representatives. For all the details, see full press release PDF February 28, 2018 Press Release Santa Fe, NM. On December 17, 2017, the Department of Energy (DOE) awarded a separate $1.4 billion contract for cleanup at the Los Alamos National Laboratory (LANL) to Newport News Nuclear BWXT-Los Alamos, LLC (also known as "N3B"). This award followed a DOE decision to pull cleanup from LANL's prime contractor, Los Alamos National Security, LLC (LANS), after it sent an improperly prepared radioactive waste drum that ruptured underground at the Waste Isolation Pilot Plant (WIPP). That incident contaminated 21 workers and closed WIPP for nearly three years, costing taxpayers at least $1.5 billion to reopen. (See all the details in the full press release) February 26, 2018 Press Release Detailed NNSA Budget Documents Accelerates Nuclear Weapons Arms Race Santa Fe, NM. Late Friday February 23, the Trump Administration released the detailed FY 2019 budget for the National Nuclear Security Administration (NNSA), the semi-autonomous nuclear weapons agency within the federal Department of Energy. Overall, NNSA is receiving a $2.2 billion boost to $15.1 billion, a 17% increase above the FY 2018 enacted level. Of that, a full $11 billion is for the budget category [Nuclear] "Weapons Activities", 18% above the FY 2018 level. Of concern to the American taxpayer, DOE and NNSA nuclear weapons programs have been on the congressional Government Accountability Office's High Risk List for project mismanagement, fraud, waste and abuse since its inception in 1990... (See all the details in the full press release) February 22, 2018 Press Release Santa Fe, NM. Today the National Nuclear Security Administration announced an Environmental Assessment to increase the amount of plutonium used in the Radiological Laboratory Utility and Office Building (aka the "Rad Lab") at the Los Alamos National Laboratory from 38.6 grams of plutonium-239 equivalent to 400 grams. This 10-fold increase is significant because it will dramatically expand materials characterization and analytical chemistry capabilities in the Rad Lab in support of expanded plutonium pit production for future nuclear weapons designs. It also re-categorizes the Rad Lab from a "radiological facility" to a "Hazard Category-3" nuclear facility. View/Download full press release February 12, 2018 Press Release Trump's Budget Dramatically Increases Nuclear Weapons Work Santa Fe, NM In keeping with the Trump Administration's recent controversial Nuclear Posture Review, today's just released FY 2019 federal budget dramatically ramps up nuclear weapons research and production. January 12, 2018 Press Release Draft Nuclear Posture Review Degrades National Security Yesterday evening the Huffington Post posted a leaked draft of the Trump Administration's Nuclear Posture Review (NPR). This review is the federal government's highest unclassified nuclear weapons policy document, and the first since the Obama Administration's April 2010 NPR. 2017 |
2017
December 22, 2017 Press Release New Mexico Environment Department Surrendered to DOE Extortion Santa Fe, NM. The New Mexico State Auditor Office recently questioned whether two settlements between the New Mexico Environment Department and the Department of Energy were in the best interests of New Mexico. That Office noted: (View/download full press release) December 20, 2017 Press Release Los Alamos Hires New Contractor - Starts Cleanup On the Cheap Santa Fe, NM- Today the Department of Energy (DOE) announced the award of the new Los Alamos National Laboratory legacy cleanup contract to Newport News Nuclear BWXT-Los Alamos, LLC. The $1.39 billion contract is for ten years, which works out to $139 million per year... View/download the full press release Public Presentation, December 2, 2017 October 31, 2017 Press Release Today, in Washington, DC, the Congressional Budget Office released its new report, "Approaches for Managing the Costs of U.S. Nuclear Forces, 2017 to 2046". The Congressional Budget Office estimates that the most recent detailed plans for nuclear forces, which were incorporated in the Obama Administration's 2017 budget request, would cost $1.2 trillion in 2017 dollars over the 2017-2046 period: more than $800 billion to operate and sustain (that is, incrementally upgrade) nuclear forces and about $400 billion to modernize them.... Driving this astronomical expense is the fact that instead of maintaining just the few hundred warheads needed for the publicly claimed policy of "deterrence," thousands of warheads are being refurbished and improved to fight a potential nuclear war. This is the little known but explicit policy of the U.S. government! October 27, 2017 Press Release Santa Fe, NM. On the evening of Wednesday October 25, the Santa Fe City Council passed a resolution requesting that the New Mexico Environment Department strengthen the revised Los Alamos National Labs cleanup order to call for additional characterization of legacy nuclear wastes, increased cleanup funding, and significant additional safety training. The resolution also called for the suspension of any planned expanded plutonium pit production until safety issues are resolved. (view/download full press release) October 6, 2017 Press Release Santa Fe, NM. Nuclear Watch New Mexico strongly applauds the awarding of the Nobel Peace Prize to the International Campaign to Abolish Nuclear Weapons (disclosure: NukeWatch is one of ICAN's ~400 member groups around the world). This award is especially apt because the peoples of the world are now living at the highest risk for nuclear war since the middle 1980's, when during President Reagan's military buildup the Soviet Union became convinced that the United States might launch a pre-emptive nuclear first strike. Today, we not only have Trump's threats to "totally destroy" North Korea and Kim Jong-un's counter threats, but also renewed Russian fears of a US preemptive nuclear attack... Generally unknown to the American taxpayer, our government has quietly tripled the lethality of the US nuclear weapons stockpile..." (view/download complete press release) NukeWatch fact sheet, September 26, 2017 The National Nuclear Security Administration's own documents have explicitly stated that expanded pit production would have no significant positive effect on job creation and the regional economy of northern New Mexico. Nuclear Watch argues that expanded plutonium pit production could actually have negative effect if it blocks other economic alternatives such as comprehensive cleanup, which could be the real job producer. Moreover, given LANL's poor safety and environmental record, expanded plutonium pit production could have a seriously negative economic impact on northern New Mexico in the event of any major accidents. September 15, 2017 Press Release Santa Fe, NM. The Los Alamos National Laboratory (LANL) has detected far more hexavalent chromium (Cr) contamination than previously estimated in the "sole source" regional groundwater aquifer that serves Los Alamos, Santa Fe and the Espanola Basin. Sampling in July from a new well meant to inject treated groundwater back into the aquifer detected chromium contamination five times greater than the New Mexico groundwater standard of 50 micrograms per liter (ug/L). View/download the full press release September 11, 2017 Press Release Talking Points: The 2016 LANL Cleanup Consent Order Should Be Rescinded The 2005 LANL Cleanup Consent Order was all about the enforceable schedules. It required DOE and LANL to investigate, characterize, and clean up hazardous and mixed radioactive contaminants from 70 years of nuclear weapons research and production. It stipulated a detailed compliance schedule that the Lab was required to meet. Under Gov. Martinez, NMED Secretary Ryan Flynn granted more than 150 compliance milestone extensions at the Lab's request, effectively eviscerating it. View/download the complete talking points July 20, 2017 Press Release Washington, DC Today, the Oak Ridge Environmental Peace Alliance (OREPA), Nuclear Watch New Mexico, and the Natural Resources Defense Council filed a federal lawsuit to stop construction of the problem-plagued Uranium Processing Facility (UPF) until legally required environmental review is completed. The UPF, located at the National Nuclear Security Administration's (NNSA's) Y-12 production plant near Oak Ridge, TN, is slated to produce new thermonuclear weapons components until the year 2080. The UPF is the tip of the spear for the U.S.'s planned one trillion dollar-plus make over of its nuclear weapons arsenal, delivery systems, and production plants. View/download the full press release June 19, 2017 Press Release Some Background on Plutonium Pit Production at the Los Alamos Lab Santa Fe, NM -The Washington Post has published the first in a series of articles on nuclear safety lapses in plutonium pit production at the Los Alamos Lab. Plutonium pits are the fissile cores of nuclear weapons that when imploded initiate the thermonuclear detonation of modern weapons. By the way, did you know? Plutonium facilities at LANL are- in principle- designed to withstand a serious earthquake of a degree expected to occur only once every 10,000 years. The last serious earthquake near the Lab is believed to have occurred 11,500 years ago. View/download the full press release ANA Report 2017: Accountability Audit May 19, 2017 Press Release SA Preview of Trump's Budget: More Nuclear Bombs and Plutonium Pit Production Santa Fe, NM. "The proposed level of funding for the National Nuclear Security Administration's (NNSA)'s Total Weapons Activities is $10.2 billion, a full billion above what was requested for FY 2017. In March, Trump's "skinny budget" stated NNSA's funding priorities as 'moving toward a responsive nuclear infrastructure', and 'advancing the existing warhead life extension programs'. Read the full press release for all the details. March 28, 2017 ANA workshop at UN Ban Treaty Conference Ban Treaty Conference: Alliance for Nuclear Accountability Panel Discussion March 28, 2017, UN, NYC:
March 2017 Fact Sheet Plutonium Pit Production at LANL (Updated March 2017) February 23, 2017 Press Release Costs Jump in Nuclear Weapons vs. Cleanup; Nuclear Weapons Winning over Environmental Protection Santa Fe, NM. America is at a crossroads, having to choose between an unnecessarily large, exorbitant, nuclear weapons stockpile, and cleanup that would protect the environment and water resources for future generations. Expanded nuclear weapons research and production, which will cause yet more contamination, is winning. Read the full press release for all the details. January 5, 2017 Press Release The National Nuclear Security Administration (NNSA) has publicly released its fiscal year 2016 Performance Evaluation Report (PER) for Los Alamos National Security, LLC (LANS), the for-profit contractor that runs the Los Alamos Lab. The Performance Evaluation Report is NNSA's annual report card on contractor performance, and overall the agency awarded LANS $59 million in profit out of a possible $65 million. The grade was 85% for the incentive part of the award. In 2012 Nuclear Watch New Mexico successfully sued NNSA to ensure that the Performance Evaluation Reports detailing taxpayers funds paid to nuclear weapons contractors are publicly available. In 2016 the NNSA decided to put the LANL management contract out for competitive bid, but granted LANS a contract extension until the end of September 2018. |
Media appearances including radio interviews are listed on the internal Media page
See the NukeWatch Channel at YouTube for our extensive playlists of key videos.
See the Nukewatch Twitter feed
See the Nukewatch Tumblr site
WatchBlog Posts:
Over 200 posts published since 2009. See archives at the WatchBlog
Earlier Work Product items are archived here