Court Rules U.S. Nuclear Weapons Production Plan Violates Federal Law

FOR IMMEDIATE RELEASE, October 3, 2024

Media Contacts:
Ben Cunningham, Esquire, SCELP, 843-527-0078, [email protected]
Tom Clements, Savannah River Site Watch, 803-834-3084, [email protected]
Jay Coghlan, Nuclear Watch New Mexico, 505-989-7342, [email protected]
Scott Yundt, Tri-Valley CAREs, 925-443-7148, [email protected]
Queen Quet, Gullah/Geechee Sea Island Coalition, 843-838-1171, [email protected]

AIKEN, S.C. — On September 30, United States District Court Judge Mary Geiger Lewis ruled that the United States Department of Energy (“DOE”) and its semi-autonomous nuclear weapons agency, the National Nuclear Security Administration (“NNSA”), violated the National Environmental Policy Act (“NEPA”) by failing to properly consider alternatives before proceeding with their plan to produce plutonium pits, a critical component of nuclear weapons, at the Los Alamos National Laboratory (“LANL”) in New Mexico and, for the first time ever, at the Savannah River Site (“SRS”) in South Carolina.

The Court found that the plan’s purpose had fundamentally changed from NNSA’s earlier analyses which had not considered simultaneous pit production at two sites.  These changes necessitated a reevaluation of alternatives, including site alternatives, which Defendants failed to undertake prior to moving forward while spending tens of billions of taxpayers’ dollars. Therefore, the Court entered judgment in favor of Plaintiffs, the nonprofit public interest groups Savannah River Site Watch, Nuclear Water New Mexico and Tri-Valley Communities Against a Radioactive Environment (CAREs); the Gullah/Geechee Sea Island Coalition; and Tom Clements as an individual plaintiff.

As a result of this ruling, the Defendants are required to newly assess pit production at a nation-wide programmatic level which will mean undertaking a thorough analysis of the impacts of pit production at DOE sites throughout the United States, including radioactive waste generation and disposal. Under the National Environmental Policy Act (NEPA), this will provide the opportunity for public scrutiny of and formal comment on their assessments.

Continue reading

High Detections of Plutonium in Los Alamos Neighborhood – As We Enter a New Nuclear Arms Race the Last One is Still Not Cleaned Up

FOR IMMEDIATE RELEASE, August 15, 2024
Dr. Michael Ketterer – 928.853.7188 | Email
Jay Coghlan – 505.989.7342 | Email

Santa Fe, NM – In April Nuclear Watch New Mexico released a map of plutonium contamination based on Lab data. Today, Dr. Michael Ketterer, Professor Emeritus of Chemistry and Biochemistry, Northern Arizona University, is releasing alarmingly high results from samples taken from a popular walking trail in the Los Alamos Town Site, including detections of some of the earliest plutonium produced by humankind.

On July 2 and 17 Dr. Ketterer, with the assistance of Nuclear Watch New Mexico, collected water, soil and plant samples from Acid Canyon in the Los Alamos Town Site and soil and plant samples in Los Alamos Canyon at the Totavi gas station downstream from the Lab. The samples were prepared and analyzed by mass spectrometry at Northern Arizona University to measure concentrations of plutonium, and to ascertain its sources in the environment.

Continue reading

NEW Pit Production Fact Sheet – July 2024

Nuclear Weapons and Waste Issues in NM – July 14 Presentation

Groups Fire Back at Feds’ Move to Dismiss Plutonium Pit Lawsuit

NNSA Delays Urgent Research on Plutonium “Pit” Aging While Spending Tens of Billions on Nuclear Weapons Bomb Core Production

FOR IMMEDIATE RELEASE, April 17, 2024
Tom Clements, SRS Watch – 803.240.7268 | Email
Scott Yundt, TVC – 415.990.2070 | Email
Jay Coghlan – 505.989.7342 | Email

Nearly three years after filing a Freedom of Information Act request, the public interest group Savannah River Site Watch has finally received the National Nuclear Security Administration’s (NNSA’s) congressionally-required “Research Program Plan for Plutonium and Pit Aging.” However, the document is 40% blacked out, including references and acronyms. Plutonium “pits” are the radioactive cores of all U.S. nuclear weapons. The NNSA claims that potential aging effects are justification for a ~$60 billion program to expand production. However, the Plan fails to show that aging is a current problem. To the contrary, it demonstrates that NNSA is delaying urgently needed updated plutonium pit aging research.

In 2006 independent scientific experts known as the JASONs concluded that plutonium pits last at least 85 years without specifying an end date [i] (the average pit age is now around 40 years). A 2012 follow-on study by the Lawrence Livermore nuclear weapons lab concluded:

“This continuing work shows that no unexpected aging issues are appearing in plutonium that has been accelerated to an equivalent of ~ 150 years of age. The results of this work are consistent with, and further reinforce, the Department of Energy Record of Decision to pursue a limited pit manufacturing capability in existing and planned facilities at Los Alamos instead of constructing a new, very large pit manufacturing facility…” [ii]

Since then NNSA has reversed itself. In 2018 the agency decided to pursue the simultaneous production of at least 30 pits per year at the Los Alamos National Laboratory (LANL) in northern New Mexico and at least 50 pits per year at the Savannah River Site (SRS) in South Carolina. Upgrades to plutonium facilities at LANL are slated to cost $8 billion over the next 5 years. The redundant Savannah River Plutonium Processing Facility in South Carolina will cost up to $25 billion, making it the second most expensive building in human history.

Continue reading

NNSA’s Nuclear Weapons Budget Takes Huge Jump

Arms Race Accelerates with MIRVed Warheads
Los Alamos Lab Cleanup Cut

FOR IMMEDIATE RELEASE, March 11, 2024
Jay Coghlan – 505.989.7342 | Email

Santa Fe, NM – Ironically the day after the film Oppenheimer was awarded multiple Oscars, the Department of Energy’s semi-autonomous National Nuclear Security Administration (NNSA) asked Congress for its biggest nuclear weapons budget ever. NNSA’s FY 2025 request for “Total Weapons Activities” is $19.8 billion, $700 million above what Congress recently enacted for FY 2024. It is also a full billion dollars above what President Biden asked for last year, which Congress then added to and will likely do so again.

The Biden Administration states that the $19.8 billion will be used to:

“[P]rioritize implementation of the 2022 National Defense Strategy and Nuclear Posture Review by modernizing the Nation’s nuclear deterrent to keep the American people safe. The Budget supports a safe, secure, reliable, and effective nuclear stockpile and a resilient, responsive nuclear security enterprise necessary to protect the U.S. homeland and allies from growing international threats.” whitehouse.gov/wp-content/uploads/2024/03/budget_fy2025.pdf, page 75.

The 2022 National Defense Strategy and Nuclear Posture Review for the first time posited two nuclear “near peers”, i.e. Russia and China, that need to be simultaneously “deterred.” This hinted at a potentially large nuclear buildup which this budget may now be implementing. That claimed need to deter two nuclear near peers was explicitly taken a step beyond just deterrence in an October 2023 report from the Strategic Posture Commission. It declared:

“Decisions need to be made now in order for the nation to be prepared to address the threats from these two nuclear-armed adversaries arising during the 2027-2035 timeframe. Moreover, these threats are such that the United States and its Allies and partners must be ready to deter and defeat both adversaries simultaneously.” ida.org/research-and-publications/publications/all/a/am/americas-strategic-posture, page vii (bolded emphasis added)

Continue reading

NNSA Suppresses How Taxpayers Money Is Spent

FOR IMMEDIATE RELEASE, January 19, 2024
Jay Coghlan – 505.989.7342 | Email

Santa Fe, NM – The National Nuclear Security Administration (NNSA) has just released cursory two or three page summaries of contractors’ performance paid for by the American taxpayer. For the just ended fiscal year 2023, NNSA gave nothing less than grades of “Excellent” or “Very Good” in six broad mission goals for its major contractors. This is despite the constant cost overruns and schedule delays that are the rule, not the exception, in the nation-wide nuclear weapons complex. NNSA and its parent Department of Energy have been on the Government Accountability Office’s “High Risk List” for project mismanagement ever since GAO started that List in 1991.

NNSA Suppresses How Taxpayers Money Is SpentA current example is the Uranium Processing Facility (UPF) at the Y-12 Plant near Oak Ridge, Tennessee, originally estimated in 2011 to cost $1.4 to $3.5 billion. After costs started going through the roof, NNSA and Senator Lamar Alexander (R.-TN), then-chair of Senate Energy and Water Appropriations, swore that UPF would never go over $6.5 billion. But even after eliminating non-nuclear weapons production missions and a formal decision to continue operations at two old, unsafe buildings slated for replacement, the Uranium Processing Facility is now estimated to cost $8.5 billion. However, even that is not the final price, as NNSA is still to “rebaseline” UPF costs at some unspecified date.

Continue reading

2023

It seems we can’t find what you’re looking for. Perhaps searching can help.

RECENT FACT SHEETS

It seems we can’t find what you’re looking for. Perhaps searching can help.

RECENT PRESS RELEASES

It seems we can’t find what you’re looking for. Perhaps searching can help.

RECENT NUCLEAR BUDGET GRAPHS

It seems we can’t find what you’re looking for. Perhaps searching can help.

Past Work Product (2020-2021)

It seems we can’t find what you’re looking for. Perhaps searching can help.

75TH ANNIVERSARY HIROSHIMA DAY ONLINE COMMEMORATION CALLING FOR THE ABOLITION OF NUCLEAR WEAPONS
August 6, 2020

"Jay Coghlan of Nukewatch.org on the history of the Los Alamos labs, where the bomb was designed and fabricated, and how it continues to play the leading role in the creation of most U.S. nuclear weapons since then."

[embeddoc url="https://nukewatch.org/wp-content/uploads/2020/05/plutonium-pit-production-fact-sheet.pdf" download="all" viewer="browser"]

PLUTONIUM PIT PRODUCTION WORKSHOP – NOVEMBER 19, 2019

RADIO INTERVIEW – SCOTT KOVAC & JON LIPSKY

Scott Kovac of Nuclear Watch New Mexico and Jon Lipsky, the FBI agent who led the 1989 raid investigating environmental crimes that shut down the Rocky Flats Nuclear Bomb Plant join Xubi to talk about Nuclear weapons, Nuclear clean up and Pit production plans at LANL.

livingontheedge.libsyn.com

RADIO INTERVIEW – JAY COGHLAN & JON LIPSKY

PIT Production at LANL with Nuclear Watch New Mexico’s Jay Coghlan and Workshop Speaker, Jon Lipsky

The Richard Eeds Show 11/18

RADIO INTERVIEW – MARYLIA KELLEY, EXECUTIVE DIRECTOR, TRI-VALLEY CARES

Nuclear Watch NM’s Workshop on LANL & PIT Production with Marylia Kelley of Tri-Valley CARES

The Richard Eeds Show 11/19


Pit Production Workshop: View the Presentations

Jon Lipsky, FBI agent that led the 1989 raid investigating environmental crimes that shut down the Rocky Flats bomb plant

Introduction by Jay Coghlan

Jay Coghlan, Executive Director, Nuclear Watch New Mexico, on plutonium pit production at LANL

Marylia Kelly, Executive Director, Tri-Valley CAREs (Livermore, CA) on the new nuclear arms race

https://www.facebook.com/NukeWatch.NM/videos/825812604488302/

Scott Kovac Nuclear Watch New Mexico, on LANL cleanup issues

Blog Posts

LANL Gestures to Gas Shortage

In response to statewide natural gas outages across New Mexico, LANL closed February 4th. The gesture may reflect that LANL gas use is roughly the equivalent[1] of 22,310 people, nearly the same as the 25,000 people that media reports are without recent service.

Although shutting down LANL would almost make up for the shortage in gas affecting northern New Mexico, it is not quite that equitable. LANL and the Los Alamos town site have their own dedicated gas pipeline coming from the NW San Juan Basin, in New Mexico. Whereas Albuquerque, Santa Fe, Espanola, Taos etc are fed natural gas from the Permian Basin gas fields in Texas. Therefore it is questionable that curtailing operations (which cost taxpayers ~$6 million/per day) at LANL helps to relieve gas supplies in northern New Mexican communities.

It also begs the question of why aren’t Northern New Mexico gas supplies coming from the plentiful San Juan basin, one of the largest reserves in the nation, which is geographically closer? Espanola and Taos are reportedly suffering in recent subzero temperatures because they are at the “end of the line” of gas coming from Texas. But the privileged Lab and Los Alamos town site would not be subject to the same short supply.


[1] According to the 2006 LANL Site-Wide Environmental Impact Statement the Lab uses an average of 37.4 million cubic meters of natural gas annually, or 1.32 billion cubic feet (1 cubic meter = 35.31 cubic feet). Wikipedia says Americans use 18.4 trillion cubic feet per year. U.S. population is around 311 million people, hence per person use = 59,164 cubic ft/yr. Population of Espanola = ~10,000, hence uses ~ 591,640,000 cubic ft/yr. Population of Taos = 5,550, hence uses ~ 328,360,200 cubic ft/yr. Therefore, LANL uses twice as natural gas as Espanola, 4 times as much as Taos. TA-55 (site of plutonium pit production) alone uses 45 million cubic ft per year.

Nuclear Science Week, by the makers of the “Bomb”

This press release from NNSA is really deceptive. The words “nuclear” and “science” are used quite a bit, but “weapons” only like in “As we continue to turn a Cold War nuclear weapons complex into a 21st century nuclear security enterprise.” The uninformed reader would get the impression that NIF, DARHT and the Z machine are not really about nuclear weapons, when of course they are.

Also, the uninformed might get the impression that the National Ignition Facility has already achieved ignition, which couldn’t be farther from the truth (and it’s doubtful that NIF ever will achieve ignition). Nor is DARHT yet working as advertised, even after more than a decade of operations.  And then there are the cost overruns: NIF from ~$1 billion to ~$5 billion and DARHT from ~$35 million to ~$275 million, not including dubious reprogramming of other monies for both projects.

And supercomputers fighting AIDS and bringing “products to market faster” (can you spell j-o-b-s?). It’s a wonderful world, this “21st century nuclear security enterprise.”

I cringe to think that a congressional staffer (or anybody) would read stuff like this and think it true.

NNSA Will Not be “Burdened” by Costs for Clean-Up at New KCP

I found what I think is an interesting quote concerning the new KCP  in NNSA’s FY 2011 Stockpile Stewardship and Management Plan (which is the plan that NNSA showboats to Congress).

“Finally, because the new facility [KCP] will be leased, there will be no capital investment and NNSA will not be burdened by costs for legacy disposition should the mission ever be discontinued.”   NNSA FY11 SSMP Annex D, p. 44,

This sounds to me like the federal government is walking away from any future obligation to clean up any contamination at the new Kansas City Plant. I think that interesting given how there is no real federal commitment to clean up the old plant which is badly contaminated.

The rest of NNSA’s FY 2011 Stockpile Stewardship and Management Plan (summary and Annex A) can be viewed.
Annex B and C are classified.

If NNSA won’t be burdened for clean-up, who will?

Weight Restrictions for Weapons Workers?

Question: What is the tripping-man impact scenario for a nuclear weapons production technician?

Answer: A 280 lb production technician traveling 2 .5 miles per hour.

We are all familiar with the horrible impacts that nuclear weapons have on humans, but now we have an Analysis of Human Impacts on Weapons. The Defense Nuclear Facilities Safety Board (Board) recently reviewed the Hazard Analysis Reports (HARs) for several nuclear explosive operations at the Pantex Plant and found that Plant could have a weight problem with its production technicians (PTs).

Of concern is that the weapons design agency supplies data on weapons responses for “tripping-man impact scenarios” based on the energy imparted by a 280 lb PT traveling 2.5 miles per hour. Tools and parts could break if someone larger tripped into a warhead while going faster that 2.5 mph. And Pantex has no controls in place to limit these human impact energies.

The DNFSB concluded that the “maximum PT impact energy does not represent an uncontrolled environment, such as lightning, earthquake, or meteorological conditions.” Pantex imposes other physical qualifications for PTs (such as age, sight, speech), as well as other limitations specified by the Human Reliability Program. They believe that weapon responses should be reevaluated for higher impact energies, or that Pantex should limit PT weights.

Once Again – It’ll Cost More and Take Longer

Decades of nuclear materials production at the Department of Energy’s (DOE) Savannah River Site in South Carolina have left 37 million gallons of radioactive liquid waste in 49 underground storage tanks. This is just a small part of DOE’s Cold War cleanup legacy that currently has an estimate of $360+ billion to remediate across the country. This estimate keeps going up.

The United States Government Accountability Office released a September 2010 report about persistent concerns with efforts to cleanup these underground radioactive waste tanks. Like so many GAO reports before, the findings are that it will cost more and take longer:

Emptying, cleaning, and permanently closing the 22 underground liquid radioactive waste tanks at the Savannah River Site is likely to cost significantly more and take longer than estimated in the December 2008 contract between DOE and Savannah River Remediation, LLC (SRR). Originally estimated to cost $3.2 billion, SRR notified DOE in June 2010 that the total cost to close the 22 tanks had increased by more than $1.4 billion or 44 percent. Much of this increase is because DOE’s cost estimate in the September 2007 request for proposals that formed the basis of the December 2008 contract between DOE and SRR was not accurate or comprehensive.

Legacy cleanup at Los Alamos is currently estimated by the Lab to be around $2-3 billion.  This is required to be complete by 2015 by a consent Order agreement with the State of NM.  This estimate includes the Lab’s version of cleanup, which is leaving most the waste in the ground perched above our aquifer. Actually removing the waste is estimated at $20 billion. The final decision on what type of cleanup will be made by the State, which would like to have you the public’s input.

Cleanup at Los Alamos is one project that needs to cost more.

CMRR is Key to Expanded Plutonium Pit Production

While being narrowly correct, LANL PR man Kevin Roark is misleading when he claims [in a June 25, Letter to the Editor of the Santa Fe New Mexican  newspaper] that plutonium pit production will not take place in the new Chemistry and Metallurgy Research Replacement Project (CMRR). What he fails to disclose is that the Lab is not building just one facility, but instead is creating an integrated manufacturing complex for expanded production for which the CMRR is absolutely key. This complex will consist of LANL’s existing production facility “PF-4” with ~$300 million in upgrades; CMRR’s already completed first phase, the $400 million “Rad Lab”; and the future $4 billion CMRR “Nuclear Facility,” now being debated.

The Nuclear Facility will be literally next door to PF-4 and linked to it via underground tunnel. While pits are physically manufactured in PF-4’s glovebox lines, the Nuclear Facility’s central missions of “materials characterization” and “analytical chemistry” are essential operations that ensure “weapons-grade” plutonium and pit production quality control. The National Nuclear Security Administration’s own documents show that the Nuclear Facility is being specifically sized to support expanded production of up to 80 pits per year, quadruple LANL’s currently approved rate. It is also planned to have a vault for up to six metric tons of “special nuclear materials,” capable of storing around 1,000 pits.

Roark must think that New Mexicans are naïve enough to accept the Lab’s claims that the CMRR is all about “science” even as LANL becomes more and more a production site. Sadly, this is only part and parcel of the substantial rebuilding of the U.S. nuclear weapons production complex, which will also include a new $3.5 billion Uranium Processing Facility in Tennessee and a new privately financed Kansas City Plant for production of the 1,000’s of nonnuclear components that go into a nuclear weapon.

Many New Mexicans hoped for serious mission diversification at Los Alamos, which some $5 billion sunk into its plutonium infrastructure will almost certainly shut the door on. Schools in Santa Fe and all across the country are being closed due to lack of funding. Nevertheless, our government is preparing to spend some $10 billion to build new production plants even as we are purportedly working toward the declared long-term national security goal of a nuclear weapons-free world. To get there, citizens need to push the politicians to meet the needs of everyday people, not those of the vested nuclear weaponeers.

Revised Estimates for Safer Gloveboxes Hurt Budget

On the heels of a GAO report made public Monday, which stated that accounting procedures used by various branches of the U.S. nuclear weapons complex are preventing NNSA from pinpointing the exact total cost of maintaining its nuclear deterrent, the Defense Nuclear Facilities Safety Board (DNFSB) has released a weekly report also showing LANL’s inability to accurately estimate even the tiniest of specific costs.

In the June 4th weekly report for Los Alamos Lab, the DNFSB stated that the Lab underestimated the cost of seismically upgrading gloveboxes at its plutonium pit production complex by an order of magnitude. The DNFSB stated, “…the expected cost of seismic upgrades to individual gloveboxes has risen from an original estimate of about $80,000 per glovebox to a current estimate of approximately $850,000.” In addition, the Lab also ended up doubling the number of gloveboxes that need the upgrades as a priority up to 157.

So, in effect, the Labs original estimate for this glovebox work was $6.4 million (80 gloveboxes at $80,000 each), but the revised estimate is now $133.4 million (157 gloveboxes at $850,000 each). It’s hard to understand how new bracing and bolts to upgrade the legs of these gloveboxes could cost $80,000 each, much less $850,000. It’s not rocket science. Maybe the private corporation running the Lab underestimated the profits that they wanted to make for this much-needed work.  Make no mistake, there will be performance- based incentive award fees  for the work, as well as for the design and even the estimates.

In safety documents, the Lab originally stated that these upgrades would be done by 2011 to mitigate the possible off-site dose of plutonium to the public in the event of a large earthquake and subsequent facility fire. Guess what? The Lab will be behind schedule as well as way over budget. But LANL is already using its commitment for future glovebox seismic upgrades to reduce the mitigated dose consequence for a seismically-induced event in its dose calculations. So the public will be safe, only on paper, until the Lab finds the time and the money to upgrade those glovebox legs.

The Lab should focus on upgrading existing facilities and equipment and prove its ability and desire to protect the public before embarking on unneeded new construction, such as the CMRR – Nuclear Facility.

A Bargain – But At What Cost?

The Government Accounting Office (GAO) released a new report today. Actions Needed to Identify Total Costs of Weapons Complex Infrastructure and Research and Production Capabilities, GAO-10-582, June 2010

I’ll start with the conclusion –

Within the global community, the Administration, and Congress, a bargain is being struck on nuclear weapons policy. Internationally, if the [START] treaty is ratified, significant stockpile reductions [will] have been negotiated between the United States and Russia. Domestically, a new Nuclear Posture Review has provided an updated policy framework for the nation’s nuclear deterrent. To enable this arms reduction agenda, the Administration is requesting from Congress billions of dollars in increased investment in the nuclear security enterprise to ensure that base scientific, technical, and engineering capabilities are sufficiently supported … For its part, NNSA must accurately identify these base capabilities and determine their costs in order to adequately justify future presidential budget requests and show the effects on its programs of potential budget increases. As it now stands, NNSA may not be accurately identifying the costs of base capabilities because … NNSA cannot identify the total costs to operate and maintain essential weapons activities facilities and infrastructure, … Without taking action to identify these costs, NNSA risks being unable to identify the return on investment of planned budget increases on the health of its base capabilities or to identify opportunities for cost saving…NNSA has the opportunity to mitigate these risks by addressing them through the ongoing revision of work breakdown structures and through identifying means of collecting the total costs … Without taking these actions, NNSA will not have the management information it needs to better justify future budget requests by making its justifications more transparent. Additionally, the availability of this information will assist Congress with its oversight function. (Pg. 25)

It looks like NNSA does not know exactly the total costs of its infrastructure budget, but it does know that it wants more. The report tells us that without identifying the total costs of products and capabilities, NNSA will be challenged to explain the effects of funding changes or justify the necessity for increased investment to support or enhance base capabilities. (Pg. 25)

The reduction in nuclear warhead numbers will mean an increase spending. “In such an environment, NNSA is likely to face increased scrutiny of its planning, programming, and budget execution to determine the effect of funding increases on the overall health of base capabilities.” (Pg. 24)

Curating the Stockpile: Remanufacturing Fogbank

I only now happened to run across the article below from the Los Alamos National Laboratory Nuclear Weapons Journal about how the remanufacturing of Fogbank was reestablished. As dated as it is, I think its implication is very important that existing programs are more than sufficient to keep the nuclear weapons stockpile safe and reliable, until eventual disarmament.

You may recall that the loss of Fogbank was a bit of a crisis that seriously delayed the W76 Life Extension Program. It had at various times been used as rationale for why existing LEPs would not work in the long run because of necessary changes to materials, loss of knowledgeable workforce, etc. By extension this was used to argue why Reliable Replacement Warheads should be designed and built.

But this article demonstrates that all that was needed was to simply give some emphasis to reestablishing fogbank production. Plus as an added bonus, it has some pleasing wonky detail. “It’s the impurity, stupid!” [see link below]

LANL Nuclear Weapons Journal, Issue 2 • 2009, pp. 21-22
Fogbank: Lost Knowledge Regained

Power of the Purse over DOE Projects

I was in Washington, DC last week and heard a number of congressional offices express support for the CMRR-Nuclear Facility, indicating what we already know, that it will be very difficult to defeat directly. However, the issue of costs is another matter, and I have some hope that the Nuclear Facility can die a death of 1,000 cuts.

For example, while in DC I met with a staff person knowledgeable about DOE project cost accounting requirements introduced by the Senate Armed Services Committee. I expressed my concern that LANL could implement its first segment of CMRR-Nuclear Facility construction without having come up with total costs, thus steamrolling the project.  [Reminder: we are now $4.5 billion for estimated total project costs and climbing.]  That staffer said that sort of thing will not be allowed to happen. Further, while being in favor of some advance site prep, that staffer said LANL would not be allowed to construct the concrete batch plant and replace 225,000 cubic yards of weak volcanic ash strata with “lean concrete” until total project costs are in.

The requirements were introduced as SEC. 4713. NOTIFICATION OF COST OVERRUNS FOR CERTAIN DEPARTMENT OF ENERGY PROJECTS.

I realize this is not a showstopper, but it is something. It should slow the CMRR-NF down some, which hopefully we can capitalize on. Further, it may provide us with ammo over the project’s tremendous and escalating costs.

Nick Roth of the Alliance for Nuclear Accountability was instrumental in suggesting this cost accounting requirement to Congress.

2019


Proposed LANL Campus in Santa Fe

Read/Download the Full Press Release HERE


Pope Frances Calls for Nuclear Weapons Abolition

Read/Download the Full Press Release HERE


VIEW LIVE RECORDING & WORKSHOP RESOURCES

Presenters:

  • Jon Lipsky, FBI agent that led the 1989 raid investigating environmental crimes that shut down the Rocky Flats bomb plant
  • Jay Coghlan, Executive Director, Nuclear Watch New Mexico, on plutonium pit production at LANL
  • Marylia Kelley, Executive Director, Tri-Valley CAREs (Livermore, CA) on the new nuclear arms race
  • Scott Kovac, Nuclear Watch New Mexico, on LANL cleanup issues

NukeWatch’s 22-page formal comments on expanded plutonium pit production

Until NNSA fully complies with the National Environmental Policy Act through the preparation of a programmatic environmental impact statement on expanded plutonium pit production, Nuclear Watch believes that any irreversible or irretrievable commitment of resources to either the expansion of pit production at the Los Alamos Lab or to the repurposing of the MOX Facility at the Savannah River Site is unlawful.

Read/Download the Full Document HERE


Scoping comments on NNSA draft EIS for plutonium pit production at the Savannah River Site

THE NEED FOR A PROGRAMMATIC ENVIRONMENTAL IMPACT STATEMENT: This is our first and primary concern, that NNSA must first complete a programmatic environmental impact statement (PEIS) on its nation-wide plans for plutonium pit production, in advance of the Savannah River Site-specific environmental impact statement. To get right to the point, we argue that the SRS EIS process should go no further than this scoping period and should resume only after a completed formal Record of Decision for a new or supplemental PEIS.

Read/Download the Full Document HERE


Expanding Nuclear Pit Production: The Facts and What You Can Do

The Facts
• The Trump administration wants the United States to produce 80 plutonium pits per year
by 2030 without offering any concrete justification for the additional nuclear bomb cores.
• Multiple studies by government agencies have found that pits last for at least 100 years.
The average pit in the US stockpile is around 36 years old.
• More than 15,000 existing pits are already stored at the Pantex Plant near Amarillo, TX.
• Independent experts find it nearly impossible that the Los Alamos National Laboratory
and the Savannah River Site will be able to meet the 80 pit per year by 2030 requirement,
and billions of taxpayer dollars will be thrown down the drain in the meantime.

Read/Download the Full Document HERE


Federal Government Meets Watchdogs’ Demand for Environmental Review of Expanded Plutonium Pit Production

In a victory for transparency and legal compliance by the government, the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) today published a “Notice of Intent” in the Federal Register to complete environmental reviews on its controversial proposal to expand plutonium “pit” production for new and refurbished nuclear weapons.

[embeddoc url="https://nukewatch.org/wp-content/uploads/2019/06/SRS-plutonium-bomb-plant6-14-19.pptx" download="all" viewer="google"]

Read/Download the Full News Release HERE


Noted Environmental Lawyers Warn Government Not to Expand Production of Plutonium Bomb Cores in Violation of National Environmental Policy Act and Public Review

On behalf of three public interest organizations - Nuclear Watch New Mexico, Tri-Valley Communities Against a Radioactive Environment and Savannah River Site Watch – attorneys for the law firm of Meyer Glitzenstein & Eubanks and the Natural Resources Defense Council recently sent a 16-page letter to Lisa Gordon-Hagerty, head of the National Nuclear Security Administration (NNSA). The detailed letter warns the nuclear agency to not proceed with aggressive plans to expand plutonium pit production without first meeting its legal requirements for timely public review and comment under the National Environmental Policy Act.

Read/Download the Full Press Release HERE


Faulty Radioactive Liquid Waste Valves Raise Crucial Plutonium Pit Production and Safety Board Issues

Last Wednesday, facility operations personnel entered a service room and noticed a leak emanating from a valve on the radioactive liquid waste (RLW) system. Upon subsequent visual inspection by a radiological control technician, RLUOB engineers believe that this valve, and 6 similar valves, may be constructed of carbon steel. The RLW system handles radioactive liquid waste streams from chemistry operations that include nitric and hydrochloric acids—carbon steel valves would be incompatible with these solutions. The suspect valves are also in contact with stainless steel piping, which would create another corrosion mechanism. RLUOB management plans to drain the affected piping sections and develop a work package to replace all of the suspect valves. They will also confirm the valve materials and if shown to be incorrect, investigate the cause of this failure in the design, procurement, and installation processes. The valves were installed in 2013 as part of a modification to add straining and sampling capabilities that were not in the included in the original design. [Please note that DNFSB reports are posted a few weeks later than dated.]

This immediately raises two crucial issues: 1) the National Nuclear Security Administration’s (NNSA’s) plans for expanded plutonium pit production; and 2) the current attempt by the Department of Energy to restrict Safety Board access to its nuclear weapons facilities.

Read/Download the Full Press Release HERE


A Tale of Two Consent Orders and What Is Needed

On March 1, 2005, after arduous negotiations and threats of litigation, the New Mexico Environment Department (NMED), Department of Energy (DOE), and Los Alamos National Laboratory (LANL) entered into a Consent Order specifying the schedule for investigation and cleanup of the Lab’s hundreds of contaminated sites. This Consent Order (CO) was LANL’s agreement to fence-to-fence cleanup of Cold War legacy wastes, which NMED began to enforce.

Read/Download the Full Comparison HERE


Global Nuclear Weapons Threats Are Rising

More than 25 years after the end of the Cold War, all eight established nuclear weapons powers are “modernizing” their stockpiles. Talks have broken down with North Korea, the new nuclear weapons power. Nuclear-armed India and Pakistan narrowly averted war last month. Russian President Vladmir Putin made new nuclear threats in response to Trump’s announced withdrawal from the Intermediate-Range Nuclear Forces Treaty. This could lead to hair-trigger missile emplacements in the heart of Europe and block extension of the New Strategic Arms Reduction Treaty with Russia. If so, the world will be without any nuclear arms control at all for the first time since 1972. Meanwhile, the U.S. criticizes non-weapons states for signing a nuclear weapons ban treaty, despite the fact there have long been treaties completely banning chemical and biological weapons of mass destruction that the U.S. seeks to enforce. The pending international NonProliferation Treaty (NPT) Preparatory Committee conference at the United Nations is widely expected to collapse in failure because of the nuclear weapons powers’ failure to enter into serious negotiations leading to nuclear disarmament. The NPT’s Article VI mandate for those negotiations has been in effect since 1970, when the Treaty was signed by 189 countries (more than any other treaty).

Read/Download the Full Press Release HERE



Nuclear Watch New Mexico — Department of Energy FY 2020 Nuclear Weapons Budget Request

Read/Download the Full Budget Compilation HERE


2018


Expanded Plutonium Pit Production for U.S. Nuclear Weapons

Plutonium pits are the radioactive cores or “triggers” of nuclear weapons. Their production has always been a chokepoint of resumed industrial-scale U.S. nuclear weapons production ever since a 1989 FBI raid investigating environmental crimes shut down the Rocky Flats Plant near Denver. In 1997 the mission of plutonium pit production was officially transferred to its birthplace, the Los Alamos National Laboratory (LANL) in northern New Mexico, but officially capped at not more than 20 pits per year. However, in 2015 Congress required expanded pit production by 2030 whether or not the existing nuclear weapons stockpile actually needs it. This will support new military capabilities for nuclear weapons and their potential use.

Read/Download the full fact sheet pdf HERE


Watchdog Groups Claim Nuclear Agency is Moving Forward to Manufacture New Plutonium Bomb Cores in Violation of National Environmental Law and Public Review

Nuclear Watch New Mexico, Savannah River Site Watch, and Tri-Valley CAREs sent a letter of demand to the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) to inform the government that its plan to quadruple the production rate of plutonium bomb cores is out of compliance with the National Environmental Policy Act (NEPA).

NNSA’s premature plan to quadruple the production rate of plutonium bomb cores (“pits”), the heart of all US nuclear weapons, is out of compliance with requisite environmental law, the groups argue, as NNSA has failed to undertake a legally-mandated programmatic review and hold required public hearings.

View/Download the entire press release HERE


DNFSB Hearing - Formal Comments

Nuclear Watch New Mexico is submitted formal comments to express in the strongest possible terms our opposition to DOE Order 140.1 Interface with the Defense Nuclear Facilities Safety Board. We find that the Department of Energy’s (DOE’s) attempt to restrict and suppress DNFSB access is very misguided, arrogant, and likely illegal in that it acts contrary to the Board’s enabling legislation.

Read the comments here


New Contractors Selected For Expanded Nuclear Weapons Production at Los Alamos

Santa Fe, NM. Today the Department of Energy's National Nuclear Security Administration (NNSA) announced its choice for the new management and operating contract for the Los Alamos National Laboratory (LANL).The new contractor, Triad National Security, LLC, is a limited liability company consisting of the Battelle Memorial Institute, the University of California and Texas A&M University. All three are non-profits, and it is unclear how this will affect New Mexico gross receipts taxes.

Battelle claims to be the world's largest non-profit technology research and development organization, and manages a number of labs including the Lawrence Livermore and Idaho National Laboratories. Texas A&M was founded in 1876 as the state's first public institution of higher learning and has the largest nuclear engineering program in the country. DOE Secretary Rick Perry is an avid A&M alumnus.

View/download full press release


Groups Release Key DOE Documents on Expanded Plutonium Pit Production, DOE Nuclear Weapons Plan Not Supported by Recent Congressional Actions

Santa Fe, NM & Columbia, SC - "Two key U.S. Department of Energy documents on future production of plutonium "pits" for nuclear weapons, not previously released to the public, fail to justify new and upgraded production facilities at both the Los Alamos National Laboratory (LANL) in New Mexico and the Savannah River Site (SRS) in South Carolina."

View/download press release


Los Alamos Cleanup

View/download Fact sheet


What's Not in NNSA's Plutonium Pit Production Decision

 

- NNSA did not mention that up to 15,000 "excess" pits are already stored at the Pantex Plant near Amarillo, TX, with up to another 5,000 in "strategic reserve." The agency did not explain why new production is needed given that immense inventory of already existing plutonium pits. (In 2006 independent experts found that pits last a least a century. Plutonium pits in the existing stockpile now average around 40 years old.)
- NNSA did not explain how to dispose of all of that plutonium, given that the MOX program is an abysmal failure. Nor is it made clear where future plutonium wastes from expanded pit production will go since operations at the troubled Waste Isolation Pilot Plant are already constrained from a ruptured radioactive waste barrel, and its capacity is already overcommitted to existing radioactive wastes. View/download Press Release


NNSA Proposal to Raise Plutonium Limit Ten-Fold in Los Alamos' Rad Lab Is First Step in Expanded Plutonium Pit Production: Environmental Assessment Is Premature and Deceptive By Omission

"NNSA should begin nation-wide review of plutonium pit production, why it's needed, and what it will cost the American taxpayer in financial, safety and environmental risks. These are all things that the public should know." -Jay Coghlan, Director, Nuclear Watch New Mexico.

View/download Press Release


LANL Rad Lab: Formal Comments Under Nat'l Environmental Policy Act

Against raising plutonium limit at LANL Rad Lab

View/download Nuclear Watch comments as submitted

Excerpt:
"This Draft Rad Lab EA is deficient. There are major omissions, for example the lack of analyses of potential beryllium hazards and Intentional Destructive Acts. Moreover, safety, occupational and seismic risks are explained away in "preliminary analyses." All this should be corrected in a more complete environmental impact statement, including final and transparent analyses of safety and seismic risks...

"NNSA should proceed with a broader environmental impact statement after its May 11 decision on the future of expanded plutonium pit production."

- NNSA is planning a 10-fold increase in plutonium at the LANL Rad Lab with a view to ramping up the production of plutonium pits for new nuclear weapons.
- NNSA wants to re-categorize the Rad Lab from a "radiological facility" to a "Hazard Category-3" nuclear facility.
- (See details in our press release)
- National Environmental Policy Act


United States To Begin Construction Of New Nuclear Bomb Plant

The National Nuclear Security Administration (NNSA) announced on Friday, March 23, that it was authorizing the start of construction of the Uranium Processing Facility (UPF) and two sub-projects at the Y-12 National Security Complex in Oak Ridge, Tennessee. The UPF is a facility dedicated solely to the manufacture of thermonuclear cores for US nuclear bombs and warheads.
Citizen watchdog groups are responding by filing an expedited Freedom of Information Act request demanding a full fiscal accounting of the UPF bomb plant- something the NNSA has refused to provide for the last five years, including to Congress, despite repeated assurances that the project is "on budget."

"This project is already a classic boondoggle, and they are just getting started," said Ralph Hutchison, coordinator of the Oak Ridge Environmental Peace Alliance (OREPA) in Knoxville, Tennessee. "Worse, it undermines US efforts to discourage nuclear proliferation around the world. How can we oppose the nuclear ambitions of other countries when we are building a bomb plant here to manufacture 80 thermonuclear cores for warheads every year?"

Jay Coghlan of NukeWatch points out that "This project already has a long history, and it is instructive. In 2013, DOE announced it was 85% finished with the UPF design when it ran into the 'space/fit' issue- and more than a half-billion taxpayer dollars were just written off. In private business, that kind of thing gets you fired. In DOE's world of contractors running amok, they not only didn't get fired, not one Congressional hearing was held and the UPF budget went up the next year!"

- See full press release for all the details (PDF)
- View/download the OREPA/NukeWatch FOIA request (pdf)


The Regional Coalition of LANL Communities: Benefits for the Select Few

Santa Fe, NM- According to media reports, Andrea Romero, Executive Director of the Regional Coalition of LANL Communities, is accused of charging some $2,200 dollars of unallowable travel costs, such as alcohol and baseball tickets, while lobbying in Washington, DC for additional funding for the Los Alamos National Laboratory (LANL). She in turn accused the nonprofit group Northern New Mexico Protects of political motivations in revealing these questionable expenses. Romero is running in the Democrat Party primary against incumbent state Rep. Carl Trujillo for Santa Fe County's 46th district in the state House of Representatives.
Perhaps more serious is the fact that Romero was awarded an undisclosed amount of money by the Venture Acceleration Fund (VAF) for her private business Tall Foods, Tall Goods, a commercial ostrich farm in Ribera, NM. According to a May 8, 2017 Los Alamos Lab news release announcing the award to Tall Foods, Tall Goods, "The VAF was established in 2006 by Los Alamos National Security [LANS], LLC to stimulate the economy by supporting growth-oriented companies."[1] LANS, primarily composed of the Bechtel Corporation and the University of California, has held the annual ~$2.4 billion Los Alamos National Laboratory (LANL) management contract since June 2006.

For all the details, see full press release PDF


Major LANL Cleanup Subcontractor Implicated in Fraud - Entire Los Alamos Cleanup Should Be Re-evaluated

Santa Fe, NM. On December 17, 2017, the Department of Energy (DOE) awarded a separate $1.4 billion contract for cleanup at the Los Alamos National Laboratory (LANL) to Newport News Nuclear BWXT-Los Alamos, LLC (also known as "N3B"). This award followed a DOE decision to pull cleanup from LANL's prime contractor, Los Alamos National Security, LLC (LANS), after it sent an improperly prepared radioactive waste drum that ruptured underground at the Waste Isolation Pilot Plant (WIPP). That incident contaminated 21 workers and closed WIPP for nearly three years, costing taxpayers at least $1.5 billion to reopen.
Tetra Tech Inc is a major subcontractor for N3B in the LANL cleanup contract... Serious allegations of fraud by Tetra Tech were raised long before the LANL cleanup contract was awarded. The US Navy found that the company had committed wide spread radiological data falsification, doctored records and supporting documentation, and covered-up fraud at the Hunters Point Naval Shipyard cleanup project in San Francisco, CA. See media links and excerpts below..."

(See all the details in the full press release)


Detailed NNSA Budget Documents Accelerates Nuclear Weapons Arms Race

Santa Fe, NM. Late Friday February 23, the Trump Administration released the detailed FY 2019 budget for the National Nuclear Security Administration (NNSA), the semi-autonomous nuclear weapons agency within the federal Department of Energy. Overall, NNSA is receiving a $2.2 billion boost to $15.1 billion, a 17% increase above the FY 2018 enacted level. Of that, a full $11 billion is for the budget category [Nuclear] "Weapons Activities", 18% above the FY 2018 level. Of concern to the American taxpayer, DOE and NNSA nuclear weapons programs have been on the congressional Government Accountability Office's High Risk List for project mismanagement, fraud, waste and abuse since its inception in 1990...

(See all the details in the full press release)


NNSA Releases Draft Environmental Assessment for LANL Rad Lab; Raises Plutonium Limit 10 Times for Expanded Pit Production

Santa Fe, NM. Today the National Nuclear Security Administration announced an Environmental Assessment to increase the amount of plutonium used in the Radiological Laboratory Utility and Office Building (aka the "Rad Lab") at the Los Alamos National Laboratory from 38.6 grams of plutonium-239 equivalent to 400 grams. This 10-fold increase is significant because it will dramatically expand materials characterization and analytical chemistry capabilities in the Rad Lab in support of expanded plutonium pit production for future nuclear weapons designs. It also re-categorizes the Rad Lab from a "radiological facility" to a "Hazard Category-3" nuclear facility.

View/Download full press release


Trump's Budget Dramatically Increases Nuclear Weapons Work

Santa Fe, NM In keeping with the Trump Administration's recent controversial Nuclear Posture Review, today's just released FY 2019 federal budget dramatically ramps up nuclear weapons research and production.
The National Nuclear Security Administration (NNSA), the Department of Energy's semi-autonomous nuclear weapons agency, is receiving a $2.2 billion overall boost to $15.1 billion, a 17% increase above the FY 2018 enacted level. Of that, a full $11 billion is for the budget category (Nuclear) "Weapons Activities", 18% above the FY 2018 level.
Digging deeper under Weapons Activities, "Directed Stockpile Work" is increased from $3.3 billion to $4.7 billion, or 41%...

(read the full press release)


Draft Nuclear Posture Review Degrades National Security

Yesterday evening the Huffington Post posted a leaked draft of the Trump Administration's Nuclear Posture Review (NPR). This review is the federal government's highest unclassified nuclear weapons policy document, and the first since the Obama Administration's April 2010 NPR.
This Review begins with "Many hoped conditions had been set for deep reductions in global nuclear arsenals, and, perhaps, for their elimination. These aspirations have not been realized. America's strategic competitors have not followed our example. The world is more dangerous, not less." The NPR then points to Russia and China's ongoing nuclear weapons modernization programs and North Korea's "nuclear provocations." It concludes, "We must look reality in the eye and see the world as it is, not as we wish it be."
If the United States government were to really "look reality in the eye and see the world as it is", it would recognize that it is failing miserably to lead the world toward the abolition of the only class of weapons that is a true existential threat to our country. As an obvious historic matter, the U.S. is the first and only country to use nuclear weapons. Since WWII the U.S. has threatened to use nuclear weapons in the Korean and Viet Nam wars, and on many other occasions.
Further, it is hypocritical to point to Russia and China's "modernization" programs as if they are taking place in a vacuum. The U.S. has been upgrading its nuclear arsenal all along. In the last few years our country has embarked on a $1.7 trillion modernization program to completely rebuild its nuclear weapons production complex and all three legs of its nuclear triad.
Moreover, Russia and China's modernization programs are driven in large part by their perceived need to preserve strategic stability and deterrence..
(read the full press release)

2017


2017


New Mexico Environment Department Surrendered to DOE Extortion

Santa Fe, NM. The New Mexico State Auditor Office recently questioned whether two settlements between the New Mexico Environment Department and the Department of Energy were in the best interests of New Mexico. That Office noted:
"The New Mexico Environment Department unnecessarily forgave tens of millions of dollars in civil penalties related to various waste management issues and missed cleanup deadlines by the Department of Energy (DOE) and its contractors. Considering the seriousness of the violations, and the clarity regarding responsibility for the violations, it appears highly unusual that the Department would not collect any civil penalties under these circumstances."
NMED completed an assessment of $54 million in penalties that would have gone to New Mexico, but did not enforce them before making the settlements with DOE. This was at a time when the state was beginning to face a serious budget crisis. As State Senator John Arthur Smith (Chair of the Senate Finance Committee) put it, NMED's failure to levy penalties when New Mexico was facing a budget crisis is "taking it out of the pockets of our kids and young people when they do something like that."
Jay Coghlan, Director of Nuclear Watch New Mexico, commented, "This is inexcusable that NMED preemptively surrendered to Department of Energy extortion. In effect DOE is saying if you, the regulator, fine us, we will cut the money the taxpayer has paid to clean up our mess that threatens the citizens you are suppose to protect."

(View/download full press release)


Los Alamos Hires New Contractor - Starts Cleanup On the Cheap

Santa Fe, NM- Today the Department of Energy (DOE) announced the award of the new Los Alamos National Laboratory legacy cleanup contract to Newport News Nuclear BWXT-Los Alamos, LLC. The $1.39 billion contract is for ten years, which works out to $139 million per year...
Jay Coghlan, Director of Nuclear Watch New Mexico, commented, "This dooms the Lab to cleanup on the cheap. This 140 million dollars per year to the cleanup contractor is based on a revised Consent Order by the New Mexico Environment Department that was a give away to the Los Alamos Lab. The original 2005 Consent Order held the Department of Energy's feet to the fire to complete real cleanup or pay stipulated penalties. In contrast, the Martinez administration gave the biggest polluter in northern New Mexico a free pass, forgiving a hundred million dollars in possible fines that should have gone to our kids' schools. New Mexicans deserve an Environment Department under a new governor that aggressively protects the environment and creates new high-paying jobs thorough enforcing comprehensive cleanup."

View/download the full press release


"Nuclear Weapons Development, Testing, Stockpile & UN Treaty" - Presentation by Nukewatch Director Jay Coghlan at the Albuquerque symposium "Dismantling the Nuclear Beast" Dec. 1-3, 2017.

View/download Power Point doc


Congressional Budget Office: Cost of Nuclear Weapons Upgrades and Improvements Increases to $1.2 Trillion

Today, in Washington, DC, the Congressional Budget Office released its new report, "Approaches for Managing the Costs of U.S. Nuclear Forces, 2017 to 2046". The Congressional Budget Office estimates that the most recent detailed plans for nuclear forces, which were incorporated in the Obama Administration's 2017 budget request, would cost $1.2 trillion in 2017 dollars over the 2017-2046 period: more than $800 billion to operate and sustain (that is, incrementally upgrade) nuclear forces and about $400 billion to modernize them.... Driving this astronomical expense is the fact that instead of maintaining just the few hundred warheads needed for the publicly claimed policy of "deterrence," thousands of warheads are being refurbished and improved to fight a potential nuclear war. This is the little known but explicit policy of the U.S. government!

(read full press release)


Santa Fe City Council: LANL Cleanup Order Must Be Strengthened & Expanded and Plutonium Pit Production Suspended Until Safety Issues Are Resolved

Santa Fe, NM. On the evening of Wednesday October 25, the Santa Fe City Council passed a resolution requesting that the New Mexico Environment Department strengthen the revised Los Alamos National Labs cleanup order to call for additional characterization of legacy nuclear wastes, increased cleanup funding, and significant additional safety training. The resolution also called for the suspension of any planned expanded plutonium pit production until safety issues are resolved.

(view/download full press release)


International Campaign to Abolish Nuclear Weapons Wins Nobel Peace Prize, NukeWatch Calls on New Mexico Politicians and Santa Fe Archbishop To Support Drive Toward Abolition

Santa Fe, NM. Nuclear Watch New Mexico strongly applauds the awarding of the Nobel Peace Prize to the International Campaign to Abolish Nuclear Weapons (disclosure: NukeWatch is one of ICAN's ~400 member groups around the world). This award is especially apt because the peoples of the world are now living at the highest risk for nuclear war since the middle 1980's, when during President Reagan's military buildup the Soviet Union became convinced that the United States might launch a pre-emptive nuclear first strike. Today, we not only have Trump's threats to "totally destroy" North Korea and Kim Jong-un's counter threats, but also renewed Russian fears of a US preemptive nuclear attack... Generally unknown to the American taxpayer, our government has quietly tripled the lethality of the US nuclear weapons stockpile..."

(view/download complete press release)


Expanded Plutonium Pit Production at LANL Will Not Result in Significant Positive Effect On Job Creation and the Regional Economy

The National Nuclear Security Administration's own documents have explicitly stated that expanded pit production would have no significant positive effect on job creation and the regional economy of northern New Mexico. Nuclear Watch argues that expanded plutonium pit production could actually have negative effect if it blocks other economic alternatives such as comprehensive cleanup, which could be the real job producer. Moreover, given LANL's poor safety and environmental record, expanded plutonium pit production could have a seriously negative economic impact on northern New Mexico in the event of any major accidents.

- view/download fact sheet


Chromium Groundwater Contamination at Los Alamos Lab Far Greater Than Previously Expected; LANL's Treatment Plan Must Be Drastically Changed

Santa Fe, NM. The Los Alamos National Laboratory (LANL) has detected far more hexavalent chromium (Cr) contamination than previously estimated in the "sole source" regional groundwater aquifer that serves Los Alamos, Santa Fe and the Espanola Basin. Sampling in July from a new well meant to inject treated groundwater back into the aquifer detected chromium contamination five times greater than the New Mexico groundwater standard of 50 micrograms per liter (ug/L).

View/download the full press release


Talking Points: The 2016 LANL Cleanup Consent Order Should Be Rescinded

The 2005 LANL Cleanup Consent Order was all about the enforceable schedules. It required DOE and LANL to investigate, characterize, and clean up hazardous and mixed radioactive contaminants from 70 years of nuclear weapons research and production. It stipulated a detailed compliance schedule that the Lab was required to meet. Under Gov. Martinez, NMED Secretary Ryan Flynn granted more than 150 compliance milestone extensions at the Lab's request, effectively eviscerating it.
In June 2016 the New Mexico Environment Department (NMED), the Department of Energy (DOE) and Los Alamos National Security, LLC (LANS) signed a revised Consent Order governing cleanup at the Los Alamos National Laboratory (LANL). The new Consent Order is a big step backward in achieving comprehensive, genuine cleanup at the Lab. The revised 2016 CO was a giveaway by NMED to DOE and the Lab, negotiated to allow DOE's budget to drive cleanup, not what is needed to permanently protect our water.
NMED should have kept the original, enforceable 2005 Consent Order that it fought so hard for under the Richardson Administration, modified as needed for the cleanup schedule and final compliance date.

View/download the complete talking points


Oak Ridge Environmental and Peace Alliance, Nuclear Watch New Mexico, and The Natural Resources Defense Council File Lawsuit Against New Nuclear Bomb Plant

Washington, DC Today, the Oak Ridge Environmental Peace Alliance (OREPA), Nuclear Watch New Mexico, and the Natural Resources Defense Council filed a federal lawsuit to stop construction of the problem-plagued Uranium Processing Facility (UPF) until legally required environmental review is completed. The UPF, located at the National Nuclear Security Administration's (NNSA's) Y-12 production plant near Oak Ridge, TN, is slated to produce new thermonuclear weapons components until the year 2080. The UPF is the tip of the spear for the U.S.'s planned one trillion dollar-plus make over of its nuclear weapons arsenal, delivery systems, and production plants.
"The story of this new bomb plant is a long tale of outrageous waste and mismanagement, false starts and re-dos, a federal agency that refuses to meet its legal obligation to engage the public, and a Senator that is bent on protecting this piece of prime nuclear pork for his home state," said Ralph Hutchison, coordinator of OREPA. "But the short version is this: when the NNSA made dramatic changes to the UPF, and admitted that it intends to continue to operate dangerous, already contaminated facilities for another twenty or thirty years, they ran afoul of the National Environmental Policy Act. Our complaint demands that the NNSA complete a supplemental environmental impact statement on the latest iteration of its flawed plans."

View/download the full press release


Some Background on Plutonium Pit Production at the Los Alamos Lab

Santa Fe, NM -The Washington Post has published the first in a series of articles on nuclear safety lapses in plutonium pit production at the Los Alamos Lab. Plutonium pits are the fissile cores of nuclear weapons that when imploded initiate the thermonuclear detonation of modern weapons. By the way, did you know? Plutonium facilities at LANL are- in principle- designed to withstand a serious earthquake of a degree expected to occur only once every 10,000 years. The last serious earthquake near the Lab is believed to have occurred 11,500 years ago.

View/download the full press release


This year's report examines the extraordinary spending at Department of Energy nuclear facilities and examines ways to reduce risks and save billions of dollars across the U.S. nuclear weapons complex.

(View/download PDF)


SA Preview of Trump's Budget: More Nuclear Bombs and Plutonium Pit Production

Santa Fe, NM. "The proposed level of funding for the National Nuclear Security Administration's (NNSA)'s Total Weapons Activities is $10.2 billion, a full billion above what was requested for FY 2017. In March, Trump's "skinny budget" stated NNSA's funding priorities as 'moving toward a responsive nuclear infrastructure', and 'advancing the existing warhead life extension programs'.
"Concerning Life Extension Programs, rather than merely maintaining and extending the lives of existing nuclear weapons as advertised, they are being given new military capabilities, despite denials at the highest levels of government. A current example is the B61-12 Life Extension Program, which is transforming a "dumb" nuclear bomb into the world's first highly accurate "smart" nuclear bomb.
"With respect to the Los Alamos National Laboratory (LANL), "responsive infrastructure" no doubt means accelerating upgrades to existing plutonium facilities and likely building two or three new underground "modules", all for the purpose of quadrupling plutonium pit production from 20 to 80 pits per year. (Plutonium pits are the fissile cores of nuclear weapons.)”

Read the full press release for all the details.


Ban Treaty Conference: Alliance for Nuclear Accountability Panel Discussion

March 28, 2017, UN, NYC:
Ban Treaty Conference: Alliance for Nuclear Accountability Panel Discussion
See video clips of some of the speakers:


Plutonium Pit Production at LANL (Updated March 2017)

(view/download PDF)


Costs Jump in Nuclear Weapons vs. Cleanup; Nuclear Weapons Winning over Environmental Protection

Santa Fe, NM. America is at a crossroads, having to choose between an unnecessarily large, exorbitant, nuclear weapons stockpile, and cleanup that would protect the environment and water resources for future generations. Expanded nuclear weapons research and production, which will cause yet more contamination, is winning.
Two recently released government reports make clear the stark inequality between the so-called modernization program to upgrade and indefinitely preserve U.S. nuclear forces (in large part for a new Cold War with Russia), and the nation-wide program to clean up the radioactive and toxic contamination from the first Cold War. The Obama Administration launched a trillion dollar nuclear weapons "modernization" program, which President Trump may expand. In contrast, cleanup of the first Cold War mess has been cut from a high of $8.5 billion in 2003 to $5.25 billion in 2016, even though comprehensive cleanup would produce far more jobs than nuclear weapons programs.

Read the full press release for all the details.


NNSA Releases Los Alamos Lab Performance Evaluation Report,Nuclear Criticality Safety Issues Still Not Fully Resolved

The National Nuclear Security Administration (NNSA) has publicly released its fiscal year 2016 Performance Evaluation Report (PER) for Los Alamos National Security, LLC (LANS), the for-profit contractor that runs the Los Alamos Lab. The Performance Evaluation Report is NNSA's annual report card on contractor performance, and overall the agency awarded LANS $59 million in profit out of a possible $65 million. The grade was 85% for the incentive part of the award. In 2012 Nuclear Watch New Mexico successfully sued NNSA to ensure that the Performance Evaluation Reports detailing taxpayers funds paid to nuclear weapons contractors are publicly available. In 2016 the NNSA decided to put the LANL management contract out for competitive bid, but granted LANS a contract extension until the end of September 2018.
Despite the passing grade that NNSA gave LANS, there is still ample reason for public concern. First, it bears repeating that in February 2014 a radioactive waste drum improperly prepared by the Los Alamos National Laboratory (LANL) burst underground at the Waste Isolation Pilot Plant (WIPP), contaminating 21 workers and closing that multi-billion dollar facility (a limited restart of operations at WIPP may occur this month).
Less widely known is the fact that LANL's main plutonium facility that produces WIPP wastes has only recently restarted operations after being shut down since June 2013 because of nuclear criticality safety concerns... (more: read full press release)

Media appearances including radio interviews are listed on the internal Media page

See the NukeWatch Channel at YouTube for our extensive playlists of key videos.

See the Nukewatch Twitter feed

See the Nukewatch Tumblr site


WatchBlog Posts:

Over 200 posts published since 2009. See archives at the WatchBlog

Earlier Work Product items are archived here